march 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... board of...

49
March 2012

Upload: others

Post on 23-Sep-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

March 2012

Page 2: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Forward Looking Statement

Certain statements contained herein regarding the Company and its operations constitute “forward-looking statements” or information. All statements other than statements of historical fact included in this presentation, including, without limitation, statements regarding future plans and objectives or expected results are forward-looking statements that are based on numerous assumptions that involve various risks and uncertainties inherent in the Company’s business, including risks related to mineral resource exploration and development. Actual results may very materially from those described in the forward-looking statements. There can be no assurance that such statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from the companies’ plans or expectations include availability of capital and financing, general economic, market or business conditions, regulatory changes, timelines of government or regulatory approvals and other risks detailed herein and from time to time in the filings made by the Company with securities regulators. The Company makes all reasonable efforts to update its corporate materials, documentation and forward-looking information on a timely basis.

Page 3: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Lincoln Mining Corp., symbol LMG, listed on TSX Venture Exchange in August 2009 (Established in 2003, formerly called Lincoln Gold Corp.)

Three Major Properties:

o Pine Grove, Nevada – 141,500 Measured ozs gold & 62,400 Indicated ozs gold & 43,100 Inferred ozs gold w/ Preliminary Economic Assessment

o Oro Cruz, California – 341,800 Inferred ozs gold w/ Technical Report

o La Bufa, Mexico – Exploration-stage project in major mining district w/ Technical Report

Exploration partnership with Elgin Mining Inc. on the Oro Cruz and La Bufa projects

Overview

Page 4: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

TSX-V symbol: LMG

Frankfurt Stock Exchange: ZMG

Issued & Outstanding: 97,384,203

Warrants: 16,946,759

Options: 8,175,000

Fully Diluted Total: 122,505,962 Source: TMX.com

As at March 2, 2012

Share Structure

TSX-V: LMG Feb 2011 – 2012

52 Week: Low $0.060; High $ 0.27

Page 5: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Board of Directors Robert Cruikshank – Mr. Cruikshank served as past President of the British Columbia Technology Industries Association and has served in many executive roles including over four years as the President of BCTEL Mobility. Mr. Cruikshank currently serves as a director of Vendtek Systems Inc. a TSXV listed technology company. Along with Chairing the Board of Carmanah Technologies, he also serves on the Advisory Board of both AfterCAD Software Inc. and Nutri-Loc, two early stage technology companies.

Robert Elton – Mr. Elton currently serves as Executive Chair of Powertech Labs and Advisor to the Board of Directors of BC Hydro. He was former President and CEO of BC Hydro for six years and prior to that, he had various senior executive positions including Chief Financial Officer of Eldorado Gold Corporation and a partner of PricewaterhouseCoopers. Mr. Elton is involved in various civic and community activities and is a Member of the Global Agenda Council, World Economic Forum.

Andrew Milligan – Chairman of the Board – Mr. Milligan is a business executive who has concentrated on mining ventures over the past 35 years. He was the founder of Skye Resources Inc. , now owned by Hudbay Minerals Inc. He also served as President & CEO of Glamis Gold Ltd., President & CEO of Cornucopia Resources Ltd. and President & CEO of TRV Minerals Corp. Since 2004 he has concentrated his efforts on Lincoln Mining Corporation.

Dr. Michael Price – Dr. Price is a mine finance consultant located in London. He holds a PhD in Mining Engineering and has more than 30 years resource banking experience. Dr. Price’s extensive experience in mining projects and financing will be a significant asset to Lincoln Mining as projects are advancing into the production stage.

Paul Saxton – Mr. Saxton has been active in the mining industry since 1969, holding various senior management positions, including mining engineer, mine superintendent, Vice President and President , with numerous Canadian mining companies including: Mascot Gold Mines Ltd., Cominco, Corona Corp., Viceroy Resource Corp., Standard Mining Corp. and Lincoln Gold Corporation. He is a mining engineer who also holds an MBA from the University of Western Ontario.

Philip Walsh – Mr. Walsh became a director of the Company when the business combination of LPT Capital Ltd. and Lincoln Gold Corporation became effective in August 2009. Prior to that Mr. Walsh was President & CEO of LPT Capital Ltd. since its incorporation in 2006. In addition, since 1996 he has been President of Taff Management Corp., a private company providing consulting, management and advisory services to public companies.

Page 6: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Management Team Paul Saxton – President and CEO Paul Saxton is the President, CEO and Director of Lincoln Mining Corporation and has been active in the mining industry since 1969. Cominco, Eastmaque, Viceroy, Pinnacle, Lincoln. Projects to Production.

Jeffrey Wilson – Executive Vice President Mr. Wilson brings to Lincoln Mining 34 years of professional exploration experience in the United States, Mexico and Central America with emphasis on gold. Tenneco, Echo Bay. Director of Exploration.

Micheal Attaway – Chief Operating Officer & Vice President Operations Mr. Attaway, a mining engineer with a Masters Degree in Business Administration, brings to Lincoln Mining over 30 years of professional experience in mine operations in the United States. Homestake, Bond International, Viceroy, Quadra. Taking projects to production and managing them.

Emmet McGrath – Chief Financial Officer Mr. McGrath, a Chartered Accountant, is a respected business advisor with over 30 years of experience in public accounting and private industry.

Sabrina Jones – Vice President Corporate Affairs & Corporate Secretary Ms. Jones has a Bachelor’s degree in Economics and has held various accounting and administrative management positions in both public and private companies.

Page 7: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Business Model & Objectives Business Model

Become a mid-tier gold and silver producer

Focus on North America – United States, Mexico & Canada

Grow the Company through cash flow from production

Objectives

Achieve gold production at Pine Grove

Achieve gold production at Oro Cruz

Advance the La Bufa gold-silver property

Expand property portfolio by acquiring additional advanced-stage gold-silver exploration properties

Page 8: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Recent Developments Pine Grove

– Positive Preliminary Economic Assessment (“PEA”) for the Pine Grove gold property announced on Dec. 8, 2011

– PEA reports the project is relatively sound with a free cash flow of US$32 million dollars at a gold price of US$1,425

La Bufa – Drill program at La Bufa was completed mid-December; results confirmed the

continuation of similar mineralized structures, quartz breccia zones and stockworks in the northern concession that exist on the southeastern La Bufa concession

– Some assays remain pending; results are being analyzed for the development of future drill programs that will offset anomalous gold-silver intercepts

Oro Cruz – Permitting for drilling (15,000 meters) at Oro Cruz is underway and a drill program is

planned for 2012

Agreement with Elgin Mining – Exploration of the Oro Cruz and La Bufa properties ($4 million initial investment)

Page 9: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Agreement with Elgin Mining Inc. Overview

Elgin Mining is Lincoln’s exploration partner at the Oro Cruz gold project in California and the La Bufa gold-silver project in Chihuahua State, Mexico

Elgin Mining’s management have extensive experience in mine finding, operations, financing, project management and mine technology

Elgin Mining has committed to spend $3MM on exploration work at the Oro Cruz and $1MM on exploration work at the La Bufa over a period of two years before making a further commitment to acquire an interest in either of the projects

Objectives

Expand the Oro Cruz mineral resource

Advance Oro Cruz project towards economic assessment, feasibility and then production

Establish a mineral resource at the La Bufa property

Page 10: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Pine Grove Gold Property

Page 11: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Development-stage project in Walker Lane Mineral Trend, Nevada

Positive preliminary economic assessment by Telesto Nevada Inc. filed in December 2011

Planned as an open-pit mine with heap-leach processing with 6 years of mine life operations

Updated resource study by Tetra Tech filed in March 2011

High-grade intercepts drilled in 2009–2010

Significant potential to grow the resource

Excellent infrastructure

Pine Grove – Project Highlights

Page 12: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Pine Grove – General Location Yerington

Pine Grove Project

Page 13: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Pine Grove – Location Map

Pine Grove Project Claims Boundary

Page 14: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Pine Grove – Mining History

Historical Production

Discovered in 1866; mined until 1887

Mined high-grade with average ≥ 1 opt gold

Lower grade gold material remains in place

Mined only to 160 ft – 180 ft

240,000 ozs gold produced

Modern Exploration

1989 to 1991 – Teck Resources – 190 holes

2009/2010 – Lincoln Gold US Corp. – 82 holes

Pine Grove – old stamp mill

Page 15: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Pine Grove – District History

Gold first discovered in 1866

Originally named the Wilson Mining District after ‘Uncle Billy Wilson’

Pine Grove population grew to over 1,000 people

Post office, 5 saloons, 3 hotels, dance hall and a school

Toll roads extended in all directions

Regional supply center with freight lines and stages

Photo of Pine Grove around 1870 from the book ‘Nevada Ghost Towns & Mining Camps’ by Stanley W. Paher

Page 16: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Pine Grove – Claims

Page 17: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Wheeler-Wilson Model

Wilson Deposit

Wheeler Deposit

Looking northward

Page 18: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Pine Grove – Mineral Resources

Total Measured + Indicated and Inferred Gold Resources

Resource Tons Cutoff Grade Average Grade Contained Category (000s) Gold (opt) Gold (opt) Ounces

Measured 4,043 0.007 0.035 141,500 Indicated 2,012 0.007 0.031 62,400 Total Measured & Indicated 6,055 0.007 0.034 203,900 Total Inferred 1,596 0.007 0.027 43,100

By Telesto Nevada Inc.

Page 19: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Pine Grove – Mineral Resources

Total Measured + Indicated and Inferred Gold Resources

Resource Tonnes Cutoff Grade Average Grade Contained Category (000s) Gold (g/t) Gold (g/t) Ounces

Measured 3,668 0.240 1.199 141,500 Indicated 1,825 0.240 1.062 62,400 Total Measured & Indicated 5,493 0.240 1.153 203,900 Total Inferred 1,448 0.240 0.925 43,100

By Telesto Nevada Inc.

Page 20: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Pine Grove – Production Scenario Preliminary Economic Assessment (“PEA”) by Telesto Nevada Inc.

PEA proposes open-pit and heap-leach processing operation; with mining commencing on Wheeler deposit then moving to Wilson deposit

Mine life of 6 years; first year pre-production, production of 26,200 to 28,200 ozs gold per year for four years, plus final year of pad rinsing

Based on gold price of $1425/oz, free cash flow of $32.2 MM

Operating costs per ounce are approximately $799/oz

Payback on capital is expected in 32 months

Total Direct Capital Costs are estimated at $22.9 MM plus $4.5 MM contingency

Internal Rate of Return of 31% after royalties, reclamation costs, and Nevada Net Proceeds Tax

Page 21: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Pine Grove – Site Layout

Page 22: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Pine Grove – Leach Pad Area

Page 23: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Pine Grove – Conceptual Operations

Base Case: 6 year mine life

o Year 1 – Preproduction

o Year 2 – 5 Production

o Year 6 – Rinse Pad

Gold production between 26,000–28,000 ounces gold per year

Plan to expand reserves and life of mine through exploration

Aerial view of a typical heap-leach operation

Page 24: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Pine Grove – Exploration Potential PEA states: Significant exploration potential exists beyond current resources

Page 25: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Oro Cruz Gold Property

Page 26: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

The Mojave-Sonora Mineral Trend crosses California and Arizona into northern Mexico. The trend has a history of open pit gold mines.

Page 27: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Oro Cruz – Land LOCATION

Imperial County, southeastern California

Tumco Mining District in the Cargo Muchacho Mountains

Approximately 14 miles south of the operating Mesquite Mine

CLAIMS

20 claims under lease – February 2010

131 claims staked in name of Company

Land position approx. 3,000 acres

Page 28: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Oro Cruz – Recent History

RECENT PRODUCTION

1995/1996 – open pit and underground

MK Gold Operations (American Girl JV)

61,000 ozs gold produced in 12 months

Ore was processed 2 miles away at American Girl Mine

Ceased operations due to low gold price

Gold resource remains in place

Oro Cruz pit – looking southwest

Page 29: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Oro Cruz – Pit & Underground Workings

Page 30: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Oro Cruz – Underground Workings

Oro Cruz portal and main decline.

Page 31: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Oro Cruz – Underground Workings

Page 32: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Oro Cruz – Database

Computerized Data Base in Technical Report o 431 surface and 60 underground drill holes

o 13,628 blast holes

o 2,960 underground channel samples

o 17,586 assays in the data base

Surface Data - 1,684 surface samples

All mineralization similar in area

Good metallurgical recoveries recorded in the past

Environmental studies underway

Gold mineralization (reddish brown areas) exposed in the Oro Cruz pit.

Page 33: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Oro Cruz – Resources Estimate

Oro Cruz Inferred Gold Resources

Cutoff Grade Resource Tons Average Contained Gold Category Gold Grade * Gold

opt – 0.02 Inferred 4,835,000 opt – 0.070 341,800 ozs (gpt – 2.20) or opt – 0.01 Inferred 7,860,000 opt – 0.050 376,600 ozs (gpt – 1.60)

* By Tetra Tech Assays capped at 1.5 opt

Page 34: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Oro Cruz – Resource Development

An exploration partnership with Elgin Mining Inc., allows Lincoln to advance the Oro Cruz gold project

Environmental Assessment Report is planned for 2012

Tetra Tech Inc. in San Bernadino, CA assisting with permitting

Preliminary pit configurations in progress

New topographic base map completed for exploration and development

Development of water sources

Page 35: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the
Page 36: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the
Page 37: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Oro Cruz Exploration Potential

$3 million allocated by Elgin Mining Inc. for initial exploration

Numerous targets marked for future exploration

Structural zones are new opportunities

Aerial photography and structural analysis planned

Aerial magnetic and radiometric survey planned

Permitting is in process; a drill program is planned for 2012

Page 38: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Oro Cruz Exploration Potential

Section Two Mine - historic workings discovered by field crew

New exploration target located in northern portion of claims

High angle shear zone

Target has never been drilled

Section Two Mine - looking northwest

Page 39: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

La Bufa Silver-Gold Property

Page 40: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Mines of the Sierra Madre Occidental

Page 41: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

La Bufa Silver-Gold Property

Location o Guadalupe y Calvo mining district

in southeastern Chihuahua State

o Excellent infrastructure

Major Historical Producer – 1835 to 1939 o El Rosario underground mine

o Over 2 million plus ozs gold

o Over 28 million plus ozs silver

Minera Lincoln de Mexico S.A. de C.V.

o 100% interest

o 2,300 hectares (5,711 acres)

o Surrounds Gammon Gold’s “GyC project”

Multi-Million Ounces Potential

Page 42: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

La Bufa Property – Guadalupe de Calvo Mining District

Page 43: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

La Bufa – Exploration Progress I.P. /Resistivity Survey conducted o 20,000 line meters in 8 lines

Surface Sampling – 234 rock chip samples · 0.06 opt Au + 28.6 opt Ag · 0.63 opt Au + 5.6 opt Ag · 0.02 opt Au + 18.3 opt Ag · 0.58 opt Au

· 0.39 opt Au + 26.3 opt Ag · 1.08 opt Au

Geologic Mapping shows large areas of favorable Lower Volcanics with abundant vein and structural targets

Drill program in south concession confirmed presence of structures similar to those that hosted the El Rosario mine

Exploration partnership with Elgin Mining Inc. Elgin Mining has allocated $1 million for exploration at La Bufa

Page 44: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

La Bufa Property – Target Areas

Page 45: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

La Bufa – 2011 Drill Program Drill program in north concession began mid-July and was completed by early December 2011

Results have confirmed the presence of anomalous gold-silver mineralization in high-angle quartz breccia veins and stockworks in the NW-SE trending structures that extend for many hundreds of meters.

The drill program also confirmed the presence of structural zones, quartz breccia zones and stockworks as an extension of the main NW-SW district target zone

Similar structures occur about 8 km south on the southern portion of the La Bufa property

Results are being analyzed

Page 46: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

La Bufa Property – 2011 Target Area

Page 47: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Looking Forward

Pine Grove Property – Nevada

o Advance project towards feasibility stage o Step-out drilling & expansion exploration programs o Path to production is in progress

Oro Cruz Property – California

o $3 MM allocated by Elgin Mining for initial exploration o Aerial photography o Environmental Assessment Report o Confirmation drilling & expansion exploration programs o Path to Production is in progress

La Bufa Property – Chihuahua, Mexico

o $1MM allocated by Elgin Mining for exploration

Wheeler deposit

Oro Cruz pit

La Bufa property

Page 48: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the

Summary

Outstanding projects in key mineral regions of Nevada, California and Chihuahua:

o Pine Grove offers near term production

o Oro Cruz offers future production opportunity

o La Bufa has large gold-silver exploration potential (advanced stage exploration)

Management team of senior mining executives, engineers and geologists have worldwide record of exploration, mine-finding and mine-building: Nickel Plate, American Girl, Castle Mtn, Brewery Creek, Borealis, Coliseum.

Lincoln Mining entered into an exploration financing agreement with Elgin Mining Inc. in 2011. This provides Lincoln with a strategic partnership and allows the Company to advance the Oro Cruz and La Bufa projects with minimum dilution to Lincoln Mining shareholders.

Page 49: March 2012 - lincolnmining.com€¦ · presentation, including, without limitation, ... Board of both AfterCAD Software Inc. and Nutri -Loc, ... Mr. Saxton has been active in the