TRANSCRIPT
MANCHESTER AIRPORT
GROUP
Tom Wilne
Project Delivery Director
2
MANCHESTER AIRPORTS GROUP
Manchester Airport - MAN
26.5m passengers
UK’s 3rd largest airport
70+ airlines & 210+ destinations
2 runways with 50% spare capacity
22m people within a 2 hour drive
London Stansted Airport – STN
24m passengers
UK’s 4th largest airport
150+ destinations
1 runway with 50% spare capacity
25m people within a 2 hour drive
Acquired February 2013
MAG Property
MAG has a property portfolio of >£600m
c.500 properties and 1,000 tenants
Lead partner in £800m Airport City Manchester
MAG-USA
Created in June 2015
Airport services company – car parks, lounges, retail and
terminal redevelopment
East Midlands Airport - EMA
4.7m passengers
UK’s largest freight airport after Heathrow – 326,000
tonnes p.a.
Located next to key road interchanges – four hours from
virtually all UK commerce
Bournemouth Airport - BOH
0.7m passengers
Significant investment in new terminal increasing
passenger capacity to 3m p.a.
Wealthy catchment area
Large land holding – on-site business park
VISION ZERO – DESIGN IT SAFE, BUILD IT SAFE, OPERATE IT
SAFELY
Keeping people safe is our top priority.
Nobody should be harmed by our business.
OUR DEVELOPMENT PLANS
STANSTED DEVELOPMENTBuilding for the Future
6
Upgrade to airside infrastructure to support an
increase in peak hour movements from 50 to 55 per
hour and to support parking for based aircraft.
• 36 new remote aircraft stands
• New Rapid Access Taxiway
• New Rapid Exit Taxiway
Arr
ivals
Depart
ure
sA
irsid
e
The Arrivals Terminal is positioned between the
current main terminal and the Radisson Blu hotel.
This dedicated arrivals building will provide
immigration, baggage reclaim, customs and
baggage (5,500 bhp).
Three level building with ~35,000 m2 floor area
The existing terminal will be transformed to a
dedicated departure only building providing.
• 130+ shore line check in & second security area
• Expanded IDL with additional seating
• Extended Remote Bussing Gate Facility (12
Gates)
The programme is focussed on three key areas that will deliver capacity to maximise
our single runway operations
Stansted Transformation Programme Overview
19/05/2017 7
Arrivals Building
Arrivals building will provide passenger facilities to support 43 mppa in a single
consolidated facility
The short term capacity challenge will be addressed by three schemes in Phase 1C
heck I
n Phase 1 of check-in works provides 30 new check-in desks
and represents the first phase of the shoreline check-in area
and reconfiguration of the departure concourse.
Increase in check-in desks necessary to support forecast
demand.
IDL
Five projects identified to improve the mix of retail and
increase seating.
Projects include reconfiguration of domestic reclaim and
departure lounge additional free seating.
Works due to be delivered during FY18.
Airfield
The new stands will be constructed together with part of the
new access taxiway and will form an extension to the existing
Echo stands. Increases overall stands from 68 to 76 narrow
bodies aircraft equivalents (Code C).
Options regarding building phases still being determined.
Short Term Capacity Needs – Phase 1
9
Long Term Capacity Growth – Phase 2
Programme
Financial year 17 17/18 18/19 19/20 20/21 21/22 22/23 23/24
Quarter 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Phase 1
Check-in, stands, retail
Phase 2
Arrivals building
Departure building
Sat 2 (sky link)
Car parks
Phase 3
Airfield - Stands
Airfield – RET and
RAT
Planning
Applications
Arrivals building
35 mppa
Legend Design and Procurement Delivery Completion
MANCHESTER – NORTHERN POWER
HOUSE
GROWTH, ASPIRATION & AMBITION
MANCHESTER AIRPORT TRANSFORMATION PROGRAMME
MANCHESTER AIRPORT TRANSFORMATION
PROGRAMME Manchester Airport investing £1bn to become one of the most modern and customer focused airports in Europe
• New stands and piers, offering improved departure
gate facilities
• A new forecourt and parking facilities
• Taxiway and airside road improvements,
providing efficient operations
• Safe-guarding for US Pre Clearance
opportunity
A NEW PASSENGER APPROACH
Improvements to the airport include new roads, car parks, a forecourt and a new front door.
New high level access road from
the motorway
New and modified road layout and
traffic flows
New multi-storey car parks
New forecourt and public areas
A MODERNISED AIRFIELD
• Increase in contact stands with
ability to optimise pier service
levels
• Simplified dual taxiway system
• More efficient airfield operating
environment
• Modern and future-proofed stand
layouts
• Safe guarded space for a fourth
pier
Concept design and latest thinking
FLEXIBLE STAND CONFIGURATION
MANCHESTER PROGRAMME DELIVERY PARTNERS
18