magnolia lake final reportmagnolia lake shoreline stabilization phase ii – final report page 5...
TRANSCRIPT
Magnolia Lake Shoreline Stabilization Project – Phase II
Final Report
June 30, 2012
Prepared By: Bucks County Conservation District
1456 Ferry Road, Suite 704
Doylestown, PA 18901
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 1
Acknowledgements
The second phase of the Magnolia Lake Shoreline Stabilization Project was
financed by Growing Greener grant SE090185 provided by the Pennsylvania Department
of Environmental Protection. The views expressed herein are those of the author and do
not necessarily reflect the views of the Department of Environmental Protection.
The District would like to thank the Bucks County Commissioners and the Bucks
County Department of Parks and Recreation for their support of this project. In particular,
the District thanks Mr. Bill Mitchell and Mr. Bob Mercer of the County Park Department
and Silver Lake Nature Center for their cooperation and assistance throughout this
project. In addition, the District would like to thank the Greenbelt Overhaul Alliance of
Levittown (GOAL), specifically Mr. Dale Frazier, for their support including providing
educational forums for the public and assisting with planting and subsequent maintenance
of the shoreline buffer.
Project Summary
This project restored 300 linear feet of shoreline erosion through a combination of
regrading and installation of geogrid systems in two heavily compacted sections of the
southern shoreline of Magnolia Lake, located in Bristol Township, Bucks County. In
addition, BCCD and volunteers established a 9,400 ft2 vegetated shoreline buffer.
Introduction
Background
Magnolia Lake is a 26-acre lake located within the Mill (Otter) Creek watershed
in Bristol Township, Bucks County. The lake, initially a borrows area used during the
construction of the Pennsylvania Turnpike, was created in 1953. The lake and
surrounding land was subsequently purchased by the County of Bucks and is currently
maintained by the Bucks County Department of Parks and Recreation (BCPR). The lake
and surrounding parkland provide visitors with a variety of recreational uses such as
fishing, walking, and picnicking. Magnolia Lake discharges to Silver Lake, the focal
point of Silver Lake County Park, via Mill Creek.
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 2
Mill (Otter) Creek is a tributary to the Delaware River. In 2003, a comprehensive
lake and watershed management plan was developed to improve and protect the water
quality of streams and County-owned lakes within the Mill (Otter) Creek watershed
(Aqua-Link, Inc. 2003). In the assessment, both Silver and Magnolia Lakes were
classified as highly eutrophic or hyper-eutrophic. Samples collected from the lakes
showed high amounts of nutrients and algae (phytoplankton), which resulted in poor
water clarity (transparency) throughout the entire study period. In addition, Magnolia
Lake was characterized by very low dissolved oxygen levels, and Silver Lake is
extremely shallow due to heavy siltation. Magnolia Lake and Silver Lake were placed on
the Commonwealth’s 303(d) list of impaired waters in 2010 for aquatic life and
recreational impairments associated with nutrient enrichment and siltation. High levels of
nutrients and sediments to the lakes are attributed to stormwater runoff from urban lands
and streambank erosion and failure. The most significant sources of nonpoint source
pollution to the lakes are Queen Anne’s Creek, a major tributary to Mill Creek, and Mill
Creek.
The assessment recommended a variety of in-lake restoration techniques,
watershed best management practices (BMPs) and institutional practices to be
implemented by vested watershed stakeholders. Of those, addressing the severely eroded
southern shoreline of Magnolia Lake was deemed a high priority as the erosion
contributes high quantities of nutrients and sediments to Magnolia Lake, which in turn
flows into Silver Lake via Mill Creek.
In 2004, Bucks County Conservation District (BCCD) received funding from the
United States Environmental Protection Agency (US EPA) and Pennsylvania Department
of Environmental Protection (PA DEP) through Section 319 (Non Point Source Program)
of the Clean Water Act. The Phase I Project, completed in 2006, was to design plans to
restore this section of the shoreline of Magnolia Lake and draft permit applications to
facilitate the implementation of those plans. In 2009, the District applied for and was
awarded funding in 2010 via the PA DEP Growing Greener grant program to continue on
to Phase II of the project.
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 3
Project Objectives
The objective of this second phase of the Magnolia Lake Shoreline Stabilization
Project was to implement the plans developed in the first phase of the project and restore
approximately 325 feet of eroded lake shoreline along the central southern shoreline and
adjacent to the lake outlet. These areas of the shoreline run along Lakeland Avenue and
were severely eroding and unable to support vegetation due to overcompaction of the
soil. Through the implementation of this shoreline stabilization project, BCCD hoped to
reduce the soil compaction and shoreline erosion which contributes to the sediment and
phosphorus load to Magnolia Lake, and ultimately, Silver Lake. In addition, the District
hoped to establish additional native vegetation along the shoreline, promoting infiltration
and providing for filtration and nutrient uptake of stormwater by the plant material.
Project Tasks
Permitting
Although draft permit documents had been prepared in Phase I of the project, the
applications were not filed, pending the receipt of funding to complete the second phase.
Once the grant contract and landowner agreement for Phase II were fully executed,
BCCD initiated the process of applying for a State Programmatic General Permit 3
(SPGP-3) to implement the shoreline restoration. A Pennsylvania Natural Diversity
Inventory (PNDI) search was completed; and as several rare and endangered species
inhabit the general project area, BCCD submitted requests for review of potential impacts
of the proposed project by Pennsylvania Fish & Boat Commission and Pennsylvania
Department of Conservation and Natural Resources. After a few months, BCCD received
‘no anticipated impact letters’ from both state agencies, providing clearance to submit the
SPGP-3 registration materials for review by PA DEP. The permit, plans and other
supporting documentation were filed on October 14, 2010 and BCCD was notified of the
authorization on January 4, 2011.
In addition to the state general permit for streambank/shoreline restoration, the
erosion and sediment control plan was submitted for review by Mr. Rich Krasselt,
Environmental Protection Specialist I of BCCD. The plan was submitted March 18, 2011
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 4
and determined adequate on March 28, 2011. Bristol Township was contacted during the
permitting process, but no municipal plan reviews were required.
Contractor Selection
After the SPGP-3 and E&S applications were filed, BCCD prepared a request for
proposals (RFP) packet to solicit contractors who had previously completed similar
projects. Seven firms received the RFP packet which included project information and
photos, notification of a pre-proposal site visit with BCCD, and final proposal submission
deadline. Packets were distributed in mid-March and a pre-proposal site meeting was set
for April 1, 2011. Of the three companies who sent representatives to the site showing,
only two submitted proposals within the deadline for review by BCCD and BCPR. After
careful review, B. Blair Corporation were selected for the project. BCCD notified B.
Blair Corporation that their proposal was accepted on May 26, 2011. BCCD finalized the
contract with B. Blair and received the required bond and insurance information on June
22, 2011.
Construction
In preparation for the construction initially targeted for summer 2011, project
partners Bucks County Parks and Recreation Department/Silver Lake Nature Center,
Friends of Silver Lake, Greenbelt Overhaul Alliance of Levittown (GOAL) completed a
volunteer clean-up of the southern and eastern shoreline of Magnolia Lake on April 30 &
May 1, 2011. Over 4 tons of old tires, household garbage and recyclables were removed
from the construction areas and surrounding lake shoreline.
The shoreline construction was initially targeted for late August/early September
to overlap with the typical seasonal dry weather; however, significant rainfall throughout
the latter half of the summer precluded heavy equipment traffic on the site until early
October. A pre-construction meeting was held with BCCD representatives and B. Blair
Corporation on October 4, 2011, and construction started October 5, 2011. The
construction process lasted for approximately 3 weeks. After installing the turbidity
barrier at ‘Area A,’ tree protection fence, and the construction entrance, earthwork was
started at ‘Area B’ near the lake outlet (refer to Appendix A for site plans). Coir logs and
geotextile fabric were installed along the edge of the shoreline, an existing dead tree with
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 5
exposed roots was cleared and grubbed. Then the steep, eroding banks of Area B were
regraded to a more gradual slope and covered with the geotextile fabric. Finally, geoweb
material was installed on top of the fabric, filled with a mixture of native soil and
imported topsoil, and the entire area was seeded and matted.
Construction of ‘Area A’ was delayed at multiple stages. First, there was a delay
in the shipment of a portion of the geoweb material; BCCD requested the portion of the
site not be disturbed until sufficient quantities of the material specified in the plans was
available. In addition, once the materials were in place, another delay was encountered
during the initial scarification and regrading due to unanticipated and extensive quantities
of decomposing organic debris that had deposited along the shoreline. Because the debris
prevented proper anchoring of the geoweb material, the material was removed and taken
to an approved yard waste composting facility. To facilitate anchoring the geoweb and
stabilizing Area A BCCD approved a field change to the plans to install additional coir
logs along the water’s edge. As the delays extended the work into mid-October, rain also
delayed construction, at which times the site was matted for temporary stabilization until
work could be continued. Once the site was fully regraded and geoweb placed, topsoil
was mixed with the stockpiled soil and filled in the geoweb. Final seeding and matting
was completed, and the site was considered fully stabilized on October 24, 2011. Per the
construction plans, two 2 ½ inch caliper maples were installed along the edge of Area B
after a final check of the site on October 31, 2011. When construction was complete,
BCCD requested B. Blair Corp. keep construction fencing up to discourage vandalism of
the site while vegetation was planted and became established.
Buffer Establishment
In July 2011, BCCD contracted with NAM Planning and Design, LLC to assist in
the design of the shoreline buffer. BCCD conducted several meetings on site with NAM
LLC principal, Nancy Minich, and Silver Lake Nature Center director, Bob Mercer to
discuss planting logistics and species selection. Due to delays in construction, the initial
planting scheduled for mid-October was pushed back to October 26 and 29. BCCD had
initially coordinated with a local church youth group to provide a large volunteer force
for planting; however, the group could not accommodate a shift in the schedule from
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 6
October 15, when the site was still under construction. BCCD distributed flyers and press
releases, posted information on the District website and local media website and
volunteer information websites and reached out at a local high school. Unfortunately, the
October 29 buffer planting was delayed due to an unforeseen early season snowstorm,
which further challenged volunteer recruitment efforts.
The final weather delay work date was scheduled to coordinate with Silver Lake
Nature Center’s regular volunteer first Saturday events. BCCD hosted a staff workday on
site on November 3, 2011 to prepare the site: installing herbaceous material in the
geoweb areas and using an auger on loan from Heritage Conservancy to pre-drill holes
and streamline the planting effort. On November 5, a total of 16 volunteers from Silver
Lake Nature Center, Delaware Valley College, Bristol Township Youth Aid Program
planted from the edge of Area A east along the southern shoreline and throughout Area
B. GOAL volunteers who were unable to assist on November 5th due to a conflict helped
complete the final portion of the buffer installation on November 9, 2011.
In February 2012, BCCD met with Bucks County Parks and Recreation to discuss
measures of preventing damage by park visitors to the newly installed buffer with the
onset of spring and increased park use. At that time, the potential for adding additional
vegetation we also discussed, as additional funds were available in the budget due to
lower than anticipated construction costs, despite the unforeseen circumstances
encountered and additional materials used. BCCD and BCPR agreed to construct a
landscape timber path to delineate walking areas for anglers and other park visitors to
access the lake through the newly established plantings without trampling them. Another
work date was scheduled to coordinate with another Silver Lake Nature Center workday,
May 5, 2012. The volunteer workday was publicized again through Silver Lake Nature
Center, press releases, email and website postings. Unfortunately, despite these efforts
volunteer turnout was very low. Despite the low number of volunteers, the landscape
timber path was completely installed and 60% of the plants were planted by the end of
the workday. BCCD and GOAL completed the additional planting over the following two
weeks.
Warm and dry weather of the late spring and early summer has highly stressed the
newly establishing buffer. BCCD has been regularly watering with the help of GOAL
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 7
volunteers, and utilized some of the remaining available funds from this project to
purchase a water pump to facilitate the watering process to maintain the young plants
through dry periods. Although the purchase of this equipment was not initially included
in the Scope of Work, it will be available to BCCD and for loan to watershed associations
upon request both to maintain the Magnolia Lake buffer and for future riparian buffer
projects as well.
Education and Outreach
For the educational component of this project, BCCD conducted two separate
presentations at the Bristol Township Senior Center that were coordinated by GOAL and
highlighted Magnolia Lake as an example of a current watershed restoration project in
the area. The first presentation on watershed management was on Sept 25, 2011, during
which Magnolia Lake was featured as a project to be completed soon. A follow-up
presentation was conducted on April 25, 2012. In addition, BCCD gave a series of lunch
session presentations on this project and the functions of riparian buffers to students at
Harry S. Truman High School on September 28, 2011. BCCD staff encouraged the
students to participate as a means of completing their community service graduation
requirement. In addition to these efforts, BCCD plans to write a newsletter article
highlighting the completion of the grant project for inclusion in both the southeastern
Pennsylvania conservation district newsletter ‘Conservation & You,’ which reaches an
audience of over 1,000 environmental professionals and partner organizations in the
region, and for the Pennsylvania Lake Management Society newsletter ‘What’s Wet,’
which reaches lake association members and environmental professionals focused on lake
management throughout Pennsylvania.
Conclusions and Recommendations
BCCD encountered several challenges in the completion of the Magnolia Lake
Shoreline Stabilization Phase II project. First, despite several outreach efforts, volunteer
involvement was relatively limited for the planting effort given the population size of the
immediate area. This low turnout is attributed in part to weather and construction delays
which hindered the development of a consistent schedule to plan months ahead for the
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 8
planting. In hindsight, all planting could have been delayed to Spring 2012 or BCCD
could have requested an extension on the performance period of the grant to conduct all
planting in Fall 2012 and provide an optimal time for planting that did not risk
overlapping with the construction schedule; however, weather delays could be equally
possible in Fall 2012. In addition to limited community involvement, the dry weather of
the late spring has also contributed to significant mortality of the newly established
buffer. The plants installed in Spring 2012 were particularly impacted by the dry weather,
despite watering and maintenance efforts by BCCD and our partners. We therefore
recommend the partners contribute funds and/or seek additional funding to replace
portions of the buffer affected by the drought and strive to install these plantings in the
autumn.
Despite the challenges and setbacks, Phase II of the Magnolia Lake Shoreline
Stabilization project was successful in stabilizing over 300 feet of overly compacted and
severely eroded shoreline despite several weather-related delays throughout the project.
Although the geoweb material did not lend itself to the installation of woody vegetation;
it provides for a stable area for public access along the shoreline that does not negatively
impact water quality. The geoweb prevents future compaction of those sections of the
shoreline even with significant foot traffic or even vehicular traffic, which allows for turf
grass coverage in areas that had previously been eroding and too compacted to allow any
vegetation establishment. In addition, the lower than anticipated cost of construction
allowed for expansion of the existing hedgerow along the shoreline, widening the
forested buffer zone along approximately 700 feet of shoreline from 15 to 25 feet wide.
As the additional 9,500 square feet of shoreline buffer becomes established it will provide
additional protection against future shoreline erosion, while filtering out nutrients and
sediment from stormwater runoff and shading of the water and enhancing wildlife
habitat.
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 9
Appendix A. Construction Plans
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 10
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 11
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 12
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 13
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 14
Appendix B. Project Photos
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 15
Photo 1. View facing east of 'Area B,' near lake outlet July 2010.
Photo 2. View facing north of severe shoreline erosion at 'Area B' July 2010.
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 16
Photo 3. View of erosion on central southern shoreline ‘Area A’ July 2010.
Photo 4. GOAL, Heritage Conservancy and BCCD show off filled dumpster from Magnolia Lake
shoreline clean-up Spring 2011.
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 17
Photo 5. GOAL volunteers removing trash from staging area near eastern shoreline of Magnolia
Lake.
Photo 6. Staging coir logs before initiation of earth work at 'Area B.'
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 18
Photo 7. Installation of geoweb near lake outlet (Area B).
Photo 8. Installation of geoweb at Area B.
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 19
Photo 9. Area A just prior to installation of stabilization measures.
Photo 10. Staged geoweb materials prior to installation at Area A.
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 20
Photo 11. Installation of geoweb and coir logs at Area A.
Photo 12. Final stabilization at Area A.
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 21
Photo 13. Start of initial planting at Area B. Orange paint denotes additional areas for plant
placement and installation.
Photo 14. Plant delivery for first phase of planting in Fall 2011.
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 22
Photo 15. BCCD staff Jake Borden and Kent Himelwright help prep the site for volunteers Fall 2011.
Photo 16. Planting volunteers break from work to pose for the camera.
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 23
Photo 17. Volunteers install buffer in Fall 2011.
Photo 18. Volunteers work to install additional trees and shrubs in Spring 2012.
Magnolia Lake Shoreline Stabilization Phase II – Final Report Page 24
Photo 19. Area A and Fall 2011 planting area in late Spring 2012.
Photo 20. Phase 2 planting area in late Spring 2012.