management training jumeirah beach residence sector 3 presented by november 15 th 2006
TRANSCRIPT
Management trainingManagement training
Jumeirah beach residenceJumeirah beach residencesector 3sector 3
Presented by
November 15th 2006
Jumeirah beach residenceJumeirah beach residencesector 3sector 3
7 towers ranging from 30 floors high to 52 floors high
5 level podium out of which 3 levels are car parkingMEP plant rooms in basement, mid-level(s) and roof.
Mechanical systems involvedMechanical systems involvedHVACHVAC
• Air conditioning system• Toilet extract system• Kitchen extract system• Refuse extract system• Lobby relief and stair well
pressuristaion system• Car park ventilation system
Mechanical systems involvedMechanical systems involvedPlumbingPlumbing
• Domestic cold water system• Hot water system
Mechanical systems involvedMechanical systems involvedDrainageDrainage
• Soil waste and vent systems• Rain water systems
Mechanical systems involvedMechanical systems involvedFire protectionFire protection
• Wet riser• Sprinkler protection• FM 200 system• Carbon di oxide system• Pre action system
Air conditioning systemAir conditioning system• Fresh air system• Standalone fan coil units• Common area fan coil units• Dx system for MDF rooms in grade
level
Fresh air systemFresh air system
Pre filtersBag filtersHeat wheelCooling coilSupply and extract fans
FAHU with heat recovery wheelFAHU with heat recovery wheel
Heat wheel
Heat wheel recovers energy from cold toilet exhaustAnd pre cool the fresh air intake
Fresh air systemFresh air system
FAHU are located in plant rooms.
Fresh air intake through sand trap louvers
Fresh air supply to apartments and lobbies
Fan coil unitsFan coil units
Fan coil units are provided with filters, cooling coil and fanAir distribution with ducting and grilles and diffusers
Dx systemDx system
MDF rooms in the gradelevel have been provided with DX system
Units are provided onduty/standby basis
Chilled water systemChilled water system
Energy transfer stations are located in the basement level
Each tower has its own ETS and two dedicated stations for podium.
Chilled water systemChilled water systemTertiaryTertiary
Tertiary heat exchangers and chilled water pumps are located in midlevelPlant rooms.
Toilet extract systemToilet extract system
Fans part of FAHU
Ducting system with ceiling mounted diffusers in toilets
Operation of the fan will be in tandem with FAHU
Kitchen extract systemKitchen extract system
Centrifugal fans located in the plant rooms
Centralised ducting and extract from diffusers mounted in kitchen
Air is passed thru carbon filter assembly (odour removal unit) prior toDischarge to atmosphere.
Refuse extract systemRefuse extract system
Ceiling mounted diffusers in every garbage collection room
Centralised ducting
Fans are located at plant rooms.
Stairwell pressurisationStairwell pressurisationand Lobby relief fansand Lobby relief fans
Both the stair wells will bePressurised in the event ofFire to avoid smoke ingress.
Stairwell pressurisationStairwell pressurisationand Lobby relief fansand Lobby relief fans
Lobby relief fans will ensureThat lobbies are not overPressurised.
Motorised dampers are installedAt every level which will openIn the event of fire
Car park ventilation systemCar park ventilation system
Covers all the three parking levels
View of the exhaust fan riser
Car park ventilation systemCar park ventilation system
Jet fans are locatedThroughout the parkingAreas.
Car park ventilation systemCar park ventilation system
Axial fans are locatedIn fan rooms withMotorised dampersAnd sound attenuators
Water supply system
DEWA incoming supply willBe stored in the basementRCC tank
Transfer pumps feed the mid-Level and roof tanks
Gravity feed to apartments
Penthouse and Loft apartmentsWill be having boosted waterSupply
Tenant water meters are locatedIn mechanical room at each level
Hot water systemHot water system
Decentralized system
Each apartment will haveOne dedicated water heater.
Drainage systemDrainage system• Soil waste and vent systems• FIC’s located at grade level close to
perimeter wall inside the sector• Grease traps have been provided for
retail kitchen waste system.• Sump pumps have been provided for
basement drainage.
Rain water systemRain water system• Roof drains have been provided at
roof and terrace levels• Balcony drains have been installed in
all balconies• Collection and discharge through
dedicated rain water stacks
Fire protection systemFire protection system
One dedicated fire tank in the basement serving entire sector
Fire pumps are on duty and Stand by basis
Ring main at the basement
Podium areas are divided into 7 fire zones
Fire protection systemFire protection system
PRV stations have been located various levels
Each floor has been provided with 2 fire hose reels and 2Landing valves.
All areas are sprinkler protected.
A view of fire protectionBranch off at typical floor
Special fire protection systemsSpecial fire protection systems
• MDF rooms have been protected by FM200 system
Special fire protection systemSpecial fire protection system
LV rooms and generatorrooms have been protectedby CO2 System.
Building management systemBuilding management system
Fully integrated BMS has been provided covering all the towersAnd podium common areas.
Main system with computer and printers are located in theSector control room
DDC’s are installed in all plant rooms.
Remote monitoring and controlling of entire HVAC systemis possible
Supplier: Honeywell