making the difference · 2019-09-09 · 28 august 2019 abhro mitra senior consultant turner &...
TRANSCRIPT
28 August 2019
Abhro Mitra Senior Consultant
Turner & Townsend 2 St. Clair Avenue West Floor 12 Toronto, Ontario M4V 1L5
t: +1 416 925 1424 e: [email protected] w: turnerandtownsend.com
Report LTA Progress Report
Central 70 Project
Kiewit Meridiam Partners
making the difference
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 02
Contents
1 Executive Summary 6
Design and Construction Progress 6
Financial Management 6
Technical Advisor Certificate 6
Areas of Concern 6
2 Design and Approvals Process 7
Progress on Design 7
Other Topics 10
2.2.1 Utility Overview 10
2.2.2 Railroad Overview 10
2.2.3 Right of Way Overview 11
Permits 11
3 Progress of the Works 12
Works Schedule 12
3.1.1 Schedule Progress 14
Schedule Analysis 15
3.2.1 Milestone Tracking 15
3.2.2 Milestone Discussion 15
Construction progress 16
Commissioning 16
Issues arising 16
3.5.1 Issues this period 16
3.5.2 Issues from previous period 18
3.5.3 Anticipated Issues 18
3.5.4 Schedule Issue 20
Health & Safety 20
Lost-Time Injuries 20
Complaints & Enquiries 20
Operations and Maintenance 20
4 Financial Management 21
Change Notices and Change Orders 21
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 03
4.1.1 Change Notices 21
4.1.2 Change Orders 21
Construction Invoice 22
Milestones 22
Cash Flow 23
4.4.1 Monthly cashflow 25
4.4.2 Cumulative cashflow 25
Deductions 25
5 Technical Advisor Certificate 27
Appendix A Progress Photographs 28
Appendix B TA Certificate 48
Rev Originator Approved Date
0 Abhro Mitra Dominic Leadsom 28 August 2019
© Turner & Townsend. This document is expressly provided to and solely for the use of Kiewit Meridiam Partners on the Central 70 Project
and takes into account their particular instructions and requirements. It must not be made available or copied or otherwise quoted or
referred to in whole or in part in any way, including orally, to any other party without our express written permission and we accept no
liability of whatsoever nature for any use by any other party.
F:\TOR\JOBS\2016 JOBS\21644LS - C-70 - DL_ABM\CONSTRUCTION MONITORING\REPORTS - 2019\REPORT 19 - AUGUST 2019\LTA PROGRESS REPORT 19.DOCX
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 04
Preface
Turner and Townsend have been retained by Kiewit Meridiam Partners (the “Consortium”) as the
Lenders Technical Advisor (“LTA”) to provide LTA services on the Central 70 Project (the
“Project”). Turner & Townsend will be undertaking construction progress monitoring for the term
of the construction period. The scope of the LTA monthly reporting includes:
Site visit (as scheduled in the LTA Terms of Engagement) to meet with the
Construction Joint Venture (CJV)’s site management team, review progress of
the works and discuss issues that may have an impact on cost and schedule.
Monitoring of and reporting on construction costs during the construction
phase, including variation analysis and approval.
Monitoring of and reporting on construction sub-contractor’s performance
against the schedule, compliance with milestone dates and any anticipated
delays and methodology proposed to overcome them.
Tracking of and reporting on discharge of permit conditions, approvals and any
other such consent as may be required.
Review and sign-off on construction invoice and other such Project Costs as
may be included in the Consortium’s Construction Requisition Certificate.
Report on the monthly drawdown application, including comparison of drawn
funds against the anticipated cashflow or milestones as required and
confirmation that the cost to complete is sufficient.
Summarize each of the above in a monthly progress report.
Project background
The Central 70 Project (the “Project”) involves redesigning a portion of I-70 Corridor in Denver,
Colorado, which stretches from I-25 on the west to Chambers Road on the east. The corridor
provides regional access from downtown Denver and the metropolitan area to Denver International
Airport; linkage as an inner beltway between I-225 and I-270; and access to adjacent employment
areas, neighbourhoods, and new development centres. The Project is to be procured as a design-
build-finance-operate-maintain through a public-private partnership model for a 30 year
concession.
The procuring authorities for the Project are Colorado Bridge Enterprise (“BE”) and High
Performance Transportation Enterprises (“HPTE”) each of which is a government-owned business
within the Colorado Department of Transportation (“CDOT”). CDOT is managed by the Colorado
Transportation Commission (the “Transportation Commission”) which is the State’s transportation
policy decision-making body. CDOT manages the State’s transportation system under the direction
from the Transportation Commission.
The Project involves work on approximately 10 miles of the I-70 corridor that includes:
restriping from I-25 to Brighton Boulevard
lowering the highway below grade from Brighton Boulevard to Colorado Boulevard
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 05
full reconstruction from Colorado Boulevard to Sand Creek
mill/overlay & widening from Sand Creek to Chambers Road; and
O&M responsibilities beyond construction from Chambers Road to Tower Road.
A map of the Project area that shows the various Project sections is provided below.
This report has been prepared on the instructions of the Consortium and is for the benefit and use
of the Lenders and the Consortium in processing construction phase payments. The contents are
confidential and should not be disclosed to any third party without the permission of the Lenders,
the Consortium and the Authors.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 06
1 Executive Summary
Risk weightings
Red Serious risk with very high likelihood of impact on the Scheduled Substantial Completion Date
Amber Notable risk with medium likelihood of impact on the Scheduled Substantial Completion Date
Green Potential risk to be monitored, low likelihood of impact on the Scheduled Substantial Completion Date
Design and Construction Progress
Design development activities are underway and we have reported in more detail on the progress
of the design in Section 2 of the report. Construction activities are currently underway and we
have reported on these in more detail in Section 3.3 of the report.
Risk Weighting
Financial Management
We have received the Construction Contractor’s monthly billing dated August 05, 2019, which
shows the current payment due for this period as $18,550,826.88. We have also reviewed the
information available to verify the cost to date represents a reasonable assessment of the works
completed at this stage of the Project to the period ending July 27, 2019.
Risk Weighting
Technical Advisor Certificate
We have received the Payment Application for the work completed through July 27, 2019 from
KMP. We have reviewed the documentation included and verified the amounts included for the
works. We have provided a copy of our Technical Advisor certificate in Appendix B.
Risk Weighting
Areas of Concern
We have identified a few items of note in Section 3.2 and 3.5 of the report with regards to ongoing
issues that have been discussed in the MPR.
Risk Weighting
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 07
2 Design and Approvals Process
Progress on Design
In Monthly Progress Report (MPR) 19, dated July 2019, Kiewit Meridiam Partners (KMP) reported
the following progress. The design work is being done by KMP’s design lead WSP and sub-
consultants. The following has been summarized in the MPR with regards to the design works that
are currently ongoing for various disciplines.
Bridges
On-going post design revisions.
Turner & Townsend has no further comments.
Railroad
UPRR
As requested by UPRR, draft comment responses for the 100% submittal were submitted
for review on June 28, 2019.
UPRR provided comments on the draft comment responses for the 100% submittal on July
18, 2019.
Submitted 100% UPRR Bridge submittal on July 20, 2019.
Submitted License Agreement revisions for CBC/42”/48” on July 22, 2019 and
Sanitary/Storm along I-70 on July 23, 2019.
Submitted Phase 4 Abutment 1 on July 19, 2019.
Phase 4 CBC/Phase 5 flipbook distributed to UPRR on July 19, 2019.
We note that some comments from the UPRR review have resulted in opening new SENs as noted
further in the report. KMP, CDOT and UPRR have been closely coordinating the comment resolution
process. As per our ongoing discussion the design solutions emerging from the SENs have been
incorporated in the UPRR plans. As noted above UPRR have provided comments on the 100%
submittal. KMP has confirmed that the ongoing comment resolution does not impede some of the
UPRR related bridge girder fabrication work and the design associated with those items are in good
standing. We expect the IFC drawings for all UPRR design related items to progress as the
comments are being resolved.
BNSF
BNSF Bridge and Crossing Plan submittals under BNSF review.
The BNSF package is at RFC stage as per our discussion with KMP.
Walls
On-going post design revision.
Turner & Townsend has no further comments.
Cover
KMP hosted Comment Resolution for the Constructability Review for 100% Pump Station.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 08
KMP requested Restricted Activity for the foundation of the Pump Station.
A variance was completed for the underdrain in the Cover Drainage package.
The pump station design has interdependencies with the drainage design and has been under
discussion during previous periods. The drainage packages have been progressing towards RFC.
Cover Systems and Cover Top packages are at 100% stage. There is continued coordination
between Denver Fire Department, CDOT and KMP for various cover design related aspects for the
pump station.
Drainage
NDC-00070 was transmitted to CDOT for review on July 15, 2019.
CDOT conditionally accepted the 100% Stormwater and FFFS Pump Station Package.
On-going post design development.
CDOT confirmed submission of the 100% UPRR Track Relocation Report to UPRR on July 2,
2019 via CDOT-EML-005623.
The west drainage is divided into West 1 & 2 and other sections include Centre and East 2. All
have either been progressing or have progressed to RFC as reported in previous periods. Design
modifications on the field are being dealt by NDCs as needed.
Environmental
No updates this period.
Geotechnical
No updates this period.
As discussed with KMP in previous periods, there have been no changes to the baseline conditions
as determined by the investigations from geotechnical studies. Geotechnical memo was sent to
BNSF, UPRR and regarding Sand Creek bridges previous period.
ITS, Signals
100% West and Center Network Plans- Addressing comments for RFC submittal
100% ITS Structural Details were transmitted to CDOT Comments addressed drawings being
revised.
46th & Monroe (N & S) Rail and Traffic signals – On-going design coordination
47th & York Rail and Traffic signals – On-going design coordination
Permanent Traffic Signal Timings – Final AM Timings in with the Department
NDC 0000108 – Updated Bridge Details for Traffic and Lighting Poles – Under development
Permanent Ramp Meter Timings – Department comments received and are being addressed
NDC 000084 West – With KMP
NDC 000158 - Conduit Crossing design- In Design
NDC 000162 – Center / Drainage adjustments-In Design
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 09
NDC 000182 – West ITS Updates- In Design
RFC Node Building Plans – With the Department
RFC CDOT East Network Plans – Addressing minor comments for RFC
Remaining Temp Splicing Plans – With KMP
CCD Project wide Network Plans – Addressing comments
FDC 000068 - Fillmore - In Design
NDC 000165 – Roadway NDC with minor ITS Adjustments
NDC 000047 – Temp Signals – In IQC
As noted above, field design changes are being handled via a NDC, as applicable.
Landscaping
KMP hosted 100% Cover Architectural IDR Comment Resolution Meeting.
The variance for the irrigation depth was submitted as an RFI, as requested by the City and
County of Denver for documentation of the approved variance.
KMP continued to work through the Drainage Variance for the Cover.
The landscape design lends itself to the finalization of the cover structure and cover system
design. There is continued efforts via task force meetings between KMP and City and County of
Denver. The Concessions/CDOT building is being designed as two separate units to be maintained
by City and County of Denver, and CDOT. As discussed with KMP this period, there has been
ongoing coordination between CCD and CDOT on landscaping related items to finalize the
landscape.
Lighting
NDC 000068 – East ITS one-line diagrams and ITS Updates R&R – With KMP
NDC 000113 - West - Ongoing post design.
NDC 000141 - Center to IQC - Ongoing post design.
NDC 000177 - 270 Lighting Changes - Ongoing post design.
Project Wide Temp Lighting NDC - Pending
Turner & Townsend have no further comments. As noted field design changes are being handled
by NDCs as applicable.
MOT
On-going post design development.
KMP continues to discuss construction strategies for MOT with the City and County.
Pavement
No updates this period.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 10
Signing & Marking
NDC 000073 – With the Department
NDC 000079 – With KMP
NDC 000114 (General clean up and corridor-wide update) - Ongoing post design.
NDC 000163 – With the Department
NDC 000164 – With the Department
Far East on hold because of roadway changes.
Center and West: 95% have anchor bolt clashes.
Turner & Townsend have no further updates. As noted field design changes are being handled by
NDCs as applicable.
Roadway
On-going coordination with Cover for final grading and curb details.
On-going coordination with drainage for final grading of school parking lot.
On-going post design development.
Turner & Townsend have no further updates.
Utilities
NDC-000083 has been released for construction
Water conduit package 2 has been sent to Denver Water for comments
Turner & Townsend have no further updates.
Survey & Mapping
No updates this period.
Other Topics
2.2.1 Utility Overview
Further details on this topic are in the MPR. Construction activity for various sanitary, water and
dry utilities have been underway. Works have been progressing on the north and south of the
Stapleton from Holly to Dhalia. All utility WO’s are being tracked on the Project schedule. There
are no specific issues with utility work at this time.
2.2.2 Railroad Overview
The following has been discussed on railroads this period:
UPRR: Design: UPRR 100% bridge package was submitted. Continuing issues with UPRR’s failure
to approve UPRR Crossing Plans, imposition of requirements beyond the applicable Review
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 11
Standards, and refusal to cooperate are described in the Supervening Event and Anticipated
Issues sections of the MPR.
Construction: Continued UPRR Phase 4 bridge shoring for 112 shoofly (post cutover shoring).
There is ongoing coordination with KMP and UPRR on various railroad related activities. Design
with 100% was submitted. As per our ongoing discussion the design solutions emerging from the
SENs have been incorporated in the UPRR plans. UPRR have provided comments on the 100%
submittal. KMP has confirmed that the ongoing comment resolution does not impede some of the
UPRR related bridge girder fabrication work and the design associated with those items are in good
standing. We expect the IFC drawings for all UPRR design related items to progress as the
comments are being resolved.
BNSF: Design: BNSF Bridge and Crossing plan submittals are under BNSF review.
As per our discussion with KMP there are no concerns with BNSF related design work items. The
BNSF works are not on the critical path for the Project. The key activity is the construction of the
BNSF Bridge for which KMP will have 9 months to execute construction activities. During this time
the BNSF track will be temporarily decommissioned. As per our discussion with KMP this period the
RFC for this package has been achieved. The PUC application was submitted previously.
2.2.3 Right of Way Overview
The details of the progress made in this topic is in the MPR. In summary, building demolition for
2019 is complete. Possession of temporary parcels, easements, notice of intent, waiver valuations
for temporary easements and MOA signing with property owners are underway.
Permits
Turner & Townsend have no further comments at this time. Items regarding permits and approvals
that are needed to progress the Project have been discussed in the MPR where appropriate.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 12
3 Progress of the Works
Works Schedule
A Revised Baseline Schedule has been approved for the Project following the execution of the
Settlement Agreement. The schedule has been prepared by dividing the Project area into
segments from 0 to 7. The picture below shows the segments and the description.
Area 2, 3 and 4 of the Project, from Brighton Blvd to Dahlia St, is the lowered section that includes
the UPRR section and the existing viaduct. Area 5 (Dahlia St. to Sand Creek) is the reconstruction
segment and Area 6 (Sand Creek to Chambers Rd) is the widening section of the Project. Area 7
involves ITS/Tolling. Area 0 and Area 1 includes the section of the Project with re-striping works. A
majority of the works on the Project is within area 2, 3, 4 and 5.
Each area is further divided into blocks. The blocks are defined for eastbound and westbound
directions and are tied with a numbering scheme to identify the respective area it is in. The Project
schedule has been developed based on this block structure. The figure below shows the block
numbering scheme and a typical numbering methodology. The breakdown of works is defined in a
block structure that helps track the various activities of the Project at a detailed level.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 13
The MPR includes a copy of the schedule as per this block methodology.
Identified below are the key milestones that have been identified in the Schedule based on the
Settlement Agreement, which has resulted in modification of the requirements for Milestones 3
and 4 and the addition of Milestones 5 and 6. The finish dates for Milestones 1 through 4 have
remained the same. The Project Substantial Completion Date has been moved from Mar 25, 2022
to Sep 21, 2022, an extension of 180 calendar days.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 14
Payment Milestones Finish Date
Milestone 1 (Sand Creek to Chambers) 09-Dec-19
Milestone 2 (Sta 2091+00 to Sand Creek Bridge) 10-Nov-20
Milestone 3 (UPRR Phase 1-5) 17-Oct-20
Milestone 4 (WB I-70 Brighton Blvd. to Dahlia St/Viaduct Demo) 26-Sep-21
Milestone 5 (EB I-70 Brighton Blvd. to Dahlia St, UPRR Phase 6) 25-May-22
Milestone 6 (SMA Paving, Cover top, 46th Avenue) 20-Aug-22
Substantial Completion 21-Sep-22
Final Acceptance 20-Dec-22
The schedule has been further broken down into design, procurement and construction related
activities. In addition there are works identified for ITS installation and testing, procurement,
installation and testing of tolling devices, activities related to right of way acquisitions for various
area parcels, partial acquisitions and temporary easements.
Turner & Townsend have provided updates on the progress of the schedule based on the Revised
Baseline in the subsequent sections. We note that any new SEN that is currently under discussion
is not factored in this schedule update.
3.1.1 Schedule Progress
We have included photographs from the construction progress in Appendix A of this report. A
detailed report on the Schedule Progress has been provided in the MPR.
In summary, work has continued on Brighton Boulevard, concrete paving of blocks, shoofly works
completed for UPRR with one remaining, Columbine and Clayton bridge works were in progress,
abutment works was also in progress to the north of this section, progress on MSE walls on
Colorado, preparation works for the Steels bridge, progress on east of Colorado between Colorado
and Dhalia and Dhalia to Holly, utility works have been in progress on various sections of the
roadway and also progress was made on the east end of the Project.
Various construction activities to support the progress noted above include, installation of erosion
control at Stapleton south of I-70, excavation activities on the south of I-70 around the Filmore,
Columbine, and Clayton bridges, channel widening near I-270, storm drainage installation on
various sections of the roadway, structural works that includes MSE walls, bridge decks, caisson,
pier caps etc. installation of guardrails on various sections, MOT activities to support the ongoing
construction, pavement laydowns, temporary striping works and installation of ITS/electrical
ductbank. These activities are highlighted in the photographs included in Appendix A of this report.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 15
Schedule Analysis
3.2.1 Milestone Tracking
More details can be found in the MPR. Below is the excerpt from the MPR showing the comparison
of milestone dates between the Revised Baseline Schedule (RBS-2) and the Schedule for this
period.
As noted in the table above, the Schedule for this period shows a 79 day delay to Substantial
Completion from the planned date in the RBS-2. At this time KMP is evaluating options to mitigate
this delay. As per our discussions with KMP, this delay is attributed to the several new SENs
related to UPRR works that are currently under discussion.
A delay has also been identified for upcoming Milestone 1 and KMP is currently evaluating options
to mitigate this delay. As per our discussions with KMP, this delay is attributed to the deferring of
the SMA paving activity that is within Milestone 1, which is now anticipated to be completed in
2020. As per our discussion with KMP, paving activities are most suitable to be completed in
warmer months. The Milestone 1 completion is scheduled for Dec 2019 and KMP is currently
discussing options with CDOT to fulfil the terms for Milestone 1 completion without the SMA paving
complete.
3.2.2 Milestone Discussion
A detailed description of the sequence of work items that are planned for each Milestone is
discussed in the MPR.
The Project Critical Path is formed by Milestone 3 and 4, 5, and leading through Substantial
Completion. It is to be noted that Milestone 3 marks the completion of UPRR Phases 1 through 5
and is targeted to finish by Oct 17, 2020. The Longest Path of the Project is Milestones 1 and 2. A
detailed task-by-task description of these Milestones can be referred to in the MPR.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 16
Continued resolution of the UPRR related items are important to keep the Project Critical Path on
target for a timely completion of the activities for Milestones 3 and 4. Also as noted, Milestone 1 is
currently projected to be delayed. Turner & Townsend would like to identify the projected delays
as an item of note.
Construction progress
Construction activities are underway. The MPR has provided a detailed description of various
construction activities that have been underway this period that includes works on MOT, utilities,
drainage, civils, pavement, permanent barrier, structures, railroad, ITS/signals/lighting, signings &
marking, cover and walls.
Turner & Townsend have undertaken a site visit on August 08, 2019 to discuss the construction
progress. We have provided photographs of the works that have been progressing in Appendix A
of this report.
Commissioning
There are no items to report on at this time.
Issues arising
3.5.1 Issues this period
3.5.1.1 Supervening Events
The MPR has outlined the following Supervening Events. We have provided a summary of these in
the section below. A detailed description of the event is provided in the MPR.
SEN 1, 2 and 4. Closed.
SEN 5. Supervening Event 5 was initiated to address asbestos that was found on a site for which
remediation works have been underway. Further discussion has been underway this period on this
SEN. As per our discussion with KMP there is no impact on the Project schedule or the cost as a
result of this SEN. This SEN is anticipated to be closed shortly.
SEN 7. Supervening Event Notice 7 is regarding the Sand Creek Bridge. KMP has identified a
Compensation Event as a result of physical damage to the section of the bridge. Discussion is also
underway between KMP and CDOT to determine whether the bridge is part of the Project and
whether it should be maintained by KMP. We would like to note that some works associated with
the Project around the Sand Creek Bridge overlaps with upcoming Milestone 1 Project works. As
per our discussion with KMP there will be no impact on Milestone 1 as a result of this. The MOT
phasing has been adjusted to mitigate the impacts. More details on this SEN is provided in the
MPR.
SEN 8. Supervening Event Notice 8 is with regards to UPRR bridge design for lateral support. KMP
has progressed the design as per UPRR’s request and continues to d iscuss this with CDOT and
UPRR. More details on this SEN is provided in the MPR.
SEN 10, 11, 12, 13, 14, and 15. These SENs relate to UPRR asking KMP to address items that
have been requested by UPRR via their comments on the design. The MPR has details on each
SEN. A proposed mitigation and next steps have been submitted by KMP in the submittal
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 17
documentation. Turner & Townsend have discussed these with KMP and would like to note that
discussions are underway between KMP, CDOT and UPRR to discuss a path forward for each of
these SENs. We have also been made aware that the 100% design that has been submitted this
month addresses these additional requests. KMP is actively engaging with CDOT and UPRR such
that any cost or time impacts to the Project are managed and mitigated as a result of these SENs.
Turner & Townsend would like to identify the above noted SENs as items of note.
SEN 16. This is in regard to the extreme weather condition termed as a “Bomb Cyclone” that
occurred on March 13, 2019 and continued through the afternoon of March 14, 2019 and the
consequential loss of productivity during this time.
SEN 17, 18. This is in regard to the shoring for 100% UPRR Trackwork Plans as compared to the
shoring requested by UPRR. This request, as noted by KMP, is deeper and more complex and will
require more time to design and approve and consequently lead to an extended duration of
installation. SEN 18 is a Delay Relief Event initiated by KMP and related to the SEN 17.
SEN 19. Withdrawn.
SEN 21, 22. These are in regard to the KMP describing how a breach of the Project Agreement
was made by the Enterprises. Specifically, it describes how the Enterprises failed to enforce
CDOT’s Railroad Agreement with UPRR in response to UPRR’s preferential demands concerning
certain steel components on the UPRR crossing. As of July 10, 2019 CDOT transmitted the
Supervening Event Notice and Submission back as Rejected.
SEN 23. This is with regards to identification of Asbestos Containing Material on a project site.
Steps have been taken to mitigate this.
SEN 24, 25, 26, 29 and 30. These are notices for Compensation Events for the SENs noted
above.
3.5.1.2 Design Progress
We have summarized the status of design for various disciplines in the sections noted above. We
note that discussions are currently underway on several SENs related to UPRR, and continue to
have a bearing on the issue of the RFC of the UPRR design. KMP is actively discussing these with
CDOT and UPRR. KMP is focussing on construction activities related to UPRR and ensuring the
design is progressing to later phases. The 100% UPRR plans that were submitted last period, KMP
continues to receive back comments from UPRR. The design solutions under discussion from the
pending UPRR related SENs continue to be incorporated in the design submittals as per KMP.
The MPR has specifically noted and our discussions with KMP had confirmed that the 95% plan
acceptance for UPRR and associated variances have allowed the team to move forward with
restricted activities on girder fabrication components in an attempt to mitigate additional time
impacts on the UPRR bridge work in advance of the release for construction documents. KMP
continues effort to meet regularly to identify mitigation opportunities on the project for
presentation to management of both KMP and the Enterprises.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 18
3.5.2 Issues from previous period
The MPR has elaborated on various Supervening Event Notices and that have been discussed
above. Updates will be made as discussions on these SENs progress.
3.5.3 Anticipated Issues
The following has been reported in the MPR:
UPRR Coordination
The following has been reported in the MPR on UPRR related coordination.
Design: Coordination difficulties continue between UPRR, CDOT and KMP; communication has been
systematically frustrated by, among other things, UPRR’s failure to appoint an authorized contact,
UPRR’s refusal to cooperate, UPRR’s refusal to communicate with KIC, and UPRR adding
previously-unspecified requirements and criteria (i.e. beyond the specified Review Standards).
UPRR periodically attended weekly task force meetings to discuss the project and design
development. The feedback and discussion from UPRR in the recent task force meetings, attended
by UPRR, has been minimal and unproductive. Frequent informal design discussions were held with
KMP designers and UPRR design reviewers for permanent and temporary design topics in early
March, which allowed a streamlined conversation on outstanding items and resulted in more
efficient comment response and submittal review periods. Due to escalating differences in design
criteria, on March 28, 2019, KMP was informed by CDOT that KMP was no longer to communicate
with UPRR or their consultants directly. As requested, KMP compiled all communications between
KMP and Benesch and transmitted to CDOT on April 1, 2019 via Aconex (KMP-TRN-006514).
On April 15, 2019, KMP was informed that UPRR would no longer review certain material until
100% bridge package is approved. This is contrary to the previous review and approval
discussions with UPRR. UPRR has since reviewed some material as the 95% package has been
reviewed; however, UPRR’s failure to cooperate may impact the project schedule.
KMP was informed on June 25, 2019 by CDOT that the primary reviewer for Benesch reviewing as
a consultant for UPRR for the Central 70 project would be taking a more involved role in multiple
UPRR projects. CDOT indicated this would likely result in less devoted time to review Central 70
material and longer review durations than previously experienced during the project. This will
likely exacerbate the impacts for which CDOT is responsible.
UPRR design representatives did not attend regularly scheduled UPRR Task Force meetings the
first two weeks of July (7/1/19 and 7/8/19) with little advance notice of their absence.
Turner & Townsend would like to note the above mentioned comments made by KMP. We
anticipate KMP, CDOT and UPRR to come to a resolution to ensure timely progress of the UPRR
related design elements. As per our discussion this period, the 100% UPRR plans that were
submitted last period have been returned with comments and at this time are not at RFC stage
yet. As per KMP, the design solutions emerging from the UPRR related SENs continue to be
incorporated in the design submissions. A delay is currently projected in the Milestone 3 (UPRR
Phases 1-5).
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 19
On July 16, 2019, KMP and CDOT personnel met with UPRR operations and design coordination
members to discuss alternate track alignment plans that allow the UPRR bridge to be built in a
single phase and reduce the overall schedule and impact to UPRR by approximately four months.
During the meeting, UPRR advised that it needed access to their complete yard to maintain
operations. KMP plans to review UPRR’s comments and attempt to develop another alternate track
alignment, and review with CDOT accordingly. On July 26, 2019 KMP and CDOT personnel with
UPRR drainage and structural reviewers to discuss revised license agreement submittals and
shoring concept development.
The above noted comments point to the coordination efforts being made by KMP regarding UPRR
related items. We anticipate that with continued discussion amongst KMP, UPRR and the Enterprise
a construction approach can be taken that helps mitigate any projected delay. Milestone 3, (UPRR
Phases 1-5) which is dated for 17 Oct 2020, is currently projected to be delayed. As per the PA,
the completion of Milestone 3 is to be achieved to the extent such that trains are to be operating
on the phase 4 and 5 structure.
Operations: UPRR crews decided to relocate the 404/405 switch work, originally in the Phase 3C,
on March 18, 2019 in order to accommodate crew availability and work flow, this sequence varies
from the 100% approved track plans. The Phase 3A was not completed as scheduled due to the
design not being approved until March 14, 2019. The approved shoring by UPRR requires shoring
that is deeper, more complex, and in new areas than indicated in the 100% Trackwork Plans and
Specifications. The increase in quantity and complexity results in an unanticipated increased
duration for shoring design and approval.
Turner & Townsend would like to note the above mentioned notes on track works. Details on SEN
17 and 18 have been provided in the MPR. We anticipate KMP, CDOT and UPRR to come to a
resolution to ensure timely progress of the UPRR related operational elements.
BNSF Coordination
The following has been reported in the MPR.
At the BNSF 100% Bridge Comment Resolution meeting on February 22, 2019, BNSF engineering
informed KMP that the bridge needed to follow BNSF specifications. BNSF had previously indicated
that CDOT specifications would be acceptable. On March 14, 2019, BNSF provided specifications
and standard details not previously provided. As discussed at the comment resolution meeting,
KMP has since provided interim submittals to address the newly provided details and notes. KMP
provided revised notes on March 29, 2019, and received a “no outstanding comments” on the
response from BNSF on April 10, 2019. KMP followed up with an access detail on April 12, 2019,
requesting review. BNSF provided a response on April 18, 2019, requesting different access
clearance criteria be met than provided in standards. KMP responded on April 22, 2019, with an
alternative design, discussion of approach and request for a meeting. Efforts to communicate by
phone were made by KMP to BNSF with each step of these design adjustments. BNSF responded
on May 7, 2019 with additional comments. KMP and BNSF exchanged e-mails on May 7th and 8th
further discussing access solutions prior to BNSF providing direction at the May 9, 2019 BNSF TF
meeting.
At the June 6, 2019 BNSF Task Force Meeting, BNSF notified KMP that they would not be utilizing
STV to support the RFC review process, who had been involved in the 30% and 60% review
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 20
efforts. BNSF noted Wilson would be reviewing the RFC drawings prior to review by the BNSF
structures group. KMP noted the concerns of bringing in a new reviewer for final review; however,
BNSF expressed Wilson would be advised to verify outstanding comments were addressed, not to
develop additional new comments, and would limit their review to 30 days. At this time, the RFC
package has not been approved, despite its initial submission in January 2019. The RFC package
was transmitted to CDOT for review on June 4, 2019. As of July 27, 2019, BNSF had not provided
any comments or feedback on the Bridge or Crossing plans, significantly later than the 30-day
review period confirmed by BNSF.
Turner & Townsend have no specific comments on the above at this time. We also note that as per
our continued discussions with KMP, the progress on BNSF design has been reported to be good.
Also, to note is that the BNSF works are not on the critical path of the Project at this time. The key
item of works involves bridge works for which KMP will have 9 months to execute the construction
activities. During this time the BNSF track will be temporarily decommissioned. RFC for this
package is anticipated as per our discussions with KMP. The PUC for BNSF related works has
already been submitted.
3.5.4 Schedule Issue
As reported in the MPR:
KMP continues to analyze the potential impacts to the Project schedule and to develop alternate
schedule approaches to mitigate delays to Project Milestones and the Project’s Substantial
Completion for review with CDOT prior to implementation. Other potential critical schedule issues
include Supervening Event 008, 010, 011, 012, 013, 014, 015, 017, and 018, which have the
potential to delay the Project.
Turner & Townsend would like to make note of KMP’s comment above with regards to the SENs 08,
10, 11, 12, 13, 14, 15, 17, 18, 21 and 22. As noted in sections above, all of these are currently
under discussion between KMP and CDOT. We note that UPRR works forms Milestone 3 (Phase 1-5)
and is on the Critical Path for the Project.
Health & Safety
Turner and Townsend have nothing to report, unless otherwise notified.
Lost-Time Injuries
Turner and Townsend have nothing to report, unless otherwise notified.
Complaints & Enquiries
Turner and Townsend have nothing to report, unless otherwise notified.
Operations and Maintenance
Operations and Maintenance Monthly Progress Report (MPR) 13 is included with the MPR. More
details on operations and maintenance incident logs etc. are reported in the O&M MPR along with
other topics of discussion. No operations related non-conformances have been reported this
period.
Turner & Townsend have no specific comments at this time.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 21
4 Financial Management
Change Notices and Change Orders
4.1.1 Change Notices
The following is the status of the Change Notices as reported in the MPR this period. A list of all
Change Orders from past period that are not active for discussion, are listed in the MPR.
More details on the Change Notices is included in the MPR. ECN #038 and #041 are items of note.
Turner & Townsend have no specific comments at this time.
4.1.2 Change Orders
A list of all Change Orders from past period that are not active for discussion, are listed in the
MPR.
Turner & Townsend have no further comments.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 22
Construction Invoice
We have received the CC’s monthly billing dated August 05, 2019 which shows the following:
Original Contract $813,185,600.00
Net change by Change Order $1,342,645.50
Contract To-Date $814,510,245.50
______________________________________________________________
Total completed & stored to-date $229,313,956.48
Change order withheld $(-)
Change order Earned $ 967,021.69
Deductions last period $534,000.00
Stored Material $ 498,540.39
Stored Material withheld 0% $ -
Total Earned $228,779,956.48
Less previous payments $210,214,129.60
Less Noncompliance/Deductions in Period $15,000.00
Current payment due $18,550,826.88
Balance to Finish Less Retainage $585,745,289.02
Milestones
Following are the schedule milestones for the primary activities achieved during this period as
noted in the MPR.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 23
Turner & Townsend have been provided with Kiewit Infrastructure Co.’s Letter of Certification to
KMP along with the draft payment application that certifies the progress. Turner & Townsend have
discussed the above with KMP and are satisfied that it is a reasonable representation of works
completed this period. The design activities are progressing in various disciplines as noted in the
sections above. The construction activities are in progress as well.
Cash Flow
The table below shows the cumulative CC work against earned value and also the cost to
complete. We are currently satisfied that the cost to complete is sufficient for the scope of works
remaining.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 24
Month
A. Construction
Contract – Appendix D – Schedule of Values (Cumulative CC Work)
B. Earned Value (Cumulative)
Differential
(B-A)
% of CC Work
Cost to Complete
Financial Close $26,642,000 $26,642,000 $0 3.28% $786,543,600
January 2018 $41,711,251 $41,711,251 $0 5.13% $771,474,349
February 2018 $54,246,486 $54,246,486 $0 6.67% $758,939,114
March 2018 $62,408,181 $62,408,181 $0 7.67% $750,777,419
April 2018 $67,557,665 $67,557,665 $0 8.31% $745,627,935
May 2018 $69,313,107 $69,313,108 $1 8.52% $743,872,492
June 2018 $75,867,788 $75,867,789 $1 9.33% $737,317,811
July 2018 $89,924,750 $89,924,752 $2 11.06% $723,260,848
August 2018 $96,496,339 $96,496,341 $2 11.87% $716,689,259
September 2018 $104,579,218 $104,579,220 $2 12.86% $708,606,380
October 2018 $119,270,836 $113,366,992 ($5,903,844) 13.94% $699,818,608
November 2018 $134,997,004 $122,090,012 ($12,906,992) 15.01% $691,095,588
December 2018 $148,471,023 $127,265,206 ($21,205,817) 15.65% $685,920,394
January 2019 $171,824,834 $135,158,145 ($36,666,689) 16.62% $678,027,455
February 2019 $192,060,857 $144,633,798 ($47,427,059) 17.79% $668,551,802
March 2019 $218,844,666 $157,298,501 ($61,546,165) 19.34% $655,887,099
April 2019 $257,256,011 $175,807,638 ($81,448,373) 21.62% $637,377,962
May 2019 $295,980,390 $184,819,114 ($111,161,276) 22.73% $628,366,486
June 2019 $325,944,706 $209,793,385 ($116,151,321) 25.80% $603,392,215
July 2019 $356,406,853 $228,346,935 ($128,059,918) 28.08% $584,838,665
We would like to note that the projected cashflow as noted above in the table above reflects the
revised cashflow that was agreed upon as per the Settlement and amendment to the Construction
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 25
Contract. An updated Appendix D was prepared and the values were generated from the revised
Financial Model.
For this period and as seen in the table above, the cumulative earned value spend has been lower
than the cumulative CC projected value. We note that as per our discussion with KMP and as
reported in the MPR, all ongoing design development activities are progressing towards RFC.
Construction activities have been progressing as noted. We anticipate the construction to catch-up
in the forthcoming periods and that should close the gap between the planned cashflow and the
earned value. We note that with the current progress the schedule is projecting a 79 delay to
Substantial Completion.
4.4.1 Monthly cashflow
4.4.2 Cumulative cashflow
Deductions
The following is the current status of NCEs and CCDs to date as reported in the MPR.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 26
The total cumulative monetary value that has been accrued for NCEs and CCDs are:
Cumulative Noncompliance (NCE points converted to dollars) $355,000.00
Cumulative Construction Closure Deduction $194,000.00
Total to date $549,000.00
Adjustments have been made to the construction invoice to reflect this deduction as noted under
Section 4.2 of this report. A letter of rectification has also been issued that aims to manage the
accrual of the NCE and CCD points. We have discussed this with KMP. CDOT and KMP are currently
under discussions to re-evaluate the deduction regime. We will provide updates as more
information has been made available.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 27
5 Technical Advisor Certificate
We have received the Payment Application dated August 05, 2019 for the work completed through
July 27, 2019 from KMP. We have received the Form of Construction Requisition Certificate
(Exhibit G) dated August 26, 2019. We have reviewed the documentation included and verified the
amounts included for the works. We have provided a copy of our Technical Advisor certificate in
Appendix B. The list below shows previously issued and the current Technical Advisor certificate.
Certificate Certificate Date
Amount (as requested in Exhibit G, Section 1 –
Withdrawal Request)
Cumulative Total
Financial Close NA $26,642,000.00 $26,642,000.00
Certificate 1 March 07, 2018 $15,069,251.00 $41,711,251.00
Certificate 2 March 27, 2018 $12,535,235.00 $54,246,486.00
Certificate 3 April 25, 2018 $8,161,695.00 $62,408,181.00
Certificate 4 May 23, 2018 $6,631,609.91 $69,039,790.91
Certificate 5 June 25, 2018 $5,186,419.44 $74,226,210.35
Certificate 6 July 24, 2018 $6,860,681.55 $81,086,891.90
Certificate 7 August 24, 2018 $14,056,882.49 $95,143,774.39
Certificate 8 September 25, 2018 $6,571,589.25 $101,715,363.64
Certificate 9 October 25, 2018 $8,405,316.15 $110,120,679.79
Certificate 10 November 26, 2018 $8,787,772.36 $118,908,452.15
Certificate 11 December 19, 2018 $10,976,220.00 $129,884,645.15
Certificate 12 January 25, 2019 $5,135,193.54 $135,019,838.69
Certificate 13 February 25, 2019 $8,150,455.09 $143,170,293.78
Certificate 14 March 26, 2019 $9,447,653.19 $152,617,946.97
Certificate 15 April 26, 2019 $13,272,979.80 $165,890,926.77
Certificate 16 May 24, 2019 $18,332,605.82 $184,223,532.59
Certificate 17 June 21, 2019 $11,325,388.93 $195,548,921.52
Certificate 18 July 24, 2019 $25,229,280.92 $220,778,202.44
Certificate 19 August 28, 2019 $18,900,826.88 $239,679,029.32
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 28
Appendix A Progress Photographs
Erosion control at E Stapleton Drive next to Holly St. south of I-70
Preparation for erosion control north of I-70 between Steele-Vasquez and Jackson St.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 29
Ongoing excavation activities south of I-70 between Brighton Blvd & Wynkoop St
Excavation activities around the Fillmore Bridge near Fillmore St. just North of I-70
Widening of the overflow channel south of I-270
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 30
Excavation activities south of I-70 at Colorado Blvd Bridge
Rip-Rap aggregated near E Stapleton Dr. S and Holly St south of I-70 in preparation for crushing near the
off-ramp north of I-70 just to the right of Havana St.
\
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 31
Storm Drain Pipes stored south of I-70 and west of Colorado Blvd
Storm drain installation in progress between I-70 and E Stapleton Drive N west of Holly St
Storm drain installation in progress between I-70 and E 40th west of Peoria St.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 32
Sanitary pipes staked near Brighton Blvd and 47th Ave below
Sanitary pipes for installation between I-70 and E Stapleton Drive N east of Grape St
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 33
Fillmore Bridge Deck installation near Fillmore St. (foreground) and Clayton bridge (background) decks
being poured
Caisson Drilling near the Columbine Bridge @ Columbine St. north of I-70
Stack pole of reinforcement steel at Brighton Blvd and E 47th Ave north of I-70
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 34
Works in progress for pier cap at the Colorado Blvd Bridge
Guardrail installation for the 270 Bridge
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 35
Works in progress for installation of walls between I-70 and E 40th east of Central Park Blvd
Works in progress for rebar on approach slab and expansion joints for the bridge deck on west of Peoria
St.
H-piles stored between north of I-70 and E 45th Ave east of Havana St.
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 36
Works in progress for rebar installation in preparation for guardrail installation at Peoria St. Bridge
Works in progress for walls, rebar and footing on Quebec St. north of I-70
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 37
MOT in place for works E 46th Ave between National Western Drive and Marion St. north of I-70
MOT in place for work on I-70 off-ramp towards Central Park Blvd.
MOT in place for roadway closure to facilitate temporary pavement work around E Stapleton Drive S
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 38
Roadway pavement on E 46th Ave between National Western Drive and Marion St. north of I-70
Roadway expansion/restriping just north of I-70 on Brighton Blvd
Paving works in progress on I-70 eastbound shoulder west of Central Park Blvd
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 39
Paving works in progress on I-70 eastbound on-ramp west of Central Park Blvd
Paving works on progress on I-70 eastbound near Peoria St. west of Peoria St. Looking west
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 40
Guardrail rebar and installation on I-70 near Central Park Blvd off-ramp
ITS ductbank installation on I-70 eastbound on-ramp east of Central Park Blvd
Works in progress for bridge deck at Clayton
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 41
KMP recorded an aerial video of the corridor on August 03, 2019. Below are some screen shots from the video
that show the progress on various sections of the roadway.
East of Brighton Blvd looking towards the UPRR railroad
Overlooking the UPRR railroad tracks
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 42
East of UPRR railroad tracks looking east on I-70 with widening works undertaken on the north of I-70
East of Josephine Street looking over the new Columbine Street Bridge deck
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 43
East of Columbine Street looking over the new Clayton Street bridge
East of Steels Street looking over the widening works around the ramps on the north/south of I-70
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 44
East of Steels Street looking over the widening works in between Steels St and Colorado Blvd north of I-70
Looking over the Colorado Blvd with bridge works on north and south of I-70
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 45
Looking over east of Dhalia Street
Looking over north and south of I-70 around Stapleton Drive N/S
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 46
Looking over I-270 on I-70 with the new bridge deck to the south of the existing
Widening works on north and south of I-70 east of the I-270
Kiewit Meridiam Partners
Central 70 Project
Turner & Townsend 47
Overlooking widening works on north and south of I-70 east of the Central Park Blvd
Looking over the Peoria Street with new bridge decks on north and south of I-70
Error! Unknown document property name. Exhibit H-1
EXHIBIT H
FORM OF TECHNICAL ADVISOR CERTIFICATE
Date: August 27, 20191
U.S. Bank National Association, as Collateral Agent
Global Corporate Trust Services
950 17th Street, DN-CO-T12C
Denver, Colorado 80202
Attention: Gretchen L. Middents
Telephone: (303) 585-4596
Email: [email protected]
U.S. Bank National Association, as Intercreditor Agent
Global Corporate Trust Services
950 17th Street, DN-CO-T12C
Denver, Colorado 80202
Attention: Gretchen L. Middents
Telephone: (303) 585-4596
Email: [email protected]
Re: Kiewit Meridiam Partners LLC
Ladies and Gentlemen:
This Lenders’ Technical Advisor Certificate (this “Certificate”) is being delivered to you by Turner
& Townsend cm2r Inc. (“Turner & Townsend”), as Lenders’ Technical Advisor pursuant to
Section 5.24(a) of the Collateral Agency and Account Agreement, dated as of December 19, 2017
(as amended, amended and restated, supplemented or otherwise modified from time to time, the
“Collateral Agency Agreement”), among Kiewit Meridiam Partners LLC (the “Borrower”), the
United States Department of Transportation, acting by and through the Executive Director of the
Build America Bureau (the “TIFIA Lender”), U.S. Bank National Association, a national banking
association, in its capacity as intercreditor agent on behalf of the Secured Creditors (in such
capacity, the “Intercreditor Agent”), U.S. Bank National Association, a national banking
association, in its capacity as collateral agent on behalf of itself and the other Secured Parties (in
such capacity, the “Collateral Agent”) and in its capacity as securities intermediary on behalf of
itself and the other Secured Parties (in such capacity, the “Securities Intermediary”) and each other
Secured Party that accedes to the Collateral Agency Agreement in accordance with Article IX
thereto. Capitalized terms used and not otherwise defined herein shall have the meanings assigned
1 Technical Advisor Certificate must be delivered at least 3 Business Days prior to the proposed date on which funds are proposed to be withdrawn from the applicable Project Account or transferred from a Project Account to another Project Account (or such shorter period of time as is acceptable to the Intercreditor Agent and the Collateral Agent).
Error! Unknown document property name. Exhibit H-2
to such terms (whether directly or by reference to another agreement) in the Collateral Agency
Agreement.
We have reviewed the provisions of Section 5.24(a) of the Collateral Agency Agreement as they
identify the responsibilities of the Lenders’ Technical Advisor related to providing this Certificate.
We last visited the Site (as defined in the Project Agreement) on August 08, 2019 and observed
the status of progress at the Project at that time. We have reviewed documentation and held
discussions with the Borrower regarding the progress of construction activities at the Project since
that time. We have received the material data made available to us by the Borrower with respect
to the Project. We have also reviewed the Construction Requisition Certificate delivered on
August 26, 2019 by the Borrower (the “Subject Requisition”).
Our review and observations were performed within the scope of the Professional Services
Agreement, dated as of May 12, 2015, between the Lenders’ Technical Advisor and the Sponsors
(or affiliates thereof) (as amended and supplemented, the “Technical Services Agreement”), and
with the degree of skill and diligence normally practiced by independent technical advisors or
consultants performing the same or similar services on like projects. Based upon the foregoing
review and review procedures and on the understanding and assumption that we have been
provided true and complete information from other parties as to the matters covered by this
Certificate, as of the date of this Certificate, except as set forth in detail in Attachment A to this
Certificate, we are of the reasonable opinion that:
(a) for any funds to be applied to Project Costs for construction work under the
Construction Contract, such funds are for payment in respect of actual work
completed or work reasonably projected to be completed (except with respect to the
initial funding of the Construction Reserve Account);
(b) no Funding Shortfall exists;
(c) all amounts requisitioned in the Subject Requisition relate to Project Costs that have
been incurred or are reasonably projected to be incurred within the next thirty-five
(35) days in connection with the Project, and none have been the basis for a prior
requisition that has been paid; and
(d) Milestone Completion for Milestone 5 is reasonably expected to be achieved on or
prior to the Longstop Date.
This Certificate has been prepared in accordance with the Technical Services Agreement. This
Certificate is solely for the information of and assistance to the Intercreditor Agent and the
Collateral Agent in their respective capacities under the Collateral Agency Agreement, the Senior
Secured Parties and the TIFIA Lender in conducting and documenting their investigation of the
matters in connection with the Project and is not to be used, circulated, quoted, or otherwise
referred to within or without the lending group for any other purpose. Turner & Townsend
disclaims any obligation to update this Certificate. This Certificate is not intended to, and may
not, be construed to benefit any party other than the Intercreditor Agent and the Collateral Agent
in their respective capacities under the Collateral Agency Agreement, the Senior Secured Parties,
and the TIFIA Lender.
Error! Unknown document property name. Exhibit H-3
[The remainder of this page intentionally left blank; signature page immediately follows.]