market rule and procedure changes in response to summer 2001 period in new england
DESCRIPTION
Agenda Item #5 1/15&16/02 MC Mtg. Market Rule and Procedure Changes in Response to Summer 2001 Period in New England ISO New England Inc. NEPOOL Markets Committee January 15-16, 2002. Background. During Summer 2001, ISO-NE experienced several days of high loads, setting successive peaks. - PowerPoint PPT PresentationTRANSCRIPT
1
Market Rule and Procedure Changes in Response to Summer 2001
Period in New England
ISO New England Inc.NEPOOL Markets Committee
January 15-16, 2002
Agenda Item #5
1/15&16/02 MC Mtg.
2
Background
During Summer 2001, ISO-NE experienced several
days of high loads, setting successive peaks. Prices during some of those days, Particularly 8/9/01,
appeared inconsistent with the level of load. ISO-NE Board asked David Patton, its Market Advisor,
to review these events and produce a report. This report produced a number of recommendations. The ISO has developed a number of market rule
changes to implement those recommendations.
3
Key Patton Report Recommendations
1. Implement SMD as soon as possible.– Provide option to self-schedule resources after the commitment
process once the multi-settlement process under SMD is
implemented
2. Seek improvements in transaction rules and
procedures between NYISO and ISO-NE
3. Modify ECP eligibility rules for peaking units and units
committed during reserve shortages
4. Reserve Market Changes- Include real-time replacement reserves in reserve
markets
- Include Opportunity Cost payments for reserves
5. Seek improvements in ISO-NE’s internal procedures
for managing transmission congestion.
4
Schedule
Rule changes will be presented at January
15 - 16, 2002 NEPOOL Markets Committee
meeting. A tentative meeting has also
been set for 1/29/02 to discuss these
changes. ISO-NE will present final rule changes to
NPC at February 8, 2002 meeting. ISO-NE will finalize rules to enable filings of
rule changes in February 2002.
5
Seek Improvements in Transaction Rules
Objective:
Address major seams issue with New York Identify and implement solutions that
would facilitate efficient trading with
adjacent markets prior to next summer. In-Day trading is area needing
improvement.
6
Seek Improvements in Transaction Rules
Current Rules and Procedures for Short
Notice
External Transactions (SNTs)
ISO-NE does not accept in-day transactions
(Short Notice Transactions) if they will cause
commitment or de-commitment of resources SNTs are transactions submitted up until 90
minutes prior to the hour in which they are
scheduled to flow. Transaction can be terminated hourly by the
participant.
7
Seek Improvements in Transaction Rules
Proposed Changes to Short Notice External
Transactions SNTs will no longer be terminated if they affect
Unit Commitment To enable this change, SNTs, once submitted,
cannot be withdrawn by the Participant ISO-NE will not use replacement reserve or
operating reserve to support SNTs Current rule permitting internal resources to
self-schedule to support SNTs after the trading
deadline remains
8
Seek Improvements in Transaction Rules
External Dispatchable Transactions limited to
100 MW blocks at single energy bid price – Reduces large swings in RTMP and inter-control
area schedules based on acceptance and non
acceptance of large block loads on an all or
nothing basis – Externals not eligible to set RTMP will be eligible
for uplift
9
Seek Improvements in Transaction Rules
Short Notice External Transactions (SNT) - Issues
Out-Service: Rationing of available Out-Service under Tariff may
restrict SNTs Elimination of Out-Service charge for hourly SNTs is
being considered Because ISO-NE still has a single settlement system,
concern about possibility of generation sellers using
SNTs to increase price in New England. A mitigation measure that would restrict an entity from
engaging in those practices from submitting SNTs will
be included in the rules.
10
Modify ECP Eligibility Rules
Patton Recommendations:
Allow all units committed intra-day and dispatched
at LOL in reserve shortage situations to contribute
to setting energy clearing prices Allow peaking generators (generally gas turbines)
to set the energy clearing price when they are
dispatched for reasons other than congestion relief
or voltage support and are the source of
incremental energy
11
Modify ECP Eligibility Rules
The response to these two recommendations will be
consolidated. They will be addressed by changes in
the eligibility of peaking units to set the ECP for the
following reasons:
Few units with more than 1-hour minimum run or minimum
down time are committed intra-day Since these events are most likely in OP4, units with long
start times would already have been called upon and would
be operating above LOL. Consequently, peaking units are the units committed intra-
day in capacity tight situations.
12
Modify ECP Eligibility Rules
Proposed Treatment of Peaking Units and
External
Dispatchable Transactions
Market Design Principle:– If the unit or external transaction is the
incremental source of energy or is needed to
avoid a reserve shortage condition, then unit
or transaction is eligible to set 5 minute RTMP Definition of a reserve shortage situation will
be when the ISO is short of Operating
Reserve, as measured by the EMS system.
13
• These proposals would change the eligibility tests currently in place that
require that an external contract set a floor price any time it is dispatched.
They will also allow peaking units running at LOL to set the ECP
in certain conditions. • Under these proposals, External Contracts and Peaking Units that are at LOL
will be treated differently in normal conditions than in reserve shortage
conditions. In normal conditions, the external contract or peaking unit
at LOL will set the floor price when it is the incremental source of energy
on the system• In reserve shortage conditions, they will eligible to set a floor price
at all times. The floor price will be evaluated every five minutes.
Changes to Current Rules - Summary
Modify ECP Eligibility Rules
14
Modify ECP Eligibility Rules
Peaking Units and External Dispatchable
Transactions
Peaking Unit Definition – Minimum run time < 1 hour– Minimum down time < 1 hour– Startup notification < 30 minutes– Dispatchable via Remote Intelligence
Gateways (RIGS) Objective is to allow flexible energy to set
RTMP Peaking Units will be “flagged” as eligible
15
A. A set of peaking units and external transactions are on-
line at this instant in time. The reliability and economic
tests will be applied to these resources to determine the
eligibility to set the next 5 minute RTMP.
B. The EMS system has determined that at this specific
time interval, there is 210 MW of capacity on-line and
available within 10 minutes in excess of the energy and
spinning reserve requirements.
C. The RTMP from the previous 5 minute SPD execution is
$160.00, and the peaking units or external transactions
were not eligible to set the RTMP.
D. The characteristics of the peaking units and external
transactions are as follows:
Modify ECP Eligibility Rules
I. Eligibility Test - Initial Conditions
16
Peakers/ETLabel Cum LOL/Block Energy $P1 10 10 200ET1 110 100 190ETP2 140 30 185P3 170 30 180P4 190 20 179P5 205 15 179P6 225 20 175ET2 325 100 170ETP7 350 25 165
The above table shows the following information:
1. LOL is the LOL of the peaking resource and Block is the MW block size of
the external transaction
2. Energy $ is the energy bid price of the block of energy being evaluated
3. The Label is an arbitrary assignment for discussion purposes
Modify ECP Eligibility Rules
Peakers/ET
17
The above table shows the following information:
1. Size is the block size of energy above the last R/T SPD DDP that is
available within 5 minutes
2. Energy $ is the corresponding energy price of the MW block. If
there are multiple energy prices from a resource available in 5
minutes, each will be evaluated independently. (See OL2a/b)
3. The Label is an arbitrary assignment for discussion purposes
On-Line Energy
Energy$ Size Cum Label400 50 360 OL9174 100 310 OL8173 30 210 OL7171 30 180 OL6170 50 150 OL5166 20 100 OL2b165 15 80 OL4164 25 65 OL3163 20 40 OL2a161 20 20 OL1
Modify ECP Eligibility Rules
On-Line Energy
18
A. As stated, there are two separate tests to be
performed to determine the eligibility status of peakers
and external transactions to set the RTMP. These tests
will be performed prior to each execution of R/T SPD,
and the eligibility status will apply to the next
execution of R/T SPD.
B. The “Reliability Test” seeks to answer the question “Is
this resource needed to create or preserve reserve
while meeting the energy requirements of the
system?”
Modify ECP Eligibility Rules
II. Evaluation Tests
19
C. The “Energy Test” seeks to answer the question “Is
there less expensive on-line energy available within
5 minutes that can be replace the energy associated
with the peaker or external transaction, and, if so,
then the energy associated with the peaker or
external transaction is not needed at this point in
time and therefore should not be eligible to set the
RTMP?”
D. The two tests will be performed independently and
the results combined to determine which, if any,
peakers or external transactions will be eligible to
set the RTMP for the next execution of R/T SPD.
Modify ECP Eligibility Rules
II. Evaluation Tests - (continued)
20
A. The criteria to be used to evaluate resources for the
Reliability Test will be the amount of excess 10
minute spinning reserve on the system as determined
by the ISO EMS system. For the purposes of this
discussion, that amount is defined to be 210 MW.
B. The Reliability Test will determine which of the
eligible resources could otherwise be de-committed
and not cause the spinning reserve criteria to be
violated. Using the eligible list of resources from I.D.
above, resources P1 and P5 (total MW of these
resources is 205MW) could be decommitted without
violating the criteria.
Modify ECP Eligibility Rules
III. Reliability Test
21
C. Therefore, the Reliability Test would designate
resource P6 through P7 as necessary to meet criteria
and these resources (absent the Energy Test) would be
eligible to set the RTMP is the next R/T SPD execution.
Modify ECP Eligibility Rules
III. Reliability Test - (continued)
22
A. As stated above, the criteria for the Energy Test is “Is
there on-line energy available in 5 minutes that is less
expensive than the energy associated with the peakers
and external transactions?”
B. Using this criteria, the peakers and external transactions
are placed into an energy stack by MW block from most
expensive to least expensive. Likewise, the on-line
energy available is placed into an energy stack by MW
block from least expensive to most expensive.
C. Functionally, the Energy Test will start with the most
expensive peaker or external transaction block and
determine if this block of energy can be replaced by a
less expensive block of energy from an on-line unit.
Modify ECP Eligibility Rules
IV. Energy Test
23
D. From the examples above, the 10 MW block of energy at $200 from unit P1
can be replaced by 10 MW block of energy at $161 from the 20 MW block of
unit OL1.
E. The 100 MW block of energy at $190 from ET1 can be replaced by 10 MW
from OL1 (at $161), 20 MW from OL2a (at $163), 25 MW from OL3 ($164),
15MW from OL4 (at $165), 20 MW from OL2b (at $166), and 10 MW from OL5
(at $170).
F. Continuing with this evaluation, the energy from P2 can be replaced with the
energy from OL5, P3 can be replaced from OL5 and OL6, P4 can be replaced
from OL6 and OL7, P5 can be replaced from OL7, and P6 can be replaced
from OL7 and OL8.
G. The energy from ET2 has an energy price of $170. Based on the energy price
bands of the remaining on-line resources (OL8 and OL9), the energy from ET2
is more economic than additional on-line energy, therefore, ET2 would be
eligible to set the RTMP for the next execution.
Modify ECP Eligibility Rules
IV. Energy Test - (continued)
24
A. The final analysis is to combine the results of the Reliability and
Energy test in order to determine the most restrictive set of
peakers and/or external transactions that should be eligible to set
the RTMP for the next execution.
B. From III.C. above, the Reliability Test has indicated that resources
P6, ET2 and P7 are required resources.
C. From IV.G, above, the Energy Test has indicated that resources
ET2 and P7 have more economic energy bands than the remaining
on-line energy bands, therefore, these resources should be eligible
to set the RTMP in the next R/T SPD execution.
D. The final analysis would “flag” resources P6, ET2 and P7 as eligible
to set the RTMP in the next execution of R/T SPD, and presuming
no other changes in system demand, resource availability and/or
energy pricing occurred, the Final RTMP would be computed as
$175 and would be set by peaker P6 operating at LOL.
Modify ECP Eligibility Rules
V. Final Analysis
25
Modify ECP Eligibility Rules
Peaking Units and External Dispatchable
Transactions
Other Rules– Evaluation completed prior to each R/T SPD
execution– All eligible resources evaluated– No eligible resources “skipped”– Tie Breaker - Largest MW block at energy bid
price– Time horizon for replacement energy is 5
minutes
26
Modify ECP Eligibility Rules
The more restrictive definition was developed because
the loss of 10 minute reserve is a better measure of true
scarcity. Entering OP-4 because of loss of 30 minute reserve is an
NPCC requirement, not a NERC requirement. NPCC allows
some flexibility in operating without 30 minute reserve. Since this reliability requirement is not as hard and fast as
the ten-minute reserve requirement, it is not appropriate
to abandon incremental energy pricing upon a shortage
of thirty minute reserve.
27
Reserve Market Reform
Patton Recommendation:
If replacement reserves in the real-time are
required to meet the NERC reliability
requirements, ISO should adjust its reserve
requirements to allow the ISO to procure these
reserves in the reserves markets, and
compensate suppliers accordingly
Provide for payment of opportunity costs to
generators designated for reserves
28
Reserve Market Reform
1. Increase the amount of reserves cleared in
the TMOR Market by the real-time
supplemental reserve requirement
2. Revise pricing and payment in the reserve
market to be consistent with New York’s
Reserve Markets
3. Require units to bid their low operating limits
at their physical low operating limit, with an
allowance for economic efficiency and
emission characteristics
29
Reserve Market Reform
1. Replacement Reserves in TMOR
Requirement
Replacement Reserves (RR) defined as 1/2
second largest contingency RR will be added to existing 30 minute
requirement for purposes of real-time
designation and market clearing RR will not be in capacity analysis for
purposes of declaring OP4 conditions
30
Reserve Market Reform
1. Replacement Reserves in TMOR Requirement
Example: Existing Conditions
– Largest Contingency = 1400MW– 2nd Contingency = 1150 MW
Today– TMSR Requirement = 1/2 LSC = 700 MW– TMNSR Requirement = 1/2 LSC = 700 MW– TMOR Requirement = 1/2 2nd Contingency = 575 MW
Proposed– TMSR Requirement = 1/2 LSC = 700 MW– TMNSR Requirement = 1/2 LSC = 700 MW– TMOR requirement = 2nd Contingency = 1150 MW
31
Reserve Market Reform
2. Revised Pricing/Payment in the Reserve
Market
A. Floor Price for Reserves will be $ 0.00
B. Hourly Reserve Prices will be capped at
Hourly Energy Price
C. Final Reserve Prices will be cascaded at
5 minute dispatch
D. TMNSR and TMOR Reserve Availability
Bids will be capped at $ 2.52
E. 5 Minute Reserve Clearing Prices will
include opportunity costs
32
Reserve Market Reform
2. Revised Pricing/Payment in the Reserve
Market
A. Reserve Floor Price of $0.00
Proposal is a clarification of existing Rules Today when in excess generation, and
hourly ECP is negative, reserve prices are
administered to $0.00 Proposal would clarify intent and set floor
price for reserves at $ 0.00
33
Reserve Market Reform
2. Revised Pricing/Payment in the Reserve
Market
B. Hourly Reserve Prices capped at Hourly ECP
Restatement of existing “Interim Bid Cap
Rule” No change is being proposed
34
Reserve Market Reform
2. Revised Pricing/Payment in the Reserve
Market
C. Reserve Clearing Prices to be Cascaded
Reserve Clearing Prices at 5 minute
dispatch will be cascaded such that:– TMSRCP > TMNSRCP > TMORCP
Cascading will occur after Reserve Clearing
Prices determined
35
Reserve Market Reform
2. Revised Pricing/Payment in the Reserve
Market
D. TMNSR and TMOR Availability Bids to be
Capped
TMNSR and TMOR availability bids will be
capped at $ 2.52 $ 2.52 is the same as the NYISO cap
36
Reserve Market Reform
2. Revised Pricing/Payment in the Reserve Market
Revision to TMSR Clearing Price
Resources will be designated for TMSR by R/T
SPD based on existing Market Rules Once the TMSR designations are complete, the
TMSRCP will be determined based on:– Maximum [Final RTMP minus Dispatch RTMP;
BidPriceCleared],• Where Final RTMP is the final RTMP as determined by R/T
SPD from the maximum of the dispatch RTMP and the
external floor price,• BidPriceCleared is the sum of the TMSR Bid Price plus the
TMSR OC as determined by R/T SPD
37
Reserve Market Reform
2. Revised Pricing/Payment in the Reserve Market
Revision to TMSR Clearing Price
Example #1 (As today)– Final RTMP (Floor Price) 45.66– Dispatch RTMP 45.66– TMSRCP (R/T SPD today) 0.55– TMSRCP (proposed) 0.55
Example #2 (Final > Dispatch)– Final RTMP 44.97– Dispatch RTMP 43.87– TMSRCP (R/T SPD today) 0.55– TMSRCP (proposed) 1.10
38
Reserve Market Reform
2. Revised Pricing/Payment in the Reserve
Market
Revision to TMSR Clearing Price
Example #3 (TMSR OC)– Final RTMP (Floor Price) 87.32– Dispatch RTMP 52.30– TMSRCP (R/T SPD today) 39.12
• TMSR Bid (1.10, unit backed down to 49.30 [87.32-
49.30=38.02]
– TMSRCP (proposed) 39.12
No change in TMSR CP calculation
39
Reserve Market Reform
2. Revised Pricing/Payment in the Reserve Market
Revision to TMNSR and TMOR Clearing Price
Resources will be designated for TMNSR/TMOR
based on existing Market Rules Once the TMNSR/TMOR designations are
complete, the Clearing Prices will be
determined based on:– Maximum [Bid plus Opportunity Costs] of
designated resources– This OC is not the same as OC for TMSR
40
Reserve Market Reform
2. Revised Pricing/Payment in the Reserve
Market
Revision to TMNSR and TMOR Clearing Price
Opportunity Costs defined:– On-line resource:
Final RTMP minus Energy Bid Price for the next
MW above DDP
– Off-line resource: Final RTMP minus [(Startup Costs/[max(min run,
1hour)]/LOL) + No Load Costs/LOL + Energy Bid
Price at LOL]
41
Reserve Market Reform
2. Revised Pricing/Payment in the Reserve Market
Revision to TMNSR and TMOR Clearing Price Example # 1 (On-line Resource designated in
TMNSR)– Final RTMP 65.45– Unit HOL/LOL 100/30– Energy Bid 30@ $25.00, 40@ $50.00, 30@ $80.00– Energy DDP 70 MW– Designated TMNSR 10 MW (MRR=1MW/min)– TMNSR Bid $1.50/MW
OC = $65.45 minus $80.00 = -$15.45 -> No OC TMNSR CP = $1.50 (Bid) No Change in Clearing Price calculation from today
42
Reserve Market Reform
2. Revised Pricing/Payment in the Reserve Market
Revision to TMNSR and TMOR Clearing Price Example #2 (Off-line Resource designated for TMNSR)
– Final RTMP 65.45– Unit HOL/LOL 15/10– Energy Bid $60.00/MW– Startup and NoLoad Costs $500 and $25– TMNSR Bid $1.10/MW– Min Run 1 hour
OC = Final RTMP minus [S/U+NL+Energy] OC = $65.45 minus [$500/10 + $25/10 + $60] = -
$47.05 TMNSR CP = $1.10
43
Reserve Market Reform
2. Revised Pricing/Payment in the Reserve Market
Revision to TMNSR and TMOR Clearing Price Example #3 (Off-line Resource designated for
TMNSR)– Final RTMP 65.45– Unit HOL/LOL 15/10– Energy Bid $60.00/MW– Startup and NoLoad Costs $0 and $0– TMNSR Bid $1.10/MW
OC = Final RTMP minus [S/U+NL+Energy] OC = $65.45 minus [$0 + $0 + $60] = $5.45 TMNSR CP = $1.10 + $5.45 = $6.55
44
Reserve Market Reform
3. Bidding Physical LOL
Bidding physical LOLs for resources promotes
additional operational dispatch flexibility,
increases available reserves and may reduce
uplift Units will be required to bid LOLs at their
physical low operating limits, with an
allowance for economic efficiency and
emission characteristics ISO’s Market Monitoring and Mitigation group
will identify “audit” requirements