management of the italian electric system current status and challenges luca d’agnese grtn ceo...
TRANSCRIPT
ManagementManagementof the Italian electric systemof the Italian electric system Current status and challenges
Luca D’AgneseGRTN CEO
Beijing, 24-25 October 2005
2
Summary
POWER SYSTEM FEATURES AND DEVELOPMENTS
OPERATIONAL EXPERIENCE
– NTC assessment
– Integrated control and telecontrol system
CHALLENGES
3
Power System Features
Peak Load Demand 54 GW
National Power Generation
84 GW(*)
Imports 7,2 GW
Voltage levels of transmission grid
380-220-150-132 kV
Network configuration
Mesh (EHV)– Radial (HV-MV)
Interconnections AC – DC links
SLOVENIA
FRANCE
AUSTRIASWITZERLAND
430
2203850
2650
300
Market zones and Transmission constraints(Winter limits – peak hours)
035
0
20002000
34002000
360
0
170
0
500
(*) updated at the end of year 2004
4
48,955,5 55,5 55,5 55,5
5,5
4,6 2,4 4,5 6,77,2
7,27,2
2005 20062003 2004
67,2
54,4
60,1
1,3 (2%)1,3 (2%)
2007
65,1
CAGR*** +3,3%
CAGR*** +3,3%
6,6 (12%)6,6 (12%) 11 (20%)11 (20%) 11,1 (19%)11,1 (19%)10,5 (19%)10,5 (19%)
69,4
Capacity vs. Load Demand Summer load demand 2003-2007GW
Load DemandAvailable capacity
Power plants changes*
Import
Internal generation
Reserve margins (GW, % of load demand)
* New power plants and changes due to conversion to combined cycle** Available capacity increase*** Compound Average Growth Rate
58,3
53,553,1
54,156,7
5
Transmission system critical areas 380 kV line overloads
ALBERTVILLE
VILLARODIN
AIROLO
SOAZZA
DIVACCIA
Slovenia
Switzerland
Austria
France
FIUME SANTOCODRONGIANOS
VILLASORSELARGIUS
CAGLIARI SUD
RUMIANCAPORTOSCUSO
SORGENTE
PATERNO’
CHIAROMONTE G.
RIZZICONI
FEROLETOSCANDALE
ROSSANOLAINO
MATERA
GALATINA
Linea a 400 kV c.c.
Greece
BRINDISI
TARANTO N.
BARI OVEST
ANDRIAFOGGIA
MONTECORVINOSTRIANO
BENEVENTO
PATRIA S.SOFIA
S.MARIA C.V.
GARIGLIANO
LARINO
VILLANOVA
TERAMO
CEPRANO
LATINA
VALMONTONEROMA S.
ROMATORVALDALIGA S.
TORVALDALIGA N.MONTALTO
ROSARA
CANDIA
FANO
S.GIACOMO
SUVERETO
PIAN DELLASPERANZA
TAVARNUZZE
CALENZANO
POGGIO A CAIANO
MARGINONE
ACCIAIOLOLIVORNO
LA SPEZIA
VADO LIGURE
S.MARTINOFORLI’
RAVENNA C.COLUNGAMARTIGNONE
S.DAMASO
CARPI
RUBIERA
PARMA
FERRARALA CASELLA
VIGNOLE
CASTELNUOVO
MAGLIANO
VENAUSACC.FERRERO
CASANOVA
PIOSSASCO
LEINI’
RONDISSONE
PLANAIS
REDIPUGLIA
UDINEOVEST
CORDIGNANO
SALGAREDA
VEDELAGOSANDRIGO
VENEZIA N.
DOLOCAMIN
ADRIA
RFX
DUGALE
NOGAROLEROCCA MALCONTENTA
PIASTRA
TRINO N.
TURBIGO
RONCOV.EDOLO
S:FIORANO
OSTIGLIACAORSO
ROSEN
PORTO TOLLE
PORTO CORSINI
MONFALCONE
PIOMBINO
VILLAVALLE
PRESENZANO
ATI
ISAB
SARLUX
BARGI
Power PlantsElectrical StationElectrical station under constructionSingle-circuit lineDouble-circuit lineLine under construction
North-East
Milan
Campania-Calabria
Naples
LombardiaPiem.-Valle d'Ao.LiguriaTrentino’s pathPugliaOthers
Overload*
Area
High-medium critical area
*telemeasured on 380kV-220kV network
34,0%
13,8%
11,2%
8,7%
7,9%5,9%4,8%
7,5%
3,5%2,8%
6
Grid Reinforcements New lines 2006-2010
North–C.North
Yearly time-period percentage of critical market separation
C.North-C.South
C.South-
South
South-
Calabria
Calabria-
Sicily 49%
23%
14%
1%
5%
C.North-Sardinia 31%
* 380kV conversion
Foggia - Benevento
Udine Ovest - Okroglo
Redipuglia - Udine Ovest
Venezia N. - Cordignano
Trino - Lacchiarella
Fano-Abbadia
Sardinia – Mainland Interconnection
Chiaramonte - Ciminna
Montecorvino - Benevento
Sorgente - Rizziconi
Colunga – Calenzano*
Grid reinforcement to avoid market zone separations and inter-area congestions
Other new line to improve security/quality of the grid and to increase the interconnection capacity
7
Summary
POWER SYSTEM FEATURES AND DEVELOPMENTS
OPERATIONAL EXPERIENCE
– NTC assessment
– Integrated control and telecontrol system
CHALLENGES
8
NTC assessmentChanges & review of applied methodology
IMPORT
MW
tPeak hours Off-Peak hours
Off-Peak hours
IMPORT
MW
tPeak hours Off-Peak hours
Off-Peak hours
IMPORT
MW
tPeak hours Off-Peak hours
Off-Peak hours
2003 2004 2005
Flat, 1 NTC value
Off-peak hours/peak hours, 2 NTC values for
modulation
Balanced, 4 NTC values for
modulation
9
Integrated Control and Telecontrol System
PRESENT SYSTEM
PRESENT SYSTEM
NEW SYSTEM
NEW SYSTEM
• Fixed configuration
• Hierarchical
• Business continuity based
on back-up
• Technology obsolescence
• Not linkable
• Flexible configuration
• Not hierarchical
• Business continuity based
on other control centers
• New technology
• Easy integration with other
systems
• Network visibility
enlargement
• Advanced EMS functions
New System Features: 3 Control centers 3-5 Telecont.
Centers 250 RTU Data acquisition:
• Central acquisition concentrators at Control centers (SIA-C)
• Regional acquisition concentrators (SIA-R)
10
Summary
POWER SYSTEM FEATURES AND DEVELOPMENTS
OPERATIONAL EXPERIENCE
– NTC assessment
– Integrated control and telecontrol system
CHALLENGES
11
Internal GenerationPower plants rated power for different technologies and sources % of total installed capacity
Thermal power plants
Hydro power plants
Wind power plants & Others
26% 25% 22%
1% 1% 3%
73% 74% 75%
2001 2005 2007
100% 100% 100%
52%52% 37%37% 40%40%
12%12% 23%23% 23%23%
% Steam turbine
% Combined Cycle
Combined cycled and coal power plants increase
12(Values updated by the end of August 2005)
SLOVENIASLOVENIA
FRANCEFRANCE
SWITZERLANDSWITZERLAND AUSTRIAAUSTRIA
299
344
TOTAL (MW) 1.603
TOTAL (MW) 1.603
Development of wind farms by the end of 2007, Scenario 2005 MW
Wind Power plants increase
664780 874
1132
1603
23562496
0
500
1000
1500
2000
2500
3000
2001 2002 2003 2004 2005 2006 2007
MW
Sardinia
At the end of 2007 43% of off-peak load
demand Sicily
At the end of 2007 38% of off-peak load
demand
11
194
755
13
OverviewTSO Integration
GRTN
Terna
+
Network management
Network ownership
New investments• choice of asset
owner• authorisation• construction
System planning
Maintenance
System Operation
• Direct assignment or bidding
• Pre-authorisation discussions
• Support discussions with local authorities
• Development plan
• Co-ordinated schedule of maintenance of grid and other transmission facilities
• Plant dispatching
• Grid supervision/reconfiguration
• Development
• Authorisation application
• Work execution
• Financial plan
• Proposals for grid maintenance works
• Work execution
• Physical operation of grid