Modernization of Manpasand Manufacturing
facility in VadodaraPresented by:Jacob Mathew140201065Mahesh Rao P B 140201071Manas Singh 140201072Pranav Pothan 140201097Ritvik Bharat 140201114Sebin Devasia 140201143Vatsal Gupta 140201050
Manpasand Beverages Limited• Gujarat based fruit drink manufacturing company • Established in 1997 by Dhirendra Singh• 2 manufacturing facilities in Vadodara and 1 in UP• Products ‘Mango Sip’, ‘Manpasand ORS’, ‘Apple Sip’• Private equity major SAIF partners made an investment of $10 million• Raised about Rs. 400 crore by issuing 12.5 million shares for expansion plan• Challenges faced
Solution to the challenge• Manpasand has a capacity of 9 lakh litres per day• New manufacturing plant in Punjab with capital expenditure of 150 crore, will
increase capacity by 50%• Modernizing its manufacturing plants in Varanasi and Vadodara with estimated cost
of around 40 crore• Separate production lines for PET bottles and PET bottle for carbonated fruit drinks.• Will include installing new plant and machinery like
• Fully automated Pet bottle manufacturing machine• Fully automated Filling machine• Fully automated Capping machine
How the machines operate
Scope
Stakeholders
Internal stakeholders • Employees of
Manpasand• Management team of
Manpasand• Owners
External stakeholders • Suppliers• Government of India• Customers of
Manpasand• Approval agencies like
Pollution Control Board, Municipal Corporation, Water authority, and Electricity board
• Creditors• Society
Work Breakdown Structure
Survey
• Shortlist potential suppliers
• Estimate the time and cost
Land acquisition
• Plant in Vadodara
• 0.5 acre of land
Designing factory layout
• Building plan• Electrical
wiring diagram
• Plumbing layout plan
Approval for expansion
• Municipal Corporation
• Pollution control board
• Power consumption approval
• Water supply permission
Factory expansion
• 2 machines each
• Space for warehousing
Ordering and installation
• Procurement team place order
• Installation by supplier
Quality check
• By Manpasand engineers
Training
• Operate the machines
• Operate PLC
Documents
• Warranty card
• Insurance• Machine
manuals
Activity Duration EstimateActivity Time
Survey 2 week
Land acquisition 1 month
Designing factory layout 2 weeks
Approval for expansion 4 month
Factory expansion 6 month
Equipment ordering and installation 1.5 month
Quality check 3 days
Training 1 week
Documentation: Insurance and warranty 1 week
Cost EstimateActivity Cost in crore
Land acquisition 1.1
Factory expansion 3
Equipment ordering and installation 1.1
Labor wages 0.17
Supervisor wages 0.05
Approval for expansion 0.05
Training 0.01
Total cost 5.48
Contingency @ 5% 0.274
Total cost after contingency 5.754
Project Scheduling
Project Scheduling• Critical path 1-2-4-5-6-7-8 and 1-2-4-5-6-7-9• Completion time as 10 months 26 days
Activity Early Start Early Finish Late Start Late Finish Total Slack(weeks)
Free Slack(weeks)
Survey 12/1/2015 12/14/2015 12/1/2015 12/14/2015 0 0
Land acquisition 12/15/2015 1/11/2016 12/15/2015 1/11/2016 0 0
Design factory layout
12/15/2015 12/28/2015 12/29/2015 1/11/2016 2 2
Approval for expansion
1/12/2016 5/2/2016 1/12/2016 5/2/2016 0 0
Factory Expansion
5/3/2016 10/17/2016 5/3/2016 10/17/2016 0 0
Equipment Ordering and Installation
9/6/2016 10/17/2016 9/6/2016 10/17/2016 0 0
Quality Check 10/18/2016 10/20/2016 10/18/2016 10/20/2016 0 0
Training 10/21/2016 10/27/2016 10/21/2016 10/27/2016 0 0
Documentation 10/21/2016 10/27/2016 10/21/2016 10/27/2016 0 0
Managing Risk
Risk identification• Machines fail • Raw material supply halts • Electricity supply fail • Water supply fail • Workers strike • Estimating
Risk Assessment
Managing Risk
Risk Assessment Form
Risk Event Likelihood Impact Detection difficulty
When
Machine fail 2 5 3 During quality check
Electricity supply fail
1 5 5 During expansion of factory and installation
Water supply fail
2 4 4 During expansion of factory and installation
Raw material supply halts
4 4 2 During expansion of factory
Worker strike 1 4 1 During expansion of factory
Estimating 2 2 5
Risk Severity Matrix
Quality Management• Typical for PET bottle production lines to yield quite a few sub-
standard products
• High velocity of product movement increases the number of defects • Use intelligent electronic technologies of visual data processing
Low Quality Raw Materials Failure of
Equipment
Working Principle
Reference Image
Equipment
Installation
MonitorTransmits Product Details
Accept or Reject Piece
Saves Data