  • 8/8/2019 Material A

    1/26

    Material Management

    Select The Blank

    Question Inspection methods analyze ________.Correct Answer Degree of inspection

    Your Answer Quality of material

    Multiple Choice Single Answer

    Question In Fixed-Order quantity system, cycle time of consumption should be :-

    Correct Answer More than lead time

    Your Answer Less than lead-time

    Select The BlankQuestion In the ________ , the composition of code is in three groups of digits that

    are separated by hyphens, the hyphens serves to break the code into easy to handle group

    of digits.

    Correct Answer Kodak system

    Your Answer Kodak system

    Multiple Choice Single Answer

    Question A buyer gives wrong idea to his supplier about his requirements or show a

    fictitious figure to get some price discount is called as :-

    Correct Answer Misrepresentation of factsYour Answer Misrepresentation of facts

    Multiple Choice Single Answer

    Question JIT is an :-

    Correct Answer Inventory reduction technique

    Your Answer Just-in-time

    Multiple Choice Single Answer

    Question Issues to top up supply to pre-fixed levels of items are :-Correct Answer Imprest issues

    Your Answer Imprest issues

    True/False

    Question Two bin system is better as compared to perpetual inventory system.

    Correct Answer False

  • 8/8/2019 Material A

    2/26

    Your Answer True

    Multiple Choice Multiple Answer

    Question Annual total cost changes :-

    Correct Answer If stock turnover rate changes , If quantity changesYour Answer If stock turnover rate changes , If procurement cost changes , If

    set-up cost changes

    True/False

    Question Functionally critical parts require to be covered under cent per cent

    inspection

    Correct Answer True

    Your Answer False

    Select The Blank

    Question GRR are sent from ________.

    Correct Answer Stores Dept.

    Your Answer Stores Dept.

    Multiple Choice Single Answer

    Question Competitive price information must be treated as confidential and should

    not be disclosed to the bidders with an intention of allowing them to rebid is :-

    Correct Answer Improprieties of bids

    Your Answer Price disclosure

    Select The Blank

    Question Good ________ relations are necessary for effective materials planning as

    every department is involved in materials planning because each department requires one

    item or other another.

    Correct Answer Departmental

    Your Answer Departmental

    Multiple Choice Multiple Answer

    Question The following are the actions would help to improve effectiveness of

    materials planning :-

    Correct Answer Accurate forecasting , Computerization , Shorter materials plan

    period

    Your Answer Accurate forecasting , Computerization , Shorter materials plan

    period

  • 8/8/2019 Material A

    3/26

    Match The Following

    Question Correct Answer Your Answer

    JE Journal Entries Journal Entries

    PO Purchase order Purchase order

    GRN Goods receipt note Goods receipt note

    DN Discrepancy note. Discrepancy note.

    True/False

    Question Cancellation of orders on flimsy ground is unethical.

    Correct Answer TrueYour Answer True

    Select The Blank

    Question Standardized containers eliminates ________

    Correct Answer Transit damage

    Your Answer Transit damage

    Multiple Choice Single Answer

    Question Purchase order offers acceptance and have been clearly laid down in :-

    Correct Answer Indian Contract act 1872

    Your Answer Indian Contract act 1872

    Multiple Choice Single Answer

    Question For the inspection of Stationery which department is responsible?

    Correct Answer Stores

    Your Answer Stores

    Match The Following

    Question Correct Answer Your Answer

    FAS (4-2) Sale at the port of destination Sale at port of export

    FOB (1-1) Sale is made on FOB vessel Sale is made on FOB vessel

    CIF (2-4) Sale is made at port of destination Sale at the port of destination

  • 8/8/2019 Material A

    4/26

  • 8/8/2019 Material A

    5/26

    Correct Answer Bonus

    Your Answer Penalty for delay

    True/False

    Question Single tender system is used when there is only one supplier of the item.Correct Answer True

    Your Answer True

    Multiple Choice Multiple Answer

    Question Following are benefits of scientific stoke management :-

    Correct Answer Reduction in downtime by efficient issues , Inventory control ,

    Very less time required to identify & issue material

    Your Answer Reduction in downtime by efficient issues , Inventory control ,

    Very less time required to identify & issue material

    True/False

    Question Stores is the "Safe Custody" for keeping materials

    Correct Answer True

    Your Answer True

    True/False

    Question Value analysis is the cost reduction technique.

    Correct Answer True

    Your Answer True

    True/False

    Question Codification avoids confusion and doubt caused by long description of

    items.

    Correct Answer True

    Your Answer True

    Multiple Choice Multiple Answer

    Question Complaints concerning should be made in such a way that negative

    reactions are avoided such as :-

    Correct Answer Delivery failures , Rejection , Shortages

    Your Answer Delivery failures , Rejection , Shortages

    True/False

  • 8/8/2019 Material A

    6/26

    Question A firm engaged in custom-built-product, is usually plagued with obsolete

    material.

    Correct Answer True

    Your Answer True

    Select The Blank

    Question ________ refers to the procurement of the requirements of all departments

    of the firm by a central purchase organization.

    Correct Answer Centralisation

    Your Answer Centralisation

    Multiple Choice Multiple Answer

    Question Conventional machine set-up time includes :-

    Correct Answer Tool replenishment , First piece inspection

    Your Answer Tool replenishment , First piece inspection , Set-up

    Multiple Choice Multiple Answer

    Question Stock-out is due to :-

    Correct Answer Unusual high demands , Delay in deliveries

    Your Answer Unusual high demands , Delay in deliveries , Machine break-down

    True/False

    Question Negotiation should end up with an unhappy supplier.

    Correct Answer False

    Your Answer False

    Select The Blank

    Question Systematic, formal and continuous analysis of all factors affect ________

    management function is known as Materials research.

    Correct Answer Materials

    Your Answer Materials

    True/False

    Question Since stock-taking is a check on storekeeper, it should not be conducted

    by him.

    Correct Answer False

    Your Answer False

    Multiple Choice Multiple Answer

  • 8/8/2019 Material A

    7/26

    Question Salient features of the working of the price panel are as under :-

    Correct Answer Usage value above which the panel is to approve of the price is

    specified. , Vendor development department is required to give cost break up to the

    secretary of the price panel , Members of the panel meet to scrutinize and discuss the cost

    aspects.

    Your Answer Usage value above which the panel is to approve of the price isspecified. , Vendor development department is required to give cost break up to the

    secretary of the price panel , Members of the panel meet to scrutinize and discuss the cost

    aspects.

    Multiple Choice Multiple Answer

    Question Application for an import license must be signed from :-

    Correct Answer Proprietor , Partner of firm , Person duly authorized by board of

    directors of company

    Your Answer Proprietor , Partner of firm , Person duly authorized by board of

    directors of company

    True/False

    Question Manual inspection is economical when volume of output is small.

    Correct Answer True

    Your Answer True

    Multiple Choice Multiple Answer

    Question For large organizations where product is made up of assemblies of

    manufactured components raw material store is subdivided into :-

    Correct Answer Foundry store , Tool crib , Maintenance store

    Your Answer Foundry store , Tool crib , Goods inward store

    True/False

    Question Post parcel consignments are cleared through customs & clearance is done

    through foreign post office.

    Correct Answer True

    Your Answer True

    Multiple Choice Single Answer

    Question What is the meaning of discharge of contract by novation?

    Correct Answer If the parties agree to substitute a new contract in place of existing

    one or alter it, original contract is discharged

    Your Answer If the parties agree to substitute a new contract in place of existing

    one or alter it, original contract is discharged

  • 8/8/2019 Material A

    8/26

    Select The Blank

    Question Quantity delivered of goods must be according to the ________.

    Correct Answer Terms of contract

    Your Answer Terms of contract

    Multiple Choice Single Answer

    Question Which of the following is not the external factor influencing materials

    planning?

    Correct Answer Corporate objective

    Your Answer Corporate objective

    Select The BlankQuestion Inspection methods analyze ________.

    Correct Answer Degree of inspection

    Your Answer Quality of material

    Multiple Choice Single Answer

    Question In Fixed-Order quantity system, cycle time of consumption should be :-

    Correct Answer More than lead time

    Your Answer Less than lead-time

    Select The Blank

    Question In the ________ , the composition of code is in three groups of digits that

    are separated by hyphens, the hyphens serves to break the code into easy to handle group

    of digits.

    Correct Answer Kodak system

    Your Answer Kodak system

    Multiple Choice Single Answer

    Question A buyer gives wrong idea to his supplier about his requirements or show a

    fictitious figure to get some price discount is called as :-

    Correct Answer Misrepresentation of facts

    Your Answer Misrepresentation of facts

    Multiple Choice Single Answer

    Question JIT is an :-

    Correct Answer Inventory reduction technique

  • 8/8/2019 Material A

    9/26

    Your Answer Just-in-time

    Multiple Choice Single Answer

    Question Issues to top up supply to pre-fixed levels of items are :-

    Correct Answer Imprest issuesYour Answer Imprest issues

    True/False

    Question Two bin system is better as compared to perpetual inventory system.

    Correct Answer False

    Your Answer True

    Multiple Choice Multiple Answer

    Question Annual total cost changes :-Correct Answer If stock turnover rate changes , If quantity changes

    Your Answer If stock turnover rate changes , If procurement cost changes , If

    set-up cost changes

    True/False

    Question Functionally critical parts require to be covered under cent per cent

    inspection

    Correct Answer True

    Your Answer False

    Select The Blank

    Question GRR are sent from ________.

    Correct Answer Stores Dept.

    Your Answer Stores Dept.

    Multiple Choice Single Answer

    Question Competitive price information must be treated as confidential and should

    not be disclosed to the bidders with an intention of allowing them to rebid is :-

    Correct Answer Improprieties of bids

    Your Answer Price disclosure

    Select The Blank

    Question Good ________ relations are necessary for effective materials planning as

    every department is involved in materials planning because each department requires one

    item or other another.

  • 8/8/2019 Material A

    10/26

    Correct Answer Departmental

    Your Answer Departmental

    Multiple Choice Multiple Answer

    Question The following are the actions would help to improve effectiveness ofmaterials planning :-

    Correct Answer Accurate forecasting , Computerization , Shorter materials plan

    period

    Your Answer Accurate forecasting , Computerization , Shorter materials plan

    period

    Match The Following

    Question Correct Answer Your Answer

    JE Journal Entries Journal Entries

    PO Purchase order Purchase order

    GRN Goods receipt note Goods receipt note

    DN Discrepancy note. Discrepancy note.

    True/False

    Question Cancellation of orders on flimsy ground is unethical.

    Correct Answer True

    Your Answer True

    Select The Blank

    Question Standardized containers eliminates ________

    Correct Answer Transit damage

    Your Answer Transit damage

    Multiple Choice Single Answer

    Question Purchase order offers acceptance and have been clearly laid down in :-

    Correct Answer Indian Contract act 1872

    Your Answer Indian Contract act 1872

    Multiple Choice Single Answer

    Question For the inspection of Stationery which department is responsible?

  • 8/8/2019 Material A

    11/26

    Correct Answer Stores

    Your Answer Stores

    Match The Following

    Question Correct Answer Your Answer

    FAS (4-2) Sale at the port of destination Sale at port of export

    FOB (1-1) Sale is made on FOB vessel Sale is made on FOB vessel

    CIF (2-4) Sale is made at port of destination Sale at the port of destination

    CFR (3-3) Sale at port of export Sale is made at port of destination

    Multiple Choice Single Answer

    Question Reprocessing of Scrap is :-

    Correct Answer Reclaiming for re-use

    Your Answer Reclaiming for re-use

    Multiple Choice Single Answer

    Question Limit gauges are used to verify :-

    Correct Answer Whether the product is within the specification

    Your Answer Whether the product is within the specification

    Multiple Choice Single Answer

    Question Which of the following is not the internal factor influencing materials

    planning?

    Correct Answer International market

    Your Answer International market

    Multiple Choice Single Answer

    Question The system should be designed in such a way that it serves the advantages

    that are expected to accrue from it, is called as :-

    Correct Answer Objective oriented

    Your Answer Objective oriented

    Multiple Choice Single Answer

    Question Real creative ideas results :-

    Correct Answer When members ventures into impossible areas

  • 8/8/2019 Material A

    12/26

    Your Answer When opportunity is given to staff

    Multiple Choice Multiple Answer

    Question Segregation of scrap means :-

    Correct Answer Sorting by type, size, grade etc. , Sorting by grade, weightYour Answer Sorting by type, size, grade etc. , Sorting by grade, weight

    Select The Blank

    Question ________clause should be inserted in the purchase order of items critical

    to project to induce supplier for early completion of the orders.

    Correct Answer Bonus

    Your Answer Penalty for delay

    True/FalseQuestion Single tender system is used when there is only one supplier of the item.

    Correct Answer True

    Your Answer True

    Multiple Choice Multiple Answer

    Question Following are benefits of scientific stoke management :-

    Correct Answer Reduction in downtime by efficient issues , Inventory control ,

    Very less time required to identify & issue material

    Your Answer Reduction in downtime by efficient issues , Inventory control ,

    Very less time required to identify & issue material

    True/False

    Question Stores is the "Safe Custody" for keeping materials

    Correct Answer True

    Your Answer True

    True/False

    Question Value analysis is the cost reduction technique.

    Correct Answer True

    Your Answer True

    True/False

    Question Codification avoids confusion and doubt caused by long description of

    items.

    Correct Answer True

  • 8/8/2019 Material A

    13/26

    Your Answer True

    Multiple Choice Multiple Answer

    Question Complaints concerning should be made in such a way that negative

    reactions are avoided such as :-Correct Answer Delivery failures , Rejection , Shortages

    Your Answer Delivery failures , Rejection , Shortages

    True/False

    Question A firm engaged in custom-built-product, is usually plagued with obsolete

    material.

    Correct Answer True

    Your Answer True

    Select The Blank

    Question ________ refers to the procurement of the requirements of all departments

    of the firm by a central purchase organization.

    Correct Answer Centralisation

    Your Answer Centralisation

    Multiple Choice Multiple Answer

    Question Conventional machine set-up time includes :-

    Correct Answer Tool replenishment , First piece inspection

    Your Answer Tool replenishment , First piece inspection , Set-up

    Multiple Choice Multiple Answer

    Question Stock-out is due to :-

    Correct Answer Unusual high demands , Delay in deliveries

    Your Answer Unusual high demands , Delay in deliveries , Machine break-down

    True/False

    Question Negotiation should end up with an unhappy supplier.

    Correct Answer False

    Your Answer False

    Select The Blank

    Question Systematic, formal and continuous analysis of all factors affect ________

    management function is known as Materials research.

    Correct Answer Materials

  • 8/8/2019 Material A

    14/26

    Your Answer Materials

    True/False

    Question Since stock-taking is a check on storekeeper, it should not be conducted

    by him.Correct Answer False

    Your Answer False

    Multiple Choice Multiple Answer

    Question Salient features of the working of the price panel are as under :-

    Correct Answer Usage value above which the panel is to approve of the price is

    specified. , Vendor development department is required to give cost break up to the

    secretary of the price panel , Members of the panel meet to scrutinize and discuss the cost

    aspects.

    Your Answer Usage value above which the panel is to approve of the price isspecified. , Vendor development department is required to give cost break up to the

    secretary of the price panel , Members of the panel meet to scrutinize and discuss the cost

    aspects.

    Multiple Choice Multiple Answer

    Question Application for an import license must be signed from :-

    Correct Answer Proprietor , Partner of firm , Person duly authorized by board of

    directors of company

    Your Answer Proprietor , Partner of firm , Person duly authorized by board of

    directors of company

    True/False

    Question Manual inspection is economical when volume of output is small.

    Correct Answer True

    Your Answer True

    Multiple Choice Multiple Answer

    Question For large organizations where product is made up of assemblies of

    manufactured components raw material store is subdivided into :-

    Correct Answer Foundry store , Tool crib , Maintenance store

    Your Answer Foundry store , Tool crib , Goods inward store

    True/False

    Question Post parcel consignments are cleared through customs & clearance is done

    through foreign post office.

  • 8/8/2019 Material A

    15/26

    Correct Answer True

    Your Answer True

    Multiple Choice Single Answer

    Question What is the meaning of discharge of contract by novation?Correct Answer If the parties agree to substitute a new contract in place of existing

    one or alter it, original contract is discharged

    Your Answer If the parties agree to substitute a new contract in place of existing

    one or alter it, original contract is discharged

    Select The Blank

    Question Quantity delivered of goods must be according to the ________.

    Correct Answer Terms of contract

    Your Answer Terms of contract

    Multiple Choice Single Answer

    Question Which of the following is not the external factor influencing materials

    planning?

    Correct Answer Corporate objective

    Your Answer Corporate objective

    Multiple Choice Multiple Answer

    Question Primary duties to be performed by purchase department are :-

    Correct Answer Receipts, sorting of purchase indents and determination of method

    of buying , Performance evaluation and feedback , Search for suppliers

    Your Answer Search for suppliers , Receipts, sorting of purchase indents and

    determination of method of buying , Performance evaluation and feedback

    True/False

    Question Indentor's copy is meant to enable indentor to follow up with the purchase

    department.

    Correct Answer True

    Your Answer True

    Select The Blank

    Question ________specification are usually flexible and can be altered during

    consultation with different manufacturers of the equipment.

    Correct Answer Equipment

  • 8/8/2019 Material A

    16/26

    Your Answer Equipment

    Multiple Choice Single Answer

    Question Second bin quantity can be qualified by :-

    Correct Answer m + L x CYour Answer m + L x C

    True/False

    Question Continuous stock-taking tends to dislocate the working of store.

    Correct Answer False

    Your Answer False

    Multiple Choice Single Answer

    Question Redundant Stock is nothing but :-Correct Answer Worthless for conversion & other use

    Your Answer Worthless for conversion & other use

    Multiple Choice Single Answer

    Question The cost incurred in providing adequate insurance cover to the materials in

    transit and in storage is

    Correct Answer Insurance cost

    Your Answer Insurance cost

    Select The Blank

    Question Set-up cost for manufactured item in own plant is ________.

    Correct Answer Very high

    Your Answer Very high

    Multiple Choice Single Answer

    Question The buying which is received in staggered lots, each lot at times may

    equal EOQ is :-

    Correct Answer Contract buying

    Your Answer Schedule buying

    Multiple Choice Single Answer

    Question Price of the commodity is conditioned by the forces of supply and demand

    is :-

    Correct Answer Demand and supply condition

    Your Answer Demand and supply condition

  • 8/8/2019 Material A

    17/26

    Multiple Choice Single Answer

    Question The submission of the final offers by the prospective sources is :-

    Correct Answer Firm bidding

    Your Answer Firm bidding

    Select The Blank

    Question ________ of the department refers to the placement of the department in

    the structure of the company.

    Correct Answer Status

    Your Answer Size

    Select The Blank

    Question Paper work cost is ________.Correct Answer Procurement cost

    Your Answer Procurement cost

    True/False

    Question The trade discount is not allowed as a percentage of published price.

    Correct Answer False

    Your Answer False

    Multiple Choice Multiple Answer

    Question What are the different methods of identifying materials?

    Correct Answer Tagging , Labeling , Engraving

    Your Answer Tagging , Labeling , Engraving

    Multiple Choice Single Answer

    Question Prices of certain commodity may be fixed by the government and thereby

    putting a restriction on both buyer and seller is :-

    Correct Answer Government restrictions

    Your Answer Government restrictions

    True/False

    Question Multiple sampling is an extension of the double sampling plan.

    Correct Answer True

    Your Answer True

  • 8/8/2019 Material A

    18/26

    Match The Following

    Question Correct Answer Your Answer

    Labour management relations Investigating into suppliers capabilities Investigating

    into suppliers capabilities

    Technical discussions between the representatives of a buyer and supplier Techno

    commercial discussion and trial order Techno commercial discussion and trial

    order

    Follow up with the supplier until sample submission Sample validation Sample

    validation

    Type of supplier Preliminary selection of the suppliers Preliminary selection of the

    suppliers

    Select The Blank

    Question Review system-optional replenishment is a modification of ________.

    Correct Answer Fixed-order interval system

    Your Answer Re-order level system

    Multiple Choice Multiple Answer

    Question Costs involved in materials management are

    Correct Answer Basic cost of materials , Government tax and levies , Ordering cost

    Your Answer Basic cost of materials , Government tax and levies , Ordering cost

    True/False

    Question Safety stock forms a fixed portion of inventories.

    Correct Answer True

    Your Answer True

    True/False

    Question Maintenance and repair costs in used equipments are relatively higher.

    Correct Answer True

    Your Answer True

    Multiple Choice Multiple Answer

    Question What are the areas of control to improve profit

    Correct Answer Increase units sold , Increase production , Reducing capital

    Your Answer Increase units sold , Increase production , Reducing capital

  • 8/8/2019 Material A

    19/26

    Multiple Choice Multiple Answer

    Question Main transport documents used by trade are :-

    Correct Answer RR , LR

    Your Answer RR , LR

    Multiple Choice Single Answer

    Question Quantity based advance license is based on standard of :-

    Correct Answer Input-output norms fixed by ALC

    Your Answer Input-output norms fixed by ALC

    Select The Blank

    Question Originating department of daily material receipt report is ________.

    Correct Answer Receiving storeYour Answer Purchase department

    Multiple Choice Multiple Answer

    Question What are the limitations of alpha betical system?

    Correct Answer Repetition of alphabets often leads to confusion and wrong

    identification , The selection of proper alphabets for each of the items is difficult. , The

    codes cannot be amplified which restricts its use to smaller firms

    Your Answer Repetition of alphabets often leads to confusion and wrong

    identification , The selection of proper alphabets for each of the items is difficult. , The

    codes cannot be amplified which restricts its use to smaller firms

    True/False

    Question Small parcels, Samples, gifts which are received from other countries

    provisions of import policy & customs not applied on them.

    Correct Answer False

    Your Answer False

    Select The Blank

    Question Malpractices are ________.

    Correct Answer Manipulations by stores staff

    Your Answer Common in all stores

    True/False

    Question The registered firms are required to submit security deposit which is

    required from unregistered firms.

  • 8/8/2019 Material A

    20/26

    Correct Answer False

    Your Answer False

    Multiple Choice Single Answer

    Question In instantaneous replenishment system :-Correct Answer Item consumption demand rate is constant

    Your Answer Item consumption demand rate is constant

    Multiple Choice Multiple Answer

    Question Store manager has to ensure security :-

    Correct Answer Of store buildings , Of stock yards

    Your Answer Of store buildings , Of stock yards , Of stores staff

    Multiple Choice Single AnswerQuestion The process of procurement of raw material, wip, finished goods, jigs,

    fixtures and other tools and equipments which are required for the operation and

    maintenance of a manufacturing plant is known as

    Correct Answer Purchasing

    Your Answer Purchasing

    Multiple Choice Multiple Answer

    Question Receiving inspector should have to :-

    Correct Answer Segregate defectives , Maintain vendor wise quality records

    Your Answer Segregate defectives , Maintain vendor wise quality records

    Multiple Choice Single Answer

    Question Identifying the need for source selection and source development is :-

    Correct Answer Source requirement stage

    Your Answer Source requirement stage

    True/False

    Question Supplier's delivery ratings should be communicated on periodical basis.

    Correct Answer True

    Your Answer True

    Match The Following

    Question Correct Answer Your Answer

    Vendor rating Right source Right source

  • 8/8/2019 Material A

    21/26

    Replenishment method Right time Right time

    Competitive bidding Right price Right price

    EOQ Right quantity Right quantity

    Multiple Choice Single Answer

    Question EOQ means :-

    Correct Answer When total cost & right quantity are balanced

    Your Answer When total cost & right quantity are balanced

    Multiple Choice Single Answer

    Question The cost incurred in movement of materials from suppliers works tobuyer's works is

    Correct Answer Freight cost

    Your Answer Freight cost

    Multiple Choice Multiple Answer

    Question Value analysis speaks about :-

    Correct Answer Cost improvement , Improvement in quality

    Your Answer Cost improvement , Improvement in quality

    Multiple Choice Multiple Answer

    Question Advantages of fixed price agreements are :-

    Correct Answer They are easy to administer , They give certainty to the buyer who

    knows from the start, amount he has to pay for the goods/services. , They protect buyer

    from possible financial risks from price escalations

    Your Answer They are easy to administer , They give certainty to the buyer who

    knows from the start, amount he has to pay for the goods/services. , They protect buyer

    from possible financial risks from price escalations

    Multiple Choice Multiple Answer

    Question Main information in the bill of material is :-

    Correct Answer Part no. , Material specification , Quantity per assembly

    Your Answer Part no. , Material specification

    Select The Blank

  • 8/8/2019 Material A

    22/26

    Question ________ is responsible for purchase of goods of right quality, quantity,

    time, price and source.

    Correct Answer Purchase division

    Your Answer Purchase division

    Multiple Choice Single Answer

    Question The system not only should identify and classify all the existing items and

    it should have enough extra unassigned codes to absorb future items is called as :-

    Correct Answer Flexibility

    Your Answer Flexibility

    Multiple Choice Single Answer

    Question Purchasing today is no longer just a commercial activity but it is a techno

    commercial activity. This is known as :-

    Correct Answer Changing nature of purchasesYour Answer Changing nature of purchases

    True/False

    Question Black listing may be for a limited period or for an indefinite period.

    Correct Answer True

    Your Answer True

    Multiple Choice Multiple Answer

    Question Actions involved in sample validation are :-

    Correct Answer Follow up with the supplier until sample submission , Sample

    inspection , Feedback on defects and defect prevention

    Your Answer Sample inspection , Sample rejection

    Select The Blank

    Question In order to make purchasing effective and to resolve the allied problems,

    there is ________ under the directorate.

    Correct Answer Planning and development wing

    Your Answer Planning and development wing

    Multiple Choice Single Answer

    Question Climatic & environmental agent is :-

    Correct Answer Temperature

    Your Answer Temperature

    Multiple Choice Single Answer

    Question The purchase of variety of items from single source is called as :-

    Correct Answer Blanket orders

  • 8/8/2019 Material A

    23/26

    Your Answer Speculative buying

    Multiple Choice Multiple Answer

    Question The following are the actions would help to improve effectiveness of

    materials planning :-

    Correct Answer Accurate forecasting , Computerization , Shorter materials planperiod

    Your Answer Accurate forecasting , Computerization , Shorter materials plan period

    Multiple Choice Multiple Answer

    Question First-order interval system is also called as :-

    Correct Answer Periodic ordering system , Periodic review system

    Your Answer Price-brake quantity system , Periodic review system , Instantaneous

    system

    True/False

    Question A rationalized classification system is a must to maintain numerous itemswhich are similar in nature but different in nomenclature.

    Correct Answer True

    Your Answer True

    Multiple Choice Multiple Answer

    Question Disadvantages of forward buying are :-

    Correct Answer Such a buying may not serve entirely the needs of the production

    department , Price expectations if not realised may result in major financial loss to the

    firm. , Large scale obsolescence may result if design changes occur.

    Your Answer Such a buying may not serve entirely the needs of the production

    department , Price expectations if not realised may result in major financial loss to the

    firm. , Large scale obsolescence may result if design changes occur.

    Select The Blank

    Question High cost of operation links to ________.

    Correct Answer Air

    Your Answer Rail & Air

    True/False

    Question The trade discount is not allowed as a percentage of published price.

    Correct Answer False

    Your Answer False

    Multiple Choice Single Answer

    Question Higher price is usually charged when the quantity required is small.

    Bigger quantities on the other hand give the buyer a leverage to negotiate for better price

    is :-

    Correct Answer Quantity requirements

    Your Answer Quantity requirements

  • 8/8/2019 Material A

    24/26

    Select The Blank

    Question ________ department in almost all companies is the biggest spending

    department and the custodian of company's purse.

    Correct Answer Purchasing

    Your Answer Stores

    True/False

    Question Training of vendors in JIT concepts brings an end to the adversarial

    relationships.

    Correct Answer True

    Your Answer True

    True/False

    Question Colour codification is commonly used for identification of lubricants.

    Correct Answer False

    Your Answer True

    True/False

    Question Purchase enquiry is raised in (n+1) copies where n is the number of

    suppliers to whom enquiry is sent.

    Correct Answer True

    Your Answer True

    Multiple Choice Multiple Answer

    Question Salient characteristics of kodak system are :-

    Correct Answer Materials are divided into few broad classifications , Each

    preliminary class is further divided into sub classes , Each sub class is next amplified into

    kind of items

    Your Answer Materials are divided into few broad classifications , Each preliminary

    class is further divided into sub classes , Each sub class is next amplified into kind of

    items

    Multiple Choice Single Answer

    Question Fire is an accident caused by :-

    Correct Answer Chemical reaction between combustible & oxygen

    Your Answer Negligence of staff

    Multiple Choice Multiple Answer

    Question Conventional machine set-up time includes :-

    Correct Answer Tool replenishment , First piece inspection

    Your Answer Set-up , Tool replenishment , First piece inspection

    True/False

    Question For effective materials research the firm must have a good library

    equipped with specialized research reference.

  • 8/8/2019 Material A

    25/26

    Correct Answer True

    Your Answer False

    Multiple Choice Multiple Answer

    Question Inspector must have :-

    Correct Answer Ability to read & interpret drawings , Knowledge of trignometry

    Your Answer Knowledge of trignometry , Ability to work hard , Ability to work in shifts

    Multiple Choice Multiple Answer

    Question Import transactions are subject to following additional laws compared to

    procurement from sources within the country as :-

    Correct Answer Import trade control act ulation , Custom act , Central excise

    Rules 2002Your Answer Import trade control act ulation , Custom act , Central excise Rules 2002

    Multiple Choice Single Answer

    Question Verification of correctness of paper work and appropriateness of supply is

    the responsibility of :-

    Correct Answer Receiving Division

    Your Answer Store keeping

    Select The Blank

    Question When one party is ready & willing to discharge its obligations at the right

    time & place but the other party does not accept performance the contract is discharged

    by________.

    Correct Answer Tender

    Your Answer Tender

    Multiple Choice Single Answer

    Question Import policy of Government is updated in :-

    Correct Answer Once in a year

    Your Answer Once in a three year

    Multiple Choice Single Answer

    Question The process of procurement of raw material, wip, finished goods, jigs,

    fixtures and other tools and equipments which are required for the operation and

    maintenance of a manufacturing plant is known as

    Correct Answer Purchasing

    Your Answer Purchasing