materials requirement planning (mrp)

34
Introduction to lean 1 Materials Requirement Planning (MRP) The approach to coordinated scheduling for dependent demand items.

Upload: aisling-crehan

Post on 02-Jan-2016

129 views

Category:

Documents


5 download

DESCRIPTION

Materials Requirement Planning (MRP). The approach to coordinated scheduling for dependent demand items. The Responsibility of Manufacturing activities. 1.Design requirements and specifications and standards. 2.Be manufactured economically and environmentally friendly. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Materials Requirement Planning (MRP)

Introduction to lean 1

Materials Requirement Planning (MRP)

The approach to coordinated scheduling for dependent demand items.

Page 2: Materials Requirement Planning (MRP)

Introduction to lean 2

The Responsibility of Manufacturing activities

1. Design requirements and specifications and standards.2. Be manufactured economically and environmentally

friendly.3. Build-in quality at each stage.4. Production methods must be sufficiently flexible to

respond to changing market demands, types of products, production rates, and production quantities and to provide on-time delivery to the customer.

5. New developments in materials, production methods, and computer integration of both technological and managerial activities.6. Safety.

Page 3: Materials Requirement Planning (MRP)

Introduction to lean 3

Production Planning and Control

Planning and control of the flow of materials through the manufacturing process

1. Production planning

Production must be able to meet the demand of the marketplace

a). Forecasting

b). Master planning

c). Material requirements planning

d). Capacity planning

2. Implementation and control

3. Inventory management

Page 4: Materials Requirement Planning (MRP)

Introduction to lean 4

Production Planning System

Page 5: Materials Requirement Planning (MRP)

Introduction to lean 5

Material Requirements Plan (MRP)

The quantities of each product group that must be produced in each period.

The desired inventory levels. The resources of equipment, labor, and

material needed in each period. Time

Page 6: Materials Requirement Planning (MRP)

Introduction to lean 6

Example 1.

Amalgamated Fish Sinkers makes a product group of fresh fish sinkers and wants to develop a production plan for them. The expected opening inventory is 100 cases, and they want to reduce that to 80 cases by the end of the planning period. The number of working days is the same for each period. There are no back orders. The expected demand for the fish sinkers is as follows:

a). How much should be produced each period?b). What is the ending inventory for each period?c). If the cost of carrying inventory is $5 per case per period

based on ending inventory, what is the total cost of carrying inventory?

d). What will be the total cost of the plan?

Page 7: Materials Requirement Planning (MRP)

Introduction to lean 7

Period 1 2 3 4 5 TotalForecast (cases) 110 120 130 120 120 600

Production

Ending

Inventory100

Page 8: Materials Requirement Planning (MRP)

Introduction to lean 8

Period 1 2 3 4 5 TotalForecast (cases) 110 120 130 120 120 600

Production 116 116 116 116 116 580Ending

Inventory100

Answer

a). Total production required = 600 + 80 - 100 = 580 cases

 

Production each period = 580 / 5 = 116 cases

Page 9: Materials Requirement Planning (MRP)

Introduction to lean 9

Period 1 2 3 4 5 TotalForecast (cases) 110 120 130 120 120 600

Production 116 116 116 116 116 580Ending

Inventory100 106

b). Ending inventory = opening inventory + production - demand

  Ending inventory after the first period = 100 + 116 - 110 = 106 cases

+ - =

Page 10: Materials Requirement Planning (MRP)

Introduction to lean 10

Period 1 2 3 4 5 TotalForecast (cases) 110 120 130 120 120 600

Production 116 116 116 116 116 580Ending

Inventory100 106

b). Ending inventory = opening inventory + production - demand

  Ending inventory after the first period = 100 + 116 - 110 = 106 cases

+ - =

Page 11: Materials Requirement Planning (MRP)

Introduction to lean 11

Period 1 2 3 4 5 TotalForecast (cases) 110 120 130 120 120 600

Production 116 116 116 116 116 580Ending

Inventory100 106 102 88 84 80

c). The total cost of carrying inventory would be:

  (106 + 102 + 88 + 84 + 80)($5) = $2300

d). Since there were no stockouts and no changes in the level of

production, this would be the total cost of the plan.

Page 12: Materials Requirement Planning (MRP)

Master Scheduling 12

Master Scheduling

Production plan:

Families of products

Master production schedule (MPS):

End items. It breaks down the production plan into the requirements for

individual end items, in each family, by date and quantity.

The total of the items in the MPS should be equal to the total

shown on the production plan.

Page 13: Materials Requirement Planning (MRP)

Master Scheduling 13

Master Scheduling

The information needed to develop an MPS :

The production plan

Forecasts for individual end items

Actual orders received from customers and for

stock replenishment

Inventory levels for individual end items

Capacity restraints

Page 14: Materials Requirement Planning (MRP)

Master Scheduling 14

Example 1.

The Hotshot Lightning Rod Company makes a family of two lightning rods, Models H and I. It bases its production planning on months. For the present month, production is leveled at 1000 units. Opening inventory is 500 units, and the plan is to reduce that to 300 units by the end of the month. The MPS is made using weekly periods. There are four weeks in this month, and production is to be leveled at 250 units per week. The forecast and projected available for the two lightning rods follows. Calculate an MPS for each item.

Page 15: Materials Requirement Planning (MRP)

Master Scheduling 15

Answer

Production Plan:

Period 1 2 3 4 Total

Forecast 300 350 300 250 1200

Projected Available

500 450 350 300 300

Production Plan 250 250 250 250 1000

Page 16: Materials Requirement Planning (MRP)

Master Scheduling 16

Forecasts for individual end items , Model H and I

Period 1 2 3 4 Total

Forecast 300 350 300 250 1200

Forecast for H 200 300 100 100 700

Forecast for I 100 50 200 150 500

Opening inventories are:

Model H 200

Model I 300

Page 17: Materials Requirement Planning (MRP)

Master Scheduling 17

Master Schedule: Model H:

Period 1 2 3 4 Total

Forecast 200 300 100 100 700

Projected Available

200 250 200 100 100

MPS 250 250 100

Master Schedule: Model I:

Period 1 2 3 4 Total

Forecast 100 50 200 150 500

Projected Available

300 200 150 200 200

MPS 250 150

Page 18: Materials Requirement Planning (MRP)

Master Scheduling 18

Master Schedule: Model H:

Period 1 2 3 4 Total

Forecast 200 300 100 100 700

Projected Available

200

MPS

Master Schedule: Model I:

Period 1 2 3 4 Total

Forecast 100 50 200 150 500

Projected Available

300

MPS

Page 19: Materials Requirement Planning (MRP)

Master Scheduling 19

The objectives in developing an MPS

To maintain the desired level of customer service by

maintaining finished-goods inventory levels or by

scheduling to meet customer delivery requirements.

To make the best use of material, labor, and

equipment .

To maintain inventory investment at the required levels.

Page 20: Materials Requirement Planning (MRP)

MRP 20

MRP Process

MRP Process uses four basic techniques Exploding and offsetting Gross and net requirements Releasing orders Low-level coding and netting

The most important thing to consider before making any decisions is lead time

Page 21: Materials Requirement Planning (MRP)

MRP 21

MRP Process

Exploding requires a planner determine actual material required by multiplying usage by the quantity needed. Information is collected from the product tree.

Offsetting takes information from explosion and plans production based upon lead-time and relationship to parent.

Page 22: Materials Requirement Planning (MRP)

MRP 22

MRP Process

Planned order composes of two elements: Planned order receipt. Planned order release.

Gross and Net requirementsNet = Gross requirements – Available inventory

Page 23: Materials Requirement Planning (MRP)

MRP 23

Example 2: 

Using the product tree and lead times shown in figure below, determine the planned order receipts and releases. There are 50 As required in week 5. Suppose there are 10 Bs available as well as the 20 As.

Page 24: Materials Requirement Planning (MRP)

MRP 24

Part #Week

1 2 3 4 5

A

Gross RequirementsProjected Available 20Net requirementsPlanned Order ReceiptPlanned Order Release

20

30

5003030

B

Gross RequirementsProjected Available 10Net requirementsPlanned Order ReceiptPlanned Order Release

C

Gross RequirementsProjected AvailableNet requirementsPlanned Order ReceiptPlanned Order Release

D

Gross RequirementsProjected AvailableNet requirementsPlanned Order ReceiptPlanned Order Release

E

Gross RequirementsProjected AvailableNet requirementsPlanned Order ReceiptPlanned Order Release

Page 25: Materials Requirement Planning (MRP)

MRP 25

Part #Week

1 2 3 4 5

A

Gross RequirementsProjected Available 20Net requirementsPlanned Order ReceiptPlanned Order Release

20

30

5003030

B

Gross RequirementsProjected Available 10Net requirementsPlanned Order ReceiptPlanned Order Release 20

103002020

C

Gross RequirementsProjected AvailableNet requirementsPlanned Order ReceiptPlanned Order Release 30

3003030

D

Gross RequirementsProjected AvailableNet requirementsPlanned Order ReceiptPlanned Order Release

E

Gross RequirementsProjected AvailableNet requirementsPlanned Order ReceiptPlanned Order Release

Page 26: Materials Requirement Planning (MRP)

MRP 26

Part #Week

1 2 3 4 5

A

Gross RequirementsProjected Available 20Net requirementsPlanned Order ReceiptPlanned Order Release

20

30

5003030

B

Gross RequirementsProjected Available 10Net requirementsPlanned Order ReceiptPlanned Order Release 20

103002020

C

Gross RequirementsProjected AvailableNet requirementsPlanned Order ReceiptPlanned Order Release 30

3003030

D

Gross RequirementsProjected AvailableNet requirementsPlanned Order ReceiptPlanned Order Release 20

2002020

E

Gross RequirementsProjected AvailableNet requirementsPlanned Order ReceiptPlanned Order Release 20

2002020

Page 27: Materials Requirement Planning (MRP)

MRP 27

MRP Process

Scheduled Receipts: Promised materials Become available to use immediately

Open Orders: Incomplete orders that have not been fully satisfied Example, we completed the production of markers but do

not have packaging

Net Requirements (Modified) = gross requirements- scheduled receipts – available inventory

Page 28: Materials Requirement Planning (MRP)

MRP 28

Example 3: 

Complete the following table. The lead time for the item is two weeks, and the order quantity is 200. What action should be taken?

Week 1 2 3 4Gross RequirementsScheduled ReceiptsProjected Available 150Net requirementsPlanned Order ReceiptPlanned Order Release

50 250200

100 50

Page 29: Materials Requirement Planning (MRP)

MRP 29

Week 1 2 3 4Gross RequirementsScheduled ReceiptsProjected Available 150Net requirementsPlanned Order ReceiptPlanned Order Release

50

100

250200

100 50

Answer

Week 1 2 3 4Gross RequirementsScheduled ReceiptsProjected Available 150Net requirementsPlanned Order ReceiptPlanned Order Release

50

100

25020050

100 50

Page 30: Materials Requirement Planning (MRP)

MRP 30

Week 1 2 3 4Gross RequirementsScheduled ReceiptsProjected Available 150Net requirementsPlanned Order ReceiptPlanned Order Release

50

100

25020050

100

5050?

50

Answer

Week 1 2 3 4Gross RequirementsScheduled ReceiptsProjected Available 150Net requirementsPlanned Order ReceiptPlanned Order Release

50

100

200

25020050

100

15050200

50

X

Page 31: Materials Requirement Planning (MRP)

Introduction to lean 31

Example 1 of MRP

Given the following product tree, explode, offset, and determine the gross and net ret requirements. All lead times are one week, and the quantities required are shown in parentheses. The master production schedule calls for the completion of 100 As in week 5. There is scheduled receipt of 100 Bs in week 1. There are also 200 Fs available.

Page 32: Materials Requirement Planning (MRP)

Introduction to lean 32

Example 2 of MRP

Given the following product tree, explode, offset, and determine the gross and net ret requirements. All lead times are one week, and the quantities required are shown in parentheses. The master production schedule calls for the completion of 100 As in week 4 and 50 in week 5. There are 300 Bs scheduled to be received in week 1 and 200 Ds in week 3. There are also 20 As available. The ordering quantity for all parts is lot-for lot.

Page 33: Materials Requirement Planning (MRP)

Introduction to lean 33

Example 3 of MRP

Given the following product tree, explode, offset, and determine the gross and net ret requirements. All lead times are one week, and the quantities required are shown in parentheses. The master production schedule calls for the completion of 100 As in week 4 and 50 in week 5. There are 100 Cs scheduled to be received in week 2. Lot size for part E is 500. Other parts are all lot-for lot.

Page 34: Materials Requirement Planning (MRP)

Introduction to lean 34

References

Dave Dixon (2004), The truce between lean and IT, IE Industrial Engineer, 36(6), 42-45.

Charles M. Parks (2003), The Bare Necessities of Lean, IE Industrial Engineer, 35(8), 39-42.