materials requirements planning vs just in time

Upload: osman-hamdi

Post on 02-Jun-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 materials requirements planning vs just in time

    1/28

    www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 20071 of 28

    Chapter 7Push and Pull Production

    Control Systems

  • 8/10/2019 materials requirements planning vs just in time

    2/28

    www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 20072 of 28

    Basic Definitions

    MRP.(Materials Requirements Planning). MRP is the basicprocess of translating a production schedule for an endproduct (MPS or Master Production Schedule) to a set ofrequirements for all of the subassemblies and parts needed

    to make that item.

    JIT.Just-in-Time. Derived from the original JapaneseKanban system developed at Toyota. JIT seeks to deliver theright amount of product at the right time. The goal is toreduce WIP (work-in-process) inventories to an absoluteminimum.

  • 8/10/2019 materials requirements planning vs just in time

    3/28

  • 8/10/2019 materials requirements planning vs just in time

    4/28

    www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 20074 of 28

    Comparison

    These methods offer two completely different approaches to basic

    production planning in a manufacturing environment. Each hasadvantages over the other, but neither seems to be sufficient on itsown. Both have advantages and disadvantages, suggesting thatboth methods could be useful in the same organization.

    Main Advantage of MRP over JIT: MRP takes forecasts for end

    product demand into account. In an environment in whichsubstantial variation of sales are anticipated (and can be forecastedaccurately), MRP has a substantial advantage.

    Main Advantage of JIT over MRP: JIT reduces inventories to a

    minimum. In addition to saving direct inventory carrying costs, thereare substantial side benefits, such as improvement in quality andplant efficiency.

  • 8/10/2019 materials requirements planning vs just in time

    5/28

    www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 20075 of 28

    MRP Basics

    The MRP system starts with the MPS or MasterProduction Schedule. This is the forecast for the

    sales of the end item over the planning horizon.

    The data sources for determining the MPS

    include: Firm customer orders

    Forecasts of future demand by item

    Safety stock requirements

    Seasonal variations

    Internal orders from other parts of the organization.

  • 8/10/2019 materials requirements planning vs just in time

    6/28

    www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 20076 of 28

    Schematic of the

    Productive System (Fig. 7.1)

  • 8/10/2019 materials requirements planning vs just in time

    7/28www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 20077 of 28

    The Three Major ControlPhases of the Productive System (Fig. 7.2)

  • 8/10/2019 materials requirements planning vs just in time

    8/28www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 20078 of 28

    The Explosion Calculus

    The explosion calculus is a set of rules for converting themaster production schedule to a requirements schedule forall subassemblies, components, and raw materials necessaryto produce the end item.

    There are two basic operations comprising the explosion

    calculus: Time phasing. Requirements for lower level items must

    be shifted backwards by the lead time required toproduce the items

    Multiplication. A multiplicative factor must be applied

    when more than one subassembly is required for eachhigher level item.

  • 8/10/2019 materials requirements planning vs just in time

    9/28www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 20079 of 28

    The Product Structure Diagram

    The product structure diagram is a graphical

    representation of the relationship between

    the various levels of the productive system. It

    incorporates all of the information necessaryto implement the explosion calculus. Figure

    7-3 (next slide) depicts an end item with two

    levels of subassemblies.

  • 8/10/2019 materials requirements planning vs just in time

    10/28www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 200710 of 28

    Typical Product Structure

    Diagram (fig. 7-3)

  • 8/10/2019 materials requirements planning vs just in time

    11/28www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 200711 of 28

    Trumpet and Subassemblies (Fig. 7-4)

  • 8/10/2019 materials requirements planning vs just in time

    12/28www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 200712 of 28

    Product Structure Diagram

    for Harmon Trumpet

    F ll 2007

  • 8/10/2019 materials requirements planning vs just in time

    13/28www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 200713 of 28

    Explosion Calculus

    Rules for translating gross requirements at one level to production

    schedule at that level and requirements at lower levels.

    Example

    Basic Equation:Net Req. = Gross req. - Scheduled Receipts - projected on hand

    inventory

    Basic Algorithm

    1. Compute time-phased requirements

    2. Determine Planned Order Release (LS)

    3. Compute ending inventory

    4. Proceed to next level (if any)

    F ll 2007

  • 8/10/2019 materials requirements planning vs just in time

    14/28www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 200714 of 28

    Explosion Calculus

    Schedule for end item A:

    Week 8 9 10 11 12 13 14 15 16 17

    Gross Req 77 42 38 21 26 112 45 14 76 34

    Sch Rpt 12 6 9

    Inv 23Net Req 42 42 32 12 26 112 45 14 76 34

    Schedule for item B (1 unit/2 weeks)

    Week 6 7 8 9 10 11 12 13 14 15

    Gross 42 42 32 12 26 112 45 14 76 34Schedule for item C (2 units/4 weeks)

    Week 4 5 6 7 8 9 10 11 12 13

    Gross 84 84 64 24 52 224 90 28 152 68

    F ll 2007

  • 8/10/2019 materials requirements planning vs just in time

    15/28www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 200715 of 28Lot Sizing For MRP Systems

    The simplest lot sizing scheme for MRP systems islot-for-lot (abbreviated L4L). This means thatrequirements are met on a period by period basis asthey arise in the explosion calculus. However, more

    cost effective lot sizing plans are possible. Thesewould require knowledge of the cost of setting up forproduction and the cost of holding each item. Thisbrings to mind the EOQ formula from Chapter 4,

    which can be used in this context. However, thereare better methods.

    Fall 2007

  • 8/10/2019 materials requirements planning vs just in time

    16/28www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 200716 of 28

    Statement of the Lot Sizing Problem

    Assume there is a known set of requirements (r1,r2, . . . rn) over an n period planning horizon.Both the set up cost, K, and the holding cost, h,are given. The objective is to determineproduction quantities (y1, y2, . . ., yn) to meet therequirements at minimum cost. The feasibilitycondition to assure there are no stockouts in anyperiod is:

    1 1

    for .1j j

    i i

    i i

    y r j n

    Fall 2007

  • 8/10/2019 materials requirements planning vs just in time

    17/28www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 200717 of 28

    Methods

    One could apply the EOQ formula by defining

    but there are better methods.

    Property of the optimal solution: every optimal solution orders

    exact requirements: that is,

    One method that utilizes this property is the Silver MealHeuristic. The method requires computing the average costfor an order horizon ofjperiods forj = 1, 2, 3,etc. and

    stopping at the first instance when the average cost functionincreases. The average cost for a production quantityspanning j periods, C(j), is given by:

    1

    1 n

    i

    i

    rn

    1 1 1 1 2 1 1 2or ,. . ., or ... ny r y r r y r r r

    2 3( ) ( 2 ... ( 1) ) /jC j K hr hr j hr j

    Fall 2007

  • 8/10/2019 materials requirements planning vs just in time

    18/28www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 200718 of 28

    Methods (continued)

    Another method that is popular in practice ispart periodbalancing. Here one chooses the order horizon to most closelybalance the total holding cost with the set-up cost.

    Finally, a third heuristic is known as the least unit cost heuristic.Here one minimizes the average cost per unit of demand (as

    opposed to the average cost per period as is done in the SilverMeal heuristic.) The average cost per unit of demand over jperiods is given by:

    2 3 1 2( ) ( 2 ... ( 1) ) /( ... ).j jC j K hr hr j hr r r r

    Fall 2007

  • 8/10/2019 materials requirements planning vs just in time

    19/28www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 200719 of 28

    Methods (concluded)

    Experimental evidence seems to favor theSilver Meal Heuristic among the fourdiscussed as the most cost efficient.

    Optimal lot sizes can be found by usingbackwards dynamic programming.

    A heuristic method for lot sizing subject tocapacity constraints is discussed in this

    section.

    Fall 2007

  • 8/10/2019 materials requirements planning vs just in time

    20/28

    www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 200720 of 28Shortcomings of MRP

    Uncertainty. MRP ignores demand uncertainty, supply uncertainty,and internal uncertainties that arise in the manufacturing process.

    Capacity Planning. Basic MRP does not take capacity constraintsinto account.

    Rolling Horizons. MRP is treated as a static system with a fixedhorizon of n periods. The choice of n is arbitrary and can affect theresults.

    Lead Times Dependent on Lot Sizes. In MRP lead times areassumed fixed, but they clearly depend on the size of the lotrequired.

    Quality Problems. Defective items can destroy the linking of thelevels in an MRP system.

    Data Integrity. Real MRP systems are big (perhaps more than 20levels deep) and the integrity of the data can be a serious problem.

    Order Pegging. A single component may be used in multiple end

    items, and each lot must then be pegged to the appropriate item.

    Fall 2007

  • 8/10/2019 materials requirements planning vs just in time

    21/28

    www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 200721 of 28

    Introduction to JIT

    JIT (Just In Time) is an outgrowth of the Kanban systemdeveloped by Toyota.

    Kanban refers to the posting board where the evolution of themanufacturing process would be recorded.

    The Kanban system is a manual information system thatrelies on various types of cards.

    Its development is closely tied to the development of SMED:Single Minute Exchange of Dies, that allowed modelchangeovers to take place in minutes rather than hours.

    (The mechanics of a typical Kanban system are pictured inFigure 7-8.)

    Fall 2007

  • 8/10/2019 materials requirements planning vs just in time

    22/28

    www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 200722 of 28

    Kanban System for Two Production

    Centers (Fig. 7-8)

    Fall, 2007

  • 8/10/2019 materials requirements planning vs just in time

    23/28

    www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 200723 of 28

    Features of JIT Systems

    Small Work-in-Process Inventories.

    Advantages:

    1. Decreases Inventory Costs

    2. Improves Production Efficiency3. Reveals quality problems (see Figure 7-10)

    Disadvantages:

    1. May result in increased worker idle time

    2. May result in decreased throughput rate

    Fall, 2007

  • 8/10/2019 materials requirements planning vs just in time

    24/28

    www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 200724 of 28

    River/Inventory AnalogyIllustrating the Advantages of Just-in-Time

    Fall, 2007

  • 8/10/2019 materials requirements planning vs just in time

    25/28

    www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    Fall, 200725 of 28

    Features of JIT Systems (continued)

    Kanban Information Flow System

    Advantages:

    1. Efficient tracking of lots

    2. Inexpensive implementation of JIT

    3. Achieves desired level of WIP

    Disadvantages:

    1. Slow to react to changes in demand

    2. Ignores predicted demand patterns

    Fall, 2007

  • 8/10/2019 materials requirements planning vs just in time

    26/28

    www.izmirekonomi.edu.tr

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    ,26 of 28

    Kanban Information System vs

    Centralized Information System (MRP)

  • 8/10/2019 materials requirements planning vs just in time

    27/28

    Fall, 2007

  • 8/10/2019 materials requirements planning vs just in time

    28/28

    i i k i d t

    Asst. Prof. Dr. Mahmut Ali GKE, Izmir University of Economics

    28 of 28

    Comparison of MRP and JIT

    Major study comparing MRP and JIT inpractice reveals:

    JIT works best in favorable manufacturingenvironments: little demand variability, reliablevendors, and small set up times

    MRP (and ROP based on Chapter 5 methods)worked well in favorable environments (comparableto JIT) and better in unfavorable environments.