major project estimating - rics.org · 18/08/2020 · major project development –much like an...
TRANSCRIPT
making the difference
Major Project Estimating
RICS Seminar
1
18th August 2020
Turner & Townsend
Introduction
2
Running order
• Intro• Major Projects Estimating – setting up for success
– 45-50mins• Questions -10mins
About me….
• Started in the construction industry when I was 18• 18 years in heavy civils contracting - site engineer
through to contracts manager• 13 years in cost consultancy • Major projects estimating for
• Highways England• Heathrow Expansion• Dublin airport• Crossrail2
Turner & Townsend
Setting Out Right
3
‘There is only one thing more painful than learning from experience and that is
NOT learning from experience’
Archibald MacLeish
Turner & Townsend 4
Setting out right
Major projects particularly in construction have a terrible history of overspending
ProjectScottish Parliament
ProjectSydney Opera House
ProjectNHS IT System
ProjectHumber Bridge
ProjectDublin Port Tunnel
ProjectJubilee Line Extension
Overrun1600%
Overrun1400%
Overrun500%
Overrun150%
Overrun160%
Overrun80%
90 years of data suggests we aren’t getting any better.
Turner & Townsend
Setting out right
5
Major Project Development – Much like an iceberg
Construction / Delivery
Planning + Development 3-5 yrs.
90% Mass below water
level
Turner & Townsend
Characteristics of failure
• Owing to their size and long planning horizons, Major Projects are inherently risky
with complex interfaces.
• Multi & complex stakeholder engagements
• Undefined scope at early stage
• Approach generally stoical around ‘Black Swan’ risks
• Overly optimistic Design & Delivery team.
Setting out right
6
‘Over budget, over time, under benefit, over and over again.’Flyberg 2011
Turner & Townsend
Setting out right
Slow Start
7
Fast Finish
Fast Start Slow Finish
Turner & Townsend
Setting out right
8
• Front end planning pushed• Bad projects not stopped• Implementation stage delayed
• Costs Soar
Turner & Townsend
Setting out right
9
Preferred decision process
Ability to impact Cost
Cost of Change
Existing Processes
Design Construction Operation
Eff
ort
/ E
ffect
MacLeamy Curve
Turner & Townsend
Setting out right
10
The importance of the estimate
InformsBusiness Decisions
Feedsthe Schedule
Baselinesthe Project
ProvidesBenefits for
Business case
Informsthe Design
Sets UpThe Project for
Success
The estimate is central to success!
Turner & Townsend
Setting out right
11
Acknowledging Risk
We need to understand
the dynamics at play in
major programmes of work
▪ Will to succeed
▪ Culture of dismissing the bad
news messengers
▪ Ignorance of Black Swan Risks
▪ Projects led by problem solvers –
Engineers and PlannersOptimism Bias will be growing in its perfect
environment
Turner & Townsend
Setting out right
12
Acknowledging Risk
What you don’t know you don’t know
What you know
What you think you know
What you think you don’t know
Costs that reflect the scope provided
Risk of design creep and growth through lifecycle
Project related risks
Uncertainties
‘Reports that say that something hasn't happened are always interesting to me, because as we know, there are known knowns;
there are things we know we know. We also know there are known unknowns; that is to say we know there are some things we
do not know. But there are also unknown unknowns—the ones we don't know we don't know. And if one looks throughout the
history of our country and other free countries, it is the latter category that tend to be the difficult ones’
–
Donald Rumsfeld – US Secretary of Defense 2001 - 2006
Turner & Townsend
Setting out right
13
2
1
4
3
5
6
Go-live
Define the Project Lifecycle and Assurance Process
Select an Estimating Software Platform & Databases
Establish Price Base & Approach to Inflation
Form linkage with Risk Teams & Embed Approach to Uncertainties
Establish Estimating process and procedures
Determine Work and Cost Breakdown Structures
Go!
Turner & Townsend
Project maturity & its impact on cost
Project Maturity - Key is to understand the purpose of the estimate
14Insert presentation title > use the Header and footer icon > apply to all
Misalignment will lead estimator to include greater levels of uncertainty, therefore, inducing higher risk
Turner & Townsend
Project maturity + Impact on cost
15
Misalignment will lead estimator to include greater levels of uncertainty, therefore, inducing higher risk
No good expecting a funding approve estimate when the scheme data supports a business case estimate.
Turner & Townsend
Project maturity & its impact on cost
16
Adherence to Stage is Key
‘Misalignment of design to requirement will lead the estimator to include greater levels of uncertainty, therefore, inducing higher risk’
Turner & Townsend
Project maturity & its impact on cost
17
Target Improve Control
Making the solution affordable
Demonstrating the price of your brief
Establishing controls and safeguarding your target
Performance Management & Reporting
Knowledge, Data & Tools
Turner & Townsend
Project maturity & its impact on cost
18
Eff
ort
Gateway Gateway Gateway
Bearer of Bad News
Impact is inevitable
Cost increase lay uncommunicated until the gateway nears
There is little or no time to rectify the impact to the budget of late arriving costs
Unverified Adjustments
Adjustments made to suit time or budget constraints
Traditional Approach
Turner & Townsend
Project maturity & its impact on cost
19
Eff
ort
Gateway Gateway Gateway
Progressive
Collaborative
Permits the consistency of knowledge bank in personnel with demand forecasted
Design + Schedule focussed by Cost derives meaningful value engineered solutions
Considered
Allows time to consider Cost, Risk, Schedule and Uncertainty before the design is finalised
Dynamic Design to Cost
Turner & Townsend
Project Maturity & Impact on Cost
20
Co
st
Gateway Gateway Gateway
Uncertainty
Risk
Base Costs
Turner & Townsend
Project maturity & its impact on cost
21
Co
st
Gateway Gateway Gateway
Maturity Cost Curves – the plan
Optimistic
Pessimistic
Turner & Townsend
Project maturity & its impact on cost
22
Co
st
Gateway Gateway Gateway
Maturity Cost Curves – the reality
Optimistic
Pessimistic
Turner & Townsend
Project maturity & its impact on cost
23
ManageSet up the Team
ExpectRisks &
Uncertainties to move
CollaborateBring the estimate along the journey
Life cycleDetermine the estimate detail
GlideThe Project Costs
NoChristmas trees
Turner & Townsend
Importance of good data & does it exist?
24
The Vacuum of Space
Prior to contractor
engagement it can be a tricky
time for estimating cost
▪ Vagueness of the tasks
▪ Availability of the right data
▪ Could, Would, Should costs
▪ Quality of information
Determining what and how data is applied is the
key to success
Turner & Townsend
Importance of good data & does it exist?
1
2 3
Pre-Design / Funding Approval
Elemental, Item Rates
Funding Approval / Award
Item Rates, First Principles
Pre-Design
Analogous, Reference Class, Elemental
25
Turner & Townsend
Requirements - Large Data set of familiar projects, intelligent data detailed enough to spot anomalies
Brilliant at the basics
Importance of good data & does it exist?
Reference ClassData
Powerful demonstrator of
likely outturn costs
Side Steps Optimism bias
May not fit your requirements
Needs to be
used alongside elemental or bottom up process
26
Pre Design
Funding Approval
Award
Turner & Townsend
Requirements - Quality reference data aligned to scope, clean and defined point of cost - Tender, Target,
Outturn etc. Good sample size
Brilliant at the basics
Importance of good data & does it exist?
Elemental Cost information
Excellent communicator of cost aligned to blockydesign
Confidence -increased granularity matchesscope
Vague scope
data may cloud accurate cost
Data Doesn’t fityour required scope
27
Pre Design
Funding Approval
Award
Turner & Townsend
Requirements - Provenance of rates Inc. location quantity & complexity, large sample data set at common points
of capture i.e. Target
Brilliant at the basics
Importance of good data & does it exist?
Item Rate information
Granularity allows application of cost to key elements
Tangible – & challengeable costs against scope
Factors –location, Qty, Complexity may not be captured
Ambiguity on scope if cost capture not done well
28
Pre Design
Funding Approval
Award
Turner & Townsend
Requirements - Good sample data , Estimating Software platform to host and manage rate builds and libraries,
requires maintaining
Brilliant at the basics
Importance of good data & does it exist?
First Principles Rate information
Clear definition of resources & quantities required
Nominal –ambiguity in scope vs. cost
Significant –data required in volume & scope
Requires expertise to develop
29
Pre Design
Funding Approval
Award
Turner & Townsend
Importance of good data & does it exist?
So, Does good data exist?
• Data is easy to find
• But Good data needs effort and persistence to get right
Yes , But…
30
Turner & Townsend
Communicating the end product
31
Keeping the focus
Hard work is done
▪ Integration
▪ Recognise our weaknesses
▪ Reporting
▪ Maintaining the focus
Turning the estimate into a meaningful and live
document
It is time to tell the story
Turner & Townsend
32
Communicating the end product
Turner & Townsend
33
Communicating the end product
Lets be honest…
• How estimators perceive themselves and how they are perceived is often mis aligned
• Recognition of a varied stakeholder demographic is key to communication
• Awareness that BOQ’s aren’t the only option
• Speak to the Audience
Turner & Townsend
Communicating the end product
34
Communication Plan
Consistent Formatting
Identify Stakeholders
Use Technology
Engage in dialogue
Different outputs for different audiences – clever use of WBS/CBS to roll up and down costs to suit all stakeholder requirements
Synergy via CBS and WBS provides peripheral interfaces to communicate with the estimate seamlessly . Grasp business analytics tools and get that data working!
Easy to understand projects costs, broken down to critical elements open up informative and effective dialogue
Consistent estimating format and reports span the years Major Projects are in design stage -Project Team familiarity is key
Turner & Townsend
Communicating the end product
35
Communication Plan
This is a Journey
Maintaining a contemporary, robust and considered cost estimate front and centre of a Major Project will be one of the key success factors to the delivery of the scheme.
Turner & Townsend
Close
36
A word from our sponsors….
• Outline the importance of the cost prediction process and the
skills and knowledge required by RICS members and RICS-
regulated firms.
• Define clear and consistent terminology.
• Describe the required inputs for successful cost prediction, their
sources and uses, and the processes required to transform them.
• Describe the prediction process at each stage of project
realisation, identifying the variability in prediction accuracy,
based upon the level of available inputs.
• Integrate ICMS as the standard for cost classification and
reporting to support benchmarking and reliable cost prediction.
RICS introducing a new Cost Prediction Professional Statement – due to launch this winter
Turner & Townsend
Questions
37