master plan & eia for ip at mallavalli village, krishna
TRANSCRIPT
ANDHRA PRADESH INDUSTRIAL INFRASTRUCTURE
CORPORATION LIMITED
Prepared By
L&T INFRASTRUCTURE ENGINEERING LIMITED (FORMERLY KNOWN AS L&T-RAMBØLL CONSULTING ENGINEERS LIMITED)
C1162902
RP007, Rev 0
June 2018
Auto-mobile &
Engg
Food & Beverage
Agro based
Aero-space
Plastic
Executive Summary
MASTER PLAN & EIA FOR IP AT MALLAVALLI
VILLAGE, KRISHNA DISTRICT, ANDHRA
PRADESH
L&T Infrastructure Engineering Ltd. Client: Andhra Pradesh Industrial Infrastructure Corporation
Limited (APIIC)
Project: Master Planning and Detailed Engineering for IP at Mallavalli
Project No.:
C1162902
Title:
Executive Summary Document No.:
RP007
Rev.:
0 This document is the property of L&T Infrastructure Engineering Ltd. and must not be passed on to any person or body not authorised by us to receive it nor be copied or otherwise made use of either in full or in part by such person or body without our prior permission in writing.
File path: l:\roads\2016\c1162902 - mp and de for ip mallavalli\outputs\reports\007- draft eia\executive summary.docx
Notes:
1.
Revision Details:
0 21.06.2018 First Submission ALJ SAP CVS
Rev. Date Details Init. Sign. Init. Sign. Init. Sign.
Prepared Checked Approved
Master Planning and Detailed Engineering for IP at Mallavalli C1162902 Executive Summary RP007 rev. 0
Table of Contents Page i
TABLE OF CONTENTS
1 Introduction .....................................................................................................................................1
2 Project Site ......................................................................................................................................1
3 Need and Justification of the Project Development ...................................................................2
4 Project Benefits ..............................................................................................................................4
5 Project Description .........................................................................................................................4
5.1 Proposed Project ......................................................................................................................4 5.2 Land use planning .....................................................................................................................5 5.3 Site Master Plan ........................................................................................................................6 5.4 Economic Impact of the Industrial Park ....................................................................................6
6 Description of Environment ..........................................................................................................6
6.1 Terrestrial Environment .............................................................................................................6 6.2 Socio-economic Conditions ......................................................................................................8
7 Anticipated Environmental Impacts with Mitigation Measures .................................................8
8 Analysis of Alternatives .................................................................................................................9
9 Environmental Monitoring Programme ........................................................................................9
10 Additional studies ...........................................................................................................................9
10.1 Risk Analysis .............................................................................................................................9 10.2 Disaster Management Plan .......................................................................................................9 10.3 Traffic and Transportation Management Plan ....................................................................... 10 10.4 Social Impact Assessment ..................................................................................................... 10
11 Corporate Environment Responsibility (CER) .......................................................................... 10
12 Corporate Social Responsibility (CSR) ..................................................................................... 11
13 Environment Management Plan ................................................................................................. 11
13.1 Budgetary Estimate for Environmental Management ............................................................ 12
14 Conclusion ................................................................................................................................... 12
LIST OF FIGURES
Figure 2-1: Project Location Map .............................................................................................................2
LIST OF TABLES
Table 5-1: Focus Sectors for Investment Envisaged in the proposed industrial park ..............................4 Table 5-2: Salient Features of IP Mallavalli ..............................................................................................5 Table 5-3: Proposed Landuse Break up for Mallavalli Industrial Park .....................................................6
LIST OF APPENDICES
Appendix A: Conceptual Master Plan of IP Mallavalli
Master Planning and Detailed Engineering for IP at Mallavalli C1162902 Executive Summary RP007 rev. 0
1 Introduction Page 1
1 Introduction
Andhra Pradesh Industrial Infrastructure Corporation Limited (APIIC) which is a wholly
owned subsidiary of Government of Andhra Pradesh (GoAP) has a mandate to develop
industrial areas across Andhra Pradesh. As part of the mandate, APIIC has initiated the
development of a Model Industrial Park near Mallavali village, Bapulapadu Mandal in Krishna
District of Andhra Pradesh and to enhance the competitiveness of the project region by
Government of Andhra Pradesh (GoAP). To achieve the above objective, APIIC has thus
identified and acquired large land parcel for the development of industrial cluster.
Considering the proximity of the site to the new capital city of Andhra Pradesh, Amaravati,
APIIC intends to develop a Model Industrial Park at the Identified site.
APIIC propose to develop Model Industrial Park near Mallavalli in an area of 1165.73 acres
(~472 ha) acres on Walk to Work concept. Project site is located in Mallavalli Village,
Bapulapadu Mandal, Krishna District, Andhra Pradesh. Proposed development comes under
jurisdiction of AP Capital Regional Development Authority. Project also falls under the
Vishakhapatnam – Chennai Industrial Corridor promoted by Government of AP and Asian
Development Bank. The proposed project will pave way for rapid industrialisation in Krishna
District and Andhra Pradesh (A.P).
APIIC intends to provide world class eco system for manufacturing industries and service
oriented industries and proposes to develop infrastructure facilities for the model industrial
park. The infrastructure development being proposed includes water supply, water
distribution, internal roads, storm water drains, electrical distribution network, internal street
lighting, wastewater and waste management facilities and services buildings.
APIIC is already in possession of the land. The processing area includes industrial plots for
different manufacturing industries and service industry selected based on the market and
demand assessment study undertaken as part of master planning exercise.
2 Project Site
The project site is located in Mallavalli Village, Krishna District of A.P at 2.4 km west of
Mirjapuram. Nuzvid is the nearest town on north at 10 km while Vijayawada lies at a distance
of 40km on south-west. Geographical co-ordinates of the site are 16º 41’ 53.34” North
Latitude and 80º 54’ 9.60” East Longitude. The project location map is shown in Figure 2-1
and given as Figure FD0101. Exhibit 1 shows few site photographs.
View of Access Road from Mirjapuram Site View
Master Planning and Detailed Engineering for IP at Mallavalli C1162902 Executive Summary RP007 rev. 0
3 Need and Justification of the Project Development Page 2
Site View Site Fencing
Exhibit 1: Site Photographs
Figure 2-1: Project Location Map
3 Need and Justification of the Project Development
Below are some of the factors based on which there is an enormous need of developing the
industrial park at this strategic location.
The region around the project site is probably the most agriculturally intensive belt of the
state. The catchment area accounts for almost 40% of the food grain; 25% of the
horticulture; 30% of Poultry and milk; and 58% of the cotton production of the state.
The region accounts for almost 30% share of educational institutions and seat intake in
Andhra Pradesh. Vijayawada is the nearest city at 40 km which is the main trading centre of
South India with well-developed social and urban infrastructure. The area is comparatively
more industrially advanced compared to other parts of the state (catchment accounting for
20% share of the Industrial output of the state) and has large number of Engineering, Food
processing, Auto components, Pharmaceutical and Textile units around it.
Master Planning and Detailed Engineering for IP at Mallavalli C1162902 Executive Summary RP007 rev. 0
3 Need and Justification of the Project Development Page 3
The location has the potential to emerge as major multi model logistics hub in the region in
future catering to needs of 3 states viz: Andhra Pradesh, Telangana and Chhattisgarh given
its strategic location close to upcoming Machilipatnam port, Presence of National Road, Rail
network and Airport in the vicinity besides future development of Kolkotta-Vijayawada
dedicated freight corridor node close to the site.
On the basis of the market analysis, area strengths, competition and case studies of
successful various formats of planned industrial infrastructure formats, it has been proposed
to have as diverse range of activities in the zone as possible. Most of the successful
manufacturing zones in the world/country have diverse product mix and industry
concentrations. Sectors have also been evaluated for their overall synergy in the industrial
corridors planned in the broader Amravati Capital Region Urban Development Plan.
The following considerations have been taken while determining sectors for Mallavalli
industrial park. Some allowances have been made to also include some of the low overall
scoring areas which otherwise are attractive considering other strategic factors like state
focus and its long term economic and employment growth impact Some sub sectors have
been combined under broad generic category to mitigate the risk of having too narrowly
focused sectors.
Sectors like textile & apparels and pharmaceuticals, are high scoring attractive sectors
but have not been considered as separate sectors for promotion due to high competition
in the catchment. Under MSME category, these sectors were considered in order to
provide more diversity of products in the region.
Some of the subsectors have been combined together to fall under generic category to
mitigate the risk of too narrowly focused areas; for example, sea food, Poultry products
and beverages could find place in generic Food and Agro sector; Similarly Automobiles
and auto components sector will be treated as part of engineering goods while Strategic
electronic included in A&D sector for the purpose of demand assessment calculations.
Aerospace & Defense Sector also includes Strategic electronic as key component due to
its synergy with the sector and also state’s focus on both Electronic and Aerospace and
defence as thrust area’s for development, The presence of BEL in Machilipatnam can
also trigger growth of ancillary Strategic Electronic Units in the Proposed Park.
The focus in the zone is mostly on manufacturing units but due to the strategic locational
advantage of Mallavalli site, Logistics & Warehousing services sector will be of a high
priority area in the catchment and has to find place in the Park owing to its proximity to
many key proposed infrastructure projects like Dedicated Freight Corridor, East
Economic Corridor (VCIC), High speed Rail and National Water way – 4 and proximity to
Proposed Machilipatnam Port etc.,
Plastic based products sector has been considered for inclusion in the final sectors list for
Mallavalli Industrial Park even though scoring comparatively less. Plastic based articles
will have a high demand in the catchment due to its affinity with high priority areas like
Food & agro products, Automobiles, auto components, Electronic and Aerospace sector.
Also plastic is receiving state’s attention in lieu of Central Government’s Plastic Park
scheme and is currently much underpenetrated area in the state with production being
much less than its actual requirement thus making it attractive for investment. Being a
future high growth area and considering stakeholder interest this sector has especially
been considered.
Master Planning and Detailed Engineering for IP at Mallavalli C1162902 Executive Summary RP007 rev. 0
4 Project Benefits Page 4
4 Project Benefits
The development of the IP at Mallavalli is being envisaged by APIIC taking into consideration
the overall development of Industries in the state. Similar such initiatives are undertaken
across the state. The Nation, the State and the region will have impetuous benefits from such
development, such as:
Skill development and Training to the local population
Localizing the global/domestic value chain
Technology transfer
Foreign Direct Investment
Improved working condition
Shifting of manpower resources from low productivity to high productive activities
Augmentation of existing clusters
Diversifying the local industrial base
Shifting activities from unorganized to organized sector
Convergence of population and thereby enhanced local consumption and spending
Project development will also attract hotel business, banking sector, small eateries,
construction, transport and other supply services
Better quality of educational and medical facilities to the local people
Improved Local Infrastructure
Improved socio-economic conditions
o Health facilities
o Education Facilities
o Employment Opportunities
Increase in Per Capita Income
Revenue Generation
5 Project Description
5.1 Proposed Project
The Proposed Industrial Park of 1165.73 Acres comprises of industrial plots along with open
space/green belt, utilities, roads and commercial area. Engineering / Manufacturing,
Chemicals and Allied Chemicals, Herbal medicines, bio pharmaceuticals and Micro, Small
and Medium Enterprise (MSME) Cluster and logistics and warehousing zone are also part of
the industrial park. Focus sectors identified based on Country’s and region’s prima facie
strength for model industrial park at Mallavalli which are as follows:
Table 5-1: Focus Sectors for Investment Envisaged in the proposed industrial park
S. No Target sector list
1 Engineering / Manufacturing
Automobiles and Auto components
Electronic and Telecom Hardware: Components and equipment
Engineering Goods: Fabricated metal products, Industrial machinery and process control equipment,
Electrical machinery, consumer durables, light engineering and metal processing
Non-conventional energy products-Wind, solar, Hydro, Bio mass
Defense and Aerospace products and strategic electronics
Master Planning and Detailed Engineering for IP at Mallavalli C1162902 Executive Summary RP007 rev. 0
5 Project Description Page 5
Metallurgical: Basic Ferrous and non -ferrous metal products with capacity restrictions
Shipping Ancillaries
2 Micro, Small and Medium Enterprise
Food and Agro processing: Edible oil, Dairy, fruit and Vegetable processing, flowers, Grain mill products,
Sea Food and Meat Processing, etc.
Textiles: spinning mills, cotton and manmade fabrics and apparels; technical textiles, except Rayon
Plastic Products including blow molding, extrusion and injection molded parts
Leather Goods
Timber /Wood Products Furniture, sports goods, wood flooring etc.
Handicrafts mainly textile based
Gem and Jewellery including diamond cutting and jewellery
Nonmetallic Mineral products
Rubber products including Tires and tubes, hoses, auto components etc.
Paper, plastic products
FMCG including Beverages, personal care, Household care etc.
3 Herbal medicines, bio pharmaceuticals
4 Logistics
5.2 Land use planning
The entire development is of 1165.73 Acres is proposed to house various industries under
automobiles & engineering goods, aerospace, defence and strategic electronics, Micro,
Small and Medium Enterprise cluster and Logistics, warehousing zone along with green
space/belt, utilities, roads and commercial area etc. The salient features of IP Mallavalli are
given in Table 5-2 and shown in Appendix A.
Table 5-2: Salient Features of IP Mallavalli
S.
No. Item Description
1 Name Industrial Park at Mallavalli
2 Area 1165.73 Acres
3 Greenbelt/Green Area/
Open Space
145.83 Acres
4 Water Requirement The total water demand for the proposed Mallavalli industrial park
is estimated as 5.9 MLD (excluding one-time firefighting demand
of 0.6 ML) whereas the water infrastructure facilities such as bulk
water arrangement, water storage and treatment facility, pumping
infrastructure, etc. will be developed for 7 MLD capacity to cater
to the surrounding industrial developments of APIIC.
The water demand for the proposed industrial park will be met
from the Nuzvid Water Supply project. Allocation letter has been
obtained.
5 Wastewater (Effluent and
Domestic Wastewater)
Industrial Wastewater of 3.51 MLD and Domestic & Landscaping
Wastewater of 0.97 MLD. Individual industries will have own
treatment facilities with reuse/recycle option.
6 Wastewater Management STP of 1 MLD capacity with recycle/reuse will be developed.
Master Planning and Detailed Engineering for IP at Mallavalli C1162902 Executive Summary RP007 rev. 0
6 Description of Environment Page 6
S.
No. Item Description
7 Solid Waste Management Provision has been made in industrial park for temporary storage
of solid/ industrial wastes for 90 days. The municipal waste shall
be transported to the nearest municipal dumping site and the
industrial wastes to the TSDF located at Vishakhapatnam for
further treatment and disposal.
8 Power The total power demand for the proposed model industrial park is
estimated as 52.1 mVA. It is proposed to have captive 220/132
KV substation within the industrial park from nearby substation.
9 Environmental Aspects Storm Water Management
Air pollution Control Measures at all Member industries
Water Pollution Control Measures at all Member Industries.
Solid Waste Management (Both MSW and HW)
Fire Protection system as per Standards of National Fire
Protection Association (NFPA)/Tariff Advisory Committee
(TAC) of India.
5.3 Site Master Plan
The area breakup Area breakup for the industrial park is shown in Table 5-3.
Table 5-3: Proposed Landuse Break up for Mallavalli Industrial Park
S. No Landuse type Area in Acres % of Area
1 Industrial Plots 827.45 70.99
2 CFC- Amenities 28.23 2.42
3 CFC- Utilities 41.09 3.52
4 Green Best/Open Space/Power Corridor 145.83 12.51
5 Roads 123.13 10.56
5.4 Economic Impact of the Industrial Park
The total output from the Park is estimated at about Rs. 11,264 Crores when the park will be
fully commissioned by 2023. The anticipated exports from the park may be approximately
Rs. 3,270 Crores per year by accounting for almost 29% of the total output. The total
investment in processing zone is estimated at Rs. 5,120 Crores.
6 Description of Environment
Project Influence Area (PIA)/Study Area: An area covering 10 km radius from IP boundary
has been earmarked as study area for baseline terrestrial environmental surveys.
Study Period: The baseline terrestrial environmental surveys were carried out during winter
season (January to March) of 2018.
6.1 Terrestrial Environment
Site is undulating terrain with levels varying from 62 m to 112 m and is found sloping
towards the canal on the south and on the north-east.
Proposed IP site falls under Zone III (Moderate Risk Zone) as per IS 1893 (Part I) and No
flood zone as per Multi-Hazard map of AP.
Master Planning and Detailed Engineering for IP at Mallavalli C1162902 Executive Summary RP007 rev. 0
6 Description of Environment Page 7
The major land use classes observed in the buffer area are: Agricultural Land –
Plantation, two season crop and Kharif crop summing to 73% of total area
As per the Project site specific meteorological data, the predominant wind directions
observed were from South West (SW) followed by West South West (WSW) and South
(S)
Maximum concentrations of Sulphur Dioxide (SO2), Nitrogen Dioxide (NO2), Particulate
Matter (PM2.5), Particulate Matter (PM10), Carbon Monoxide (CO), Ozone (O3) and
Ammonia (NH3) are well within the National Ambient Air Quality Standards for Residential
areas at all monitoring locations during the study period. However Lead (Pb), Benzene
(C6H6), Benzo (a) Pyrene (BaP) – Particulate phase only Arsenic (As), Nickel (Ni) were
Below Detectable Limit (BDL) during the monitoring period at all the monitoring locations.
o PM10 ranged between 52.4 µg/m3 to 71.5 µg/m3. NAAQ stipulated standard for PM10 for
24 hr average is 100 µg/m3
o PM2.5 values varied from 23.3 µg/m3 to 33.8 µg/m3. NAAQ stipulated standard for PM2.5
for 24 hr average is 60 µg/m3
o SO2 ranged between 13.2 µg/m3 and 20.1 µg/m3. NAAQ stipulated standard for SO2
for 24 hr average is 80 µg/m3
o NO2 ranged between 15.8 µg/m3 to 23.6µg/m3. NAAQ stipulated standard for NO2 for
24 hr average is 80 µg/m3
o O3 ranged between 19.8 µg/m3 to 27.3 µg/m3. NAAQ stipulated standard for O3 for 8 hr
average is 100 µg/m3
o CO ranged between 0.1 mg/m3 to 0.7 mg/m3. NAAQ stipulated standard for CO for 8
hr average is 02 mg/m3
o NH3 ranged between 11.2 µg/m3 to 17.7 µg/m3. NAAQ stipulated standard for NH3 for
24 hr average is 400 µg/m3
Day equivalent noise levels (Ld) ranged between 47.24 dB(A) to 49.76 dB (A) and Night
equivalent noise levels (Ln) ranged between 37.26 dB(A) to 39.31 dB (A) for all the
locations
Groundwater samples are within the permissible limits specified for drinking water quality
standards as per IS: 10500 (2012), except Iron values which are exceeded the desirable
limits at all the locations in the PIA may be due to the geological condition of iron ore
formation in the district.
All the parameters for Surface water samples are within the limits specified for Class C,
Drinking water source after conventional treatment and disinfection as per ISI-IS: 2296-
1982.
Soil types are Sandy Clay loam, Sandy loam, loam and clay loam and the soil samples
are slightly alkaline in nature.
None of the plant species recorded either from the core area or Project influence area
belongs to the Rare/Endangered/Endemic/Threatened category.
Passerine and migratory birds had been observed in the general study area, but there
were no nesting grounds as such. They were only using the area as resting spots during
their migratory routes. There may be a network of power lines coming out from the IP.
Power lines are often known to be the main reason for bird collision and death. Power
lines shall be kept at a safe distances from sensitive bird habitats such as water bodies
and forest plantation areas in order to avoid bird mortalities due to collisions
Master Planning and Detailed Engineering for IP at Mallavalli C1162902 Executive Summary RP007 rev. 0
7 Anticipated Environmental Impacts with Mitigation Measures Page 8
6.2 Socio-economic Conditions
In the study area of 10.0 km covers 40 villages include tandas aka hamlets also in the 7
mandals are falling in two districts namely Krishna District in which there are five mandals
Musunuru, Nazividu, Bapulapadu, Agripalle, Gannavaram mandals and West Godavrai
District in which Peda Vegi and Pedapadu mandals falls.
In the study area, the population is 183799 of which males are 50.62% and females
49.37%. The sex ratio of the study area is 975 females over 1000 males of the total
population.
Total 0-6 population is 19064 which is 10.37%.
The literacy in the study area is 106436 which constitute to be 57.91% of the total
population of the study area.
The working population of the project is 98102 of which males are 57471 which constitute
to be 58.59% and females are 40631 which account to be 41.42%.
7 Anticipated Environmental Impacts with Mitigation Measures
Anticipated impacts on the environmental and social attributes, which are likely to arise due
to construction and operation of proposed project have been identified, predicted and
evaluated.
Out of 1165.73 acres of the Mallavalli IP area, APIIC is in the possession of 1127.65
acres of land, rest 38.08 acres is yet to be acquired which is a patta land. The possession
certificate is obtained and the balance land will be acquired in compliance with the
prevailing laws/acts.
The Project site is comprised predominantly with agriculture plantation, dense scrub land
and open scrub land. The primary survey reveals that the major part of the project area is
mainly consists of scattered and thick vegetation i.e. Prosopis juliflora, Borassus
flabellifer, mango orchards etc. Planning for the proposed development is carried out
based on the concept of zoning.
Natural drains are observed in the site. The development shall be carried out in such a
way to ensure proper drainage by providing surface drainage systems including storm
water network, etc.
Individual Industries will have their own effluent treatment facilities in their premises to
treat the effluent with ZLD options and STP will be developed in the I.P.
The water demand for the proposed industrial park will be met from the Nuzvid Water
Supply project. Allocation letter has been obtained.
The water requirement during the construction phase will be met through the bore wells
within the site till the laying of the pipeline from Nuzvid municipal water scheme
Jakkampudi tapping point to the site. Measures including Rain Water Harvesting are
proposed as a part of development to improve the ground water scenario
Construction camps will be provided with self-sufficient infrastructure to minimise
impact/strain on the existing infrastructure.
All the necessary Air pollution control measures will be adopted by member industries to
control the fugitive emissions of VoCs, particulates, organic vapours etc., shall be
followed.
The impact on air environment was studied through air quality modelling studies. The 1st
highest 24 Hour average and Annual Average resultant concentrations of NO2, PM10,
PM2.5 and SO2 at all receptor locations are found to be well within the National Ambient
Air Quality Standards (NAAQS), 2009.
Master Planning and Detailed Engineering for IP at Mallavalli C1162902 Executive Summary RP007 rev. 0
8 Analysis of Alternatives Page 9
The solid waste generated during construction phase may impact soil quality, water
quality and public health if not regulated properly. Construction waste will be re-used
within plant site for filling of low lying areas. Other wastes which can be re-cycled will be
sold and hazardous waste shall be stored as per prescribed safety norms and disposed
through approved APPCB vendors. Also, strict guidelines will be put in place in order to
manage the solid waste generation during the operational phase of the development.
8 Analysis of Alternatives
APIIC has identified large land parcel to promote the industrial development in the state of
Andhra Pradesh. Out of which 1165.73 acres (472 ha) of identified land parcel near Mallavalli
Village, Krishna District of A.P has been proposed development of industrial park. Site was
selected considering the important features such as Strategic location, demand, connectivity,
well qualified man power, water and power availability, No R&R, no Sensitive area etc.,
making the site suitable for the development. The site meets the requirement of all critical
factors that are important for success of development of Model Industrial Park in the state
and could be a pre-eminent location.
9 Environmental Monitoring Programme
Environmental monitoring programme has been formulated for the environmental attributes
(air, water, noise, and soil) and the same will be implemented. The effective implementation
and close supervision of the environmental management to mitigate the environmental
impacts, which are likely to arise due to the construction and operation phases of the project
could be achieved through a suitable institutional mechanism.
10 Additional studies
10.1 Risk Analysis
Preliminary Risk analysis study was carried out to assess risks associated with the
construction and operation of the proposed IP. Member industries or units coming up in the
I.P has to carry out risk analysis by considering the hazards associated with handling of
chemicals based on nature of process and inventory. A systematic risk analysis will help in
identification of the hazards and associated risk. The risk assessment thus carried out also
provides inputs for formulating the onsite Disaster Management Plan (DMP).
The Risk Analysis can be broadly divided into three basic steps.
Hazard Identification
Failure Frequency
Consequence or Effect and Damage calculations
10.2 Disaster Management Plan
The Disaster Management Plan (DMP) is aimed to ensure safety of life, protection of
environment, protection of installation, restoration of production and salvage operations in
this same order of priorities. For effective implementation of DMP, it should be widely
circulated and a personnel training is to be provided through rehearsals/drills. To tackle the
Master Planning and Detailed Engineering for IP at Mallavalli C1162902 Executive Summary RP007 rev. 0
11 Corporate Environment Responsibility (CER) Page 10
consequences of a major emergency inside the industry or immediate vicinity of the industry,
a DMP has to be formulated.
A framework for DMP was prepared to minimise damages in the event of a disaster. An On-
Site Emergency Preparedness Plan and Off-Site Emergency Preparedness Plan were
broadly prepared to deal with emergencies and prevent disasters.
An institutional framework with clear assignment of roles and responsibilities was broadly
prepared with which location of Emergency Control Centre and Assembly Points will be
identified. Communication system and alarm systems for effective communication in the
event of a disaster are broadly identified. DMP for natural hazards such as cyclones was
broadly prepared. Mutual aid scheme, composition of District Level Emergency Committee
and aspects relating to community involvement for dealing with off-site disasters were
broadly prepared.
10.3 Traffic and Transportation Management Plan
The traffic survey and forecast carried out for Mallavalli Industrial project to understand the
current traffic pattern and forecast projected in future. From I.P at Mallavalli, it is expected to
generate 24192 PCU/day.
10.4 Social Impact Assessment
This assessment is specifically addressing the potential impacts which will be generated as a
result of proposed development.
Land is under possession of APIIC. No R&R is envisaged.
The impact on nearby settlements during construction phase will be due to air pollution
and the noise generating activities. However, the activities are limited to the construction
phase and will cease upon completion of the construction. Necessary mitigation
measures are proposed to be adopted.
Construction of IP requires large work force. To ensure that there is no strain on the
existing infrastructure, worker camps will be self-sufficient and would not relay on local
resource.
During the operation phase the Industrial Park is expected to bring a direct employment
of 16,700 personnel. Indirect employment is also expected in different areas. This
includes Skilled (Engineers and other officials), semiskilled and unskilled labour. The
local employment could be higher for unskilled labour due to the availability of this
category at local level
11 Corporate Environment Responsibility (CER)
As a responsible company towards the conservation, restoration and redevelopment of
ecosystem and environmental conditions in the vicinity of the IP, APIIC shall implement the
Corporate Environmental Responsibility (CER) activities. The following activities can be
considered under CER:
Social Enterprise and Livelihood Development (Agriculture/ Vocational Training for skill
development/Development of Mahila Mandals/SHG groups)
Natural Resources Management (Watershed/Aquifer Rehabilitation/ Rainwater
Harvesting / Desilting of existing water tanks)
Master Planning and Detailed Engineering for IP at Mallavalli C1162902 Executive Summary RP007 rev. 0
12 Corporate Social Responsibility (CSR) Page 11
Infrastructure Development (Village Internal Roads/Drainage/Sewerage/Street
lights/Water Supply/Community Infrastructure/School Infrastructure/Hospital/ Sanitation
Infrastructures)
Human Capital Development (Education/ Health/ Potable drinking water through supply
of RO water systems/Sanitation and Latrine Facility/Education/Girl child education)
CER for the proposed project will fall under the Greenfield category of MoEF&CC Office
memorandum dated vide May 01,2018, 1.5% of project cost need to be invested as capital
investment i.e., Rs.6.09 Crores.
12 Corporate Social Responsibility (CSR)
The industries coming up in the I.P at Mallavalli has to follow the Company’s Act, 2013
(Schedule VII of the Companies Act, 2013). As per the same, the act encourages companies
to spend at least 2% of their average net profit in the previous three years on CSR activities.
As a responsible company towards the development of social conditions in the vicinity of the
IP, APIIC shall implement the Corporate Social Responsibility (CSR) activities. This shall be
based on the gap assessment in and around (up to 10.0 km radius from Project site) villages.
Preliminary studies show that following area may be considered for improvement:
13 Environment Management Plan
The main objectives of Environmental Management are to:
Identify key environmental issues envisaged to be encountered during construction and
operation phases of the project.
Provide guidelines for appropriate mitigation measures
Establish systems and procedures for implementing mitigation measures
Ensure the mitigation measures are being implemented
Monitor the effectiveness of mitigation measures
Institutional framework includes the responsibilities for environment management as well
as responsibility for implementing environmental measures
Take necessary prompt action when unforeseen impacts occur
Based on the above objectives in mind, the following specific environmental management
plan/measures are provided
Administrative and Technical Setup for Environmental Management
Greenbelt development
Solar power harnessing
Rainwater harvesting
Occupational health and safety: Occupational health & safety needs attention both during
construction, erection, operation and maintenance phases.
Institutional arrangements/framework for environmental management.
The effective implementation and close supervision of the environmental management to
mitigate the environmental impacts, which are likely to arise due to the construction and
operational phases of the IP could be achieved through a suitable institutional mechanism.
The proposed institutional mechanism recommended for the implementation of the mitigation
measures is presented in EIA report.
Master Planning and Detailed Engineering for IP at Mallavalli C1162902 Executive Summary RP007 rev. 0
14 Conclusion Page 12
13.1 Budgetary Estimate for Environmental Management
The budgetary estimate (Capital Cost) for Environmental Management is INR 137 Million
(INR 13.7 Crores) and the annual recurring cost is INR 13 Million (INR 1.3 Crores).
14 Conclusion
In order to meet the growing needs of the industrial sector, it is necessary to identify new
sites for industrial development. On the basis of the market analysis, area strengths and
likely investment proposals in pipeline, it has been proposed to have all high market potential
and high growth areas. Proposed development will not envisage any resettlement.
Typically any developmental projects also trigger a set of environmental and social impacts.
These environmental and social impacts (proposed development will not envisage any
resettlement) due to infrastructure development projects occur in different forms. An
Environmental Impact Assessment has been carried out to study the potential environmental
and social impacts due to the proposed IP. Potential environmental and social impacts due to
the proposed development on environment attributes like air quality, noise, water quality, soil,
flora, socio-economic, etc. have been assessed as part of this EIA study. Appropriate
mitigation measures to help minimize/avoid impacts from the development have been
recommended. The measures include avoidance measures, mitigation measures and
environmental enhancement measures.
The proposed IP will be developed for attracting the major investors and strategically located.
The vision is to develop the IP with integrated well planned infrastructure and an efficient
management structure which shall ensure continual global competitiveness. The proposed IP
shall emerge as a benchmark in the State and the Country both in terms of market relevance
and in terms of environmental sustainability.
B
1
3
-
A
c
.
0
.
2
2
18
M
R
oW
18
M
R
oW
18 M RoW 18 M RoW
18
M
R
oW
18
M
R
oW
18
M
R
oW
Ac.2.08
1.34 AC
1.33 AC
CFC-2
30 M
R
oW
30 M
R
oW
18 M RoW 18 M RoW18 M RoW
12 M
R
oW
12
M
R
oW
12 M
R
oW
18 M
R
oW
12 M
R
oW
18 M
R
oW
12 M
R
oW
18 M RoW
CFC-1
E
X
I
S
T
.
G
O
L
L
A
P
A
L
L
I
R
O
A
D
E
X
I
S
T
.
G
O
L
L
A
P
A
L
L
I
R
O
A
D
CANAL
TO MALLAVALLI
UTILITY - POWER
ELECTRIC SUBSTATION
Entry/Exit
TO MALLAVALLI
PROPOSED EXTERNAL
CONNECTOR TO
10.00Ac.
NUZIVIDU ~ 1 KM
30m RoW
30
m R
oW
30m RoW
30
m R
oW
30m RoW
18m RoW
30
m R
oW
30
m R
oW
16
m R
oW
Entry/Exit
TO ANATASAGARAM
Open Space-13
N
3.5 Ac.
(~13.5KM)
TO NH 16
SH 14
(HANUMAN JN.)
Mirjapuram
45 m Green Field Road
TO NUZIVIDU
~3.7 km
15 M
B
UF
FE
R
1
5
M
B
U
F
F
E
R
0 km 0.5 km
Scale
E
x
i
s
t
i
n
g
H
T
L
i
n
e
1
0
m
P
a
t
h
w
a
y
1
0
m
P
a
t
h
w
a
y
1
0
m
P
a
t
h
w
a
y
E
x
i
s
t
i
n
g
H
T
L
i
n
e
5.40Acs.
30
m R
oW
15 m Green Buffer
5
8
12
13
ANDHRA PRADESH INDUSTRIAL INFRASTRUCTURE CORPORATION
TO N
H 16
TO NUZIVIDU
Entry/Exit
MEGA FOOD PARK ~100 AC.
MODEL INDUSTRIAL PARK~1165.73 AC.
AS PER G.O.MS. NO : 456LEFT FOR COMMUNITY
PURPOSE ~100 AC.
Mirjapuram
~
3
.7
k
m
SH 14
(~9
KM)
(HAN
UM
AN JN
.)
4
5
m
G
re
e
n
-
(~13.5KM)
F
ie
ld
R
o
a
d
KEY MAP
Note: Patta Land of 38.08 Acres is existing within the Mallavalli Model Industrial Park.
OS-24
4.67Ac
13.78 Ac.
Open space-2
10.05 Ac.
9.66 Ac.
2.24 Ac.
2.24 Ac.
OS.-9- 1.51Acs. OS-10-3.08 Acs.
E
X
I
S
T
.
G
O
L
L
A
P
A
L
L
I
R
O
A
D
E
X
I
S
T
.
G
O
L
L
A
P
A
L
L
I
R
O
A
D
2.00Ac
CFC-5
CFC-6
0
.
7
0
A
c
18m RoW
18
M
R
oW
0
.
4
0
A
c
12
M
R
oW
3.78 Acs.
1
.
2
0
A
c
0.16Ac
0.13Ac
0.37Ac
0.21Ac
0.13Ac
0.88Ac
POWER CORRIDOR ( 12 m) Ac. 2.54 Cents
0
.
7
4
A
c
0
.
4
3
A
c
0.88Ac
0.46Ac
O
P
E
N
S
P
A
C
E
-
7
OPEN SPACE-4
OPEN SPACE-8
1
0
m
P
a
t
h
w
a
y
Proposed 24m Wide Road
45m RoW
10
18
9
23
PLOTTED AREA
ROADS
OPEN SPACE, POWER CORRIDOR
: Ac. 1165.73 Cents
TOTAL EXTENT OF LAYOUT (Excluding of water body)
1.
2.
3.
4.
LAYOUT BOUNDARY
ROADS
GREEN BELT/O.S/ POWER CORRIDOR
CFC - AMENITIES
REFERENCE :
L.P NO: 05/2017/VJA
CFC-2
UTILITY - WATER
SUPPLY AND
DISTRIBUTION WATER
TREATMENT PLANT
12
m R
oW
11000
10250
5750
300020502050 4000
4000
4000
2250
2250
3750
750750
750
1750
1750
1250
1250
1250
1250
1250
1250
1250
1250
1250
2250
2500
1750
5242
2750
504
501
510
507
503
763
504
512
507
502
519
545
1415
501
501
501
501
501
501
501
501 501
501 501
501 501
501 501
501501
501
501
501
501
501 501
501
501
501501
501
501 501
501
501
501501
501501
501
501
501 501
501 501
501 501
501 501
501 501
10021002
1406
10250
10001000
2045
1500
1000
1000
1000
3235
3750
3500 3500
3500 3500
4052
4052
3250 3250
2000
2123
2000
20002000
20002000
20002000
2000
2000
5750
4016
4257
2754
25062506
2506 2506
2506
2506
1500
15001500
2250
2250
3002
8008
6014
3752
1875
1875
1000
4000 4005
4005
1002
1002
1002
1002
18
M
R
oW
0.16Ac
2250
2250
2771
4714
0.43Ac
1750
1
0
m
P
a
t
h
w
a
y
1
0
m
P
a
t
h
w
a
y
12
M
R
oW
12
M
R
oW
12
M
R
oW
18
M
R
oW
18
M
R
oW
0.63Ac
0.11Ac
OS-25
0
.
4
9
A
c
500
500
500
500
500
500
500
500
500
500
500
750
500
500
500
500
500
725
500
500
500
500
500
500
500
500
12
M
R
oW
750
500
725
0.55 Ac
500
12
M
R
oW
1750
1750
1750
1500
1250 1250 1250 1250
1500
3000
1250 1250
1250 1250
1000 1000
1000 1000
1000 1000
1000
1000
651500500500500
500
500
500500
500500
500500
500500
500500
500500
500500
500
500
500
500
500500
500500
500500
500
500
500
500
750
2000
750 940
1250
1250
750
750 750
1475
CFC-3
0.35Ac
0.20Ac
1500
1500
1500
1500
1500
125012501250
1250
2250
1000
1000
1000
1000
1000
1000
1283
890
1250
12501250
1250
1250
1250
1250
1012
4264
0.62Ac
0.33Ac
11
12 M RoW
12
M
R
oW
12
M
R
oW
12
M
R
oW
12
M
R
oW
16510
14950
10685
501
708
1172
501
501 501
501 501
501 501
501 501
501 501
501 501
501 501
501 501
501 501
501 501
501 501
501 501
501
708
501 501
501 501
501 501
501 501
501 501
501 501
501 501
501 501
501 501
501 501
501 501
501 501
501 501
501 704
501
501
3039
1751
1751
1751
1751
2250
2250
1654
1654
4254
1353
1000
1003 1003 1003 1028
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
750
750
750
750
750
750
750
750
750
750
1265
500
0.20Ac
1250
2502
2503
2442
1250
1250
1250
1250
OS-17
2.05Ac
12 M
R
oW
12 M RoW
12
M
R
oW
500 500
500 500
500 500
500 500
500 500
500 500
500 500
500 500
502502
1503
502502
502502
502502
502502
502502
502502
502502
502502
502502
502502
502502
502502
502502
573
573
502502
17531753
17531753
502502
502502
502502
750
750
750
502
1000
1503
1503
1503
1503
1000 1000
1000
1000
18
M
R
oW
12
M
R
oW
12
M
R
oW
12
M
R
oW
18
m R
oW
18
m R
oW
504 504
514514
502
819
502
18
m R
oW
18
m R
oW
18
m R
oW
2.00 Ac.
2.49 Ac.
2.52 Ac.
751
998
998
502
502502
502
502
502502
502502
502502
502502
502502
502502
502502
502502
502
502
502
502
502502
502502
502502
502
502 502
502 502
502 502
502 502
502 502
502 502
502 502
502 502
502502
504 504
504 504
504 504
504 504
504 504
504 504
504 504
504 504
504
504
501 501
501
501
501 501
501 501
501 501
501 501
501 501
501 501
501
501
OPEN SPACE-18
Ac. 4.43
OPEN SPACE-19
1750
1750
17501750
760
760760
596
596
752752
752752
752752
752752
752752
752
752
752752
752752
752752
752752
752752
752752
752752
751
751751
751751
751751
751751
501 501
501 501
1503
1503
15031503
15031503
1503
1503
12531253
12531253
12531253
Ac. 1.54
(6249 SQ.M)
Ac. 2.22
(6262 SQ.M)
12
M
R
oW
16
m R
oW
24m RoW
13.15 Acs.
Open space-11
502502
576576
1754
1625
1625
1501
750
750
2260
12 M RoW
503503
503503
503503
503503
503503
503503
12511251
10071007
0.52
1.00 Ac.
1.08 Ac.
501
501
501
501
501
501
501
501
501
501
501
501
466
Ac. 6.63
OPEN SPACE-3
503
503
503
503
503503
503
503
503
503
503
503
503
503
503503
503503
503503
503503
503503
503503
503503
503
503
503
503
503
503
503
503
503
503
503
503
503503
503503
503503
503503
503503
503 503
1952
3752
750 750
491
500 500
501
501
501
501
501
501
501
501
690
690
1008
1008
1008
2321
3752
3752
1640
663
OS-15
Ac.2.64
1
3
6
7
17
154.50
11
8.93
1
8
9
.
3
7
228
.4
4
CFC-4
UTILITY
ADMINISTRATIVE BUILDING
AND TRAINING CENTER
AC. 17.26 Cents
5.00 Ac.
5.00 Ac.
5.00 Ac.
4.70 Ac.
16
BULK LAND-2
Ac. 7.73
Ac. 18.67
OPEN SPACE-14
AC. 25.55 Cents
OPEN SPACE-1
AC. 19.55 Cents
2.01Ac
OPEN SPACE-5
OS-6
CFC-3
UTILITY
STP & SUB STATION
Ac. 23.76 Cents
OS-20
AC. 2.40
OS-21
AC. 0.86
OS-23
AC. 1.97
OS-27
OS-30
OS-32
OS-29
OS-28
OS-33
OS-34
OS-36
OS-37
OS-35
OS-26
CFC-4
10/6
10/5
10/4
10/3
10/2
10/1
10/7
10/8
10/9
10/10
10/11
10/12
10/13
10/14
10/15
10/16
10/17
10/18
10/19
10/20
10/21
10/22
10/23
10/24
10/25
10/26
10/27
10/28
10/29
10/30
10/31
10/32
10/33
10/34
10/35
10/36
10/37
10/38
10/39
10/4010/41
10/42
10/44
10/45
10/46
10/82
10/81
10/47
10/48
10/49
10/80
10/79
10/78
10/50
10/77
10/51
10/76
10/52
10/75
10/53
10/74
10/54
10/55
10/56
10/57
10/58
10/59
10/60
10/61
10/62
10/64
10/65
10/66
10/67
10/68
10/69
10/70
10/71
10/72
10/73
10/83
10/84
10/85
10/86
10/87
10/88
10/89
10/90
10/99
10/91
10/98
10/92
10/97
10/93
10/96
10/94
10/95
10/102
10/110
10/103
10/109
10/104
10/108
10/105
10/107
10/106
10/43
10/63
10/100
10/101
18m RoW
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
501
752
1729
501
501
501
501
472 472
501
501
501
501
501
501
501
501
501
472
472
3953
2003
1537
1537
752
752
752
752
752
711
1001 1001
2000
1250 1250 1250 1250 1250 1003 1003
1047
11/1
11/2
11/3
11/4
11/5
11/6
11/7
11/8
11/9
11/10
11/11
11/12
11/13
11/14
11/15
11/16
11/17
11/18
11/19
11/20
11/21
11/22
11/23
11/24
11/25
11/26
11/27
11/28
11/42
11/41
11/40
11/39
11/38
11/37
11/36
11/35
11/34
11/33
11/32
11/31
11/30
11/29
11/43
11/44
11/45
11/46
11/47
11/48
11/49
11/50
11/51
11/52
11/53
11/54
11/55
11/56
11/67
11/66
11/65
11/64
11/63
11/62
11/61
11/60
11/59
11/58
11/57
752
752
752
752
11/69
11/70
11/71
11/72
11/73
11/68
11/74
11/75
11/76
11/7711/78
11/7911/80 11/81
11/82
11/83 11/84
:(-) Ac. 38.08 Cents
DEDUCT PRIVATE LAND
: Ac. 1127.65 CentsNET LAYOUT AREA
Ac. 4.00
(16510 SQ.M)
Ac. 1.06
(4287 SQ.M)
4443
5204
2003
2003
8824
8314
2746
9/1 9/2 9/3 9/4
9/5
9/10
9/17
9/18
9/19
9/20
9/21
1000
9/22
9/23
9/30
9/31
9/32
9/33
9/34
9/36
9/35
9/37
9/38
501
9/51
9/52
9/65
9/66
9/67
9/81
9/82
9/96
9/97
9/98
9/99
9/100
9/101
9/102
9/114
9/115
9/131
9/132
9/1359/136
9/137
9/138
9/139
Ac. 6.48
(26239 SQ.M)
Ac. 2.39
(9670 SQ.M)
Ac. 1.87
(7570 SQ.M)
6007
3029
Ac. 1.54
(6249 SQ.M)
1000
1000
1000
10001000
0.70Ac
OS-31
1044
1500
500
500
501
833
Ac. 0.26
Ac. 0.26
Ac. 0.53
Ac. 0.35
Ac. 0.35
Ac. 0.35
Ac. 0.35
Ac. 0.35
Ac. 0.35
Ac. 0.35
Ac. 0.34
2528
Ac. 0.43
Ac. 0.43
475 475 475 518
1775
1609
1443
1276
1109
947
715
738
CFC-1
SOLID WASTE
200420042004162016201620162016202488
2707
1747
17/1 17/2
17/3
17/6
17/7
17/817/9
17/10
17/11
17/15
17/1617/17
17/1817/19
17/20
17/25
17/26 17/27 17/28
17/29
17/34
17/3517/36 17/37
17/38
17/39
500
17/40
500
17/41
17/42
17/46
17/47
17/68
17/55
17/56
17/63
17/64
17/69
17/70
17/78
17/79
17/85
17/86
17/91
17/92
17/100
18/1
18/2
18/6
18/7
18/8
18/9
18/10
18/11
18/12
18/14
18/15
18/16
18/1718/18
18/19
18/22
18/23
18/24
18/25
18/26
18/27
18/28
18/29
18/30
18/34
18/35
18/36
18/37
18/41
18/42
18/43
18/45
18/4618/47
18/48
18/51
18/52 18/53
18/54
18/56
18/57
18/61
18/62
18/64 18/65
18/67
18/68
18/69
18/72
18/73
18/74
18/75
18/80
18/81
18/86
18/87
18/93
18/94
18/100
18/101
18/102
18/103
18/104 18/105
18/106
18/107
18/108
18/109
18/110
18/116
18/117
18/118
18/119
18/120
18/121
18/122
18/123
18/124
18/125
18/126
18/127
18/128
760
18/129
18/130
18/131
18/132
18/133
18/134
18/140
18/151
18/152
18/161
18/162
18/170
18/17418/175
18/180
18/187
18/188
18/197
18/198
18/200
18/210
18/215
18/216
18/226
18/227
18/243
18/230
18/240
18/244
18/250
18/260
18/261
18/270
18/271
18/272
2
4
Ac. 25.00 Cents
Ac.10.10
Ac.15.10 Cents
12/6
12/3
12/4
12/5
12/1
12/2
14/1
14/2
15/1 15/2 15/3 15/4 15/5 15/6 15/7 15/8 15/9
19/1
19/419/5
19/8
19/9
19/10
19/11
19/12
19/13
20/1
20/2
20/3
20/4
20/5
19
20
21
21/1
21/2
21/3
21/4
21/5
21/6
22
22/1
22/822/9
22/16
23/1
23/8
23/9
23/10
23/11
23/12
23/19
23/20
23/26 23/27
23/33
23/34
23/39
23/40
23/44
23/45
23/5823/59
23/72
Ac. 0.86
2424/1
24/2
24/3
24/4
24/5
24/6
24/7
24/8
24/924/10
24/11 24/12
25
25/1
25/2
25/3
OS-12
1729
OS-16
OS-18
OS-22
AC. 0.21
POWER CORRIDOR ( 12 m) Ac. 7.87 Cents.
15M
W
ID
E B
UF
FE
R-1 A
c. 2.91
1
5
M
B
2
-
A
c
.
0
.
2
6
15M B 3- Ac. 0
.44
1
5
M
B
4
-
A
c
.
1
.
1
2
1
5
M
W
ID
E
B
U
F
F
E
R
6
- A
c
. 7
.8
4
15M
B
7- A
c. 2.33
1
0
M
B
1
0
-
A
c
.
0
.
6
2
1
0
M
B
1
1
-
A
c
.
0
.
4
6
B
1
2
-
A
c
.
0
.
1
10M WIDE BUFFER14- Ac. 1.07
1
0
M
W
I
D
E
B
U
F
F
E
R
1
5
-
A
c
.
0
.
6
0
1
0
M
W
ID
E
B
U
F
F
E
R
1
6
-
A
c
. 0
.4
7
15M B 18- Ac. 0.99
15M
B
19- A
c. 0.61
15M
B
20- A
c. 0.50
CFC - UTILITIES
TOTAL
5.
750
10M
W
ID
E B
UF
FE
R17- A
c. 0.51
1
0
M
B
-
9
-
A
c
.
0
.
5
7
1
0
M
B
-
8
-
A
c
.
0
.
4
7
18
m R
oW
5m wide buffer-5 AC. 0.34
2.30 Ac.
WATER BUFFER AND 15/10M BUFFER
CFC - AMENITIES
Ac. 81.01 Cents
BULK LAND-1
Ac. 283.08 Cents
750 750
1032
2777
1959
1307
1125
1006
1082
2988
1703
687
664
523
1483
26
26/16
26/15
26/17
26/18
26/19
26/2026/21
26/22
26/23
26/24
26/25
26/26
26/27
26/28
26/29
2136
26/30
26/31
310
27
CFC - UTILITY
28
29
18/339
18 M RoW
18 M RoW
501501
501 501
501 501
501 501
501 501
501 501
477477
26/1
26/726/8
26/14
18/278
18/279
18/280
18/28818/287
18/296
18/298
18/310
18/32018/303
18/302
18/297
18/301
18/321
18/338
18/299
18/300
18/31118/312
18/329
18/330
754
689708 801
735
783
985
10/111
30
18/340
26/32
70.98%
Ac. 123.13 Cents 10.56%
Ac. 145.83Cents 12.50%
Ac. 827.45 Cents
Ac.41.09 Cents3.64%
Ac. 1165.73 Cents 100%
Ac.28.23 Cents2.50%
APPENDIX A - CONCEPTUAL MASTER PLAN
L:\R
oad
s\2016\C
1162902 - M
P an
d D
E fo
r IP
M
allavalli\D
raw
in
gs\R
ep
ort D
wg
s\09-D
raft EIA
\FD
0202-M
allavalli C
MP
.d
wg
, 22-06-2018 04:20:27 P
M, D
WG
To
P
DF.p
c3