majestic progress report - august
DESCRIPTION
MIS FOR CONSTRUCTION SITETRANSCRIPT
MAJESTIC TOWER
Progress Report Date: 05/09/2014
A. Majestic Tower Residential Sale Building – (BUA – 22, 00,000 sft approx.) 2 basement + ground floor + 6 podium + 36 floors with 4 wings.
1. A wing : (2.5 BHK- 208 flats excluding Refuge area)
1st typical floor slab completed.
2. B wing : (2.5 BHK- 140 flats, 2 BHK – 68 flats excluding Refuge area)
Typical 10th floor slab completed.
Typical 11th floor slab 25 % completed.
Column above Typical 10th floor is completed.
Block work on 1st Floor is started for Sample Flat.
3. C wing : (2.5 BHK- 64 flats, 2 BHK – 140 flats, 3 BHK – 72 flats excluding Refuge area)
Typical 11th floor slab completed.
4. D wing : (2 BHK – 132 flats, 3 BHK – 144 flats excluding Refuge area)
Typical 13th floor slab completed.
Typical 13th To 14th floor column 35 % completed.
Note:
Drawing of 6th podium slab of podium area is not finalized yet.
B. Majestic Tower Rehab building – (BUA 9, 50,000 sft approx.)
1. Building 1 : Ground floor + 17 floors with 6 wings.
a. A wing : No. of flats – 134 excluding refuge area , balwadi , society office and meter room.
RCC and Brick work completed External Plaster 80 % of periphery area completed. Gypsum Plaster 78/134 flats completed.
b. B wing: No. of flats – 134 excluding refuge area, balwadi, society office and meter room.
RCC and Brick work completed External Plaster 35 % of periphery area completed. Gypsum Plaster 78/134 flats completed.
c. C wing : No. of flats – 134 excluding refuge area , balwadi , society office and meter room.
RCC and Brick work completed Casting of OHWT is completed. Gypsum Plaster 62/134 flats completed.
d. D wing: No. of flats – 134 excluding refuge area, balwadi, society office and meter room.
RCC and Brick work completed Fixing of marble frame on 17th floor is completed. Gypsum Plaster 54/134 flats completed.
e. E wing: No. of flats – 134 excluding refuge area, balwadi, society office and meter room.
RCC and Brick work completed External Plaster 25 % of periphery area completed. Gypsum Plaster 118/134 flats completed.
f. F wing: No. of flats – 134 excluding refuge area, balwadi, society office and meter room.
RCC and Brick work completed External Plaster 90 % of periphery area completed. Gypsum Plaster 118/134 flats completed. Basecoat in Bath & WC from 5th floor to 10th floor is completed.
2. Building 2: Ground floor + 16 floors with 4 wings.
a. A wing: No. of flats – 126 excluding refuge area, balwadi , society office and meter room.
RCC and Brick work completed External Plaster 80 % of periphery area completed. Gypsum Plaster 78/126 flats completed.
b. B wing: No. of flats – 126 excluding refuge area, balwadi, society office and meter room.
RCC and Brick work completed. External Plaster 10 % of periphery area completed. Gypsum Plaster 102/126 flats completed.
c. C wing: No. of flats – 127 excluding refuge area, balwadi, society office and meter room.
RCC and Brick work completed External Plaster 60 % of periphery area completed. Gypsum Plaster 80/127 flats completed.
d. D wing: No. of flats – 126 excluding refuge area, balwadi, society office and meter room.
RCC and Brick work completed External Plaster 90 % of periphery area completed. Gypsum Plaster 118/126 flats completed.
3. Building 3: Ground floor + 16 floors with 3 wings.
a. A wing: No. of flats – 90 excluding refuge area, balwadi, society office and meter room.
RCC work completed excluding OHWT. Brick work up to 9th floor completed. Gypsum Plaster 40/90 flats completed.
b. B wing: No. of flats – 124 excluding refuge area, balwadi, society office and meter room.
RCC and Brick work completed. Gypsum Plaster 70/14 flats completed.
c. C wing: No. of flats – 142 excluding refuge area, balwadi, society office and meter room.
RCC work completed excluding OHWT. Brick work up to 8th floor completed. Gypsum Plaster 67/142 flats completed.
4. Building 4: Ground floor + 16 floors with 3 wings.
a. A wing: No. of flats – 94 excluding refuge area, balwadi, society office and meter room.
Typical 11th floor slab completed. Brick work on 3rd, 4th, 5th & 6th floor completed.
b. B wing: No. of flats – 108 excluding refuge area, balwadi, society office and meter room.
Casting of Typical 12th floor slab completed. Brick work on 3rd, 4th, 5th & 6th floor completed.
c. C wing: No. of flats – 134 excluding refuge area, balwadi, society office and meter room.
RCC work completed. Brick work up to 16th floor completed. Fixing of Marble in Door & window frames is going on.
Description August -14 July-14 June-14 May -14
1 Labor strength per day 452 nos 351 nos 313 nos 300 nos
2 Average concreting per day 45 cum 23 cum 32 cum 18 cum
3 Average steel consumption per day 6.5 T 6.5 T 7.2 T 3.36 T
MAJESTIC TOWER PROGRESS REPORT
DATE : 05 / 09 / 2014
TOTAL PROJECT COMPLETED TILL DATE IN % =
25.05%
SR.NO
DESCRIPTION% WISE
CONTRIBUTIO
N IN PROJECT
A WIN
G
B WIN
G
C WIN
G
D WIN
G
COMPLETED%
WISE
CONTRIBUTION
1 EXCAVATION 5% 100%100.00
%
100.00
%
100.00
%
100.0
%5.00%
2 R.C.C. 45%29.57
%42.86% 49.67% 56.14%
44.6
%20.05%
3 BRICKWORK 10% 0.00% 0.00% 0.00% 0.00% 0.0%
4INTERNAL
PLASTER10% 0.00% 0.00% 0.00% 0.00% 0.0%
5EXTERNAL
PLASTER8% 0.00% 0.00% 0.00% 0.00% 0.0%
6WATERPROOFI
NG3% 0.00% 0.00% 0.00% 0.00% 0.0%
7 PLUMBING 5% 0.00% 0.00% 0.00% 0.00% 0.0%
8 FIRE FIGHTING 1% 0.00% 0.00% 0.00% 0.00% 0.0%
9ELECTRICAL
WORK3% 0.00% 0.00% 0.00% 0.00% 0.0%
10 TILING 6% 0.00% 0.00% 0.00% 0.00% 0.0%
11 PAINTING 2% 0.00% 0.00% 0.00% 0.00% 0.0%
12`MISCLLEANEO
US2% 0.00% 0.00% 0.00% 0.00% 0.0%
13 TOTAL 100% 0.0% 25.05%
NAHUR REHAB PROGRESS REPORT
TOTAL PROJECT COMPLETED TILL DATE IN % = 63 %
SR.NO
ACTIVITY
% W
ISE
CON
TRIB
UTI
ON
IN
PRO
JECT
BLD
G.N
O.1
BLD
G.N
O.2
BLD
G.N
O.3
BLD
G.N
O.4
ACTI
VITY
CO
MPL
ETED
IN
%
COM
PLET
ED%
WIS
E
CON
TRIB
UTI
ON
REM
ARKS
1 EXCAVATION 5% 100% 100% 100% 100% 100% 5%
2 R.C.C. 45% 100% 100% 100% 81% 95% 43%
3 BRICKWORK 10% 94% 94% 64% 46% 75% 7%
4 INTERNAL GYPSUM 10% 71% 71% 47% 0% 45% 5%
5EXTERNAL PLASTER
8% 40% 61% 0% 0% 25% 2%
6 WATERPROOFING 3% 0% 0% 0% 0% 0% 0%
7 PLUMBING 5% 0% 0% 0% 0% 0% 0%
8 FIRE FIGHTING 1% 0% 0% 0% 0% 0% 0%
9 ELECTRICAL WORK 2% 94% 94% 58% 20% 67% 1%
10ELECTRICAL WORK
SWITCH FITTING1% 0% 0% 0% 0% 0% 0%
11 TILING 6% 0% 0% 0% 0% 0% 0%
12 PAINTING 2% 0% 0% 0% 0% 0% 0%
12 MISCELLANEOUS 2% 0% 0% 0% 0% 0% 0%
13 TOTAL 100% 38% 40% 28% 19% 31% 63% SALE & REHAB STEEL OPENING SCHEDULE
DIA. RECEIVED USE BALANCE MT.
8mm 2203.99 2148.99 5510mm 362.352 341.352 2112mm 982.22 940.22 4216mm 955.755 929.755 2620mm 1537.72 1496.72 4125mm 1857.085 1790.085 6732mm 813.13 751.13 62
TOTAL 8712.252 8398.252 314
RMC CONSUMPTIONREHAB
SR. NO. CONCRETE PREVIOUS TODAY' S CUMML. GRADE QUANTITY QUANTITY QUANTITY CU.M.1 M15 1195 0 11952 M20 3 M25 15548.75 0 15548.754 M30 15108.75 0 15108.755 M35 6 M40 7 M45 8 M50
TOTAL 31852.5 0 31852.5
RMC CONSUMPTIONSALE
SR. NO. CONCRETE PREVIOUS TODAY' S CUMML.
GRADE QUANTITY QUANTITY QUANTITY CU.M.1 M15 54 0 542 M20 45 0 453 M25 4.5 0 4.54 M30 38.45 0 38.455 M35 8673.4 0.75 8674.156 M40 0 0 07 M45 506.5 0 506.58 M50 435.05 8.05 443.139 M55 7326.55 6.7 7333.2510 M60 91.5 0 91.511 M65 55.5 0 55.5
TOTAL 17230.45 15.5 17245.95
CEMENT CONSUMPTIONSALE AND REHAB
MATERIAL OPC 53 BULKER PPC GRADE
TOTAL RECEIVED 111465 15167.295 44718TOTAL CONSUMED 111260 15106.274 43908
TODAY' S RECEIVED 0 0 0OPENING BALANCE 205 61.021 810
TODAY' S CONSUMPTION 25 6.816 150
BALANCE ON SITE 180 54.205 660