Page 1: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

March 2011

Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

Page 2: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

2

Sunridge Gold – Highlights

The Asmara Project in Eritrea hosts four deposits. Sunridge has completed independent, TSX 43-101 approved resource estimates on three deposits, Emba Derho, Adi Nefas and Debarwa. Combined Indicated resources total:

• 1.28 billion lbs (580,000 tonnes) copper

• 2.5 billion lbs (1,130,000 tonnes) zinc

• 1.05 million oz gold

• 31.8 million oz silver

In addition a fourth deposit, the Gupo Gold deposit, contains an Inferred resource of 189,000 ounces of gold.

Page 3: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

3

Sunridge Gold – Highlights

• Feasibility Study at Debarwa focusing on fast tracking high grade copper zone to production

• Prefeasibility Study underway on three Northern Deposits

• Major drill programs with five rigs operating by end of first quarter

• Experienced management team

• “De-riskification” of region continues

• Discovery of potential new VMS district in Madagascar

• Well funded – $24 million in treasury

Page 4: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

4

Eritrea and the Asmara Project

ERITREA LOCATIONS

Asmara

MassawaBisha

Hambok

Zara

Asmara Projects

Eritrea

38°E

16°NRed Sea

Sunridge Gold VMS/Gold Projects ~ 800 sq kmOther VMS/Gold Projects

Page 5: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

5

Eritrea

• Population approx 4 million, business in English

• Asmara considered one of the most beautiful and safest cities in Africa

• Mining code based on Northern Territory, Australia

• Excellent infrastructure; paved roads, grid power, rail & road to Port of Massawa

• Nevsun and Enamco’s (Government of Eritrea) Bisha Mine now in production

Page 6: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

Asmara Project – Three Main Focus Areas

Antofagasta-Sunridge Exploration Area:

- Antofagasta funding exploration drilling on new targets

Northern Projects:

- Emba Derho, Adi Nefas, and Gupo Gold- 100% Sunridge Owned- Prefeasibility Study commenced

Debarwa Copper-Zinc-Gold VMS Deposit:

- 100% Sunridge Owned- Feasibility began in November 2010

6

Page 7: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

7

Debarwa Deposit

Feasibility Study underway at Debarwa Project with objective of fast tracking to production high grade copper material (18-20 % Copper).

100% Sunridge Owned

Highlights of intercepts in the copper supergene zone:

Debarwa high-grade copper-zinc-gold VMS deposit

• D-005 20.36 % Cu, 2.18 g/t Au over 13.00 m.

• D-019 21.27 % Cu, 2.29 g/t Au over 9.80 m.

• D-021-D 20.59 % Cu, 1.96 g/t Au over 11.30 m.

• D-022-D 19.31 % Cu, 5.80 g/t Au over 7.0 m.

• D-036-D 20.87 % Cu, 1.99 g/t Au over 11.00 m.

• D-044-D 20.19 % Cu, 2.18 g/t Au over 6.05 m.

Page 8: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

8

Debarwa Deposit

Debarwa Indicated Resources*

* Resource Estimate by MSA Geoservices (Pty) filed on SEDAR March 4,2008

open

North

open open

Direct shipment material (18-20% Cu)

1.4 km

Page 9: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

9

Debarwa Deposit: Section 99965N

Page 10: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

10

Debarwa Feasibility Study Schedule

Study commenced November 2010

• November 2010 - Drilling for metallurgical and structural analysis, resource definition and expansion

• April 2011 - Final resource model

• May 2011 - Metallurgical parameters and flow-sheet criteria

• June 2011 - Mine design and production schedule complete

• June 2011 - Decision to fast-track direct ship ore

• August 2011 - Finalized process plant design

• September 2011 - Preliminary Draft Report

• October 2011 - Final Report

• Completion of SEIA by late 2011

Page 11: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

11

Northern Deposits of Asmara Project

Emba Derho – 62.5 million tonnes Indicated resource containing 996 Mlbs Cu, 1,907 Mlbs Zn, 574,000 oz Au, 20 M oz Ag

Adi Nefas – 2.7 Mt (Indicated) resource at 1.4%Cu, 8.4% Zn, 2.9 g/t Au, 99.3 g/t Ag

Gupo Gold - 189,000 Oz (Inferred) at 2.99 g/t Au

• Positive Scoping Study at Emba Derho demonstrates strong economic potential with open pit mining plan

• Gold exploration potential at Medrizien Gold Target located 500 meters from Emba Derho

• Prefeasibility for Northern Deposits commenced February 2011

• Ideally located 15 km from Asmara on excellent infrastructure

Page 12: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

12

Emba Derho 43-101 Resource Wardrop, September 17, 2008

Summary of Indicated Mineral Resource

Page 13: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

13

Emba Derho 43-101 Resource Wardrop, September 17, 2008

Total Contained Metal at Emba Derho

Page 14: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

14

Northern Deposits – Emba Derho

Ideal for open pit mining

Page 15: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

15

Emba Derho 43-101 Resource Model

Page 16: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

16

Emba Derho Scoping Study – Base Case

Completed June 2009 by Wardrop UK – Base Case Study:

• Open pit mining at 4 M tonnes per year for 10.4 years (42 Mt out of 62 Mt) - potential mine life extension

• Base Case IRR - 21.6%

• Initial estimated capex: US$331.8 M, sustaining capital US$67.3 M

• Base Case NPV -US$203.9 M at 10% discount rate pre-tax

• Produce 200,000 t of Cu & Zn concentrates annually containing 55,000 t Zn, 25,000 t Cu, 20,000 oz Au & 0.6 m oz Ag

• Total operating costs - US$21.19/tonne milled

Page 17: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

Scoping Study – Sensitivity to Metal Prices

Historical average metal prices sourced from London Metal Exchange as of June/09

17

Page 18: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

18

Emba Derho Optimization

Opportunities for improving Emba Derho economics:

•Include 95,000 ozs Au @ 0.84 g/t from Oxide Gold Zone in pre-feasibility study

•Include Adi Nefas and Gupo Gold in Prefeasibility Study

•Removal of ~20% internal waste with DMS system

•Steepen pit slope.

•Drill programs at Emba Derho, Adi Nefas, Gupo Gold, and Medrizien as part of Prefeasibility study and exploration

•Much stronger copper, zinc, gold, and silver prices since scoping study

•New metallurgical tests show positive recovery results, 92%Cu with 28% concentrate and 88%Zn with 62% concentrate.

Page 19: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

19

Emba Derho Optimization

Page 20: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

20

Northern Deposits – Adi Nefas

INDICATED RESOURCES *

Adi Nefas and Gupo Gold are within 6 km of Emba Derho and will be included in future prefeasibility/feasibility studies at Emba Derho:

Adi Nefas:- high grade zinc-copper-gold VMS deposit.

* Resource Estimate by MSA Geoservices (Pty) filed on SEDAR March 4,2008

Page 21: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

21

Northern Deposits – Gupo Gold and Medrizien

Gupo Gold Deposit:

•189,000 ounces gold grading 2.99 g/t gold in Inferred category

•Potential for low cost open pit which could enchance start up operations for the northern deposits

Medrizien Gold Prospect:

•500 meters from Emba Derho Deposit

•65 rock grab samples taken over the strike length of the prospect, with 10 samples over 1.0 g/t Au averaging 12.13 g/t Au, highest assay being 74.7 g/t Au

Page 22: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

22

Northern Deposits – Prefeasibility

Prefeasibility scheduled commenced on Northern Deposits :

•Study to assess Emba Derho, Debarwa, Adi Nefas as one operation

•Study to include Gold Oxide cap at Emba Derho

•Trade off studies to include Debarwa, currently in Feasibility

•Study to consider steeper pit walls and DMS at Emba Derho

•To include upcoming drilling to expand Adi Nefas, Gupo, and initial drilling at Medrizien Gold prospect

Page 23: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

23

Antofagasta – Sunridge Exploration Area/JV

• Antofagasta Minerals S.A. signs strategic alliance agreement for US$10 M in exploration expenditures over five years for a 60% interest in the Exploration Area (October 2, 2009)

• Sunridge will be operator until a total of US $7 M has been funded by Antofagasta

• Antofagasta may earn an additional 15% for a total of 75% interest by completing a feasibility study on any project within the Exploration Areas

Page 24: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

Adi Rassi Copper-Gold Prospect

Adi Rassi:

• a potentially large new copper and gold zone discovery, July 2010

• Drilled over 500 meters along strike to date, zone remains open

Drill Highlights include: 

• AR-002D: 84 metres grading 1.32 g/t gold and 0.84% copper

• AR-003D: 25 metres grading 0.75 g/t gold and 0.54% copper

• AR-004D: 78 metres grading 0.22 g/t gold and 1.0% copper

24

Adi Rassi

Page 25: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

25

Madagascar – Besakoa Project

A New Emerging VMS District:• Similar to both the Asmara

Project and Nevsun’s Bisha Project in Eritrea

• Coincident surface gossans, strong soil and gravity anomalies, airborne EM conductors

• Surface expression of VMS systems

• Over 10 strong copper, zinc, gold, and lead geochemical anomalies between 1 and 4 kilometres in length

• Numerous large (longer than 1 kilometre) strong gravity anomalies, coincident with elevated base and precious metal values

• Initial drill program planned for Q2 2011

Page 26: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

26

Madagascar – Besakoa Project

Page 27: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

27

SGC - Share Structure Jan.2011

Symbol: SGC/TSX.V Shares outstanding: 116,684,500Options: wt. avg = $1.25 9,238,500Wts. 10 M @ 0.75 exp. Oct. 27/12 10,000,000Wts. 18.5 M @ 1.40 exp. Nov. 17/15 18,500,000Fully diluted shares: 154,423,000Current cash: CDN $ 24 millionFD cas CDN $ 71 million

Market cap. Approx. $130 million

Lundin Mining: 7.4%

www.sunridgegold.com

Page 28: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

28

SGC – 3 Year Chart

Page 29: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

29

Sunridge Gold Management and Directors

Michael Hopley – President/C.E.O., Director

David Daoud – Exploration Manager

Scott Ansell – VP Project Development

Doris Meyer – CFO & Director

Greg Davis – VP Business Development

Amanuel Arafine – Eritrean Country Manager, Eritrea

Craig angus – Chairman

Neil O’Brien – Director (Senior VP Lundin Mining)

Stephen Gatley – Director (GM, Lundin Mining)

Mark Corra – Director (CFO of B2 Gold)

Eric Edwards – Director

Page 30: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

30

Summary of Asmara Project

1. Debarwa – Feasibility Study focusing on direct shipment of high grade copper (18-20% Cu) material

2. Northern Deposits - Prefeasibility commenced. Positive scoping study at Emba Derho with strong IRR and NPV, Drilling started February 2011

3. Exploration Areas – Exploration drilling on several targets – Q1 2011

• Discovery of potential new VMS district in Madagascar – drilling to begin in spring 2011

• Management team has over 35 years of experience in Eritrea

• Excellent project infrastructure and strong government support

• Well funded - $ 24 million

Page 31: March 2011 Developing Copper, Zinc and Gold Deposits at the Asmara Project, Eritrea

31

Regulatory Notes

All of Sunridge Gold’s exploration programs and pertinent disclosure of a technical or scientific nature are prepared by, or prepared under the direct supervision of Michael J. Hopley, CPG, Sunridge Gold’s President and CEO, who serves as the qualified person (QP) under the definitions of National Instrument 43-101.

Certain disclosures in this presentation, including management’s assessment of Sunridge Gold’s plans and projects constitute forward-looking statements that are subject to numerous risks, uncertainties, and other factors that may cause future results to differ materially from those expressed or implied. Readers are cautioned not to place undue reliance on forward-looking statements.