managing electrical connections systems and wire integrity on … · 2002. 2. 7. · 4 aging wiring...
TRANSCRIPT
-
1
Managing Electrical Connections Systems and Wire Integrity on Legacy Aerospace Vehicles
Presented by:Presented by:Luci Crittenden, ATSRAC MemberLuci Crittenden, ATSRAC MemberNASA Langley Research CenterNASA Langley Research Center
-
2
Managing Electrical Connections Systems and Wire Integrity on Legacy Aerospace Vehicles
Steven SullivanSteven SullivanKennedy Space CenterKennedy Space Center
NASANASAand and
George SlenskiGeorge SlenskiMaterials DirectorateMaterials Directorate
Air Force Research LaboratoryAir Force Research Laboratory
-
3
Outline
! Introduction
! Aging Wiring Issues
! Shuttle Wiring Failure
! Shuttle Wiring Inspections
! Conclusions
-
4
Aging WiringWiring is just one part of the electrical Interconnection system
– Wiring, connectors, relays, circuit breakers, powerdistribution panels, and generators makeup the system
Aging wiring can be understood as degraded performancedue to accumulated damage from long-term exposure.
– Damage is from chemical, thermal, electrical, andmechanical stresses
– Stresses are often induced by the operationalenvironment and installation and maintenance practices
– Wiring failures often appear as broken conductors anddamaged insulation which can disrupt electrical signalsand/or lead to arcing.
-
5
Wiring System FailuresWiring System Failures
In-Flight Electrical FireIn-Flight Electrical Fire InitiationInitiation
Site Site
-
6
Chafed Wire Failure
Phase A
Phase B
Phase C
Failure Initiated by DegradedBearings and Wire Chafing
-
7
Wiring Failure MechanismsWiring Failure Mechanisms
ElectricalElectrical MechanicalMechanical
ChemicalChemicalThermalThermal
-
8
Arc Tracking Wire Failures
Field FailureField Failure
Dry Arc TrackingDry Arc Tracking
PolyimidePolyimide Insulation Insulation(Mil-W-81381)(Mil-W-81381)
-
9
Aging Aircraft Wiring Systems
Wiring Failure Data for a Typical Fighter–46% Broken Wires–30 % Insulation Chafing Damage–14% Outer Layer Chafing–10% Failure in Contractor Connector
-
10
Function
interconnections 43%
electronics 23%
electromechanical 34%
System
instruments 26%
power systems 45%
avionics 9%
total electrical failure-system
unknown 1%
fuel systems 8%
flight control 11%
Age Groups of Mishap Aircraft
0
10
20
30
40
50
60
70
2 to 5 6 to 10 11 to 15 16 to 20 21 to 25 26 to 30 31 to 35 36 to 53
AF Mishap Data For Electronic RelatedFailures
(1989-99)
Data provided by the AF Safety Agency
-
11
AF Mishap Data Related to ElectronicFailures (1989-99)
Components Contributing to AF Mishaps
conductors 29%
light 0%
generator 18%
batteries 1%
capacitors 1%
circuit breakers 2%
avionics 7%
electric panel 8%
fuel probe 1%
relays 7%
motors 2%
resistors 1%
switch 3%
transformers 6%
connectors 14%
Data provided by the AF Safety Agency
-
12
PROCESS ENGINEERING
OV102 Launch STS-93
-
13
PROCESS ENGINEERING
OV102 Electrical Short- Midbody
-
14
OV102 Electrical ShortPROCESS ENGINEERING
-
15
PROCESS ENGINEERING
-
16
Closeup of Burred ScrewPROCESS ENGINEERING
-
17
Electron Microscope Picture of FaultPROCESS ENGINEERING
No evidence of vibrationinduced damage
(3 Independent Labs andAFRL Mal Lab)
Damage was caused bysignificant impact to cable
Oxide growth revealed thatdamaged wire had flownseveral times
-
18
What To Inspect?? “A learning process”
Orbiter Wire Inspection Decision Logic
Inspect &Repair
Cleared For FlightPerform Inspection
of Areas DuringOMM to Confirm
Validity ofAssumptions
Redefine InspectionCriteria &Corrective
Action
5
HighTrafficArea?
ModWork
?
YES
NO
PRACAHistory?
Redun’Together or
Crit 1/1?
Vulnerable?
NO
InspectionRisk/BenefitAcceptable
?
YES
YES
YES
YES
YES
New RootCause
Identified?
NO
NO
YES
Document Rationale
PROCESS ENGINEERING
-
19
Analysis of W
iring Dam
age History
PRA
CA
SUM
MA
RY (FW
D/M
ID/A
FT)
0
100
200
300
400
500
600
700
Thrust Str (Side Wall/LH2/LO2 Umb/Floor)
Avionics Bay (FWD)
Avionics Bay (AFT)
Below Wire Tray (MID)
VESS
Flight Deck
APU Area
ECLSS
1307 Bulkhead
Mid Deck
Wire Tray
Body Flap
FRCS
SILL/MPM
WING/ELEVON
LNDG GR
Lwr Heat Shield
576 Bulkhead
Mission Station/Pld
ODS/AIRLOCK
Vert Stab
On-Orbit Station
Location
Wire Damage (# of wire)
Series1
Areas Inspected
PRO
CESS EN
GIN
EERIN
G
-
20
PROCESS ENGINEERING
Wire Harness Inspection
-
21
PROCESS ENGINEERING
Wire Harness Inspection
-
22
Orbiter Midbody Wire Harness InspectionPROCESS ENGINEERING
-
23
PROCESS ENGINEERING
Wire Harness Inspection
-
24
PROCESS ENGINEERING
1500 VDC DWV Testing
HOW GOOD IS A DWV TEST (HIPOT)????
-
25
Types of DamagePROCESS ENGINEERING
-
26
Convoluted TubingPROCESS ENGINEERING
-
27
PROCESS ENGINEERING
Glass Cockpit Modifications – MEDS
-
28
PROCESS ENGINEERING
-
29
When you think you have seen everything??PROCESS ENGINEERING
-
30
Wire Harness Separation ModificationPROCESS ENGINEERING
View inside a “closedwire tray”
-
31
Orbiter/ External Tank Electrical Monoball ProductionBreak
PROCESS ENGINEERING
-
32
PROCESS ENGINEERING
“Inspect & Protect” Awareness Campaign
-
33
PROCESS ENGINEERING
Repetitive Dielectric Withstanding Voltage (DWV) Study(Planned)
• Effects of Repetitive DWV
Larry Ludwig – NASA KSC Mal Lab (321)-867-7049
-
34
Solid Rocket Booster Cabling
-
35
Wire Damage MappingPROCESS ENGINEERING
-
36
Wire Damage Mapping - MidbodyPROCESS ENGINEERING
-
37
Transmitter/
Receiver(3 ea)
Xo = 941.6Yo = -86.4Zo = 347.8
PlasticPick-up
Location Aid
Display
Wire Damage Mapping – x y z coordinate locator(Study Phase)
PROCESS ENGINEERING
*Note: Latest concept does not use transmitters
-
38
PROCESS ENGINEERING
LASER 3-D ScanningStudy Phase
-
39
PROCESS ENGINEERING
LASER 3-D Scanning Study Phase
-
40
Standing Wave Reflectometry
PROCESS ENGINEERING
-
41
Summary:
•Scheduled wire inspections at major modification (Performed by twoindependent inspectors NASA quality and USA quality)
•Inspector and technician training and certification on wire damage assessment
•“Hands on Trainer” developed and class
•Wiring specifications tightened and clarified for assessing cable damage
•Maintenance requirements added that when cable clamps removed technicianand quality will fan wire harness out for inspection
•Platforms and area protection on work platforms
•Convoluted tubing installed in “high traffic” areas (>150lbs per orbiter)
•Aging polyamide wire study with Boeing and Lectromec (800 page report)
•Orbiter wire separation study to assess any areas that there may have been aviolation of critical circuits routed together
SummaryPROCESS ENGINEERING