Massachusetts Water Resources Authority

Mechanical ImprovementsBiosolids Processing Facility

Contract 7153

June 20, 2018

Page 3: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

• Construction completed in 1991

• Operated by New England Fertilizer Company (NEFCo)

• Process an average of 100 Dry Tons Per Day/Total Suspended Solids

3

Biosolids Processing Facility (Background)

Page 4: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Scope: Replace the following:

• Nine of twelve Separator Conveyors• Two Dust Collection Systems• Dome Cover Braces (four storage tanks)• Gas Boiler • Nitrogen Purge Generator System• Air Compressor System

4

Contract 7153 Summary

Page 5: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

5

Process Overview

Page 6: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

6

Separator Conveyor

Page 7: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

7

Dust Collector System

Dust Collectors

Page 8: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

8

7153-Scope of Work

Sludge Tank Roof Cover(braces under roof cover)

Gas Boiler

Page 9: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

9

7153-Scope of Work

Nitrogen Purge Generator (fire suppression system)

Air Compressor System

Page 10: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

• Contractor: Daniel O’Connell’s Sons, Inc.

• Contract Price: $2,700,000 (+15% Design/CA fee)

• Contract Duration: 420 days

10

Contract 7153 Summary

Page 11: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank
Page 12: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Massachusetts Water Resources Authority

Remote Headworks and Deer Island Shafts StudyContract 7237

June 20, 2018

Page 13: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

13

Contract 7237 Shafts Location Plan and Scope of Work

SCOPE OF WORK

• Visual inspection, probing and hammer sounding of 7 shafts and 3 connecting structures and effluent channels

• Concrete cores taken from 7 shafts for lab testing

• Ventilation evaluation• Corrosivity analysis• Measurement of actual shaft diameters

Page 14: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

14

Ward Street, Columbus Park and Chelsea Creek Headworks

Page 15: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

15

Ward Street, Columbus Park and Chelsea Creek Headworks

Doorway from Connecting Structure into Shaft at Chelsea Creek Headworks

Page 16: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

16

Ward Street, Columbus Park and Chelsea Creek Headworks

Deteriorated Concrete in Shaft at Chelsea Creek Headworks

Page 17: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

17

Ward Street, Columbus Park and Chelsea Creek Headworks

Top of Effluent Shaft at Columbus Park Headworks

Page 18: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

18

Nut Island Headworks Shaft

South System Shaft at Nut Island Headworks

Page 19: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

19

Deer Island Treatment Facility Shafts

Shaft “C” Shaft “No. 1”

Page 20: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

• Two proposals were received on May 21, 2018

Arcadis U.S., Inc. $1,194,580 2,334 hoursMott MacDonald, LLC $1,371,788 4,856 hoursEngineer’s Estimate $802,010 3,878 hours

• Contract Start: July 2018

• Duration: 10 Months

20

Contract 7237 Procurement

Page 21: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank
Page 22: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Massachusetts Water Resources Authority

Chelsea Creek Headworks UpgradeContract 7161 - Change Order 14

June 20, 2018

Page 23: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Chelsea Creek Headworks: Exterior Walls As Found

23

Page 24: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Chelsea Creek Headworks: Masonry Repairs

24

Page 25: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Chelsea Creek Headworks: Masonry Repairs

25

Page 26: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Chelsea Creek Headworks: Masonry Repairs

26

Page 27: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Chelsea Creek Headworks: Masonry Repairs

27

Page 28: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Chelsea Creek Headworks: Masonry Repairs

28

Page 29: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Chelsea Creek Headworks: Masonry Repairs

29

Page 30: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Chelsea Creek Headworks: Temporary Roofing

30

Page 31: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Chelsea Creek Headworks: New 480V Electrical Service

31

Page 32: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Chelsea Creek Headworks: New Exterior Siding

32

Page 33: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank
Page 34: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Massachusetts Water Resources Authority

Marlborough Maintenance FacilityConract 6650B, Change Order 10

June 20, 2018

Page 35: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Pre

Building Entrance

Current

Page 36: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Silo Ash Silos – Converted to Covered Storage

Soda Ash Storage Covered Storage

Page 37: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

CO2 Tanks Removed – Future Parking Area

Page 38: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

CO2 Room – Converted to Plumbing Shop

Page 39: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Fluoride Room Converted to SCADA Room

Page 40: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Portion of Pump Room Converted to Mechanical Shop

Page 41: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Portion of Pump Room Converted to Electric Shop

Page 42: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Mechanical Equipment Room Updated

Page 43: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Portion of Mechanical Equipment Room Now Break Room

Page 44: Massachusetts Water Resources Authority · Contract 7153 Summary. 5 Process Overview. 6 Separator Conveyor. 7 Dust Collector System Dust Collectors. 8 7153-Scope of Work Sludge Tank

Change Order No. 10 – Concrete Curbing

• Original Design in 2007 • Part of three Projects• Section of Concrete Curb Deemed to

be in Good Condition now in need of replacement

• Deteriorating Condition - Unforeseen• Cost of $29,346