managing project processes managing project processes

79
Managing Managing Project Project Processes Processes

Upload: anna-copeland

Post on 12-Jan-2016

231 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Managing Project Processes Managing Project Processes

Managing Managing ProjectProjectProcessesProcesses

Page 2: Managing Project Processes Managing Project Processes

Characteristics of a ProjectCharacteristics of a Project

• A unique, one-time effort

• Requires completion of a large number of interrelated activities

• Resources, such as time and/or money, are limited

• Typically has its own management structure

Page 3: Managing Project Processes Managing Project Processes

Critical Path Method (CPM)Critical Path Method (CPM)

• Designed to provide intense micro-control

• System is dynamic; it continues to provide periodic reports as project progresses

Page 4: Managing Project Processes Managing Project Processes

Manager’s View of CPMManager’s View of CPM

• List of project activitiesList of project activities• Precedence relationship among activitiesPrecedence relationship among activities• Estimate of each activity’s durationEstimate of each activity’s duration

• Estimated duration of projectEstimated duration of project• Identification of critical activitiesIdentification of critical activities• Amount of slack for each activityAmount of slack for each activity

CPM processing proceduresCPM processing procedures

Page 5: Managing Project Processes Managing Project Processes

CPM TerminologyCPM Terminology• Activity

– A task or certain amount of work required in the project

– Requires time to complete– Represented by an arc (AOA) or a node (AON)

• Dummy activity (AOA only)

– Indicates only precedence relationships– Does not require any time of effort

11 22

33

55

66

44 77

88a

b

e

d

c

h

g

f

i

Page 6: Managing Project Processes Managing Project Processes

CPM TerminologyCPM Terminology• Network

– Shows sequential relationships among activities using nodes and arrows

11 22

33

55

66

44 77

88a

b

e

d

c

h

g

f

i

Page 7: Managing Project Processes Managing Project Processes

CPM TerminologyCPM Terminology• Path

– Connected sequence of activities leading from starting event to ending event

• Critical path– Longest path (time); determines project

duration

• Critical activities– All of the activities that make up critical

path

Page 8: Managing Project Processes Managing Project Processes

CPM TerminologyCPM Terminology• Earliest start (ES)

– Earliest that an activity can begin; assumes all preceding activities have been completed

• Earliest finish (EF)– ES + activity time

• Latest finish (LF)– Latest that an activity can finish and not change

project completion time• Latest start (LS)

– LF - activity time

Page 9: Managing Project Processes Managing Project Processes

Steps in CPM AnalysisSteps in CPM Analysis

• Draw the CPM network– A graphic view of relationships among

required activities

• Path analysis– Determine length of each path (time

required to complete each path)– Longest path is the critical path

Page 10: Managing Project Processes Managing Project Processes

Steps in CPM AnalysisSteps in CPM Analysis• Network analysis

– Working from left to right, find the EF and ES for each activity

– Working from right to left, find LF and LS for each activity

– Compute activity’s slack• Total Slack = LS - ES = LF - EF • This slack is shared with other activities

– Free slack• Time an activity may be delayed without impacting the ES of

successor activities

Page 11: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s HospitalImmediate

Activity Description Predecessor(s)

ASelect administrative and medical staff.BSelect site and do site survey.CSelect equipment.DPrepare final construction plans and layout.EBring utilities to the site.FInterview applicants and fill positions in nursing,

support staff, maintenance, and security.GPurchase and take delivery of equipment.HConstruct the hospital.IDevelop an information system.JInstall the equipment.KTrain nurses and support staff.

Page 12: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s HospitalImmediate

Activity Description Predecessor(s)

ASelect administrative and medical staff.—BSelect site and do site survey.—CSelect equipment.ADPrepare final construction plans and layout.BEBring utilities to the site.BFInterview applicants and fill positions in nursing,

support staff, maintenance, and security.AGPurchase and take delivery of equipment.CHConstruct the hospital.DIDevelop an information system.AJInstall the equipment.E,G,HKTrain nurses and support staff.F,I,J

Page 13: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s HospitalImmediate

Activity Description Predecessor(s)

ASelect administrative and medical staff.—BSelect site and do site survey.—CSelect equipment.ADPrepare final construction plans and layout.BEBring utilities to the site.BFInterview applicants and fill positions in nursing,support staff, maintenance, and security.AGPurchase and take delivery of equipment.CHConstruct the hospital.DIDevelop and information system.AJInstall the equipment.E,G,HKTrain nurses and support staff.F,I,J

Completion Time

Page 14: Managing Project Processes Managing Project Processes

ImmediateActivity Description Predecessor(s)

ASelect administrative and medical staff.—BSelect site and do site survey.—CSelect equipment.ADPrepare final construction plans and layout.BEBring utilities to the site.BFInterview applicants and fill positions in nursing,support staff, maintenance, and security.AGPurchase and take delivery of equipment.CHConstruct the hospital.DIDevelop and information system.AJInstall the equipment.E,G,HKTrain nurses and support staff.F,I,J

St. Adolf’s HospitalSt. Adolf’s Hospital

Completion Time

Start

A12

Page 15: Managing Project Processes Managing Project Processes

ImmediateActivity Description Predecessor(s)

ASelect administrative and medical staff.—BSelect site and do site survey.—CSelect equipment.ADPrepare final construction plans and layout.BEBring utilities to the site.BFInterview applicants and fill positions in nursing,support staff, maintenance, and security.AGPurchase and take delivery of equipment.CHConstruct the hospital.DIDevelop and information system.AJInstall the equipment.E,G,HKTrain nurses and support staff.F,I,J

St. Adolf’s HospitalSt. Adolf’s Hospital

Completion Time

Start

A12

B9

Page 16: Managing Project Processes Managing Project Processes

ImmediateActivity Description Predecessor(s)

ASelect administrative and medical staff.—BSelect site and do site survey.—CSelect equipment.ADPrepare final construction plans and layout.BEBring utilities to the site.BFInterview applicants and fill positions in nursing,support staff, maintenance, and security.AGPurchase and take delivery of equipment.CHConstruct the hospital.DIDevelop and information system.AJInstall the equipment.E,G,HKTrain nurses and support staff.F,I,J

St. Adolf’s HospitalSt. Adolf’s Hospital

Completion Time

StartC

10

A12

B9

Page 17: Managing Project Processes Managing Project Processes

ImmediateActivity Description Predecessor(s)

ASelect administrative and medical staff.—BSelect site and do site survey.—CSelect equipment.ADPrepare final construction plans and layout.BEBring utilities to the site.BFInterview applicants and fill positions in nursing,support staff, maintenance, and security.AGPurchase and take delivery of equipment.CHConstruct the hospital.DIDevelop and information system.AJInstall the equipment.E,G,HKTrain nurses and support staff.F,I,J

St. Adolf’s HospitalSt. Adolf’s Hospital

Completion Time

StartC

10

D10

A12

B9

Page 18: Managing Project Processes Managing Project Processes

ImmediateActivity Description Predecessor(s)

ASelect administrative and medical staff.—BSelect site and do site survey.—CSelect equipment.ADPrepare final construction plans and layout.BEBring utilities to the site.BFInterview applicants and fill positions in nursing,support staff, maintenance, and security.AGPurchase and take delivery of equipment.CHConstruct the hospital.DIDevelop and information system.AJInstall the equipment.E,G,HKTrain nurses and support staff.F,I,J

St. Adolf’s HospitalSt. Adolf’s Hospital

Completion Time

StartC

10

D10

E24

A12

B9

Page 19: Managing Project Processes Managing Project Processes

ImmediateActivity Description Predecessor(s)

ASelect administrative and medical staff.—BSelect site and do site survey.—CSelect equipment.ADPrepare final construction plans and layout.BEBring utilities to the site.BFInterview applicants and fill positions in nursing,support staff, maintenance, and security.AGPurchase and take delivery of equipment.CHConstruct the hospital.DIDevelop and information system.AJInstall the equipment.E,G,HKTrain nurses and support staff.F,I,J

St. Adolf’s HospitalSt. Adolf’s Hospital

Completion Time

Start

F10

C10

D10

E24

A12

B9

Page 20: Managing Project Processes Managing Project Processes

ImmediateActivity Description Predecessor(s)

ASelect administrative and medical staff.—BSelect site and do site survey.—CSelect equipment.ADPrepare final construction plans and layout.BEBring utilities to the site.BFInterview applicants and fill positions in nursing,support staff, maintenance, and security.AGPurchase and take delivery of equipment.CHConstruct the hospital.DIDevelop and information system.AJInstall the equipment.E,G,HKTrain nurses and support staff.F,I,J

St. Adolf’s HospitalSt. Adolf’s Hospital

Completion Time

Start

F10

C10

D10

E24

G35

A12

B9

Page 21: Managing Project Processes Managing Project Processes

ImmediateActivity Description Predecessor(s)

ASelect administrative and medical staff.—BSelect site and do site survey.—CSelect equipment.ADPrepare final construction plans and layout.BEBring utilities to the site.BFInterview applicants and fill positions in nursing,support staff, maintenance, and security.AGPurchase and take delivery of equipment.CHConstruct the hospital.DIDevelop and information system.AJInstall the equipment.E,G,HKTrain nurses and support staff.F,I,J

St. Adolf’s HospitalSt. Adolf’s Hospital

Completion Time

Start

F10

C10

D10

E24

G35

H40

A12

B9

Page 22: Managing Project Processes Managing Project Processes

ImmediateActivity Description Predecessor(s)

ASelect administrative and medical staff.—BSelect site and do site survey.—CSelect equipment.ADPrepare final construction plans and layout.BEBring utilities to the site.BFInterview applicants and fill positions in nursing,support staff, maintenance, and security.AGPurchase and take delivery of equipment.CHConstruct the hospital.DIDevelop and information system.AJInstall the equipment.E,G,HKTrain nurses and support staff.F,I,J

St. Adolf’s HospitalSt. Adolf’s Hospital

Completion Time

Start

I15

F10

C10

D10

E24

G35

H40

A12

B9

Page 23: Managing Project Processes Managing Project Processes

ImmediateActivity Description Predecessor(s)

ASelect administrative and medical staff.—BSelect site and do site survey.—CSelect equipment.ADPrepare final construction plans and layout.BEBring utilities to the site.BFInterview applicants and fill positions in nursing,support staff, maintenance, and security.AGPurchase and take delivery of equipment.CHConstruct the hospital.DIDevelop and information system.AJInstall the equipment.E,G,HKTrain nurses and support staff.F,I,J

St. Adolf’s HospitalSt. Adolf’s Hospital

Completion Time

Start

I15

F10

C10

D10

E24

G35

H40

J4

A12

B9

Page 24: Managing Project Processes Managing Project Processes

ImmediateActivity Description Predecessor(s)

ASelect administrative and medical staff.—BSelect site and do site survey.—CSelect equipment.ADPrepare final construction plans and layout.BEBring utilities to the site.BFInterview applicants and fill positions in nursing,support staff, maintenance, and security.AGPurchase and take delivery of equipment.CHConstruct the hospital.DIDevelop and information system.AJInstall the equipment.E,G,HKTrain nurses and support staff.F,I,J

St. Adolf’s HospitalSt. Adolf’s Hospital

Completion Time

Start

K6

I15

F10

C10

D10

E24

G35

H40

J4

A12

B9

Page 25: Managing Project Processes Managing Project Processes

ImmediateActivity Description Predecessor(s)

ASelect administrative and medical staff.—BSelect site and do site survey.—CSelect equipment.ADPrepare final construction plans and layout.BEBring utilities to the site.BFInterview applicants and fill positions in nursing,support staff, maintenance, and security.AGPurchase and take delivery of equipment.CHConstruct the hospital.DIDevelop and information system.AJInstall the equipment.E,G,HKTrain nurses and support staff.F,I,J

St. Adolf’s HospitalSt. Adolf’s Hospital

Completion Time

FinishStart

K6

I15

F10

C10

D10

E24

G35

H40

J4

A12

B9

Page 26: Managing Project Processes Managing Project Processes

ImmediateActivity Description Predecessor(s)

ASelect administrative and medical staff.—BSelect site and do site survey.—CSelect equipment.ADPrepare final construction plans and layout.BEBring utilities to the site.BFInterview applicants and fill positions in nursing,support staff, maintenance, and security.AGPurchase and take delivery of equipment.CHConstruct the hospital.DIDevelop and information system.AJInstall the equipment.E,G,HKTrain nurses and support staff.F,I,J

St. Adolf’s HospitalSt. Adolf’s Hospital

Completion Time

FinishStart

K6

I15

F10

C10

D10

E24

G35

H40

J4

A12

B9

Path Expected Time (wks)

A-F-K 28A-I-K 33A-C-G-J-K 67B-D-H-J-K 69B-E-J-K 43

Page 27: Managing Project Processes Managing Project Processes

ImmediateActivity Description Predecessor(s)

ASelect administrative and medical staff.—BSelect site and do site survey.—CSelect equipment.ADPrepare final construction plans and layout.BEBring utilities to the site.BFInterview applicants and fill positions in nursing,support staff, maintenance, and security.AGPurchase and take delivery of equipment.CHConstruct the hospital.DIDevelop and information system.AJInstall the equipment.E,G,HKTrain nurses and support staff.F,I,J

St. Adolf’s HospitalSt. Adolf’s Hospital

Completion Time

FinishStart

K6

I15

F10

C10

D10

E24

G35

H40

J4

A12

B9

Path Expected Time (wks)

A-F-K 28A-I-K 33A-C-G-J-K 67B-D-H-J-K 69B-E-J-K 43

Page 28: Managing Project Processes Managing Project Processes

ImmediateActivity Description Predecessor(s)

ASelect administrative and medical staff.—BSelect site and do site survey.—CSelect equipment.ADPrepare final construction plans and layout.BEBring utilities to the site.BFInterview applicants and fill positions in nursing,support staff, maintenance, and security.AGPurchase and take delivery of equipment.CHConstruct the hospital.DIDevelop and information system.AJInstall the equipment.E,G,HKTrain nurses and support staff.F,I,J

St. Adolf’s HospitalSt. Adolf’s Hospital

Completion Time

FinishStart

K6

I15

F10

C10

D10

E24

G35

H40

J4

A12

B9

Path Expected Time (wks)

A-F-K 28A-I-K 33A-C-G-J-K 67B-D-H-J-K 69B-E-J-K 43

Page 29: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Earliest StartandEarliest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

I

15

F

10

FinishStart

Page 30: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Earliest StartandEarliest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0

I

15

F

10

Earliest start time

FinishStart

Page 31: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Earliest StartandEarliest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

Earliest start time Earliest finish time

FinishStart

Page 32: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Earliest StartandEarliest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

0 9

FinishStart

Page 33: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Earliest StartandEarliest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

9 33

0 9 9 19

FinishStart

Page 34: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Earliest StartandEarliest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22

9 33

0 9 9 19

12 22FinishStart

Page 35: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Earliest StartandEarliest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22

19 59

9 33

0 9 9 19

12 22FinishStart

Page 36: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Earliest StartandEarliest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22

22 57

19 59

9 33

0 9 9 19

12 22FinishStart

Page 37: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Earliest StartandEarliest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22

22 57

59 6319 59

9 33

0 9 9 19

12 22FinishStart

Page 38: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Latest StartandLatest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 6319 59

9 33

0 9 9 19

12 22FinishStart

Page 39: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Latest StartandLatest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 6319 59

9 33

0 9 9 19

12 22

63 69 Latestfinishtime

FinishStart

Page 40: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Latest StartandLatest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 6319 59

9 33

0 9 9 19

12 22

63 69

Lateststarttime

Latestfinishtime

FinishStart

Page 41: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Latest StartandLatest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 6319 59

9 33

0 9 9 19

12 22

48 63

53 63 63 69

59 63

FinishStart

Page 42: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Latest StartandLatest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 6319 59

9 33

0 9 9 19

12 22

48 63

53 63 63 69

24 59

19 59

35 59

59 63

FinishStart

Page 43: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Latest StartandLatest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 6319 59

9 33

0 9 9 19

12 22

48 63

53 63 63 69

14 24 24 59

9 19 19 59

35 59

59 63

FinishStart

Page 44: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Latest StartandLatest Finish Times

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 6319 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63 63 69

14 24 24 59

0 9 9 19 19 59

35 59

59 63

Earliest start time Earliest finish timeLatest start time Latest finish time

Critical path

FinishStart

Page 45: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s HospitalGantt Charts

Page 46: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Activity Slack Analysis

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 6319 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63 63 69

14 24 24 59

0 9 9 19 19 59

35 59

59 63

FinishStart

Page 47: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Activity Slack Analysis

Start

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 6319 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63 63 69

14 24 24 59

0 9 9 19 19 59

35 59

59 63

Finish

Activity Slack

Page 48: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Activity Slack Analysis

Start

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 6319 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63 63 69

14 24 24 59

0 9 9 19 19 59

35 59

59 63

Finish

Activity Slack

Slack = LS – ES

or

Slack = LF – EF

Page 49: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Activity Slack Analysis

K

6

63 6963 69

Start

A

12

C

10

G

35

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22

22 57

19 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63

14 24 24 59

0 9 9 19 19 59

35 59

Activity Slack

SlackK = 63 – 63

or

SlackK = 69 – 69

J

4

59 6359 63

Finish

Page 50: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Activity Slack Analysis

Start

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 6319 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63 63 69

14 24 24 59

0 9 9 19 19 59

35 59

59 63

Finish

Activity Slack

SlackK = 0

or

SlackK = 0

Page 51: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Activity Slack Analysis

Start

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 6319 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63 63 69

14 24 24 59

0 9 9 19 19 59

35 59

59 63

Finish

Page 52: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Activity Slack Analysis

Start

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 6319 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63 63 69

14 24 24 59

0 9 9 19 19 59

35 59

59 63

Finish

Node Duration ES LS Slack

Page 53: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Activity Slack Analysis

Start

A

12

K

6

C

10

G

35

J

4

H

40

B

9

D

10

E

24

0 12

I

15

F

10

12 27

12 22 63 69

22 57

59 6319 59

9 33

0 9 9 19

12 22

48 63

2 14 53 63 63 69

14 24 24 59

0 9 9 19 19 59

35 59

59 63

Finish

Node Duration ES LS Slack

A 12 0 2 2B 9 0 0 0C 10 12 14 2D 10 9 9 0E 24 9 35 26F 10 12 53 41G 35 22 24 2H 40 19 19 0I 15 12 48 36J 4 59 59 0K 6 63 63 0

Page 54: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Critical Path

C

10

G

35

E

24

I

15

F

10

12 27

12 22

22 57

9 33

12 22

48 63

53 63

14 24 24 59

35 59

B

9

0 9

0 9

D

10

9 19

9 19

H

40

19 5919 59

J

4

59 6359 63

K

6

63 6963 69

Finish

Node Duration ES LS Slack

A 12 0 2 2BB 99 00 00 00C 10 12 14 2DD 1010 99 99 00E 24 9 35 26F 10 12 53 41G 35 22 24 2HH 4040 1919 1919 00I 15 12 48 36JJ 44 5959 5959 00KK 66 6363 6363 00

Page 55: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s Hospital

Critical Path

C

10

G

35

E

24

I

15

F

10

12 27

12 22

22 57

9 33

12 22

48 63

53 63

14 24 24 59

35 59

B

9

0 9

0 9

D

10

9 19

9 19

H

40

19 5919 59

J

4

59 6359 63

K

6

63 6963 69

A

12

0 12

2 14

FinishStart

Page 56: Managing Project Processes Managing Project Processes

St. Adolf’s HospitalSt. Adolf’s HospitalActivity Slack

Page 57: Managing Project Processes Managing Project Processes

Program Evaluation andProgram Evaluation andReview Technique (PERT)Review Technique (PERT)• PERT is based on assumption that an

activity’s duration follows a probability distribution instead of being a single value.

• Probabilistic information about activities is translated into probabilistic information about project.

Page 58: Managing Project Processes Managing Project Processes

PERTPERT

• Three time estimates are required to compute parameters of an activity’s duration distribution:– Pessimistic time (b ) - time activity would

take if things did not go well

– Most likely time (m ) - consensus best estimate of activity’s duration

– Optimistic time (a ) - time activity would take if things did go well

Page 59: Managing Project Processes Managing Project Processes

Steps in PERT AnalysisSteps in PERT Analysis

• Draw network as in CPM• Analyze paths through network and find

critical path• Length of critical path is mean of project

duration probability distribution– assumed to be normal (really beta)

– 50% probability the project will be completed in this amount of time

Page 60: Managing Project Processes Managing Project Processes

Steps in PERT AnalysisSteps in PERT Analysis

• Standard deviation of project duration is computed by adding variances of critical activities (all activities that make up critical path) and taking square root of that sum

• Probability computations can now be made using normal distribution table

Page 61: Managing Project Processes Managing Project Processes

Calculating Probabilistic Calculating Probabilistic Activity TimesActivity Times• Three time estimates

– optimistic (a)– most likely (m)– pessimistic (b)

22

( 4 )

6

6

( )6

e

a m bt

b a

b a

Page 62: Managing Project Processes Managing Project Processes

a, m, and b Estimatesa, m, and b Estimates

Page 63: Managing Project Processes Managing Project Processes

PERT Example

Page 64: Managing Project Processes Managing Project Processes
Page 65: Managing Project Processes Managing Project Processes
Page 66: Managing Project Processes Managing Project Processes
Page 67: Managing Project Processes Managing Project Processes

Question

• What is the probability of completing the project within 23 weeks?

Page 68: Managing Project Processes Managing Project Processes
Page 69: Managing Project Processes Managing Project Processes

• Look up z value in normal distribution table – see page 457 in text

• Z=1.52 corresponds to area under the curve of .9357

• Probability project completes within 23 days equals .9357

Page 70: Managing Project Processes Managing Project Processes

• Probability project completes takes longer than 23 days equals .0643 (1.0 - .9357)

Page 71: Managing Project Processes Managing Project Processes

Project Life CycleProject Life Cycle

Definition and

organization

Planning Execution Close out

Start Finish

Res

ou

rce

req

uir

emen

ts

Time

Page 72: Managing Project Processes Managing Project Processes

Activity Cost-Time TradeoffsActivity Cost-Time Tradeoffs

• Project managers may have option or requirement to crash project, or accelerate completion of project.

• This is accomplished by reducing length of critical path(s).

• Length of critical path is reduced by reducing duration of activities on critical path.

Page 73: Managing Project Processes Managing Project Processes

Cost-Time Cost-Time TradeoffsTradeoffs• If each activity requires expenditure of an

amount of money to reduce its duration by one unit of time, then project manager selects least cost critical activity, reduces it by one time unit, and traces that change through remainder of network.

Page 74: Managing Project Processes Managing Project Processes

Cost-Time Cost-Time TradeoffsTradeoffs• As a result of a reduction in an activity’s

time, a new critical path may be created.

• When there is more than one critical path, each of the critical paths must be reduced.

• If length of project needs to be reduced further, process is repeated.

Page 75: Managing Project Processes Managing Project Processes

Computer Software Computer Software for Project for Project ManagementManagement• Artemis Views (Artemis Management Systems)

• FastTrack Schedule (AEC Software)• Microsoft Project (Microsoft Corp.)• Oracle Projects (Oracle Corp.)• PowerProject (ASTA Development)• Primavera Project Planner (Primavera Systems)• SuperProject (Computer Associates International)• TurboProject (IMSI)

Page 76: Managing Project Processes Managing Project Processes
Page 77: Managing Project Processes Managing Project Processes
Page 78: Managing Project Processes Managing Project Processes
Page 79: Managing Project Processes Managing Project Processes

Evaluation of Evaluation of CPM/PERTCPM/PERT

• Activities are assumed to be independent.• A precise breaking point where one activity ends

and another begins is also assumed.• Initially-critical activities might not receive attention

they deserve until it is too late.• Activity time estimates might be biased.• Cost of CPM/PERT might not be justified by value

of information it provides.• Employees might not understand statistical

underpinnings of PERT.