Thesetechtipsareofferedfreeofchargeinthespiritofsharingknowledgewithothers.Theydonotincludetechnicalsupport,shouldyouhaveaproblemwiththem.Wearealwaysinterestedinhowtheycanbeimproved,pleasedonothesitatetoemailusyourcomments.Thesetipshavebeenthoroughlytestedbyourconsultantsinavarietyofenvironments.Pleasereadthesetechtipsthoroughlyandbe
surethatyouunderstandthembeforetryingtousethem.Wecannotberesponsibleforissuesthatdevelopbecauseoftheconfigurationofyourhardware,technicalenvironmentorapplicationofthetechmemos.Ifyouarenotsure,thenweurgeyoutocontactOracletechnicalsupportoryourlocalsupportconsultantforassistance.
AttheconclusionofaRiskexercise,wouldn’titbenicetobeabletohavethatadjustedscheduleforfuturereference?Useforcomparisonlaterintheproject?Maybeuseasareplacementscheduletoyouroriginalforecast?AnicefeatureincludedintheAcumenRisktool,istheabilitytocreateanadjustedschedulefromtheinput/outputs.
ContainedwithintheDeltekAcumentoolsuiteisafunctioncalledBuildScenario.Thefunctionallowsformakingacopyofanexistingfileintheworkbook,buildanewscenariobasedontheRiskInputs(durationuncertaintyvaluesonactivities)orcreateascenariobasedonRiskOutputsatwhateverP-valuedesired.
Figure1—AcumenS3//Riskscreen
MARCH 2018 DELTEK ACUMEN RISK
RISK ADJUSTED SCHEDULE
Page 2
RISK ADJUSTED SCHEDULE
Withintheprogram,athree-pointestimateisestablishedbytheuserforeachactivitytoaccountfordurationuncertainty.Durationuncertaintyisthevariabilityindurationthataparticulartasktakestoexecuteduetoavarietyoffactors,includingproductivity,weatherconditions,complexactivity,etc.Additionally,riskeventsareaddedtothemodelbywayofmappingtoactivities,WBSelementsortheentireplan.Theserisksareestablishedwithaprobabilityofoccurenceaswellasarangeofduration.When“rollingthedice”adurationbetweentheminimumandmaximumisselectedandalongwiththeriskeventsplusthelogiccontained,anewschedulemodelisderivedforeachiteration.Theprogram,aspartoftheriskanalysissetofiterations,calculatesP-durations/valuesforeachindividualactivityinthemodel.TheseP-valuedurationsarethenassembledintoadeterministicschedule.WhenusingthisScenariofunction,thatschedulecanthenbeextractedoutforwhateverP-valuedesiredbytheteam.AprojectteammaydesiretoseehowaP-50andP-80comparetothedeterministicandwanttoextractforreviewinthescheduletool.
Figure2—AcumenRiskscenariooptions
Page 3
RISK ADJUSTED SCHEDULE
ToexecutecreatingascenarioofaP-valueschedule,selectBuildScenarioundertheS3//Risktab.InFigure2,50wastheselectedvalue.Next,clickontheRiskOutputScenariosection.ThisoptionwillonlybeactivewhenaprojectisselectedintheS1//Projectsscreen(seeFigure3).
Page 4
RISK ADJUSTED SCHEDULE
Onceselected,AcumenautomaticallycopiesthefileandcreatesthescenariogiventheP-valueselection.Oncecomplete,asecondschedulewillappearintheProjectsscreenwithScenariointhedescription(seeFigure4).
Figure4—AcumenS3//RiskProjects
Page 5
RISK ADJUSTED SCHEDULE
WiththeScenarionowpopulated,theusercanthenusethatcopytoexportoutforinclusioninthescheduleprogramofchoicebeitMSProject,DeltekOpenPlanorP6.ThisExportroutinecantakeplacebackintheS1//Projectstab(seeFigure5).Theusercansavethenewfileinthelocationorfolderofchoice.
Figure5—AcumenS1//Projectstab