SUBJECTS MANAGEMENT AN IV CE 1. Calculate the hourly rate for material transporting in the following conditions: - Distance 20 km - Average speed 40 km/h - Load-unload time 0.5 hour - Hourly rate of the transporting mean 10 lei/h Versions: a. 10 lei b. 15 lei c. 20 lei d. 25 lei e. 30 lei 2. The informational roles of a manager are: a. entrepreneur, supervisor, leader b. supervisor, representative figure, entrepreneur c. supervisor, disseminator, spokesman d. disseminator, resource alocator, negociator e. entrepreneur, supervisor, negociator 3. The urbanism certificate has data regarding: a. The construction evaluation, specialty statement, construction’s height b. The maximum value of the land occupancy percent, the construction’s positioning, the construction’s height c. The maximum value of the land occupancy percent, technical expertise, property act d. The resistance project, construction’s height, construction’s positioning e. The construction’s height, construction evaluation, construction’s positioning 4. The indirect expenses represent: a. Managers` wages, utilities, non-productive personnel’s wages 1

Upload: cristina-vlaicu

Post on 19-Jul-2016

2 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Management

SUBJECTS MANAGEMENT AN IV CE

1. Calculate the hourly rate for material transporting in the following conditions:- Distance 20 km- Average speed 40 km/h- Load-unload time 0.5 hour- Hourly rate of the transporting mean 10 lei/hVersions: a. 10 lei

b. 15 leic. 20 leid. 25 leie. 30 lei

2. The informational roles of a manager are:a. entrepreneur, supervisor, leaderb. supervisor, representative figure, entrepreneur c. supervisor, disseminator, spokesman d. disseminator, resource alocator, negociatore. entrepreneur, supervisor, negociator

3. The urbanism certificate has data regarding:a. The construction evaluation, specialty statement, construction’s heightb. The maximum value of the land occupancy percent, the construction’s positioning,

the construction’s heightc. The maximum value of the land occupancy percent, technical expertise, property

actd. The resistance project, construction’s height, construction’s positioninge. The construction’s height, construction evaluation, construction’s positioning

4. The indirect expenses represent:a. Managers` wages, utilities, non-productive personnel’s wagesb. Productive personnel’s wages, value of materials, utilitiesc. Equipment expenses, non-productive personnel wages, utilitiesd. Raw material expenses, equipment expenses, utilitiese. Non-productive personnel’s wages, utilities, productive personnel’s wages

5. The type of the traditional contracts are:a. Total price contract, partnership contract, unit price contract b. Total price contract, target-cost contract, unit price contract c. Total price contract, lump sum fee contract, global contractd. Total price contract, work quantities price contract, unit price contracte. Reimbursable cost contract, unit price contract, partnership contract

1

Page 2: Management

6. The time spent to perform the finishing works for a 30 mp surface, with 4 workers (NT = 1.2 lei/mp) in 10 ore is:

a. 0.5 daysb. 0.6 daysc. 0.7 daysd. 0.8 dayse. 0.9 days

7. The minimum term to finish an activity using the Critical Path is calculated by the formula:

a. ttm(i) = max [tî

m(i-1)]b. tt

m(i) = min [ttM(i+1)]

c. ttm(i) = tî

m(i) + t(i)

d. ttm(i) = tî

m(i) - t(i)

e. ttm(i) = min [tî

M(i+1)]

8. Establish the time and the activities of the Critical Path for:Activity Time Previous

A 1 STARTB 3 AC 5 AD 7 BE 6 DF 4 C,E

a. 21 days: A-B-D-E-Fb. 21 days: A-D-E-Fc. 22 days: A-B-D-E-Fd. 23 days: A-C-Fe. 23 days: A-B-D-E-F

9. The simple elementary chains have the following features:a. Unequal sectors, equal work quantities, equal time b. Equal sectors, equal work quantities, different time c. Equal sectors, different work quantities, equal time d. Equal sectors, different work quantities, equal number of teamse. Equal sectors, equal work quantities, equal time

10. The material stock for the site organization is estimated by the formula:a. Qstoc = tstoc x qmax/day

b. Qstoc =

c. Qstoc = x ksc

d. Qstoc = Sstoc x qmax/day

e. Qstoc = Sstoc x ksc

BIBLIOGRAPHY1. HOSSU, T., s.a., “Managementul firmelor de construcţii”, Editura Casa Cărţii de Ştiinţă, 2001