Maplewood Middle School
Addition
Board of Education Meeting
May 7, 2012
Approval Process
• Identify Program Requirements and Budget• Develop Design Documents • NJDOE Approval (educational capacity)• Planning Board Courtesy Review• NJDCA Approval (specification codes)• Bid• Construct
Identify Program RequirementsSchool Year Middle School Enrollments Increase Over Previous Year
2002-2003 1,547
2003-2004 1,504 (40)
2004-2005 1,468 (36)
2005-2006 1,414 (54)
2006-2007 1,371 (43)
2007-2008 1,332 (39)
2008-2009 1,356 14
2009-2010 1,394 38
2010-2011 1,404 10
2011-2012 1,416 57
2012-2013 projected 1,440 24
2013-2014 projected 1,544 104
2014-2015 projected 1,584 40
Develop Design Documents
• 2010-2011 Confirmed Need to Address Increasing Enrollment
• 2010-2011 Identified Need to Renovate Science Labs
• Reviewed 2001-2003 Original Addition Plans • Updated Plans for current needs, efficiencies,
and cost analysis• 2011-2012 Funding for Project Identified
Plan Development and Approvals
• NJDOE Approved Project and Educational Capacity
• Maplewood Planning Board Raised question regarding brick façade facing Maple Avenue and Impact on Existing Foliage
• Interior Details Being Finalized for Submittal to NJDCA
Future Timeline
• June 2012 Submittal to DCA• Summer 2012 Bid for Project
• (dependent on DCA review)
• September 2012 Begin Construction• (dependent on DCA review)
• September 2013 Opening of New Addition
Site Plan for
Maplewood Middle School
Addition
Existing BuildingFront FaçadeFacing Burnet Street
Addition Facing the Front of the School
View from Rear of Addition
Existing Building Side View Facing Maple Avenue
Side of Addition Facing Maple Ave
Revised Side View for Discussion
Existing Tree in Front of Maplewood Middle School Near the Site of the Addition
First and Second Floor Science Labs
Basement Level Classrooms
What’s Next?• Finalization of Plans and Internal Space• June 2012 Submittal to DCA• Summer 2012 Bid for Project • September 2012 Begin Construction• September 2013 Opening of New Addition
Communication to Neighbors:– Sign up for Notification this evening– Send contact information to: