madhya pradesh power transmission company ...sldcmpindia.com/uploads/meeting/minutes of 58th occm...

69
MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR Telephone: (0761) 2970089 Fax: (0761) 2664343/2970119 e-mail [email protected] Corporate office: Madhya Pradesh Power Transmission Co. Ltd., Block No.2, Shakti Bhawan, Rampur, Jabalpur 482008, CIN-U40109MP2001SGC01 vkbZ ,l vks : 9001-2008 ISO: 9001-2008 No.07-05/SG-9B-II/1833 Jabalpur, dated:16.08.2017 To As per distribution list Sub: Minutes of 58 th meeting of Operation and Coordination Committee of MP. The Minutes of 58 th meeting of the Operation and Coordination Committee of MP held on 14 th July 2017 at Hotel Kalchuri, Jabalpur has been uploaded on the website of SLDC ‘www.sldcmpindia.com’ and can be downloaded. (R.A. Sharma) Member Secretary, OCC SLDC, MPPTCL, Jabalpur

Upload: others

Post on 24-Oct-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

  • MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED

    STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR Telephone: (0761) 2970089 Fax: (0761) 2664343/2970119 e-mail [email protected]

    Corporate office: Madhya Pradesh Power Transmission Co. Ltd., Block No.2, Shakti Bhawan, Rampur,

    Jabalpur 482008, CIN-U40109MP2001SGC01

    vkbZ ,l vks : 9001-2008

    ISO: 9001-2008

    No.07-05/SG-9B-II/1833 Jabalpur, dated:16.08.2017

    To

    As per distribution list

    Sub: Minutes of 58th meeting of Operation and Coordination Committee of MP.

    The Minutes of 58th meeting of the Operation and Coordination Committee of MP held on

    14th July 2017 at Hotel Kalchuri, Jabalpur has been uploaded on the website of SLDC

    ‘www.sldcmpindia.com’ and can be downloaded.

    (R.A. Sharma) Member Secretary, OCC SLDC, MPPTCL, Jabalpur

    mailto:[email protected]

  • Distribution List 1. The Chief Engineer (Works), MP Power Transmission Co. Limited, Shakti Bhawan, Jabalpur, email-

    [email protected]. 2. The Chief Engineer (T&C), MP Power Transmission Co. Limited, Jabalpur. Fax No- 0761-2665593,

    2702710 Email- [email protected] 3. The Chief Engineer (Transmission-East Zone), MP Power Transmission Co. Limited, Shakti Bhawan,

    Jabalpur. Email- [email protected]. 4. The Chief Engineer (Transmission-West Zone), MP Power Transmission Co. Limited, Indore. 5. The Chief Engineer (Transmission-Central Zone), MP Power Transmission Co. Limited, Bijlee Nagar,

    Govindpura, Bhopal, email- [email protected]. 6. The Chief Engineer (Plg & Des), MP Power Transmission Co. Limited, Jabalpur, Fax No- 0761-2660908

    Email- [email protected] 7. The Chief Engineer (Procurement.), MP Power Transmission Co. Limited, Jabalpur, .Fax No- 0761-

    2660908 Email – [email protected] 8. The Executive Director (O & M:Gen), MP Power Generating Company Limited, Jabalpur. Fax No- 0761-

    2664749, Email- [email protected], Email- [email protected] 9. The Chief Engineer (O&M:Hydel), MP Power Generating Co. Ltd, Jabalpur, Fax No-0761-2664749. 10. The General Manager(PM), MPPMCL, Jabalpur Email – [email protected]

    [email protected] 11. The Superintending Engineer (GCC), MPPGCL, Jabalpur Email – [email protected]

    [email protected]. 12. The General Manger (DCC-EZ), DISCOM Control Centre, MP Poorva Kshetra Vidyut Vitaran Co.Limited,

    Jabalpur, Fax No- 0761-2668503, Email – [email protected]. 13. The Dy. General Manager (DCC –CZ), DISCOM Control Centre, MP Madhya Kshetra Vidyut Vitaran Co.

    Limited, Bhopal, Fax No-0755-2580611,Email- [email protected]. 14. The Executive Engineer (DCC-WZ), DISCOM Control Centre, MP Paschim Kshetra Vidyut Vitaran Co.

    Limited, Near Polo Ground, Jail Road, Indore, Fax No- 0731-2421554, Email- [email protected]. 15. The Executive Engineer, Sub Load Despatch Centre, MPPTCL, Indore, Fax No- 0731-2874515, Email –

    [email protected]. 16. The Executive Engineer, Sub Load Despatch Centre, MPPTCL, Bhopal, Fax No- 0755-2885220, Email –

    [email protected] 17. The General Manger(RO), MPPMCL, In front of Bhojpur Club, E-4, Arera Colony,Bhopal, Fax No-0755-

    2423046, [email protected] 18. The Chief Engineer (PM&C), Narmada Hydroelectric Development Corpn. Ltd, NHDC Parisar, Shamla

    Hills, Bhopal – 462013., Fax No- 0755-4030130,Email – [email protected] 19. The Chief Electrical Distribution Engineer, West Central Railway (WCR), General Manager’s Office,

    Electrical Department, Jabalpur-482001 (MP), Fax: 0761-2627629, Email- [email protected], [email protected], M-9752415312, Mr.Satyendra Kumar (Dy.CE), Mob.9752415301 (CEDE, WCR).

    20. The General Manager, Indira Sagar Power Station, NHDC Office complex, PO : Narmada Nagar, Distt : Khandwa (MP) – 450 119, Fax No- 07323-284080, Email – [email protected]

    21. The General Manager, Omkareshwar Power Station, Prashsnik Bhawan, Urja Vihar, Sidhwarkut, Distt : Khandwa (MP) – 450 554, FaxNo-07280-271703, Email- [email protected], [email protected], [email protected].

    22. The Director (Projects), BLA Power Limited, At : Niwari, PO: Khorsipan, Tah : Gadarwara, Distt ; Narsinghpur 487 551, Fax No. 07791-243667 / 243669, Email – [email protected]

    23. The Sr. Vice President, Jaiprakash Power Ventures Ltd., Village Sirchopi Subpost Office-Agasod, Post Office-Bina- 470113 Distt- Sagar, Fax No. 07580-277200, Email – [email protected]

    24. The Chief Executive Officer, Kalpataru Satpura Transco Pvt. Ltd., Satpura Colony, Betul Road, Old Itarsi, Distt. Hoshangabad, Email – [email protected]

    25. M/s Ujaas Energy Ltd. 701, NRK Business park, Vijay Nagar Sqaure, Indore – 452010, Email id :[email protected]

    26. M/s Suzlon Global Services Ltd., 1090, Scheme no. 114, Park-2, Ring Road, Universal Hospital Row, Email- [email protected], Indore – 452010, [email protected]

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]

  • The 58th meeting of Operation & Coordination Committee of MP was held on 14th July 2017 at 11:00 AM at hotel Kalchuri, Jabalpur under the Chairmanship of Shri K.K.Prabhakar C.E.(SLDC) & Chairman OCC. The list of participants is enclosed at Annexure -1.0.

    Shri Amit Sarkari, Addl. Chief Engineer (O&E), JP Bina on behalf of JP Bina welcomed Shri

    K.K.Prabhakar, C.E.(SLDC) & Chairman OCC and Shri R.A.Sharma, SE(Opn.), SLDC & Member Secretary OCC with bouquet of flower. He also welcomed all the guest and participants. Thereafter he requested Shri. R.S.Sharma, Sr. President JP Bina to address the meeting.

    Shri R.S.Sharma, Sr.President, JP Bina on behalf of JP Bina & SLDC welcomed Shri K.K.Prabhakar,

    C.E.(SLDC) & Chairman OCC and Shri R.A.Sharma, SE(Opn.), SLDC & Member Secretary OCC, all the participants & guests and thanked the committee for giving them the opportunity to host the 58th OCC meeting after a gap of 4 years, mentioning that previously JP Bina hosted one of the OCC meetings in 2013. Thereafter he requested the committee that whenever the power of JP Bina is being rescheduled or revised, the duration of rescheduled power shall be kept constant for at least 04 Hrs. as the frequent increase or decrease in generation schedule of a thermal power plant results in degrading the Unit and its efficiency in long term. Further he also assured that JP Bina will support the grid as per the system requirement.

    Thereafter Chairman OCC thanked Shri R.S.Sharma, Sr.President, JP Bina hosting the 58th OCCM of

    MP and making such good arrangement. He informed the committee that in OCC meeting operational issues are discussed and resolved and it is of great pleasure to inform that all the operational issues that were brought in the forum (i.e., MP OCCM) have been amicably resolved & implemented with the concurrence/endorsement & co-operation of the concerned entities. He stated that in future also the operational issues will be resolved with co-operation of all the entities, if brought in this forum.

    Further he stated that the issues included in the MP OCCM are submitted by SLDC itself as per their

    observations and no operational issues/agenda points are being submitted by any other entity, which leads to the conclusion that the entities are not having any operational problems/issues. He also stated that JP Bina might have some commercial issues that shall be discussed with MPPMCL separately. Thereafter he requested all the entities to submit the agenda point if they are having any operational issues, so that the grid operation can be made more safe & secure with our combined efforts. He also requested all the generating stations to absorb MVAR from the grid in case of high voltage and MPPTCL shall do the switching operation of reactor. Also MPPTCL with coordination of Discom shall operate the capacitor banks as per system requirement to support the grid.

    Thereafter Chairman, OCC requested the Member Secretary to take up the agenda points. Member

    Secretary, Shri R.A. Sharma expressed his thanks to JP Bina for conducting the 58th OCCM and all participants on the occasion for participating. He stated that the operational issues as mentioned by Chairman OCC is of great importance for operating the grid in safe & secure manner, however the commercial issues cannot be neglected but those issues can be addressed and discussed. He also stated that the incidences of blackout like the one in 2012 has not yet been resolved and SLDC’s & other concerned entities are being penalized. Hence to avoid such black outs in future and the safe & secure operation of the grid can only be maintained by proper co-ordination & co-operation of the grid entities. Further he requested for a formal introduction of all the participants.

    Thereafter Member Secretary, OCC took up the agenda points.

    MINUTES OF 58TH MEETING OF OPERATION & COORDINATION COMMITTEE OF MP HELD ON 14TH JULY 2017 AT 11:00 AM AT HOTEL KALCHURI, SOUTH CIVIL LINE, NEAR RLY. STATION, JABALPUR .

  • ITEM NO. 1 : CONFIRMATION OF MINUTES : Member Secretary, OCC informed the committee that the Minutes of 57th meeting of Operation & Coordination Committee of MP held on 5TH May 2017 at SLDC, MPPTCL, Jabalpur were forwarded to the committee members vide No. 07-05/SG-9B-II/1090 Jabalpur dated 08.06.2017.

    ITEM NO. 2 : REVIEW OF SYSTEM OPERATION DURING THE MONTHS APRIL 2017 TO MAY 2017. 2.1. Frequency Particulars: Member Secretary, OCC informed the committee that during April 2017 the system frequency was below 49.9 Hz for 9.05% of time against 9.09 % of time during May 2017. The system frequency was above 50.05 Hz for 16.46% of time during April 2017 against 19.46% of time during May 2017. The system frequency was within the IEGC range of 49.9-50.05 Hz for 74.49% of the time during April 2017 against 71.45% of time during May 2017. The average monthly frequency was 49.99 Hz during month of April 2017 and 49.99 Hz during month of May 2017. The system frequency did not touch 49.20 Hz during the above period.

    The detailed frequency particulars for the month of April 2017 and May 2017 are enclosed at

    Annexure-2.1. The brief detail of frequency profile is given here under:

    Month Average frequency

    Minimum Integrated frequency over an hour

    Maximum integrated frequency over an hour

    Instantaneous Minimum Frequency

    Instantaneous Maximum Frequency

    April 2017 49.99 Hz 49.83 Hz 50.14 Hz 49.66 Hz 50.26 Hz May 2017 49.99 Hz 49.78 Hz 50.18 Hz 49.64 Hz 50.26 Hz

    Member Secretary OCC stated that the instantaneous Minimum Frequency for the month of April-2017 was 49.66 Hz & for the month of May-2017 was 49.64 Hz which is a matter of concern as the frequency below 49.7 Hz is not secure for system operation and also has commercial implications. Hence the frequency shall be maintained within permissible range. 2.2 Operational Matters

    2.2.1 Operational Discipline : Member Secretary, OCC informed the committee that the System operated

    in terms of frequency profile for the months April 2017 and May 2017 is as given below for discussion by the

    committee :

    Month % of time Frequency Below 49.9 Hz

    % of time Frequency above 50. 05 Hz

    % of time frequency within the permissible range of 49.9-50.05 Hz.

    Average monthly frequency

    No. of times frequency dipped below 49.2 Hz

    April 2017 9.05% 16.46% 74.49% 49.99 Hz 0 May 2017 9.09% 19.46% 71.45% 49.99 Hz 0

  • 2.2.2 Voltage Profile: Member Secretary, OCC informed the committee that during the months April 2017 and May 2017 the maximum and minimum voltage as recorded at following important 400 KV s/s in MP Grid:-

    April 2016 May 2017 Max. Voltage Min. Voltage Max. Voltage Min. Voltage Name of observed Observed Observed Observed Sr 400 KV

    Voltag Volt

    No Substation Voltage ag Voltage Date E Date Date Date KV e KV KV KV

    1 Indore 418 22.04.17 397 13.04.17 422 07.05.17 398 23.05.17

    2 Itarsi 414 23.04.17 394 13.04.17 417 28.05.17 394 23.05.17

    3 Bina 411 10.04.17 392 10.04.17 418 28.05.17 394 25.05.17

    4 Gwalior 421 11.04.17 380 09.04.17 417 21.05.17 384 07.05.17

    5 Nagda 420 27.04.17 381 04.04.17 422 07.05.17 397 23.05.17

    6 Satpura 421 23.04.17 406 13.04.17 427 28.05.17 407 11.05.17

    7 Birsinghpur 423 23.04.17 405 24.04.17 427 28.05.17 405 24.05.17

    8 ISP 423 10.04.17 404 13.04.17 427 07.05.17 406 11.05.17 Member Secretary OCC stated that as per IEGC the safe operating voltages for 400 KV system is 380-420 KV and in the monsoon months due to low demand, the transmission lines are lightly loaded resulting in higher system voltage as mentioned above. Hence during such high system voltage conditions it is the primary responsibility of generators to absorb MVAR from the system as per their capability curve & also the OLTC setting of the GT should be such that it helps in maintain their bus voltages and contribute in maintaining the grid voltage within safe operating range. Representative from MPPGCL requested that the voltage for SSTPS shall also be included in the above list. Thereafter Member Secretary OCC confirmed the same.

    2.2.3 Status of Capacitor Banks in sub-transmission system: Member Secretary, OCC informed the committee that the updated information of the status of capacitor banks in sub-transmission system as on 31st May 2017 as submitted by DISCOMs is detailed below:

    DISC

    OM

    Capacitor bank installed in good condition (No)

    Capacitor Banks healthy but not in service due to control ckt problem

    Capacitor bank installed but defective & are repairable (No)

    Requirement of repair against each unit (No)

    Requirement against non-repairable capacitor banks

    Capacitor banks already covered under ADB T-V

    Balance capacitor banks to be covered in other schemes

    600 KVAR

    1200 KVAR

    1500 KVAR

    600 KVA

    R

    1200 KVA

    R

    1500 KVA

    R

    600 KVA

    R

    1200 KVAR

    1500 KVAR

    No of 100 KVAR Units

    required

    600 KVAR

    1200 KVAR

    600 KVAR

    1200 KVAR

    600 KVAR

    1500 KVAR

    EZ 404 142 29 30 9 3 14 08 1 30 - - - - - 80

    CZ 5 687 686 0 0 0 0 0 0 0 0 0 0 588 0 0

    WZ 627 544 559 17 15 06 19 18 110 181 2 10 - - - 9

  • Member Secretary OCC stated that the Capacitor banks installed and its healthiness & availability shall be ensured by Discoms during the Rabi season to maintain voltages within safe limits. 2.2.4 Status of Shunt Capacitor Banks installed at various EHV Transmission Substation: Member Secretary, OCC informed the committee that the updated information of the status of installed capacitor banks (in MVAR) in EHV transmission system as on 31.05.2017 as submitted by MPPTCL is given below:-

    Chairman OCC stated that instances have been observed in real time where the capacitor banks are not in working condition, whereas its availability was ensured by MPPTCL in previously as per above mentioned data. Representative from MPPTCL informed that the non-availability of capacitor banks at a particular instance was due to some temporary/minor problems and ensured that the proper availability report will be submitted in future. 2.2.5 Status of completion of ongoing Transmission Schemes being executed by MPPTCL: Member Secretary, OCC informed committee that the various ongoing Transmission Schemes completed during the previous financial year 2017-2018 (up to May 2017) and plan for completion of various ongoing Transmission Schemes for the Year 2017-2018 is enclosed as Annexure 2.2.5(i) and 2.2.5(ii) respectively.

    2.2.6 U/F and df/dt Relay Operation (i) U/F and df/dt Relay Operation: Member Secretary, OCC informed committee that the frequency did not

    touch 49.20 Hz during April 2017 and May 2017. There was no df/dt operation during the same period. (ii) Defective u/f, df/dt relays: Member Secretary, OCC informed committee that MPPTCL has informed that

    all the df/dt relays are in good/healthy working condition and where the U/F relays are not available, the numerical relays programmed for under frequency operation.

    2.3 Power Cuts / Load restrictions/Differential Load Shedding by DISCOMS & group allocation to 33

    KV feeders : (i) Member Secretary, OCC informed committee that the details of DISCOM wise Power supply given to

    various domestic categories during the period April 2017 and May 2017 is enclosed at Annexure 2.3(i).

    (iii) Group Allocation to Newly Commissioned existing EHV substations:- Member Secretary, OCC informed committee that the region wise list of 33 KV feeders emanating from various newly

    Voltage Class

    Capacitor bank installed as on

    31.05.17(MVAR)

    Capacity Added after Last OCC Meeting (MVAR)

    Capacitor banks already covered under ADB T-V

    TOTAL CAPACITY AS ON 31-05-17

    Capacitor Bank Installed but

    defective & are not repairable (No &

    MVAR) 220 KV 100.00 0.00 - 100.00 All in Service

    132 KV 1238.00 0.00 - 1238.00 33 KV 4600.50 24.00 - 4624.50 Total 5938.50 24.00 - 5962.50

  • commissioned/existing EHV substations for which groups have not been allocated is given in Annexure 2.3 (ii). The DISCOM wise details of pending group allocation to 33 KV feeders is given below:-

    SN DISCOM Region No of 33 KV feeders for which groups to be allocated

    01

    EAST

    Jabalpur 02 02 Sagar 01 03 Rewa 03 04 Total 06 05

    WEST Indore 12

    06 Ujjain 06 07 Total 18 08

    CENTRAL Bhopal 08

    09 Gwalior 08 10 Total 16

    TOTAL Grand Total 40 Representative from East Discom informed the committee that all the feeders of Jabalpur, Sagar &

    Rewa regions the groups have been allocated for above mentioned feeders.. Representative from West Discom informed the committee that 08 no. of feeders group have been

    allocated and remaining 10 no. 33 KV feeders, group allocation shall be done at the earliest. Representative from Central Discom informed the committee that 02 no. of feeders group have been

    allocated and remaining 4 no. 33 KV feeders, group allocation shall be done at the earliest. Representative from P&D, MPPTCL requested that confirm status of feeders to be group allocated

    shall be submitted well in advance by Discoms. Further Member Secretary OCC stated that it shall be done by proper coordination & cooperation between the concerned entities and requested Discoms to submit the details as soon as possible. ITEM NO. 3 : OPERATIONAL PLANNNING: 3.1 Generating Units under planned outage and proposed maintenance programme : Member Secretary, OCC informed committee that the annual maintenance /outages of thermal generating units of MPPGCL during July 2017 to Aug 2017 is enclosed as below.

  • FROM DATE TO DATE1 SGTPS 5 15.06.2017 15.07.2017 AOH2 STPS 8 01.07.2017 25.07.2017 AOH

    3 STPS 11 01.07.2017 19.08.2017AOH/ ESP

    WORK4 SGTPS 3 15.07.2017 08.08.2017 AOH5 SSTPS 1 15.07.2017 29.07.2017 AOH6 SSTPS 2 01.08.2017 21.08.2017 AOH7 STPS 9 01.08.2017 25.08.2017 AOH8 SGTPS 2 15.08.2017 29.08.2017 AOH9 STPS 1 01.09.2017 15.09.2017 AOH

    PLANNED OUTAGE DURATION S.no STATION UNIT NO. REASON

    Representative from MPPGCL informed the committee that the revised maintenance schedule has

    been submitted to SLDC. SLDC requested MPPMCL to submit their comments on above maintenance programme. No comments has been received from MPPMCL.

    3.2 Proposed shutdown programme of Transmission lines / Transformers: Member Secretary, OCC informed committee that the proposed shutdown of transmission elements for the period 01.07.2017 to 31.08.2017 submitted by MPPTCL is enclosed as Annexure-3.2.

    3.3 Long Outages of transmission elements and protections: Member Secretary, OCC informed committee that the status submitted by MPPGCL /MPPTCL are given below:-

    Sr. No

    Line/Transformer/ etc under long Outage

    Outage date Reason Response from Utility

    1. 315 MVA, 400/220kV ICT-1, Sr. No. 6005210 at 400 kV S/s Bina

    15.10.15 Differential Due to Buchholtz relay alarm.

    The 315MVA X’mer has been commissioned after repairs at 17:00 hrs on 09.05.17 .

    2. Main Breaker of 400 KV Nagda-Rajgarh-II.

    23.07.15

    Y-phase CT burst/ BKR Problem

    400 KV Rajgarh II is charged from 400 KV Main Bus-I, for ensuring connectivity with Main Bus-II. The work is in progress with work of providing Reactor on ISP Bay 400 KV Rajgarh-I is shifted in diameter of 315 MVA ICT-IV, which has facility to connect on Main Bus-I and Main Bus-II. This will impact when outage of Bus-II occurs in outage of Nagda- Rajgarh–II circuit. Representative from MPPTCL informed the committee that the Main CB has

  • been taken in service on 23.05.2017. Member Secretary OCC stated that the information/intimation of taking the Main CB into service shall be sent to SLDC.

    3. 315 MVA, 400/220 KV X’mer II (TELK make) Main Breaker at 400 KV S/s Katni

    03.11.2015

    X’mer commissioned through bus coupler breaker since commissioning.

    It has come to notice that the transformer-II has been connected through bus coupler breaker both side (400 KV & 220 KV) and there is no main breaker for this 315 MVA X’mer-II. In 54th , 55th, 56th and 57th OCCM MPPTCL informed the committee work of 220 KV Ckt breaker has been completed and 400 KV Ckt. Bkr. work is under progress. Representative from MPPTCL informed the committee that 220 KV side Main CB is taken in service & 400 KV side Main CB work is in progress and CB expected to be commissioned by September-2017.

    4. 12.5 MVA, 132/66/33 KV X’mer CGL make Sr. No. 23615 at 132 KV S/s Pichhore

    19.05.2016 Transformer failed on

    19.05.2016 as intimated by T&C, MPPTCL.

    The load is manageable through (1x20 + 1x40) MVA X’mers in running condition at S/s Pichhore. Hence replacement of failed X’mer is not required as intimated by MPPTCL. In 52nd 53rd 54th & 55th OCCM, Chairman OCC requested MPPTCL, P&D to submit the letter for removal of transformer from Asset. In 56th and 57th OCC Chairman OCC stated that T&C and P&D will perform load growth / load assessment study prior to decommissioning and intimate to SLDC. Representative from P&D informed the committee that the concurrence for decommissioning of X’mer from concerned Discom is required as per their load growth. Member Secretary OCC stated that the matter shall be taken up by P&D with Discom and thereafter it shall be discussed in this forum as it includes policy matter also.

    5. 12.5MVA, BBL Make (Sr. No.-1428/3) at 132 KV S/s Chapda.

    Not intimated X’mer failed

    The 12.5MVA BBL make Transformer Sl.No. 1428/3 failed and proposed to be withdrawn from system as intimated by MPPTCL. In 56th and 57th OCC representative from T&C informed the committee that correspondence is being done with P&D, MPPTCL for load growth study and decommissioning of the transformer. Member Secretary OCC stated that the matter shall be taken up by P&D with Discom and thereafter it shall be discussed in

  • this forum as it includes policy matter also.

    6. 160 MVA, 220/132 KV Sr. No. 626452037050 BHEL X’mer at 220 KV S/s Jabalpur

    30.09.2016 Tripped on Differential indication.

    Transformer dismantled and sent to M/s BHEL for inspection / repairs as intimated by MPPTCL. Representative from MPPTCL informed the committee that the X’mer is expected to be taken in service by end of September-2017.

    7. 20 MVA, 132/33 KV GEC X’mer at 132 KV S/s Waidhan

    22.02.17 Kept out due to increased key gases.

    Transformer charged on 04.05.17 after checking and oil filteration work.

    8. 63MVAR 400KV Bus reactor-II at STPS, Sarni 06.09.2016

    MPPGCL has intimated that 63 MVAR Bus Reactor-II has been taken into service on 11.05.2017.

    9. 63 MVA Auto X’mer at ATPS Chachai.

    14:30 Hrs/ 16.03.2017

    Generation of Acetylene Gas in the DGA result was found beyond dangerous limit.

    MPPGCL informed that personnel from BHEL has carried out inspection at site. Order has been placed to BHEL for overhauling of Auto Transformer. Representative from MPPGCL informed the committee that the X’mer is expected by end of August-2017.

    10. 50 MVA, 132/33 KV BHEL make X’mer Sr. No. 2042474 at 132 KV S/s Katni

    28.05.2017

    Tripped on differential indication.

    Representative from MPPTCL informed the committee that X’mer is being sent to BHEL for testing & repair and is expected by end of Novemebr-2017.

    ITEM NO. 4 : OPERATIONAL STATISTICS FOR THE MONTH OF APRIL 2017 AND MAY 2017: Member Secretary, OCC informed committee that the details of actual generation, Schedule from Central Sector, demand etc. are given in the following Annexures: Annex. 4.1 Unit wise actual Generation of MPPGCL thermal Units and station wise Generation of

    MPPGCL & NHDC Hydel Units. Annex. 4.2 Power Supply Position. Annex. 4.3 Hourly Average of Availability and Demand. Annex. 4.4 Hourly average schedule Vs Drawal of DISCOMs. ITEM NO. 5.0 : SYSTEM DISTURBANCE IN MP DURING APRIL 2017 AND MAY 2017 : Member Secretary, OCC informed committee that there was no major grid disturbance in MP during April 2017 and May 2017. Moreover, the Grid Disturbances and Grid Incidents in MP during these months are given in Annexure 5.0.

    Member secretary stated that the proper indications shall be submitted by OSP to SLDC for any tripping prior to issue of charging code. ITEM NO. 6.0 : IMPORTANT OPERATIONAL ISSUES:- 6.1 STATUS OF COMPLETION OF ONGOING SCHEMES FOR COMMISSIONING OF REACTORS / TRANSMISSION ELEMENTS:-, Member Secretary OCC informed committee that the present status regarding schedule and commissioning of reactors / transmission elements is as below:-

  • S.No. 400 KV S/s Size MVAR

    Implementing Agency

    Expected Date of Commissioning as intimated in last OCC

    1. Bus Reactor : ISP 125 MVAR NHDC

    Representative from NHDC informed the committee that delivery of all equipment is expected by August 2017. Thereafter erection & commissioning work will be carried out. It is expected that the reactor will be in service by October 2017 as informed by NHDC.

    2. Line Reactor on 400 kV Satpura–ISP line at STPS

    50 MVAR MPPGCL

    In 56th OCCM, MPPGCL informed the committee that procurement of line reactor is under tendering stage and expected to be commissioned by Oct-2017. Representative from MPPGCL informed the committee that the tender has been floated and is expected by July-2018.

    3. Bus Reactor at SSTPS 125 MVAR MPPGCL

    Work will be carried out under PSDF as intimated by MPPGCL. In 56th OCCM MPPGCL informed the committee that purchase tender will be opened on 31.03.2017. Representative from MPPGCL informed the committee that the price bid is to be opened and is expected to be commissioned by January-2018.

    6.2 Provision of synchronization facility at EHV sub-stations of MPPTCL:- Member Secretary OCC

    informed committee that as per Grid Code, the synchronization facility should be available at all the Power

    Stations, 400 KV Sub-stations and 220 KV Sub-stations and 132 KV sub-stations in the path of black start. In

    last OCC meeting MPPTCL representative informed the committee that order for 69 no. synchronization

    trolleys has been placed and 1 no. synchronization trolley has been delivered for checking and testing purpose

    at 220KV S/S Barwaha.

    The status of installation and commissioning of synchronization trolleys at different substations has not

    been intimated by the MPPTCL till date. MPPTCL is requested to submit latest status along with time line in

    the meeting.

    Representative from MPPTCL informed the committee that the synchronization trollies have been

    supplied at the sub stations, further its wiring/commissioning is to be done. It is expected that the

    synchronization trolley will be commissioned by at earliest.

    Chairman OCC stated that the synchronization trolley shall also be installed at 132 KV S/s on the

    black start path and the problem regarding non availability of line CVT in all three phase of lines at 132 KV S/s

    shall be resolved. Thereafter representative from T&C informed the committee that the synchronization trolley

    is expected to be commissioned by end of September-2017. Further Member Secretary OCC stated that

    progress of installation of trolleys shall be intimated to SLDC on regular basis.

    6.3 Ten Daily Reservoir operation table of MPPGCL HPS:- Member Secretary OCC informed committee that in the meeting held in Regional Office of MPPMCL at Bhopal on 24.09.2016 to discuss availability from

  • Sardar Sarovar Project, ISP & OPS and State Hydel Plants for Rabi season, MPPGCL had agreed to obtain ten daily reservoir operation table from WRD and NVDA for their operation of their hydro generators. In last 54th, 55th,, 56th and 57th OCCM, request has been made to MPPGCL for furnishing the same to SLDC within a week,

    MPPGCL has not submitted the ten Daily Reservoir Table of all the power stations of MPPGCL for the

    year 2017-18. It is requested that MPPGCL shall submit the Ten Daily Reservoir Table of all hydel power stations in coordination with NVDA and WRD for optimum utilisation of available water in the reservoirs during real time operation.

    Representative from MPPGCL informed the committee that for Bargi & Bansagar the required Ten daily data will be submitted by end of September-2017. Thereafter Member Secretary OCC requested MPPGCL to submit the Ten daily details of the remaining HPS at the earliest.

    6.4 : MAPPING OF FEEDERS WIRED UNDER AUFLS TO SLDC SCADA :- Member Secretary OCC informed committee that in the 4th, 5th & 6th NPC meetings, mapping of the Feeders / Lines covered under AUFLS on SCADA systems of SLDC's/RLDC's was discussed. NPC have desired that monitoring of the feeders / loads under the AUFLS shall be done at SLDC's / RLDC's, so as to ascertain that the desired results are ensured during the events, frequency falling below the AUFLS frequency settings. In last OCC meetings the matter was discussed. It is therefore requested that latest status in this matter may please be submitted to SLDC in them meeting. Also constraints, if any, faced in mapping AUFLS feeders in their SCADA System may be intimated. Member Secretary OCC stated that the status of the operation of under frequency relays and load relief obtained due to operation of AUFLS shall be mapped. He also informed the committee that a separate meeting should be conducted with M/s Dongfang to discuss the process for mapping of feeders under AUFLS to SLDC scada. 6.5 MONITORING OF SCHEMES FUNDED FROM PSDF :- Member Secretary OCC informed committee that it was decided in the 6th meeting of NPC held on 19th December 2016 at Bengaluru, that all the RPCs in the monthly OCC meetings may follow up with the utilities to expedite the completion of schemes by giving due priority. The implementation of most of the schemes are based on the recommendation of the enquiry committee on grid disturbance of July 2012 headed by Chairperson, CEA. Therefore timely implementation of these schemes would enhance the grid security and reliability. Accordingly the details of grant sanctioned from PSDF for the schemes of MP is enclosed at Annexure- 6.5A. The status of implementation of above schemes (physical as well as financial progress) may please be reviewed and the entities are requested to expedite implementation of the schemes. The utilities were advised to furnish the information in the format enclosed at Annexure – 6.5B by first week of every month on regular basis to Member Convener, PSDF project monitoring group (AGM, NLDC, POSOCO) with a copy to NPC, WRPC division and SLDC. The status of the same is being monitored by WRPC in OCC meeting of WRPC every month. It is observed that MPPTCL and MPPGCL are not submitting the requisite information to SLDC in first week of every month for onward transmission to WRPC. It is therefore requested that concerned official may please instructed to submit the same to SLDC with time limit.

  • The matter was discussed in the meeting & MPPTCL & MPPGCL assured to submit the same within time. 6.6 MVAR absorption by Generating Stations to Control High voltage: It was observed that during the monsoon, demand in WR reduces by 4000-5000 MW. In the past, even after taking all Switchable Shunt Reactors in service and opening lightly loaded lines, high voltages are observed at most of the EHV nodes during night hours. In view of inadequate shunt reactive compensation, the generating units are being advised to contribute in voltage regulation by operating their units in under-excited mode (absorb Reactive Power) within the capability curve. The issue was discussed by WRLDC and SLDC in various OCC meeting and advised generators not to inject reactive power into the grid even when the bus voltage is above nominal. The MW, MVAR and Voltage of generating units was analyzed for the month of May 2017 with the help of SCADA data available at WRLDC and SLDC . it is observed that almost the same generators of MPPGCL are contributing to inject MVAR in to grid even when voltage if above nominal a. Satpura (U#10 & U#11) b. Singhaji (U#1 & U#2) It was observed that almost the same list of generators mentioned in 494th OCCM are continuing to inject MVAR into grid even when voltage is above nominal. SLDC is continuously requesting all the concern generating stations in real time to control high voltage scenario by absorbing MVAR by their generating units. It is therefore requested all concern Generating Stations not to inject MVAR into grid when there is over voltage for safe, secure and reliable operation of the grid. Member Secretary OCC stated that during Monsoons ,due to low demand EHV transmission lines are lightly loaded , resulting in the high system voltages. Hence generating station shall absorb the MVARs as per the capability curve and support the grid. 6.7 REPORTING OF FLASH REPORT, DR and EL FOR 400KV, Interstate Transmission Elements & Detailed Tripping Report:- Member Secretary OCC informed committee that as per the provisions of Regulation 5.2 (r) of CERC (Indian Electricity Grid Code) Regulations 2010 and Regulation of 5(9) of CERC (Indian Electricity Grid Code) (First Amendment) Regulations, 2012 all the Regional Entities of the Region shall furnish the tripping details including DR & SEL output to RLDC with in 24 hrs of the event for analysis and identify the real time measures required in future to ensure secured grid operation. The flash report is also required to be furnished to SLDC within an hour of tripping. It is observed that FLASH REPORT, DR & EL of station is not made available after tripping of transmission grid element by the State Grid Entities and the flash report is also not being sent after repeated pursuation. All intra-state entities are requested to submit the FIR, DR & EL of station during tripping of transmission grid elements.

    Member Secretary OCC stated that the flash report of any occurrence/ tripping in the system shall be submitted by the concerned entity to the SLDC in the shortest time and detailed report further.

  • 6.8 RGMO Status of Generating Stations : - As per Regulation 5.2(f) of Part 5 of IEGC (fifth amendment ) of the Principal Regulations" “All Coal/lignite based thermal generating units of 200 MW and above, Open Cycle Gas Turbine/Combined Cycle generating stations having gas turbines of capacity more than 50 MW each and all hydro units of 25 MW and above shall be operated under restricted mode of operation all the time.

    MPPGCL is requested to submit the latest status of availability/commissioning of RGMO in all eligible units. JP Bina and NHDC is also requested to keep their governor in restricted mode of operation and confirm the same in the meeting. The above one time information shall be submitted by all concerned entities in the format as below:-

    Sno. Name Of Eligible Unit

    RGMO Commissioned Working Condition In Service Yes/No If not

    commissioned then reason for not commissioning

    Yes/No If not in working condition then reason for not working.

    Yes/No If not in Service then reason for not in service.

    Chairman OCC informed that JP Bina, ISP, OSP has submitted the RGMO/FGMO details thereafter he requested MPPGCL to submit the details in above format at the earliest to SLDC.

    6.9 Procedure for Availing Shut Down

    6.9.A:- Availing of outage of Interstate and 400 KV transmission elements and 220 KV lines radiating

    from PGCIL Sub-stations:- Member Secretary OCC informed committee that in the WRPC in 493rd OCCM

    informed all the entities that the standard procedure for availing outages on interstate and 400 KV transmission

    elements / 220 lines radiating from PGCIL sub-stations has been devised by WRPC and WRLDC in line with

    guidelines of CEA and NLDC. This process is approved in OCC meeting of WRPC and has been implemented

    w.e.f. 1st March 2017. The above directives have been conveyed vide letter No. 07-05/RPC-42/4392 dated

    06.03.2017. Subsequently, vide this office letter No. 144 dated 17.04.2017 all the state entities are requested

    to adhere with above directives of WRPC.

    As per standard procedure of WRPC, all proposed outages of interstate, 400 KV transmission elements and

    220 KV lines radiating from PGCIL sub-stations for next month should be got approved in the OCC meeting of

    WRPC in the current month. All the constituents of WR shall inform to WRLDC for readiness for availing

    outage of transmission elements on D-3 basis i.e. 3 days before the date of approved outage. Further in

    WRPC meeting it was also decided that non-OCCM outages should be discouraged.

    During 496th OCCM of WRPC which was held on Mumbai on 13.06.2017, Member Secretary, WRPC has

    informed that no any shutdown shall be entertained / approved on D-3 basis, except emergency nature

    shutdown. Therefore it becomes mandatory to get approval of all the shutdown in OCCM. It may please be

    noted that WRPC is reluctant to give consent of outage of transmission elements for maintenance /

    construction activities since long except OCCM approved shutdown. Now, WRPC is not giving consent for

    outages which are not approved in OCCM of WR.

  • In view of above, it is therefore requested that all proposed shutdown of 400 KV elements, interstate

    lines and all 220 KV line radiating from PGCIL sub –stations may be included in proposal of outages for

    consideration of OCCM of WR as per practice in vogue so that maintenance / construction activities may not

    be hampered and shutdown may be availed systematic pre-planned manner as desired by WRPC. All the

    proposed shutdown for OCCM by T&C/ EHT-Maint./ EHT-Constn. shall be complied by O/o CE(T&C)

    MPPTCL Jabalpur and a consolidated list of proposed shutdown shall be submitted to SLDC within stipulated

    time for onward submission to WRPC. Similarly all other entities also shall follow the above outage procedure,

    for getting approval of transmission elements from WRPC OCCM.

    Further, if approved shutdown has not been availed then reason of not availing shutdown may also be

    intimated to SLDC for onward communication to WRPC and WRLDC.

    6.9.B:- Procedure for availing outages on EHV elements (other than point No. A), for which outages

    shall be approved by SLDC:

    Member Secretary OCC informed committee that for availing shutdown on EHV elements which do

    not covered under criteria mentioned under point A and the approval shall be given by SLDC, such proposal

    should be forwarded to CE (SLDC) in prescribed format enclosed as per Annexure-6.9.B for availing

    shutdown on EHV element. The same should also be e-mailed at least one day ahead of date of shutdown.

    Only emergency shutdown shall be entertained on same date.

    Member Secretary OCC informed that all the intra state entities shall apply for the approval of S/d in

    the prescribed format as enclosed on D-1 basis.

    6.10 Inspection of Automaitc Under Frequency Load Shedding : As Per MPEGC Clause 6.1.17 “all Users shall provide automatic under-frequency load shedding in their respective premises, to arrest frequency

    decline that could result in a collapse/disintegration of the grid, as per the plan separately finalised by the

    concerned REB forum, and shall ensure its effective application to prevent cascade tripping of .generating

    units in case of any contingency. All Users shall ensure that the under frequency load shedding/islanding

    schemes are functional.. SLDC shall carry out periodic inspection of the under frequency relays and maintain

    proper records of the inspection.

    In 31st WRPC meeting and 478th OCC meeting of WRPC it is decided that SLDCs shall collect the

    data of self certification by Discoms/STUs and inspection carried out by intra-circles of Discoms/STUs and

    submit to WRPC. In the last meeting of OCC of WR, WRPC suggested to carry out the AUFLS inspection for

    at least 10-20 % by WRPC Secretariat & others shall be self-certified by S/s in-charge.

    In view of the above it is requested that suitable instruction may please issued to the concerned

    SE(Testing) to self certify the healthiness of the UFRs under their jurisdiction and submit the same SLDC on

    monthly basis, so that the same could be forwarded to WRPC. Further as per regulatory provisions. SLDC

    shall carry out periodic inspection of the under frequency relays.

  • The matter was discussed in the meeting. Member Secretary informed the committee that certification

    of the healthiness of UFRs is not received from any T&C Division till date. He requested MPPTCL to take up

    the matter with all SE(T&C) to submit the same to SLDC at the earliest.

    6.11 COMPLIANCE TO LOW VOLTAGE RIDE THROUGH (LVRT) BY WIND GENERATORS:- :- Member Secretary OCC informed committee that as per CEA regulations(Technical Standards for Connectivity)- Regulations-2013 (Part-II) provides that all Wind Electric Generating stations commissioned on or before 15.04.2016 and connected at a voltage level of 66 Kv and above shall remain connected to the grid when voltage at the interconnection point on any phases dips upto 0.15 pu. This CEA standard is applicable to the wind generating stations &n generating stations using invertors.

    CERC on its order dtd. 05.01.2016 in petition no. 420/MP/2014 directed that LVRT should be implemented for all wind turbines commissioned before 15.04.2014 and connected to voltage level of 66 KV and above and having a Installed capacity equal to or more than 500 KW. Further CERC direct that the solar generators whose bidding process has not yet commenced i.e NIT has not been issued on the date of the order shall take necessary steps to implement LVRT in their generating Stations.;

    In 494th OCC meeting of WRPC, Member Secretary WRPC, requested all states to indicate the

    present methodology of checking LVRT compliance in vogue for giving clearance for integration and update the status of LVRT compliance. The details may be compiled in the format given below and submit the same to WRPC and WRLDC

    Location Pooling Station

    Deverloper Turbine make

    Turbine type

    Turbine Capacity

    If turbine commissioned before 15.04.2014 Expected date of completion of retrofitting

    If turbine commissioned after 15.04.2014 whether compliant to LVRT (Yes/No)

    In view of the above it is requested that all wind and solar generators should comply the directives of

    CERC and submit the information to SLDC for onward transmission to WRPC and WRLDC. In future the injection permission of wind and solar generators shall be issued by SLDC after compliance of LVRT. MPPTCL is also requested to include the same its connectivity agreement/permission while issuing to RE generators. The matter was discussed in the meeting. 6.12 Formation of State Level Relay setting group- Review and Coordination of relay setting in state of

    MP :- As decided in 128th Protection Committee meeting of WRPC held on 06th & 07th Dec. 2016 , relay

    review group for state of MP has been constituted vide this officer letter No.07-05/RPC-14/596 Jabalpur dtd

    22.05.2017. The details of nominated officers for state level relay setting group are enclosed at Annexure-6.12. In the above context all entities are requested to provide relay settings of all important nodes & all other

    nodes where relay settings are required to be examined considering protection issues. As desired by WRLDC

  • important nodes like Indore PG, Bhopal etc. required to be examined first, which have huge effect on reliability

    and security of Grid.

    In view of above, it is requested to provide relay settings of all important nodes, so that the same may

    be communicated to all respective entities so that they can study the same and matter may be discussed in

    meeting, and remedial action could be evolved for addressing the protection issues. Further all entities are

    also requested to furnish agenda point from their end which are required to discussed in relay review group

    meeting. The meeting of relay review group of MP state shall be organized after capturing above data and

    shared with group members. The date of proposed meeting shall be intimated separately.

    Member Secretary OCC informed stated the relay setting data shall be submitted by the concerned

    entities and thereafter a meeting will be called to discuss the matter.

    6.13 Web portal on weather information for power sector :- :- Member Secretary OCC informed committee that as per the MoU signed between Earth System Science Organisation-India Metrological Dept. (ESSO-IMD), Ministry of Earth Sciences and Power System Operation Corporation Ltd.(POSOCO), Weather Website of Western Region has been made operational w.e.f 01.06.17. The Link is http://amssdelhi.gov.in/WRLDC/MAIN/MAIN.html The objective of MoU was to use the weather information provided by ESSO-IMD by Power System Operators across India for better management of Indian Power System and for the purpose of analysis. The data available is useful for both real time load management (radar imagery) as well day ahead and term ahead load/Generation planning (through meteograms). Representative from WRLDC informed that the compiled meteorological data/information is available at the above site, which can be very useful to know the RE generation pattern & also useful for the purpose of load forecasting in the State. The matter was discussed in the meeting. ITEM NO. 7: BLACK-START MOCK DRILL OF HYDEL POWER STATIONS : Black Start mock drill of Hydel stations of MPPGCL:- During 2017-18 the black start mock drill successfully carried out at Bargi and Pench Hydel power station on dtd 23.05.2017 and 06.06.2017 respectively. The Black Start Mock drill exercise at Gandhi Sagar Power station was also carried out on dtd 30.05.2017 but synchronization of islanded system with national grid was not successfully done due to problem in bus coupler breaker at Gandhsagar Power Station. MPPGCL may apprise the same in the meeting. The black start mock drill exercise of other power stations shall be planned in the month of September 2017 and October 2017. The date of the same shall be finalized by SLDC and intimated to all the concern in due course of time. Member Secretary OCC stated that the it is proposed to conduct the Black Start Mock Drill at remaining HPS during the month of September-2017 after monsoon and SLDC will intimate the Proposed dates to concerned entities.

    ITEM NO. 8: AVAILABILITY BASED TARIFF (ABT) RELATED ISSUES: 8.1 Status of AMR system installed at SLDC:

    SLDC representative informed the Committee about the status of data received through AMR system

    in the month of June 2017. He informed that the complete data of 574 meters was received through AMR

  • system and data of 50 Nos meters (Monthly- 37 & Partial – 13) was not received through AMR system. He also informed that status of data received through AMR system is invariably sent to all concerned offices including SE(T&C) offices through email for furnishing the missing data alongwith monthly JMR data latest by 4th of every month. Further following points are discussed and resolved as under:-

    1. SLDC representative requested the CE(T&C) office to take up the matter with M/s Secure Meters Ltd for

    resolving the issues of the 37 Nos meters not read during the month of June 2017. Details are shown in

    enclosed Annexure-8.1.i CE(T&C) office have have assured to take up the matter with M/s Secure Meters

    Ltd. for resolving the issues related with 37 Nos. meters not read during the month of June’2017.

    2. SLDC representative informed that Integration of ABT meters installed at the interface points of newly

    commissioned substation / Xmers / HT consumers / OACs – 40 Nos as Annexure-8.1.ii is pending. He

    also informed that SLDC vide email dated 06.07.2017 has forwarded the list of interface points to

    CE(T&C) office for furnishing the details of meters, modem and SIMs for integrating the ABT meters with

    AMR system of SLDC. He requested the (T&C) office to arrange to furnish the same on priority basis so

    that integration of the ABT meters with AMR system could be done by SLDC. CE (T&C) office have

    assured to furnish the details shortly.

    8.2 AMR facility for the ABT meters installed at MPPGCL :

    SLDC representative informed that MPPGCL has provided AMR facility on 107 Nos ABT meters installed at the interface points and all the meters were successfully integrated with AMR server. He also informed that ABT meter data of 50 Nos meters were not received through AMR system in the month of June 2017, the status of data received through AMR system was also emailed to GCC, MPPGCL on 06th July 2017. He requested MPPGCL to take up the matter with site officials and M/s Secure Meters Ltd. to resolve the problems related with non readability of meters integrated successfully.

    SLDC representative also requested to MPPGCL to instruct the Gandhi Sagar HPS & Silpara HPS

    officials for furnishing JMR data of the ABT meters integrated with AMR system. MPPGCL have assured to take up the matter with Gandhi Sagar and Silpara HPS.

    Further, SLDC representative also requested MPPGCL to intimate the plan for integrating the ABT

    meters installed at SSTPS. MPPGCL representative informed that secure meters with modem and SIM has been installed and integration with AMR system will be done shorthly.. 8.3 Non receipt of injection data (JMR) timely of Wind & Solar Power Project for issuance of monthly State Energy Account :

    SLDC representative informed that SE(O&M), Dewas, Agar, Sehore and Ratlam are not furnishing the wind & solar data timely i.e. by 3rd or 4th of every month for issuanace of monthly State Energy Account. He also informed that these SE(O&M) are furnishing the data on 6th (A.N) of every month after repeated pursuance, however, SE(O&M) Dewas is not furnishing the complete data by 7th of every month.

  • SLDC representative further informed that concerned SE(O&M)’s do not furnish the monthly injection data of following newly commissioned Wind & Solar Power Project connected at 33KV level, however, SLDC is incorporating the injection data recorded in ABT meter in SEA, but, verification of data could not be done.

    i) 15MW Dhar Renewable Pvt. Ltd. connected connected at 33KV Dashera Maidan substation. –

    SE(O&M) Dhar. ii) 15MW Tripupati Dhar Renewable connected at 33KV Jaitpura substation. SE(O&M) Dhar. iii) 30MW Wind Power Project of M/s Sudheer Project Pvt. Ltd. connected at 132KV Maxi Substation. –

    SE(O&M) Ujjain. iv) 30MW Wind Power Project of M/s Sudheer Project Pvt. Ltd. connected at 132KV Bercha Substation.

    – SE(O&M) Shajapur v) 6.3 MW Wind Power Project of M/s Suzlon Gujrat Wind Park connected at 220KV Badod. SE(O&M)

    Agar. vi) 30MW Wind Power Project of M/s Kshema Power & Infra connected at 132KV Ghosla substation.

    SE(O&M) Ujjain. vii) 30MW Wind Power Project of M/s Kshema Power & Infra connected at 132KV Behrugarh. SE(O&M)

    Ujjain. viii) 15MW Solar Power Project of M/s Simcom Pvt. Ltd. (Simcom(1MW), Eastman(4MW) & Made

    Easy(10MW) connected at 220KV Ganjbasoda. –SE(O&M) Vidisha ix) 29.4MW Wind Power Project of M/s Suzlon Gujrat Wind Park Ltd. connected at 132KV Khachrod

    substation. –SE(O&M) Ujjain.

    SLDC representative requested DDC, Indore to take up the matter with CE(Comml), MPPKVVCL for

    issauance of directives to concerned SE(O&M)’s to furnish the wind & solar generation data by 3rd or 4th of every month including the above mentioned wind & solar projects. Chairman OCC advise DCC to take responsibility to coordinate with Discoms officials on monthly basis to ensure timely receipt of wind and solar energy data to SLDC for issuance of State Energy Account.

    Further, SLDC representative informed that JMR injection data of the following wind & solar generators

    connected at 132KV level and above is not furnished by the concerned SE(O&M)’s or EE(T), MPPTCL. SLDC consider the data received through AMR or through MRI by site official in monthy SEA, but verification of data could not be done.

    i) 42MW Wind Power Project of M/s Suzlon Gujrat Wind Park Ltd. connected at 220KV Badnagar substation

    through 132KV Ckt.

    ii) 21MW Wind Power Project of M/s Sarjan Realities Ltd. connected at 220KV Badnagar substation through

    132KV Ckt.

    iii) 200MW Wind Power Project of M/s Innox Wind Infra Structure Services (Lahori) conncetd at 220KV

    Shajapur through 220KV Ckt.

    iv) 43MW Solar Power Project of M/s Rajkot Gujrat Pvt. Ltd. connected at 220KV Badod through 132KV Ckt.

    v) 40MW Solar Power Project of M/s Malwa Solar Power Projects (IL&FS) connected at 220KV Badod

    through 132KV Ckt.

    vi) 11.5MW MSW Plant of M/s Essel Power Ltd., Marhotal, Jabalpur connected at 132KV Marhotal substation

    through 132KV Ckt.

  • The Committee has discussed the matter and requested CE(T&C) office to issue necessary directives to field offices for furnishing the JMR data of the above RE Projects. Further, Chairman OCC advised the Discoms officials to furnish the JMR data of RE projects connected at 33KV level and T&C officials for furnishing JMR data of RE projects connected at 132KV level and above. ITEM NO 9: SCADA/EMS RELATED ISSUES: 9.1 ARRANGENEMENT OF TELEMETRY OF IMPORTANT 220KV SUB STATIONS & 132KV S/S HAVING INJECTION FROM RENEWABLES/CAPTIVE POWER PLANTS OR HAVING INTERDISCOM FEEDERS & HAVING TRACTION FEEDERS-

    SLDC informed that a list of 50 S/s were identified for commissioning of telemetry. However, telemetry of Seventeen RTUs (132KV Biora,132KV Arniakala,132KV Kannod, 132KV Poliakala, 132KV Jeerapur ,132KV S/s Tarana, 132 KV Bankhedi S/s, 132 KV Khapaswami S/s, 132 KV Chanera S/s, 132KV Banmore S/s, 132KV Morena S/s, 132KV Datia, 132KV Mungaoli S/s, 132KV Shujalpur S/s, 132KV Meghnagar S/s, 132 KV Semri Harchan S/s & 132 KV Amla S/s) is still pending for integration with SLDC SCADA system.

    SLDC, further informed that most of the RTUs commissioned recently is not working properly and functioning intermittently. The telemetry of 220 KV Rewa, 220 KV Morena, 220 KV Gwalior II, 400 KV Satpura Extension, 400 KV JP Bina TPS, 220 KV Anuppur, 220 KV Dewas, 220 KV Indore SZ, 220 KV Barwaha, 132 KV Jaora, 132 KV Chapda, 132KV Khilchipur, 132 KV Betul, 132 KV Chhindwara, 132 KV Shankargrah, 132 KV Kukshi, 132Kv Umreth is commissioned but functioning intermittently.

    MPPTCL representative assured to look into it and arrange commissioning of telemetry of balance RTUs as well as arrangement for round the clock smooth functioning of these newly commissioned RTUs.

    9.2 UPGRADATION OF EXISTING RTUS & DISCREPANCY IN TELEMETRERED VALUES RECEIVED FROM DIFFERENT EHV S/S & POWER STATIONS The present status of telemetry discrepancy including upgradation requirement is discussed in detail. The list of following important locations where RTU upgradation is required to accommodate renewable feeders/other feeders/transformers was discussed in detail:-

    Sl No.

    Name of Substation whose RTU is required to

    be upgraded Name of feeders/transformers required to be

    included in telemetry

    01

    220 KV Tons

    Telemetered values of following feeders is wrong:- 1. 220 KV Tons-Sirmour 2. 220 KV Tons-Rewa 3. 220 KV Tons-Satna 4. 220 KV Tons-Kotar 5. 220 KV Tons-Satna CB status 6. 220 KV Bus Coupler CB status

    Above discrepancy is pending since more then year. In Last OCCM it was ensured by MPPGCL that the

  • same shall be rectified within a week but no action.

    02 400 KV ISP Telemetry of all generators is non-current when the generators are taken out of service.

    03 400 KV Chhegaon Breaker status of 400 KV Bus Reactor, 400 KV Bus coupler, 220 KV Bus Coupler, 220 KV breaker of 220/132 KV Xmer III. SOE to be verified

    04 400 KV Birsingpur TPS 400 KV Bus Coupler CB status, Station Xmer 3 & 4 CB status,400/220 KV Xmer CB status, 220/33 KV Xmer values, 220 KV Bus-II value, 220 KV Bus Coupler CB status

    05 220KV Birsingpur S/s

    The telemetry of 220KV IC-1 & 4 feeder is not available since last eight months. The Value of 220/132KV TRF and 132KV Umariya feeder is wrong since long time and need to be rectified.

    06 220 KV Rewa S/s Telemetry of 132 KV Rewa-Rewa Interconnector II, 132 KV Mangawan II, 132 KV JP Cement is not available. CB status of 132 KV Rampur Naikin, 220/132 KV Xmer II (132 KV side) is wrong.

    07 Pench HPS Voltage & Frequency of 132 KV Bus-II not available. It is not available since long time.

    08 220 KV Itarsi Telemetered value of 220 KV Pipariya-II feeder & 220 KV Bus II Voltage, frequency is wrong.

    10 220 KV Maihar Telemetered value of 220 KV Satna-PG, 220 KV Bus Voltage & Frequency, 132/33 KV 40 MVA Xmer & 132/33 KV 20 MVA Xmer is wrong.

    11 220 KV Bhopal Telemetered values of 132 KV Bagroda, 132 KV Bhel, 132 KV STDS, 132 KV Amrawat Khurd is not available, Values of 220 KV Bus-II frequency, 132 KV Bus-I & II frequency, 220 KV Bus coupler CB status.

    12

    132 KV Jaora S/s

    33 KV Choksi wind 1,2 is not available

    13 220KV Anuppur S/s 132KV Shahdol,132KV Kotma 2, 132KV TRF 2 telemetry not available.

    14 132KV Kotma S/s 132KV Anuppur feeder telemetry not available 15 220KV Pandurna S/s 220KV Pandurna-Sarni telemetry is not available &

    the telemetered value of 132/33 KV 20 MVA Xmer II is wrong.

    16 220KV Ratlam Telemetry of 132/33KV 40 MVA trf-3 telemetry not available

    17

    220Kv Indore SZ

    Telemetry of 132 KV CAT II feeder is not available.

    18 220 KV Narsingpur Telemetered value of 220 KV Bus Voltage is wrong. 19 220 KV Sukha Bus Tie CB, Bus Coupler CB, 220 KV Panagar I CB

    status. 20 220 KV Sirmour Bus Coupler CB, 160 MVA Xmer CB status. 21 220 KV Seoni Telemetred value of 220 KV Seoni-Seoni (PG) ckt I is

    wrong since two months. CB status of 160 MVA Xmer II (132 KV side).

    22 220 KV Sidhi 220 KV Bus-II Voltage & Frequency value is not available.

    23 220 KV Satna 220 KV Bus II Voltage & Frequency, 132 KV Bus-II Voltage & frequency, 220 KV & 132 KV Bus-Coupler

  • CB status. 23 132 KV Seoni Bus Coupler CB status

    SLDC informed that lot of inconvenience in grid management is observed and hence upgradation of above mentioned RTU is to be taken up on top most priority for which MPPTCL agreed.

    9.3 PRESENT STATUS OF PROCUREMENT OF RTUs BY MPPGCL:- The matter of procurement of RTU for Rajghat HPS and Bansgar III HPS was discussed in detail. The Telemetry of Rajghat HPS is out since last three years. In response MPPGCL informed that the order has already been placed & RTU is also delivered at site. Commissioning shall be taken up after receipt of cable.

    9.4 Extension of RGMO/FGMO signal to SLDC/WRLDC :-

    SLDC informed that as per IEGC 5.2(f), RGMO/FGMO is mandatory for all thermal units above 200 MW and hydro units above 10 MW. Further considering the high penetration of renewable to grid and also the Government target to achieve 175 GW, it is essential to monitor operation of RGMO/FGMO at SLDC/RLDC for ensuring grid security and compliance of regulation. Subsequently SLDC vide letter no. 07-05/RPC-27/3739 dated 18-01-2017, letter No. SE/LD:E&T/693 dated 23-01-2017, letter No. SE/LD:E&T/34 dated 13-04-2017, letter No. SE/LD:E&T/143 dtd.26-05-17 requested MPPGCL/NHDC for integration of telemetry of RGMO/FGMO in RTU installed at power station and forward the object address configured in RTU so that same may also be configured in SLDC SCADA and RGMO/FGMO status may be displayed in SCADA system.

    Integration of telemetry of RGMO/FGMO has been completed in ISP, ATPS, SGTPS

    (Unit no.5) , Tons HPS & JP Bina TPS. & RGMO/FGMO signal of following generating units is still to be extended to SLDC SCADA system :-

    S.No. Name of Generating Station Unit.No.

    1 Satpura TPS 10,11 2 SGTPS 1,2,3,4 3 SSTPS 1,2 4 JP BINA TPS 1,2 5 BARGI HPS 1,2 6 PENCH HPS 1,2

    SLDC requested to expedite the extention of telemetry of RGMO/FGMO of above generators for which MPPGCL engineers agreed. 9.5 COMMISSIONING OF COMMUNICATION CHANNELS FOR DUAL REPORTING OF RTUS AS PER

    BACKUP SLDC REQUIREMENT:-

    SLDC informed that the commissioning of SCADA/EMS system at SLDC Jabalpur and backup SLDC Bhopal is already completed and the additional communication channel is required to be extended to respective control Centre’s for functioning of RTUs with new SCADA/EMS system. SLDC requested MPPTCL & MPPGCL to provide RTU wise progress.

  • SLDC further informed that strengthening of existing wideband communication node is also required to be arranged so as to ensure reliable backbone communication network. The requirement of new wideband nodes and OPGW has already been submitted to MPPTCL and MPPGCL & it was also requested to provide the current status of the same. It was informed by MPPGCL that work shall be taken up shortly. 9.6 (i) Arrangement of Air Conditioners for wideband locations :-

    The matter regarding arrangement of air conditioners for wideband locations was discussed

    in detail. SLDC informed that air conditioners at wideband locations namely 220 KV Jabalpur, 400 KV Bina, 220 KV Satna, 220 KV Itarsi, 220 KV Damoh & 400 KV Nagda are either faulty or not available. SLDC requested MPPTCL to intimate the schedule of arranging air conditioners at these locations. The MPPTCL informed that the order for procurement of air conditioner has already been placed and installation shall be completed shortly.

    (ii) Location of Wide Band equipments at Substations/Generating Stations:- Recently wideband equipments were delivered at EHV substations under Master Telecom Phase II. The installation team from M/s Valiant Communications Limited visited the site for installation & found that the provided location for PDH equipments is at a distance of more than 20 meters from the RTU locations at 220 KV S/s Neemuch, 220 KV S/s Shujalpur, 220 KV S/s Indore SZ, 220 KV S/s Pithampur, 220 KV S/s Ratlam & 220 KV Rajgarh. Further it was informed that as per RS 232 platform, for traveling of signal the length of cable should be within 20 meters & after 20 meter distance converters are required to propagate the signal. MPPTCL is thus requested to ensure that distance between PDH equipment & RTU should be within 20 meters, else MPPTCL should arrange for converters. MPPTCL representative informed that they will ensure the same. 9.7 MAINTENANCE OF OPGW

    SLDC informed that the 8 No. fibers had been installed on EHV line section between 220 KV Jabalpur to 220 KV Katni S/s under ULDC project in 2003. Presently three number fibres out of eight number of fibers is not serviceable/ ready to use due to problem in joint box placed at 20 KM distance from 220 KV S/s Jabalpur towards Katni. The SLDC vide letter No.SE/LD:E&T/707/826 dt. 06/03/2017 already requested, SE (EHT:Maint), Jabalpur to arrange for replacement of the Joint box and ensure that all 8 fibers between 220 KV Jabalpur S/s to 220 KV Katni S/s being healthy and ready to use. However, replacement of joint box is still pending. MPPTCL representative informed that the arrangement for replacement of joint box shall be done shortly. 9.8 NON AVAILABLITY OF SOE AT SLDC SCADA SYSTEM

    SLDC informed that the problem in receipt of SOE from field is observed. Further, WRLDC vide

    letters dtd. 03.05.17 & 15.05.17 intimated that SOE of grid disturbance at 220 KV S/s Mahalgaon & 400 KV S/s Indore is not received in Back-up LDC SCADA/Sub-LDC SCADA system respectively. SLDC is carrying out data validation of various substations periodically & it is observed that SOE from various substations like 220 KV S/s Damoh, 220 KV S/s Anuppur, 220 KV S/s Malanpur, 220 KV S/s Tikamgarh, 220 KV S/s Mahalgaon, 220 KV S/s Hoshangabad, 220 KV S/s Bhopal, 220 KV Shujalpur, 220 KV S/s Ujjain, 220 KV S/s Badod was not received at SLDC SCADA system. Subsequently SLDC vide letter SE/LD:E&T/200 dtd. 14-06-17 requested MPPTCL to arrange simulation testing for SOE of all RTUs.

    Receiving of SOE is very essential for analysis & investigation of major tripping in the grid. SLDC

    requested MPPTCL is thus requested to arrange simulation testing for SOE of all RTU’s in

  • coordination with SLDC SCADA/Back Up SLDC/Sub LDC SCADA system & also issue necessary instructions to sort out the issues for ensuring proper receipt of SOE in SLDC SCADA system for which MPPTCL and MPPGC:L agreed 9.9 INTERMITTENT TELEMETRY DUE TO NOISE IN COMMUNICATION CHANNEL :-

    SLDC informed that the telemetry of Bargi HPS, Pench HPS, 132 KV S/s Seoni, 220 KV

    Seoni, 132 KV Chhindwara, 220 KV Chhindwara, 220 KV Pandhurna, 132 KV Balaghat, 220 KV Dewas, 220 KV Indore SZ, 220 KV Barwaha, 132 KV Jaora, 132 KV Chapda,220 KV S/s Ujjain, 220 KV S/s Shajapur is intermittent due to heavy noise in the communication channel. Further these noisy channels interrupt the functioning of FEP at the SLDC/Back Up LDC/Sub LDC which leads to inconvenience in system operation & control.

    MPPTCL is thus requested to arrange for alignment of PLCC Channel & identify/replace the outdoor equipments which injects the noise in the channel/system for which MPPTCL representative agreed.

    9.10 LONG OUTAGE OF RTUS, PROBLEM IN DATA AND VOICE CHANNELS The long outage of telemetry of following S/s is discussed in detail:-

    Sl No. Name of Sub Station Out from /Remark

    01 Rajghat HPS Out from last three years 02

    132KV Morwa S/s

    More then one and half Year

    03 132KV Waidhan S/s Out from one year. Channel problem between Anuppur to Jabalpur

    04 132KV Beohari S/s Out from more than one year

    05 132 KV Deolond S/s Out due to PLCC channel

    06 220 KV Gwalior II & 220 KV Morena

    Telemetry of either of the two sub stations i.e. 220 KV Morena or 220 KV Gwl-2 is functioning.

    MPPTCL, MPPGCL officials confirmed to look into the matter to sort out/ rectification of above RTU/data channel. MPPGCL and MPPTCL informed that the action regarding restoration of telemetry of above sub stations /power stations shall be taken up on top most priority. 9.11 Telemetry of railway TSS Sub Stations:- SLDC informed that the telemetry of railway TSS is to be commissioned by June 2017. However, the desired progress in the matter is not observed. The railway representative informed that the tender for the telemetry arrangement is yet to be floated by railway and railway is planning to float tender for providing telemetry of 20 railway TSS and not for all 38 existing TSS. SLDC informed that in view of the existing progress status, the arrangement of telemetry by June 2017 is not yet possible and railway is required to expedite the matter.

  • Further, MPPTCL representative informed that in addition to existing 38 No. Railway TSS in MP, planning for establishment of around 25 new TSS is also under progress. Thus railway is required to plan for arranging telemetry of all 38 existing TSS as well as for 25 upcoming TSS. Accordingly, SLDC requested railway to expedite the matter and arrange telemetry of all TSS sub stations. Railway officers informed that they will takeup the matter with there management. Minutes of Supplementary Points SA-I Tripping of Indore –ISP feeder at ISP on 09.07.2017 :- Member Secretary OCC informed committee that 400 kV Indore-ISP ckt. II tripped at 19:55 Hrs on dtd. 09/07/17 from ISP end only on the

    indication DT received from other end. 400 kV S/s Indore of MPPTCL has intimated that DT send was not

    recorded at their end. The line was charged by ISP at 23:18 Hrs of 09.07.2017 with delay of 3 Hrs 23 Min.

    Despite repeated pursuance from SLDC, line could not be charged timely and ISP did not intimate SLDC

    regarding details of fault at their end. Outage of this critical element of the transmission network for such a long

    time may affect the grid security. The ISP is requested to submit detailed report regarding false DT received

    and delayed synchronisation of the ckt for discussion in the meeting.

    Representative from ISP informed the committee that the above tripping occurred due to PT fuse fail

    and ensured that in future the reason for tripping & readiness for charging of element will be provided on time.

    SA-II Frequent tripping of 132 KV Datia - Railway Traction Ckt – II on overload :- Member

    Secretary OCC informed committee that it is to intimate that 132 KV Railway Traction – II emanating from 132 KV S/s Datia of MPPTCL s/s is tripping frequently on overload in past few days. Details of tripping of feeder are given below:-

    S. No. Feeder/X’mer Date

    Tripping Time

    Charging Time Indication & Remark

    1. 132 KV Datia Railway Traction - II 05.07.2017 01:01 01:05 O/C.

    2. 132 KV Datia Railway Traction - II 07.07.2017 22:03 23:07 O/C, R&B-Phase

    3. 132 KV Datia Railway Traction - II 09.07.2017 13:48 13:53 O/C, R&B-Phase, Master Trip.

    4. 132 KV Datia Railway Traction - II 09.07.2017 13:58 14:09 O/C, R&B-Phase, Master Trip.

    5. 132 KV Datia Railway Traction - II 10.07.2017 03:49 03:53 O/C, R&B-Phase, Master Trip.

    The Current Transformer (CT) and other equipments installed at 132 KV sub-station Datia on 132 KV

    Railway Traction feeder I & II, are of the ratings as per earlier Contract Demand of Indian Railway with Discom.

    Now the Indian Railways has increased drawal from 132 KV sub-station Datia by putting some additional load

    on this TSS. Continuous excess drawal of power by Railways i.e. beyond the permissible capacity of the

    equipments installed at Datia on railway bay may cause failure of equipments at MPPTCL end.

    In view of the above it is requested that additional load connected to 132 KV Datia TSS in the recent

    past may be taken off immediately and Railway should maintain their drawal at this TSS point below 24 MVA

    for safeguard of the equipments installed at MPPTCL end.

  • Member Secretary OCC stated that the railway shall reduce the loading of the circuit if it is possible,

    otherwise if its not possible to reduce the load, the matter shall be takeup with T&C for capacity augmentation

    of equipments required to avoid over loading at this feeder. Accordingly T&C shall prepare a proposal as per

    the loading requirement and intimated to Railway..

    Representative from Railway informed the committee that railway is ready to augment the equipment

    as per the proposal submitted by MPPTCL.

    SA-III MP Overdrwal on dtd. 08.07.2017 : Member Secretary OCC informed committee that on 08th and 09th July there was heavy MP overdrawal from the grid. WRLDC was also issuing warning notice to SLDC for

    restriction of drawal within schedule. The shift incharge SLDC requested the shift incharge MPPMCL control

    room thorugh telephonically as well through email. However no action has been taken by MPPMCL.

    Overdrawal by MP from the grid on 08.07.2017 on account of the following factors –

    • Intermediate dry spell in the region leading to rise in temperature and consequent demand

    • Reduction in generation from wind RES

    • Restriction on generation from hydro stations of Indirasagar, Omkareshwar & Sardar Sarovar

    • Absence of adequate thermal capacity on bar.

    Looking to the constant schedule of ISP & OSP and other factors mentioned above, the power from other

    sources would have been arranged by MPPMCL on day-ahead basis which have not been done. WRLDC has

    opened 4 lines of MP due to continuously overdrawal of MP from grid which had deteriorated grid security. The

    MPPMCL is required to always maintain the drawal within safe and secure limits and cooperate in system

    operation in order to avoid jeopardise the grid.

    The Matter was discussed in the meeting. Member Secretary informed the committee that the overdrwal of MP

    on dtd 08.07.2017, WRLDC has taken seriously in the OCC meeting of WR, He further informed that the

    overdrawal was also observed on last few days but on dtd 08.07.2017 there was huge overdrwal by MP and

    WRLDC has opened 4 lines of MP and further tripping of other line may lead to grid disturbance. He also

    informed that due to looking of demand which are continuously increasing day by day, MPPMCL should plan

    to take RSD units on bar for meeting the increased demand.

    SA-IV Maintaining reserves to handle grid contingencies :- Member Secretary OCC informed committee that as per the CERC suo-motu orders, secondary reserves of 800 MW has to be maintained at the

    regional level while the States have to maintain tertiary reserve of 330 MW in Maharashtra, 330 MW in Gujarat;

    300 MW in Madhya Pradesh; 250 MW in Chhattisgarh. WRLDC has taken this point for discussion in

    forthcoming OCC of WRPC. It is mentioned in WRPC OCC Agenda that the OCC members may like to

    deliberate on the following issues: 1. Ensuring real-time telemetry from RES in the State 2. Forecast of RES

    and demand by the SLDCs 3. Keeping thermal units on bar to maintain spinning reserve in the grid. MPPMCL

    and RE generators are requested for necessary action in this regard.

  • The Matter was discussed in the meeting. Member Secretary requested MPPMCL to take necessary

    action to keep the reserve as mandated by CERC in its order.

    ITEM No 10 : DATE AND VENUE OF NEXT OCC MEETING :

    It is proposed to hold 59th Operation and Coordination Committee meeting of MP on 29.08.2017. The host and venue of the same shall be intimated seperately.

    ***********

  • Annexure-2.1

    S. No. Particulars

    1

    1.1 Maximum Frequency 50.14 HzBetween 12.00 hrs & 13.00 Hrs on 05.04.17

    50.18 HzBetween 17.00 hrs & 18.00 Hrs on 21.05.17

    1.2 Minimum Frequency 49.83 HzBetween 14.00 hrs & 15.00 Hrs on 27.04.17

    49.78 HzBetween 22.00 hrs & 23.00 Hrs on 02.05.17

    1.3 Average Frequency 49.99 Hz 49.99 Hz

    2

    2.1 Maximum Frequency 50.26 HzAT 18.02.10 HRS ON 30.04.17

    50.26 Hz AT 18.07 HRS ON 21.05.17

    2.2 Minimum Frequency 49.66 Hz AT 19.15 HRS ON 18.04.17 49.64 HzAT 15.11. HRS ON 11.05.17

    3 Percentage of time when frequency was :-

    %age of time when frequency was Apr-17 May-17

    3.1 Below 48.5 Hz 0.00 0

    3.2 Between 48.50 Hz and 48.8 Hz 0.00 0

    3.3 Between 48.80 Hz and 49.2 Hz 0.00 0

    3.4 Between 49.20 Hz and 49.5 Hz 0.00 0

    3.5 Between 49.50 Hz and 49.7 Hz 0.00 0

    3.6 Between 49.70 Hz and 49.9 Hz 9.05 9.09

    3.7 Between 49.9 Hz and 50.05 Hz 74.49 71.45

    3.8 Between 50.05 Hz AND 51.5 Hz 16.45 19.46

    3.9 Above 51.5 Hz 0.00 0.00

    4 No. of times frquency touched 48.80 Hz 0 0

    4.1 No. of times frquency touched 48.60 Hz 0 0

    4.2 No. of times frquency touched 51.0 Hz 0 0

    FREQUENCY PARTICULARS

    INTEGRATED OVER AN-HOUR

    INSTANTANEOUS FREQUENCY

    Apr-17 May-17

  • I S.

    No. NAME OF THE TRANSMISSION LINE / (FINANCED BY)

    TYPE OF CIR CUITS

    ROUTE LENGTH

    CIRCUIT KMS.

    DATE OF COMPL- ETION

    DATE OF COMMI-SSIONING

    A. 400 KV TRANSMISSION LINES

    NIL 0 0

    B. 220 KV TRANSMISSION LINES

    1 NIL 0 0.00

    C. 132 KV TRANSMISSION LINES

    1 NIL 0 0.00

    II.

    S. No.

    NAME OF SUBSTATION / (DISTRICT) / (FINANCED BY)

    VOLTAGE RATIO

    (KV)

    No.OF X-mer & Cap.(MVA)

    EFFECTIVE CAPACITY

    MVA

    DATE OF COMPL-ETION

    DATE OF COMMI-

    SSIONING

    A. 400 KV SUBSTATIONS

    1 Nil 0.00

    B. 220 KV SUBSTATIONS

    a. 220 KV NEW SUBSTATIONS

    1 Nil 0

    b. 220KV ADDITIONAL TRANSFORMERS

    1 Nil 0

    C. 132 KV SUBSTATIONS

    a. 132KV NEW SUBSTATIONS

    1 Nil 0

    ANNEXURE-2.2.5.iM.P POWER TRANSMISSION COMPANY LIMITED

    TRANSMISSION WORKS COMPLETED DURING 2017-18 (UP TO 31.05.2017)

    EHV TRANSMISSION LINES

    EHV SUB - STATIONS

  • Page 1 of 5

    S. No.

    NAME OF THE TRANSMISSION LINECKT.KMS.

    PROGRESS IN %

    Proposed Target for completion

    A. 400 KV TRANSMISSION LINES

    1400kV DCDS (Quad moose) line from Shri Singaji TPS (stage-II) - Pithampur (2x69.968)

    140 3% 2018-19

    2 400kV DCDS (Quad moose) line from Pithampur - Badnawar (2x70) 140 1% 2018-19

    3LILO of both ckt. Of 400kV Nagda to Rajgarh line at 400kV S/s Badnawar (4x8.163)

    33 1% 2018-19

    B. 220 KV TRANSMISSION LINES

    1 2nd Ckt of 220kv Satna - Chhatarpur line (152) 160 8% 2017-18

    2LILO of 2nd circuit of Damoh (MPPTCL) - Sagar 220KV line at Damoh (PGCIL) 400 kV Sub-station Damoh (4x0.592)

    2.368 99% 2017-18

    3LILO of one circuit of Satna (MPPTCL) - Chhatarpur 220KV line at Satna (PGCIL) 400 kV Sub-station (2x1.726)

    3.452 37% 2018-19

    4LILO of one Ckt of 220kv DCDS Ashta - Dewas line at 220kv S/S Chapda (DCDS) (2x32.782)

    66 3%

    5 220Kv DCDS line from Pithampur-Depalpur line (2X31) 62 37%

    6220Kv FCFS line for LILO of both Ckt. Of Badnagar -Ratlam D/C line at 400Kv S/s Badnawar (2x1+4x8)

    34 4% 2018-19

    7 220Kv DCDS Julwaniya- Kukshi (2X58) 116 16%

    8 220Kv DCSS Shujalpur- Narsinghgarh line (1X43.6) 44 15%

    9LILO of both ckt of Badod-Kota/Modak 220kV line at 220Kv S/s Suwasara (4x4.382)

    17 6% 2017-18

    10LILO of 2nd ckt Nagda - Neemuch 220kV line at 220Kv S/s Daloda (2x12.2)

    24.4 9% 2017-18

    11220Kv DCDS line for inter-connection of 400Kv S/s Betul with 220Kv S/s Betul (2x1.88)

    3.76 60% 2017-18

    12 LILO of 220kV Sarni - Pandhurna at 220kV S/s Betul (2x38.864) 77.728 5% 2018-19

    13220Kv DCDS Morena(400KV S/s CWRTL Adani Group) - Sabalgarh DCDS line & lilo of Morena 400KV S/s (Adani) to Sabalgarh at Morena 220Kv s/s (2X92 + 2x0.5)

    185 16% 2017-18

    14LILO of one circuit of Malanpur - Mehgaon at 400Kv S/s CWRTL (Adani) (2x6.031)

    12.062 13% 2017-18

    15LILO of 2nd ckt. Of Birsinghpur - Amarkantak 220kV line at Shahdol 220 KV S/s. (2X5.6)

    11.2 13% 2017-18

    16LILO of 2nd ckt. Of Bansagar - Satna 220Kv line at Kotar 220 KV S/s. (2X5.693)

    11.386 52% 2017-18

    17220kV DCDS line for LILO of one ckt of 220kV DCDS Indore - Indore-II(Jaitpura) line at Mangliya (2x0.3)

    2 20% 2017-18

    18LILO of 2nd ckt. Of Itarsi(MPPTCL) - Hoshangabad 220Kv line at Itarsi(PGCIL) 400 KV S/s. (2X0.060)

    0.12 99%

    19220Kv DCDS line from 220kV Pooling S/s RUMS at Goojarkhedi, Suwasara (For interconnection of Solar PV Plant of RUMS) (2X43.426)

    86.852 18%

    20220kV DCDS Barsitadesh (220kV Pooling S/s) - 400kV Grid S/s PGCIL line (2X0.917)

    1.834 14%

    21220kV DCDS Ramnagar (220kV Pooling S/s) - 400kV Grid S/s PGCIL line (2X2.572)

    5.144 3%

    Annexure-2.2.5.iiEHV TRANSMISSION WORKS UNDER PROGRESS AS ON 31.05.2017

  • Page 2 of 5

    22220kV DCDS Badwar (220kV Pooling S/s) - 400kV Grid S/s PGCIL line) (2X0.917)

    4.33 2%

    C. 132 KV TRANSMISSION LINES

    1 132 kv DCDS Ujjain(220 kv) -Chandrawatiganj line (2x35.42) 70.84 98% 2017-182 132 kv DCSS Dewas-Barotha line (1x23) 23 60% 2018-193 132 kv DCSS Ghatabillod-Betama line (1x18) 18 29% 2017-184 132kv DCSS Gautampur -Depalpur line (1x19) 19 20% 2017-185 132kv Nagda(220kv)- Kachrod-Jaora DCSS line (1x64) 64 18% 2018-196 132kv Mugaliya Chaap - Sehore DCSS line (1x24) 24 30% 2018-197 2nd Ckt of 132 kv Badnagar - Gautampura line (1x23.24) 23.24 27% 2017-188 2nd Ckt of 132 kv Pithampur - Betama line (1x14) 14 77% 2017-18

    9132 kv DCSS line between 132Kv S/s Nasrullaganj & 220KV Itarsi s/s(1x53.209)

    53.209 42%

    10LILO of S/C ckt of 132 KV Seoni-Lakhnadon line at 220kv S/S Seoni (2x20)

    40 17% 2018-19

    11 132 kv DCSS Guna-Eshagarh line (1x72) 72 32%

    12LILO of one circuit of 132 kv Neemuch220 - Ratangarh DCDS line at 132 KV S/s Morwan (2x1)

    2 0%

    13 132 kv DCSS Line from 220Kv S/s Shivpuri-132Kv Bairad (1x32.859) 32.859 35% 2017-18

    14 132 kv DCSS from 220Kv S/s Datiya-132kv S/s Indergarh (1x27.1) 27.1 50% 2017-18

    15 132 kv DCSS line from 132Kv S/s Kymore-132Kv S/s Barhi (1x35) 35 83% 2017-18

    16 132 kv Sirmour - Katra DCDS line (2x37.67) 75.34 18%

    17132 kv DCSS line from220Kv S/s Chichli - 132Kv Karapgaon (1x31.059)

    31.059 96% 2017-18

    18 132 kv Sagar-Rahatgarh DCSS line (1x55) 55 87% 2017-18

    19LILO of Both circuit of 132 kv DCDS Gwalior(Mahalgaon) - Dabra/Karera line at 220 KV S/s Gwalior II) (2x2x7.87)

    55.09 36%

    20132Kv DCSS line from 220Kv S/s Rajgarh to 132Kv S/s Jhabua (1x67.749)

    67.749 74% 2017-18

    21132Kv DCDS line for extension of 132Kv line from Manliya(132) - Mangliya (220) (2x1)

    2 20% 2017-18

    22 132 kv DCSS Dewas-Agrod line (1x20.76) 20.76 28%

    23 132 kv DCSS Khurai- Khimlasa line (1x20.937) 20.937 20%

    24LILO of 132Kv Mungaoli Traction feeder at 132Kv S/s Mungaoli (4x7.8+2x0.7) Note: (4x7.8ckt.km line charged on 30.12.2015 by tapping )

    32.6 96%

    25 LILO of 132Kv Vidisha- Bairasiya line at salamatpurr (2x0.162) 0.324 46%

    26 132 kv DCDS Line Chichli - Udaypura (2x47) (On 220Kv Tower) 94 51%

    27 132 kv DCSS Panagar - Patan line (1x22.749) 22.749 7%28 132 kv DCSS Badnagar - Chhayan Line (1x31) 31 34%29 132 kv DCSS Dhar - Teesgaon line (1x15.35) 15.35 16%

    30LILO of 132 kv Ratlam - Meghnagar line at 132Kv S/s Petlawad (2x7.4)

    14.8 5%

    31 132 kv DCDS Beragarh - Intkhedi (2x8.7+4x1.5) 23.4 81%

    32 132 kv DCSS Udaipura - Silvani line (1x25.8) 25.8 38%

    33 132 kv DCSS Narsinghpur - Devnagar (1x23) 23 18%

    34 132 kv DCSS Karakbel - Belkheda (1x24.445) 24.445 11%

    35 132 kv DCDS Narsinghpur - Karakbel line (2x23) 46 15%

  • Page 3 of 5

    36LILO of 132KV Gwalior- Dabra/Karera line at Chinour (132KV DCSS Dabra- Chinour line) (2X13.68) & LILO of 2ND CIRCUIT OF 132KV Gwalior- pIChore at 132Kv S/s Dabra (2X0.108)

    27.36 31% 2017-18

    37 132KV DCSS Sabalgarh - Kelaras line (1x25) 25 51% 2017-1838 132kv DCSS Chhegaon -Singot line (1x58) 58 8% 2017-1839 132kv DCSS Chhanera -Khirkiya line (1x30.42) 30.42 48% 2017-18

    40 LILO of 132kv Nagda - Ratadiya line Unhel 132KV Sub-station (2x2) 4 20% 2017-18

    41LILO of one ckt of 132kv Neemuch - Mandsore line at Budha 132KV Sub-station (2x22.077)

    44.154 12%

    42LILO of both ckt of 132kv Gandhisagar - Suwasara/Garoth line at Bhanpura 220KV S/s (4x14)

    56 1% 2018-19

    43LILO of both ckt of 132kv Gandhisagar - Suwasara/Garoth line at Suwasara 220KV S/s (2x3)

    6 6%

    44 132kv DCSS Mugaliyachhap - Bilkishganj line (1x17.274) 17.274 6%45 132kv DCDS Rajgarh - Khujner/Sindaota line (2x26.499+ 4x1.457) 57 4%

    46 132kv DCSS Betul-Bisnoor/Masod line (1x35.245) 35 3%

    47 132kv DCDS line Guna-Bhonra (2x21.394) 21 1%

    48 132kv DCSS line Bhonra - Kapasi (1x22.534) 23 2% 2017-1849 2nd ckt. Stringing of 132kV Shivpuri - Kolaras line (35) 35 14% 2017-1850 132kv DCSS line from Kolaras - Mada line (1x18.366) 18.366 53% 2017-1851 132kv DCSS line Chhindwara-Saori line (1x31.60) 31.6 14% 2017-1852 132kv DCSS Damoh-Patera line (1x38) 38 2%

    53132kv Birsinghpur -Shahdol DCSS line (1x45) (Revised Estt. Sanc.no.0187dtd.05.09.2016)

    45 25% 2017-18

    54 132 KV DCSS Kukshi - Jobat line (1x33.74) 33.74 47% 2017-1855 132kV MACT (Bhopal) - Mugaliachhap line (2x30.368) 60.736 12% 2018-19

    56 132kV Julwaniya400 - Shahpura DCSS line (2nd ckt-28 + 1x46.866) 74.866 1% 2018-19

    57132Kv DCSS line from GWSTPP to upcoming Make up Water Pump House river Narmada (Line-I)(1x24.192)

    24.192 55%

    58132Kv DCSS line from GWSTPP to upcoming Make up Water Pump House river Narmada (Line-II)(1x24.152)

    24.152 16%

    59132Kv DCSS line from proposed 132Kv s/s Tamot to Sagar Yarn plant of M/s Sagar Manufacturer (P) Ltd.(1x3.1)

    3.1 36%

    60132Kv DCSS line from 220kV s/s Pithampur for supply of 5MVA to M/s SRF Ltd.(1x2.423)

    2.423 84%

    61132Kv DCSS 2 phase 2wire line from 132Kv s/s Bankhedi for PS to RTS Bankhedi (1x7.9)

    7.9 43%

    62132Kv DCSS 2 phase 2wire line from proposed 220Kv s/s Narsinghpur 5MVA PS to RTS Narsinghpur (1x7.253)

    7.253 12%

    63 132Kv DCSS line from 400Kv s/s Katni - RTS Patwara (1x19.417) 19.417 15%

    64132Kv DCSS 2 phase 2wire line from 220Kv s/s Maihar for PS to TSS Bhadanpur(1x13.1)

    13.1 47%

    65132Kv DCSS 2 phase 2wire line from 220Kv s/s KOtar for PS t