march 2020 m o n t h l y p r o g r e s s r e p o r...
TRANSCRIPT
![Page 1: March 2020 M O N T H L Y P R O G R E S S R E P O R Tfiles.seasidesd.schoolinsites.com/construction/SSDGOBond...March 2020 M O N T H L Y P R O G R E S S R E P O R T PROJECT DASHBOARD](https://reader033.vdocuments.us/reader033/viewer/2022050312/5f74fc727b36fd0bae00cc85/html5/thumbnails/1.jpg)
March 2020
M O N T H L Y P R O G R E S S R E P O R T
PROJECT DASHBOARD
PROJECT: SEASIDE SCHOOL DISTRICT 2017 GO BOND PROJECT
MONTH OF: MARCH 2020
PREPARED FOR: SEASIDE SCHOOL DISTRICT
PREPARED BY: MEGAN PRITCHARD, DAY CPM PROJECT COORDINATOR
OWNER’s REPRESENTATIVE: DAY CPM
ARCHITECT: BRIC ARCHITECTURE INC.
CM/GC: HOFFMAN CONSTRUCTION COMPANY OF OREGON
![Page 2: March 2020 M O N T H L Y P R O G R E S S R E P O R Tfiles.seasidesd.schoolinsites.com/construction/SSDGOBond...March 2020 M O N T H L Y P R O G R E S S R E P O R T PROJECT DASHBOARD](https://reader033.vdocuments.us/reader033/viewer/2022050312/5f74fc727b36fd0bae00cc85/html5/thumbnails/2.jpg)
2
BUDGET SCHEDULE SCOPE COMMUNITY
Monthly Rating
MARCH 2020 MILESTONES APRIL 2020 TARGET MILESTONES
Completed Heights Gym Scheduling for Plans A & B at the
Heights based on State CV-19
COVID-19 adjustments in schedule and
operations at the Heights Contract furniture order for both
schools
Completed paving of Fire Lane at the
Heights Continue curbs and paving at MS/HS
roads and parking
First layer of paving at the east parking lot
at MS/HS Connect and test main water line to
the reservoir
MS/HS windows and window testing
complete Start Heights B-Pod remodel
ON TARGET CAUTION BEHIND
![Page 3: March 2020 M O N T H L Y P R O G R E S S R E P O R Tfiles.seasidesd.schoolinsites.com/construction/SSDGOBond...March 2020 M O N T H L Y P R O G R E S S R E P O R T PROJECT DASHBOARD](https://reader033.vdocuments.us/reader033/viewer/2022050312/5f74fc727b36fd0bae00cc85/html5/thumbnails/3.jpg)
3
EXECUTIVE SUMMARY
CONSTRUCTION Work proceeding at HS/MS:
o Site – curb and sidewalk installation
o Site – continue paving
o Site – electrical installation at field
o Drywall ongoing at Level 2
o Gym wood flooring installation
o Kitchen hoods
o Ceiling grid installation
o Interior painting
o Classroom cabinets and carpet installation
Work at Seaside Heights
o Demolition starting at Phase 2
o Plumbing rough-in both new and lead pipe replacement
o Data and Electrical installation
o Mechanical Rough-in ongoing
o Develop schedule options for CV-19 impacts
CITY OF SEASIDE: Construction Coordination - Seaside Public Works:
o Pump station
Work proceeding onsite
Building under way
o Reservoir
Reservoir tank fabrication nearly complete
PROJECT BUDGET:
Budget:
o Heights – renovation ‘discoveries’ are a factor for existing utility systems, some
framing, and impacts of seismic upgrades
o CV-19 impacts unknown based on spread and appropriate governmental
response
o Continuing to work to provide best value for the District
![Page 4: March 2020 M O N T H L Y P R O G R E S S R E P O R Tfiles.seasidesd.schoolinsites.com/construction/SSDGOBond...March 2020 M O N T H L Y P R O G R E S S R E P O R T PROJECT DASHBOARD](https://reader033.vdocuments.us/reader033/viewer/2022050312/5f74fc727b36fd0bae00cc85/html5/thumbnails/4.jpg)
4
![Page 5: March 2020 M O N T H L Y P R O G R E S S R E P O R Tfiles.seasidesd.schoolinsites.com/construction/SSDGOBond...March 2020 M O N T H L Y P R O G R E S S R E P O R T PROJECT DASHBOARD](https://reader033.vdocuments.us/reader033/viewer/2022050312/5f74fc727b36fd0bae00cc85/html5/thumbnails/5.jpg)
5
BUDGET:
$114,256,709 $8,567,442 $5,672,363 $1,412,165
$74,273,631 $7,843,155 $2,839,698
$934,166
$-0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
CONSTRUCTION PROFESSIONAL
SERVICES:
OWNER/ DISTRICT
ADMIN COST
CONSULTANT
COSTS/NON-PROF &
TECH SERVICES
OWNER
CONTINGENCY:
Project Risk
ContingencyBudget Actual Spent
PROJECT BUDGET
![Page 6: March 2020 M O N T H L Y P R O G R E S S R E P O R Tfiles.seasidesd.schoolinsites.com/construction/SSDGOBond...March 2020 M O N T H L Y P R O G R E S S R E P O R T PROJECT DASHBOARD](https://reader033.vdocuments.us/reader033/viewer/2022050312/5f74fc727b36fd0bae00cc85/html5/thumbnails/6.jpg)
6
END OF REPORT