Street Resurfacing Selected Contractor: Shelly Construction Curb to Curb Resurfacing Resurfacing will take place in phases, three phases in total. Construction will begin: March 23 rd (weather permitting) Madison Avenue Reconstruction

TRANSCRIPT

Page 1: Madison Avenue Reconstruction Department of Planning and Development

Madison

AvenueReconstructi

onDepartment of Planning and Development

Page 2: Madison Avenue Reconstruction Department of Planning and Development

Project Overview

Madison Avenue will be completely resurfaced from

Riverside to West 117th.

The project is being funded through Federal, State and

County funds.

$2.8 million

Cuyahoga County Department of Public Works is overseeing

project

Madison Avenue Reconstruction

Page 3: Madison Avenue Reconstruction Department of Planning and Development

Street ResurfacingSelected Contractor:

Shelly Construction

Curb to Curb Resurfacing

Resurfacing will take place in phases, three phases in total.

Construction will begin:March 23rd

(weather permitting)

Madison Avenue Reconstruction

Page 4: Madison Avenue Reconstruction Department of Planning and Development

Madison Avenue Reconstruction

Curb to Curb Construction

Page 5: Madison Avenue Reconstruction Department of Planning and Development

Madison Avenue Reconstruction

Phase AreaApprox.

Start DateApprox.

Finish Date

Phase 1 Riverside to Mars March 23rd May 6th

Phase 2 Mars to Wyandotte May 6th June 22nd

Phase 3 Wyandotte to W. 117th June 22nd September 4th

Traffic will be maintained in each direction, at all times.

Page 6: Madison Avenue Reconstruction Department of Planning and Development

Madison Avenue Reconstruction

Page 7: Madison Avenue Reconstruction Department of Planning and Development

Madison Avenue Reconstruction

Traffic LightsThe current traffic lights along Madison will be replaced with new signals and poles.

Concrete work will continue until June as the complete curb and ramp repairs.

Traffic poles are scheduled to be delivered in April

The new light system should be operational in July.

Page 8: Madison Avenue Reconstruction Department of Planning and Development

Madison Avenue Reconstruction

2015

J F M A M J J A S O N D

Traffic Signal Installation

Street Resurfacing

Page 9: Madison Avenue Reconstruction Department of Planning and Development

Madison

AvenueReconstructi

onDepartment of Planning and Development

Updated Information available at:www.onelakewood.com/Madison