major project estimating - rics.org · 18/08/2020  · major project development –much like an...

37
making the difference Major Project Estimating RICS Seminar 18 th August 2020

Upload: others

Post on 28-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

making the difference

Major Project Estimating

RICS Seminar

1

18th August 2020

Page 2: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Introduction

2

Running order

• Intro• Major Projects Estimating – setting up for success

– 45-50mins• Questions -10mins

About me….

• Started in the construction industry when I was 18• 18 years in heavy civils contracting - site engineer

through to contracts manager• 13 years in cost consultancy • Major projects estimating for

• Highways England• Heathrow Expansion• Dublin airport• Crossrail2

Page 3: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Setting Out Right

3

‘There is only one thing more painful than learning from experience and that is

NOT learning from experience’

Archibald MacLeish

Page 4: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend 4

Setting out right

Major projects particularly in construction have a terrible history of overspending

ProjectScottish Parliament

ProjectSydney Opera House

ProjectNHS IT System

ProjectHumber Bridge

ProjectDublin Port Tunnel

ProjectJubilee Line Extension

Overrun1600%

Overrun1400%

Overrun500%

Overrun150%

Overrun160%

Overrun80%

90 years of data suggests we aren’t getting any better.

Page 5: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Setting out right

5

Major Project Development – Much like an iceberg

Construction / Delivery

Planning + Development 3-5 yrs.

90% Mass below water

level

Page 6: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Characteristics of failure

• Owing to their size and long planning horizons, Major Projects are inherently risky

with complex interfaces.

• Multi & complex stakeholder engagements

• Undefined scope at early stage

• Approach generally stoical around ‘Black Swan’ risks

• Overly optimistic Design & Delivery team.

Setting out right

6

‘Over budget, over time, under benefit, over and over again.’Flyberg 2011

Page 7: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Setting out right

Slow Start

7

Fast Finish

Fast Start Slow Finish

Page 8: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Setting out right

8

• Front end planning pushed• Bad projects not stopped• Implementation stage delayed

• Costs Soar

Page 9: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Setting out right

9

Preferred decision process

Ability to impact Cost

Cost of Change

Existing Processes

Design Construction Operation

Eff

ort

/ E

ffect

MacLeamy Curve

Page 10: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Setting out right

10

The importance of the estimate

InformsBusiness Decisions

Feedsthe Schedule

Baselinesthe Project

ProvidesBenefits for

Business case

Informsthe Design

Sets UpThe Project for

Success

The estimate is central to success!

Page 11: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Setting out right

11

Acknowledging Risk

We need to understand

the dynamics at play in

major programmes of work

▪ Will to succeed

▪ Culture of dismissing the bad

news messengers

▪ Ignorance of Black Swan Risks

▪ Projects led by problem solvers –

Engineers and PlannersOptimism Bias will be growing in its perfect

environment

Page 12: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Setting out right

12

Acknowledging Risk

What you don’t know you don’t know

What you know

What you think you know

What you think you don’t know

Costs that reflect the scope provided

Risk of design creep and growth through lifecycle

Project related risks

Uncertainties

‘Reports that say that something hasn't happened are always interesting to me, because as we know, there are known knowns;

there are things we know we know. We also know there are known unknowns; that is to say we know there are some things we

do not know. But there are also unknown unknowns—the ones we don't know we don't know. And if one looks throughout the

history of our country and other free countries, it is the latter category that tend to be the difficult ones’

Donald Rumsfeld – US Secretary of Defense 2001 - 2006

Page 13: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Setting out right

13

2

1

4

3

5

6

Go-live

Define the Project Lifecycle and Assurance Process

Select an Estimating Software Platform & Databases

Establish Price Base & Approach to Inflation

Form linkage with Risk Teams & Embed Approach to Uncertainties

Establish Estimating process and procedures

Determine Work and Cost Breakdown Structures

Go!

Page 14: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Project maturity & its impact on cost

Project Maturity - Key is to understand the purpose of the estimate

14Insert presentation title > use the Header and footer icon > apply to all

Misalignment will lead estimator to include greater levels of uncertainty, therefore, inducing higher risk

Page 15: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Project maturity + Impact on cost

15

Misalignment will lead estimator to include greater levels of uncertainty, therefore, inducing higher risk

No good expecting a funding approve estimate when the scheme data supports a business case estimate.

Page 16: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Project maturity & its impact on cost

16

Adherence to Stage is Key

‘Misalignment of design to requirement will lead the estimator to include greater levels of uncertainty, therefore, inducing higher risk’

Page 17: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Project maturity & its impact on cost

17

Target Improve Control

Making the solution affordable

Demonstrating the price of your brief

Establishing controls and safeguarding your target

Performance Management & Reporting

Knowledge, Data & Tools

Page 18: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Project maturity & its impact on cost

18

Eff

ort

Gateway Gateway Gateway

Bearer of Bad News

Impact is inevitable

Cost increase lay uncommunicated until the gateway nears

There is little or no time to rectify the impact to the budget of late arriving costs

Unverified Adjustments

Adjustments made to suit time or budget constraints

Traditional Approach

Page 19: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Project maturity & its impact on cost

19

Eff

ort

Gateway Gateway Gateway

Progressive

Collaborative

Permits the consistency of knowledge bank in personnel with demand forecasted

Design + Schedule focussed by Cost derives meaningful value engineered solutions

Considered

Allows time to consider Cost, Risk, Schedule and Uncertainty before the design is finalised

Dynamic Design to Cost

Page 20: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Project Maturity & Impact on Cost

20

Co

st

Gateway Gateway Gateway

Uncertainty

Risk

Base Costs

Page 21: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Project maturity & its impact on cost

21

Co

st

Gateway Gateway Gateway

Maturity Cost Curves – the plan

Optimistic

Pessimistic

Page 22: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Project maturity & its impact on cost

22

Co

st

Gateway Gateway Gateway

Maturity Cost Curves – the reality

Optimistic

Pessimistic

Page 23: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Project maturity & its impact on cost

23

ManageSet up the Team

ExpectRisks &

Uncertainties to move

CollaborateBring the estimate along the journey

Life cycleDetermine the estimate detail

GlideThe Project Costs

NoChristmas trees

Page 24: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Importance of good data & does it exist?

24

The Vacuum of Space

Prior to contractor

engagement it can be a tricky

time for estimating cost

▪ Vagueness of the tasks

▪ Availability of the right data

▪ Could, Would, Should costs

▪ Quality of information

Determining what and how data is applied is the

key to success

Page 25: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Importance of good data & does it exist?

1

2 3

Pre-Design / Funding Approval

Elemental, Item Rates

Funding Approval / Award

Item Rates, First Principles

Pre-Design

Analogous, Reference Class, Elemental

25

Page 26: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Requirements - Large Data set of familiar projects, intelligent data detailed enough to spot anomalies

Brilliant at the basics

Importance of good data & does it exist?

Reference ClassData

Powerful demonstrator of

likely outturn costs

Side Steps Optimism bias

May not fit your requirements

Needs to be

used alongside elemental or bottom up process

26

Pre Design

Funding Approval

Award

Page 27: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Requirements - Quality reference data aligned to scope, clean and defined point of cost - Tender, Target,

Outturn etc. Good sample size

Brilliant at the basics

Importance of good data & does it exist?

Elemental Cost information

Excellent communicator of cost aligned to blockydesign

Confidence -increased granularity matchesscope

Vague scope

data may cloud accurate cost

Data Doesn’t fityour required scope

27

Pre Design

Funding Approval

Award

Page 28: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Requirements - Provenance of rates Inc. location quantity & complexity, large sample data set at common points

of capture i.e. Target

Brilliant at the basics

Importance of good data & does it exist?

Item Rate information

Granularity allows application of cost to key elements

Tangible – & challengeable costs against scope

Factors –location, Qty, Complexity may not be captured

Ambiguity on scope if cost capture not done well

28

Pre Design

Funding Approval

Award

Page 29: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Requirements - Good sample data , Estimating Software platform to host and manage rate builds and libraries,

requires maintaining

Brilliant at the basics

Importance of good data & does it exist?

First Principles Rate information

Clear definition of resources & quantities required

Nominal –ambiguity in scope vs. cost

Significant –data required in volume & scope

Requires expertise to develop

29

Pre Design

Funding Approval

Award

Page 30: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Importance of good data & does it exist?

So, Does good data exist?

• Data is easy to find

• But Good data needs effort and persistence to get right

Yes , But…

30

Page 31: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Communicating the end product

31

Keeping the focus

Hard work is done

▪ Integration

▪ Recognise our weaknesses

▪ Reporting

▪ Maintaining the focus

Turning the estimate into a meaningful and live

document

It is time to tell the story

Page 32: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

32

Communicating the end product

Page 33: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

33

Communicating the end product

Lets be honest…

• How estimators perceive themselves and how they are perceived is often mis aligned

• Recognition of a varied stakeholder demographic is key to communication

• Awareness that BOQ’s aren’t the only option

• Speak to the Audience

Page 34: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Communicating the end product

34

Communication Plan

Consistent Formatting

Identify Stakeholders

Use Technology

Engage in dialogue

Different outputs for different audiences – clever use of WBS/CBS to roll up and down costs to suit all stakeholder requirements

Synergy via CBS and WBS provides peripheral interfaces to communicate with the estimate seamlessly . Grasp business analytics tools and get that data working!

Easy to understand projects costs, broken down to critical elements open up informative and effective dialogue

Consistent estimating format and reports span the years Major Projects are in design stage -Project Team familiarity is key

Page 35: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Communicating the end product

35

Communication Plan

This is a Journey

Maintaining a contemporary, robust and considered cost estimate front and centre of a Major Project will be one of the key success factors to the delivery of the scheme.

Page 36: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Close

36

A word from our sponsors….

• Outline the importance of the cost prediction process and the

skills and knowledge required by RICS members and RICS-

regulated firms.

• Define clear and consistent terminology.

• Describe the required inputs for successful cost prediction, their

sources and uses, and the processes required to transform them.

• Describe the prediction process at each stage of project

realisation, identifying the variability in prediction accuracy,

based upon the level of available inputs.

• Integrate ICMS as the standard for cost classification and

reporting to support benchmarking and reliable cost prediction.

RICS introducing a new Cost Prediction Professional Statement – due to launch this winter

Page 37: Major Project Estimating - rics.org · 18/08/2020  · Major Project Development –Much like an iceberg Construction / Delivery Planning + Development 3-5 yrs. 90% Mass below water

Turner & Townsend

Questions

37