MATERIALS ON HAND Standard Specification 1906.2 allows for payment of materials on hand (MOH) upon contractor’s written request. See page 91 of the 2014 Standard Specifications for Construction, (Larger Book) for specific requirements to qualify for requested payment. To add MOH to OneOffice Select corresponding project item form the IRA and select “Add Material On Hand.”

Upload: eugenia-logan

Post on 24-Dec-2015

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MATERIALS ON HAND Standard Specification 1906.2 allows for payment of materials on hand (MOH) upon contractor’s written request. See page 91 of the 2014

MATERIALS ON HANDStandard Specification 1906.2 allows for payment of materials on hand (MOH) upon

contractor’s written request. See page 91 of the 2014 Standard Specifications for Construction, (Larger Book) for specific requirements to qualify for requested payment.

To add MOH to OneOffice Select corresponding project item form the IRA and select “Add Material On Hand.”

Page 2: MATERIALS ON HAND Standard Specification 1906.2 allows for payment of materials on hand (MOH) upon contractor’s written request. See page 91 of the 2014

Using the information on Contractor’s request fill in data fields. Keeping in mind not to exceed

the contract amount of associated work.OneOffice provides for the attachment of electronic copies of invoices, which makes

for easy referencing.

Once information is entered select “Add Material on Hand Transaction”

Page 3: MATERIALS ON HAND Standard Specification 1906.2 allows for payment of materials on hand (MOH) upon contractor’s written request. See page 91 of the 2014

Take special note: this is still a Materials on Hand window. To assist in distinguishing it from an IRA take note of a few

differences. Column Titles are different.

MOH has a Payment No. and lacks Sta-to-Sta and Documentation columns.MOH is also missing a View / Edit Tally Sheet or Sketch button.

Page 4: MATERIALS ON HAND Standard Specification 1906.2 allows for payment of materials on hand (MOH) upon contractor’s written request. See page 91 of the 2014