Managing Mobility:Engineering an Express Lane Network
ITS CaliforniaOctober 15, 2014
Lisa Klein, PrincipalMetropolitan Transportation Commission
![Page 2: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/2.jpg)
MTC Wears Many Hats
2
Metropolitan Transportation Commission (MTC) —Since 1971. Planner, coordinator, manager and banker.
Bay Area Toll Authority (BATA) — Since 1998. Responsible for collecting tolls, overseeing seismic retrofitting of the state toll bridges and running the FasTrak® electronic toll collection program.
![Page 3: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/3.jpg)
What is an Express Lane?
3
• High Occupancy Toll (HOT) Lanes• HOV with toll option
– Carpools, buses free – Other drivers can choose to pay
• Electronic toll• Dynamic tolls keep lane free
flowing (congestion pricing)
![Page 4: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/4.jpg)
Why Express Lanes?
While the region grows…Spending on new infrastructure is set
4
![Page 5: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/5.jpg)
5
Goal: Improve Mobility• Encourage carpools and
express buses• Make the best use of HOV
lane capacity• Offer a new choice • Provide more reliable
travel times
Bay Area Express Lanes
5
Authorized Express Lanes
![Page 6: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/6.jpg)
6
Bay Area Express Lanes Network by Operator
6
Regional Coordination• Executives• Technical Staff• Public Information Staff
![Page 7: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/7.jpg)
Bay Area Express Lanes Web Portal
7
![Page 8: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/8.jpg)
Regional Customer Service Center
8
BATA Regional Customer Service Center
ACTC I‐680I‐580 (2015) Express Lanes
VTA SR‐237 US 101/237 (2017)Express Lanes
Golden Gate BridgeAutomatic Tolling BATA
7 State‐OwnedToll Bridges
SFO Parking
MTCExpress Lanes
(2016)
![Page 9: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/9.jpg)
9
MTC Focus
![Page 10: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/10.jpg)
10
• The Bay Area Infrastructure Financing Authority was created by MTC and BATA in 2006 to finance the toll bridge seismic program.
• Amended in 2011 to include implementation, operation and financing of express lane for MTC.
• Membership can be augmented as the network grows
Bay Area Infrastructure Financing Authority Membership 1. MTC Chair 2. BATA Oversight Chair 3. MTC Commissioner from Alameda County4. MTC Commissioner from Contra Costa County 5. MTC Commissioner from Solano County 6. Cal STA (non‐voting)
10
Multi‐County Governance
![Page 11: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/11.jpg)
Opportunities and Challenges
11
![Page 12: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/12.jpg)
Opportunities and Challenges
12
![Page 13: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/13.jpg)
Achieving Mobility Improvements• Mostly single lane in each direction• Maintain open access where possible
– Use buffers where necessary
• Dynamic pricing• Enforcement
13
![Page 14: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/14.jpg)
Mobility Improvements by Managing Weaving
14
![Page 15: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/15.jpg)
Enforcement• Switchable toll tags• License plate recognition• Increased CHP presence
• Beacon light alerts• CHP enforcement areas• Citations issued for violations
15
![Page 16: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/16.jpg)
Toll System Innovations• Single contract for three corridors with the ability to add corridors
16
• Complex trip building due to open access. Must match toll tags and license plates consistently, multiple times.
![Page 17: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/17.jpg)
Backhaul Network• Data communications network• Repair existing, empty conduit• Down payment on a broader regional transportation
communications network
17
![Page 18: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/18.jpg)
Progress
181818
In Progress• Environmental: I‐880, I‐680 Northern
Segment; I‐80• Communications Backhaul Network design• Toll system design• I‐680 civil design• Review sequencing of next projects
Next Steps 2015• Backhaul construction contract• I‐680 civil construction contract• Civil design on I‐880, SOL‐80• Managed Lanes Implementation Plan
Complete• Concept of Operations• Toll System Integrator awarded• I‐680 Southern Segment environmental
![Page 19: Managing Mobility: Engineering an Express Lane Network · 15/10/2014 · Golden Gate Bridge Automatic Tolling BATA](https://reader031.vdocuments.us/reader031/viewer/2022031010/5b94766d09d3f22b0a8d5150/html5/thumbnails/19.jpg)
Managed Lanes Implementation Plan
19
• Define and evaluate the performance of existing, planned and expanded system
• Assess managed lanes policies (e.g., vehicle occupancy, hours of operations, access)
• Evaluate system enhancements (e.g., freeway management, express bus, park‐ride lots)
• Engage partner agencies & interested organizations