madera quarry project

201
MADERA QUARRY PROJECT DRAFT REVISED ENVIRONMENTAL IMPACT REPORT STATE CLEARINGHOUSE NO. 2003102128 VOLUME I: DRAFT REVISED EIR DECEMBER 2009 Lead CEQA Agency Madera County Planning Department Applicant/Operator Madera Quarry, Inc.

Upload: others

Post on 12-Jan-2022

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MADERA QUARRY PROJECT

 

 

M A D E R A Q U A R R Y P R O J E C T D R A F T R E V I S E D E N V I R O N M E N T A L I M P A C T R E P O R T S T A T E C L E A R I N G H O U S E N O . 2 0 0 3 1 0 2 1 2 8  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

V O L U M E I : D R A F T R E V I S E D E I R  

 

DECEMBER 2009  

 Lead CEQA Agency Madera County Planning Department  

 Applicant/Operator Madera Quarry, Inc.  

 

Page 2: MADERA QUARRY PROJECT

 

 

M A D E R A Q U A R R Y P R O J E C T D R A F T R E V I S E D E N V I R O N M E N T A L I M P A C T R E P O R T S T A T E C L E A R I N G H O U S E N O . 2 0 0 3 1 0 2 1 2 8  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

V O L U M E I : D R A F T R E V I S E D E I R  

 

DECEMBER 2009  

 Lead CEQA Agency Madera County Planning Department 2037 West Cleveland Avenue, Mail Stop G, Madera, California 93637  Applicant/Operator Madera Quarry, Inc. P.O. Box 994248, Redding, California 96099-4248 Preparer Resource Design Technology, Inc. 4990 Hillsdale Circle, Suite 400, El Dorado Hills, California 95762

Page 3: MADERA QUARRY PROJECT

TABLE OF CONTENTS VOLUME I: DRAFT REVISED ENVIRONMENTAL IMPACT REPORT SUMMARY........................................................................................................S-1 1.0 INTRODUCTION ................................................................................. 1.0-1

1.1 EIR Purpose, Use, and Scope ..................................................................... 1.0-1 1.1.1 Purpose and Use .....................................................................................................1.0-2 1.1.2 Nature and Background of Project ..................................................................1.0-2 1.1.3 CEQA and Litigation Process ..............................................................................1.0-3 1.1.4 Changes to the Project Subsequent to Prior EIR Resulting from

the Applicant’s Consultants’ Studies Done in Response to the Judicial Decisions....................................................................................................1.0-5

1.1.5 County Approach to DREIR .............................................................................. 1.0-10 1.1.6 Notice of Preparation ......................................................................................... 1.0-10 1.1.7 Public Scoping Meeting .................................................................................... 1.0-11 1.18 DREIR Scope........................................................................................................... 1.0-11 1.1.9 Effects Found Not to be Significant .............................................................. 1.0-12 1.1.10 Areas of Controversy .......................................................................................... 1.0-13 1.1.11 Disposition of Issues Raised and Remaining Areas of Controversy.. 1.0-18 1.1.12 Document Availability ....................................................................................... 1.0-18

1.2 DREIR Public Review ................................................................................1.0-19

RESOURCE DESIGN TECHNOLOGY, INC. i

Page 4: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Table of Contents

2.0 REVISIONS TO PROJECT DESCRIPTION IN RESPONSE TO JUDICIAL DECISIONS, ENTITLEMENTS, AND CONTRACTS SUBSEQUENT TO THE FEIR ............................................................... 2.0-1 2.1 Introduction................................................................................................ 2.0-1 2.2 Minor Changes to Project as Defined in DEIR .......................................... 2.0-2

2.2.1 Affected Acreage Recalculated .........................................................................2.0-2 2.2.2 Modifications Resulting from Hydrology, Groundwater,

and Surface Water Studies ..................................................................................2.0-2 2.2.3 Modified Phasing Plan ..........................................................................................2.0-5 2.2.4 Additional Traffic Contributions Resulting from 2006

Hearing Process ......................................................................................................2.0-5 2.3 Entitlements and Contracts Obtained Subsequent to the FEIR ............. 2.0-8

3.0 REVISIONS TO ENVIRONMENTAL SECTIONS

3.1 Revisions to Hydrology and Water Quality Section in Response to Judicial Decisions ....................................................................................... 3.1-1 3.9.1 Summary....................................................................................................................3.1-1 3.9.2 Introduction..............................................................................................................3.1-2 3.9.3 Existing Setting and During and Post-Mining Conditions ......................3.1-8

3.9.3.1 Surface Water Quantity......................................................................................3.1-8 3.9.3.2 Surface Water Quality ......................................................................................3.1-11 3.9.3.3 Groundwater Quantity....................................................................................3.1-11 3.9.3.4 Groundwater Quality........................................................................................3.1-20

3.9.4 Standards of Significance, Environmental Consequences, and Mitigation Measures .................................................................................. 3.1-21 3.9.4.1 Standards of Significance ..............................................................................3.1-21 3.9.4.2 Impacts and Mitigation Measures............................................................3.1-22

3.9.5 Cumulative Impacts and Mitigation Measures......................................... 3.1-29

3.2 Revisions to Noise and Vibration Section in Response to

Judicial Decisions ....................................................................................... 3.2-1 3.11.1 Introduction..............................................................................................................3.2-1 3.11.2 Noise and Vibration Fundamentals and Terminology .............................3.2-3

3.11.2.1 Background on Noise and Vibration..........................................................3.2-3 3.11.2.2 Effects of Noise on People ...............................................................................3.2-4

RESOURCE DESIGN TECHNOLOGY, INC. ii

Page 5: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Table of Contents

3.11.3 Affected Environment...........................................................................................3.2-7 3.11.3.1 Project Location and Description................................................................3.2-7 3.11.3.2 Land Uses in the Project Vicinity ..................................................................3.2-8 3.11.3.3 Description of Existing Ambient Noise Environment in 2004....3.2-8 3.11.3.4 Description of Existing Ambient Noise Environment in 2009.3.2-10 3.11.3.5 Description of Current Ambient Vibration Environment...........3.2-11

3.11.4 Regulatory Setting .............................................................................................. 3.2-11 3.11.4.1 Local Jurisdictional Guidelines ...................................................................3.2-11 3.11.4.2 Madera County General Plan Noise Element ....................................3.2-11 3.11.4.3 Madera County Noise Ordinance .............................................................3.2-13 3.11.4.4 Noise Level Increase Significance Criteria................................ 3.2-13

3.11.5 Impacts and Mitigation Measures ................................................................. 3.2-15 3.11.5.1 CEQA Environmental Checklist for Noise.............................................3.2-15 3.11.5.2 Application of CEQA Guidelines to the Proposed Project –

Standards of Significance ..............................................................................3.2-15 3.11.5.3 Methodology for Assessing Noise Impacts Associated with

On-Site Equipment............................................................................................3.2-17 3.11.5.4 Methodology for Assessing Blasting Noise

and Vibration Impacts .....................................................................................3.2-22 3.11.5.5 Methodology for Assessing Off-Site Truck Traffic

Noise Levels ...........................................................................................................3.2-23 3.11.5.6 Methodology for Assessing Construction Noise Impacts .........3.2-25 3.11.5.7 Specific Project Impacts and Noise Mitigation Measures..........3.2-26 3.11.5.8 Cumulative Noise Impacts............................................................................3.2-30

3.3 Revisions to Traffic Section in Response to Judicial Decisions............... 3.3-1

3.12.1 Introduction..............................................................................................................3.3-1 3.12.2 Affected Environment...........................................................................................3.3-2

3.12.2.1 Project Elements Affecting Traffic ...............................................................3.3-2 3.12.2.2 Study Area and Time Period ...........................................................................3.3-4 3.12.2.3 Existing Lane Configurations..........................................................................3.3-4 3.12.2.4 Planned Improvements.....................................................................................3.3-6

3.12.3 Traffic Methodology ..............................................................................................3.3-6 3.12.3.1 Level of Service .......................................................................................................3.3-6

3.12.4 Traffic Impact Study............................................................................................ 3.3-13 3.12.4.1 Project Traffic Volumes....................................................................................3.3-13 3.12.4.2 Existing Traffic Volumes..................................................................................3.3-14

RESOURCE DESIGN TECHNOLOGY, INC. iii

Page 6: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Table of Contents

3.12.4.3 Cumulative Traffic Volumes .........................................................................3.3-20 3.12.4.4 Intersection Analyses .......................................................................................3.3-20 3.12.4.5 Road Segment Analyses.................................................................................3.3-24

3.12.5 Standards of Significance, Environmental Consequences, and Mitigation Measures .................................................................................. 3.3-27 3.12.5.1 Standards of Significance ..............................................................................3.3-27

3.12.6 Impacts and Mitigation Measures ................................................................. 3.3-27 3.12.6.1 Discussion of Existing and Existing-Plus-Project Analyses ........3.3-27

3.12.7 Cumulative Impacts and Mitigation Measures......................................... 3.3-30

4.0 NEW LEGISLATIVE MANDATE........................................................... 4.0-1

4.1 Introduction to Greenhouse Gas (AB 32, SB 375) .................................... 4.0-1 4.1.1 Greenhouse Gases..................................................................................................4.0-1 4.1.2 Existing Greenhouse Gases.................................................................................4.0-2

4.2 Regulatory Setting ..................................................................................... 4.0-2 4.3 Standards of Significance .......................................................................... 4.0-4 4.4 Impacts and Mitigation Measures............................................................. 4.0-5 4.5 Cumulative Impacts and Mitigation Measures ......................................4.0-11

5.0 LIST OF PREPARERS........................................................................... 5.0-1

5.1 Lead Agency Staff....................................................................................... 5.0-1 5.2 Consultants and Other Individuals Involved in the

Preparation of the EIR ................................................................................ 5.0-1 5.2.1 Applicant Team .......................................................................................................5.0-1 5.2.2 Applicant Team Technical Consultants..........................................................5.0-2 5.2.3 Peer Review, Editorial, and Formatting..........................................................5.0-3

RESOURCE DESIGN TECHNOLOGY, INC. iv

Page 7: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Table of Contents

LIST OF TABLES Table S-1 Summary of Impacts and Mitigation Measures Table 1.0-1 Table of Appendices Table 2.0-1 Contracts and Entitlements Table 3.11-1 Ambient Noise Measurement Survey Summaries (April 19-20, 2004) Table 3.11-2 Madera County Noise Element Performance Standards Applicable to Land

Uses Affected by Heavy Industrial Uses Table 3.11-3 Significance of Chances in Cumulative Noise Exposure Table 3.11-4 Major Noise Producing Equipment and Associated Noise Levels Table 3.11-5 Scenarios Evaluated for the Madera Quarry Project Table 3.11-6 Predicted Project Noise Levels from On-Site Sources Table 3.11-7 Project-Related Changes in Existing Traffic Noise Levels at

Existing Residences Table 3.11-8 Project-Related Changes in Cumulative Traffic Noise Levels Table 3.12-1 Madera County Level of Service Definitions for Signalized Intersections Table 3.12-2 Level of Service Characteristics for Unsignalized Intersections Table 3.12-3 Level of Service Characteristics for Signalized Intersections Table 3.12-4 Capacities per Hour per Lane for Various Highway Facilities in the

Madera County Table 3.12-5 Project Trip Generation Table 3.12-6 Intersection Analysis Summary – Existing Conditions Table 3.12-7 Intersection Analysis Summary – Existing Plus Project Conditions Table 3.12-8 Intersection Analysis Summary – 2030 Cumulative No Project Conditions Table 3.12-9 Intersection Analysis Summary – 2030 Cumulative With Project Conditions Table 3.12-10 Road Segment LOS Summary – Existing Conditions Table 3.12-11 Road Segment LOS Summary – Existing Plus Project Conditions Table 3.12-12 Road Segment LOS Summary – 2030 Cumulative No Project Conditions Table 3.12-13 Road Segment LOS Summary – 2030 Cumulative With Project Conditions Table 4.0-1 CARB’s Interim GHG Significance Standards for Industrial Projects Table 4.0-2 Summary of GHG Emissions from On-Site Equipment and Quarry Trucks Table 4.0-3 Summary of Transportation-Related Emissions Table 4.0-4 CO2 Emissions from Electricity Generation Table 4.0-5 Estimate of CO2 Sequestration Table 4.0-6 Summary of Avoided Emissions – Scenario 1 (2009 to 2011) Table 4.0-7 Summary of Avoided Emissions – Scenario 2 (Beyond 2011)

RESOURCE DESIGN TECHNOLOGY, INC. v

Page 8: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Table of Contents

LIST OF FIGURES Figure S-1 Site Location Figure 1.0-1 Current Acreage Calculations Figure 2.0-1 Mining Plan Alternate 2 Figure 2.0-2 Assessor’s Parcel Figure 3.9-1 Locations of Wells Used For Well No. 10 Aquifer Test Figure 3.9-2 Locations of Quarry Wells and Wells Used for 2005 Aquifer Tests Figure 3.9-3 Plan View of Project Site Figure 3.9-4 Location of Private Wells in Vicinity Figure 3.9-5 Maximum Projected Drawdowns in Wells During Mining Figure 3.9-6 Projected Drawdowns in Wells During Reclamation Phase Figure 3.9-7 Table 10 Summary of Aquifer Tests Figure 3.9-8 Table 10 Summary of Aquifer Tests (Continued) Figure 3.9-9 Table 10 Summary of Aquifer Tests (Continued) Figure 3.11-1 Site Plan, Noise Measurement Locations, and Receiver Locations Figure 3.11-2 Typical A-Weighted Sound Levels of Common Noise Figure 3.12-1 Vicinity Map Figure 3.12-2 Existing Lane Configurations Figure 3.12-3 Cumulative Lane Configurations Figure 3.12-4 Opening Day Project Traffic Volumes Figure 3.12-5 Ultimate Project Traffic Volumes Figure 3.12-6 Project Traffic Distribution Percentages Figure 3.12-7 PCE Project Traffic Volumes Figure 3.12-8 2030 PCE Project Traffic Volumes Figure 3.12-9 Existing Traffic Volumes Figure 3.12-10 Existing Plus Project Traffic Volumes Figure 3.12-11 Cumulative 2030 No Project Traffic Volumes Figure 3.12-12 Cumulative 2030 With Project Traffic Volumes Figure 4.0-1 Location of Alternate Sources of Aggregate in Madera County Vicinity

RESOURCE DESIGN TECHNOLOGY, INC. vi

Page 9: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Table of Contents

VOLUME II: TECHNICAL APPENDICES OF DRAFT REVISED EIR AND PREVIOUSLY CIRCULATED ENVIRONMENTAL IMPACT REPORTS (Original on CD-ROM)

Appendix A-1 Fifth District Court of Appeal Opinion, Case No. F053661,

Gray v. County of Madera Appendix A-2 Judgment Granting Petition for Writ of Mandate on Remand, Madera Co.

Case No. SCV005567, Gray v. County of Madera Appendix B-1 Notice of Preparation Appendix B-2 Scoping letters Appendix C-1 Technical Memorandum, Review of 'Hydrogeologic Conditions At and Near

the Proposed Madera Quarry,' Luhdorff & Scalmanini, Consulting Engineers, dated October 28, 2009

Appendix C-2 Hydrogeologic Conditions At and Near the Proposed Madera Quarry, Kenneth D. Schmidt and Associates, Groundwater Quality Consultants, Fresno, California, dated October 2009

Appendix C-3 Madera Quarry Surface Water Hydrology Report, Blair, Church & Flynn, Consulting Engineers, dated October 2009

Appendix C-4 Wellco Drilling, Inc., Letter to Madera Quarry, Inc, dated September 23, 2009 Appendix D Traffic Impact Study for Proposed Madera Quarry, Peters Engineering

Group, dated October 13, 2009 Appendix E Department of Conservation Letter to Madera County Assessor's Office,

with Williamson Act Cancellation Valuation Agreement Attached, all dated August 28, 2008

Appendix F Compensation and Grazing Agreement Waiving Potential Noise Impacts to

Residents for Mining and Asphalt Project Truck Traffic, between Madera Quarry, Inc. and the Wagner Family Trust, dated February 2009

Appendix G Conservation Easement Deed, Madera County Contract No. 8512-C-2008,

dated January 15, 2008 Appendix H U.S. Army Corps of Engineers Permit, dated January 12, 2009, 2005-673

(includes July 1, 2008 U.S. Department of Interior Fish & Wildlife Service Biological Opinion)

Appendix I U.S. Department of Interior, Fish & Wildlife Service, Comments on

Avoidance Minimization and Compensation Measures, dated December 17, 2007

RESOURCE DESIGN TECHNOLOGY, INC. vii

Page 10: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Table of Contents

RESOURCE DESIGN TECHNOLOGY, INC. viii

Appendix J-1 CA Office of Historic Preservation, Historic Properties Comment Letter to USACOE, dated November 13, 2008

Appendix J-2 Cultural Resources Inventory and Evaluation Report for The Madera Ranch Quarry Project, Madera County, California, Pacific Legacy, dated June 2008

Appendix J-3 Supplemental Cultural Resources Inventory and Evaluation Report for The Madera Ranch Quarry Project, Pacific Legacy, dated September 2008

Appendix K CA Regional Water Quality Control Board, Section 401 Water Quality

Certification, dated July 17, 2008 Appendix L CA Department of Fish & Game Section 1602 Stream Alteration Agreement

No. 2007-0209-R4, Hildreth Creek - Madera County, dated June 13, 2008 Appendix M Analysis of Greenhouse Gas Emissions, Madera Quarry, Inc., Madera County,

California, October 1, 2009 Appendix N Madera County Road Impact Fee Program Update, November 2009 Appendix O-1 Acoustical Terminology Appendix O-2 Continuously Measured Hourly Noise Levels Appendix O-3 Madera Quarry Noise Source Data Appendix O-4 FHWA-RD-77-108 Highway Traffic Noise Prediction Model Appendix P Road Construction, Maintenance and Reimbursement Agreement, Madera

County Contract No. 8511-C-2008, dated January 15, 2008 Appendix Q Traffic Mitigation Agreement Capital Deferment, Madera County Contract

No. 8513-C-2008, dated January 15, 2008 June 2005 Draft Environmental Impact Report (Original on CD-ROM) February 2006 Final Environmental Impact Report (Original on CD-ROM)

Page 11: MADERA QUARRY PROJECT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

SUMMARY

Page 12: MADERA QUARRY PROJECT

 

 

 

 

 

 

 

 

 

 

SUMMARY  

 

 

SUMMARY OF THE PROJECT  

Project Purpose, Location, and Background Information  

This  Draft  Revised  Environmental  Impact  Report  (DREIR)  has  been  prepared  in 

accordance with  the California  Environmental Quality Act  (CEQA)  (Public Resource 

Code,  Section  21000,  et.  seq.)  and  the  State Guidelines  for  implementation  of CEQA 

(Title 14, California Code of Regulations, Section 15000,  et.  seq.).   This DREIR will be 

used  by Madera County  (County)  in  its  consideration  of  the Madera Quarry Project 

(Project)  as  proposed  by Madera  Quarry,  Inc.  (Applicant  or  Operator).    Except  as 

modified by this DREIR, this document incorporates the Draft EIR (DEIR) and Final EIR 

(FEIR), dated June 2005 and February 2006, respectively.   Digital versions of the DEIR 

and FEIR are attached  to  this DREIR and hard copies are available  for viewing at  the 

Madera County Planning Department at the following location: 

 

Madera County Planning Department 

2037 W. Cleveland Avenue, Mail Stop G  

Madera, California 93637 

(559) 675‐7821 

 

Site Location  

The Project site  is  located  in central Madera County, California, about 2 miles west of 

State  Route  (SR)  41,  4 miles  north  of  SR  145,  and  16 miles  northeast  of  the City  of 

Madera (Figure S‐1, Site Location).  It lies in Section 4 of Township 10 South, Range 20 

 

RESOURCE DESIGN TECHNOLOGY, INC. S-1

Page 13: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

East  of  the  Little  Table  Mountain,  California  7.5  U.S.  Geological  Service  (USGS) 

topographic map.   The  realignment and  improvements  to County Road 209 will also 

affect portions of Sections 9, 16, 21, 28, and 33 of the previously identified township and 

range.  The Project/Quarry site, including processing facilities, would be located entirely 

within the boundaries of the Madera Project site (Assessor’s Parcel Number [APN] 050‐

082‐007.  The owner of record for the Madera Quarry property is Madera Quarry, Inc., 

P.O. Box 994248, Redding, California 96099‐4248. 

 

Project Overview  

Madera  Quarry,  Inc.  proposes  to  develop  a  new  hard  rock  quarry  and  associated 

aggregate processing facilities in central Madera County.  The processing facilities will 

be  located  on  a  28‐acre  portion  of  one  of Madera  Quarry,  Inc’s  parcels,  while  the 

aggregate material will be mined from an approximately 77.8‐acre portion of the same 

parcel (these acreages are the net acres to be disturbed in the construction of the mine 

and processing areas).  Table 2.0‐1 of the Project Description of the previously circulated 

DEIR provides  a detailed description of  the processing  facilities.   The Project will be 

located on a 540‐acre parcel, being one of the four owned by Madera Quarry, Inc, which 

total  approximately  1,000  acres.    The  entire  property  is  currently  primarily  used  for 

rangeland cattle grazing.  The Project is located about 16 miles northeast of the City of 

Madera  in  the  lower  granitic  foothills  of  the  western  slope  of  the  southern  Sierra 

Nevada Mountains.   The  topography  is variable,  ranging  from  flat and gently  rolling 

hills  to  steep, boulder‐strewn  fields.   The area has  some history of  rock quarries,  the 

most  visible  of which  can  be  seen  to  the  east  of County Road  209  just  south  of  the 

Project site. 

 

As proposed, the Project would result in the mining, processing, and off‐site transport 

of a maximum of 900,000 tons of aggregate material annually for up to 50 years.  Project 

support  facilities  associated  with  the  quarry  would  include  aggregate  processing 

equipment, a hot mix asphalt plant, an administration complex and various stockpiles, 

sediment ponds, etc.   A  two‐lane paved mine access road would be constructed  from 

the  processing  area  to  County  Road  209  (a  distance  of  about ¼ mile).    Substantial 

upgrading, reconstruction, and realignment of County Road 209 from the mine entrance 

south about 4.5 miles to the intersection of Highway 41 would also be a component of 

the  Project.    Further,  the  Applicant  will  construct  left‐turn,  acceleration,  and 

deceleration  lanes  at  the  intersection  of  County  Road  209  and  Highway  41.    The 

Applicant will perform  improvements on Highway 41 between County Road 209 and  

 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. S-2

Page 14: MADERA QUARRY PROJECT
Page 15: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

Highway  145  and  on  County  Road  209  from  the  Project  Site  to  the  intersection 

of County  Roads  209  and  406  as more  fully  discussed  in  Section  2.2.4  of  this Draft 

Revised Environmental Impact Report. 

 

Need and Objectives  

The  availability,  consumption,  and demand  for  aggregate  resources  in California  are 

issues of  concern and  interest  to planning and  transportation agencies and  industries 

throughout  the  state.    Aggregate  resources  provide  the  construction  aggregate 

necessary  for  a wide  range  of  public works  and  private‐sector  construction  projects.  

Because the cost of aggregate is largely dependent on the distance the material must be 

hauled  from where  it  is mined  and  processed  to where  it  is  sold,  local  sources  of 

aggregate play a major role in maintaining reasonable costs to the consumer. 

 

California’s Surface Mining and Reclamation Act of 1975  (SMARA)  requires  the State 

Geologist to classify land into Mineral Resource Zones (MRZs) based on the known or 

inferred mineral resource potential of that land.  The process is based solely on geology, 

without  regard  to existing  land use or  land ownership.   The primary goal of mineral 

land  classification  is  to  help  ensure  that  the mineral  resource  potential  of  lands  is 

recognized and considered  in  the  land‐use planning process.   The Project site has not 

been designated at this time. 

 

The overall goal of  the Project  is  to develop  the maximum known aggregate  reserves 

which  can  feasibly  be mined within  the  current  design  plan  area.    Specific  Project 

objectives include: 

 

Location:    Secure  approvals  to mine  the  reserves  on  site,  which  are  located 

within central Madera County, thus providing a reliable and economic source to 

meet current and projected demand in the region. 

Profit:  Responsibly operate a profitable aggregate mine and processing facility. 

Period:  Provide for approximately 50 years of approved aggregate extraction, in 

accordance with availability of known resource reserves, mining and reclamation 

plans, and foreseeable market demands.  Implementation and monitoring of final 

reclamation  activities would be  completed within  three years of  exhaustion of 

reserves or expiration of the permit.   

Production:    Provide  for  an  annual maximum  permitted  production  level  of 

900,000  tons  (about  533,000  cubic  yards); with  sequencing  broken  into  several 

mining phases dependent on geology, terrain, current technological capabilities, 

 

RESOURCE DESIGN TECHNOLOGY, INC. S-4

Page 16: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

and  the  intent  to  incorporate  the  visual  screening  provided  by  the  existing 

terrain. 

Employment:    Provide  on‐site  staffing  of  between  15  and  20  employees 

throughout the production life of the mine.  Two shifts could be employed when 

special night operations are needed and three to five workers would be added to 

the labor force.  

Site Conservation:  Avoid sensitive natural resources to the extent possible and 

provide adequate mitigation when avoidance  is not feasible; minimize aesthetic 

impacts  through  site  design,  phasing,  and  concurrent  reclamation;  and 

implement reclamation concurrently with mining operations throughout the life 

of the mine to return the site to a productive post‐mining open space land use.   

Use of PCC Grade Material:  Maximize the use of on‐site PCC grade aggregate 

sources  to  service  the  Applicant’s  current  and  future  construction  industry 

clients that require strict adherence to specifications of federal, state, county and 

city standards. 

Operational Flexibility:  Secure permission to occasionally operate at night and 

during  early  morning  hours  to  better  serve  existing  and  future  clients  that 

require  early morning  and  nighttime  deliveries  to meet  project  schedule  and 

traffic mitigation requirements. 

Market  Share:    Increase  company  position  and  market  share  as  a  leading 

regional aggregate provider in the San Joaquin Valley market area. 

 

Draft Revised Environmental Impact Report Scope (DREIR)  

Background  

The initial application was submitted in October 2002.  The County conducted a Public 

Scoping Meeting on October 27, 2003.  The County then circulated the DEIR for public 

review  from  late  June  through early August 2005.   The FEIR  (consisting of  the DEIR, 

minor  revisions  thereto,  and  the Responses  to Comments) was prepared  in February 

2006.   After  a  series  of Planning Commission  and Board  of  Supervisor  hearings,  the 

County’s Board approved the Project and certified the FEIR as adequate. 

 

Opponents  to  the  Project  filed  a  Petition  for Writ  of  Mandate  and  Complaint  for 

Injunctive  and Declaratory Relief  regarding  the  adequacy  of  the  FEIR.    The County 

prevailed  in  the Madera County Superior Court.   However, on October  24, 2008,  the 

Court  of  Appeal  for  the  Fifth  Appellate  District  (Court  of  Appeal)  reversed  the 

judgment and remanded the matter to the Madera County Superior Court.   The Court 

 

RESOURCE DESIGN TECHNOLOGY, INC. S-5

Page 17: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

of Appeal  concluded  that  there were deficiencies  in  the FEIR’s hydrology mitigation 

measures, traffic mitigation measures, cumulative noise impact evaluation, cumulative 

impact evaluation, and required that the County to consider whether it was obligated to 

provide  an  SB  610  Water  Supply  Assessment  (WSA)  to  the  extent  the  Project,  as 

mitigated, involved the construction and operation of a public water system.  A copy of 

the Court of Appeal’s opinion (Opinion) is provided in Appendix A‐1. 

 

A  detailed  discussion  of  the  Court  of  Appeal’s  opinion  and  the  trial  judge’s 

implementing  judgment  (Judicial  Decisions)  is  provided  in  Section  1.1.3  in  the 

Introduction to this Draft Revised EIR.  Further, Section 1.1.4 of this DREIR provides a 

description of changes to the Project since certification of the EIR and Judicial Decisions. 

 

County Approach to DREIR  

As  discussed  above  in  Section  1.1.3,  Judicial Decisions  determined  that  only  limited 

portions  of  the  Final  EIR  were  inadequate.    The  County  and  the  EIR  author  have 

accepted  the direction of  the Appellate Court, and  the subsequent Writ  issued by  the 

Trial  Court,  as  set  forth  in  the  Judicial  Decisions.    This  DREIR  will  address  the 

deficiencies outlined above, minor revisions in background conditions and components 

of  the  Project.    Based  on  a  review  of  the  previously  circulated  FEIR,  the  County 

determined  to evaluate  those  issues outlined  in  the  Judicial Decisions, any changes  to 

the Project which resulted from the studies undertaken to address the Judicial Decisions 

and  anything  mandated  by  changed  legislation,  such  as  the  Project’s  impacts  on 

greenhouse gas emissions. Other sections of the FEIR which were found to be adequate 

in the Judicial Decisions are anticipated to be largely left intact. 

  

On December 23, 2008, the County circulated a Notice of Preparation of a Draft Revised 

Environmental Impact and Notice of Scoping Meeting.  A scoping meeting was held on 

January 16, 2009 at 6:00 p.m. at the Coarsegold Community Center.  A brief summary of 

the NOP and Scoping Process is provided below. 

 

Notice of Preparation  

A  Notice  of  Preparation  (NOP)  for  the  EIR  was  distributed  to  the  State 

Clearinghouse,  responsible  agencies,  interested  groups  and  individuals,  and 

surrounding  property  owners  on  December  23,  2008,  for  a  30‐day  comment 

period.  Copies of the NOP and mailing list are included in Appendix B‐1, Notice 

of Preparation and Mailing List.  One‐hundred and thirty letters were received in 

 

RESOURCE DESIGN TECHNOLOGY, INC. S-6

Page 18: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

response  to  the  NOP  and  are  included  as  Appendix  B‐2, Written  NOP  and 

Scoping Comments.   

 

The NOP advised: 

 

“The Court  of Appeal  concluded  that  there were  deficiencies  regarding 

specified  EIR’s  hydrology  mitigation  measures,  traffic  mitigation 

measures  cumulative  noise  impact  evaluation,  cumulative  impact 

evaluation,  and whether SB 610 was  applicable  to hydrology mitigation 

measures. 

 

A  summary  of  the  Final  EIR’s  impact  evaluations  and  mitigation 

measures are provided in Table S‐1, Summary of Impacts and Mitigation 

Measures Attachment A, hereto.  However, based on the Court of Appeal’s 

decision discussed above, the nature and extent of impacts and mitigation 

will  be  updated  consistent  with  the  decision  in  the  revised  EIR,  and 

therefore could be different than provided in Attachment A.” 

 

The Court of Appeal determined  that many of  the sections of  the EIR were not 

defective.  It was expected that any comments would be limited to areas noted by 

the  Court  of  Appeal  to  be  deficient  in  the  EIR,  or  matters  of  changed 

circumstance or law (i.e., AB 32, mandatory greenhouse gas analysis).  Based on 

a  review  of  comments  submitted  during  the NOP  review  period,  aside  from 

addressing  changes  discussed  above,  the  County  has  determined  that  the 

previously circulated EIR adequately addresses NOP comments and this DREIR 

will  not  address  comments  that  address matters  1)  not  raised  by  the  Project 

Opponents  in  the  Superior Court  and Court  of Appeal,  and  2)  for which  the 

courts determined either the EIR to be adequate and/or the actions of the Madera 

Board  of  Supervisors  to  be  proper.   At  the  time  of  the  Scoping meeting,  the 

Amended  Judgment Granting  Petition  for Writ  of Mandate  had  not  yet  been 

entered, but it incorporated the directions of the Court of Appeal. 

 

Public Scoping Meeting  

A  Public  Scoping Meeting was  held  at  6:00  p.m.  on  January  16,  2009  at  the 

Coarsegold Community Center  in Coarsegold, California.   The EIR Consultant 

described the Project.   County staff and  its EIR Consultant then solicited public 

comments and concerns to be considered in the analysis for this EIR.  Thirty‐four 

people  signed  the  attendance  list,  and  approximately  80  people  attended.  

 

RESOURCE DESIGN TECHNOLOGY, INC. S-7

Page 19: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

Written  comments  were  accepted  from  governmental  agencies,  a  non‐profit 

organization and various private parties.  

   

DREIR Scope  

The Judicial Decisions outlined those matters of which this DREIR would need to 

adequately address  to comply with CEQA requirements.   Based on a review of 

the  previously  circulated  FEIR,  the County  determined  to  evaluate  the  issues 

outlined in the Judicial Decisions as well as the Project’s impacts on greenhouse 

gas emissions. An overview of the scoping process completed for this Project  is 

provided in Sections 1.1.6 and 1.1.7. 

 

 This DREIR contains the following sections: 

 

Summary (substantially revised since the FEIR); 

Section 1.0:  Introduction (superseding 2006 DEIR); 

Section  2.0:    Revisions  to  Project  Description  in  Response  to  Judicial 

Decisions,  Entitlements,  and  Contracts  Subsequent  to  the  FEIR 

(amendment to DEIR and FEIR); 

Section  3.1:    Revisions  to  Hydrology  and  Water  Quality  Section  in 

Response to Judicial Decisions (replaced previous version); 

Section  3.2:    Revisions  to Noise  and  Vibration  Section  in  Response  to 

Judicial Decisions (replaced previous version); 

Section 3.3:  Revisions to Traffic Section in Response to Judicial Decisions 

(replaced previous version);  

Section 4.0:  New Legislative Mandate; and 

Section 5.0:  List of Preparers. 

 

Impacts Found to be Significant and Unavoidable  

After applying CEQA standards of significance  to  the entire range of adverse  impacts 

that would  result  from  implementation  of  the  Project,  7  significant  and  unavoidable 

impacts  have  been  identified  through  systematic  analysis  of potential Project  effects.  

These  impacts  are  related  to  air  quality  (2),  off‐site  traffic  noise  (2),  land  use,  and  

traffic (2). 

 

Air  quality  emissions  from  the  Project  will  contribute  to  a  net  increase  of  criteria 

pollutants  including NOX and ROG within  the San  Joaquin Valley Air Basin.   Engine 

 

RESOURCE DESIGN TECHNOLOGY, INC. S-8

Page 20: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

exhaust  emissions will  contribute  to  the  net  increase  in  criteria pollutants,  including 

NOx  and ROG.    The  Project would  generate  criteria  pollutants  that would  result  in 

levels of NOX and PM10 emissions exceeding the threshold of significance established by 

the San Joaquin Valley Unified Air Pollution Control District.  Therefore, this air quality 

impact is considered significant and unavoidable. 

 

Additionally,  as project‐specific  impacts  related  to  the  criteria pollutants  of NOx  and 

PM10 exceed applicable thresholds of significance,  it  is anticipated that  impacts related 

to  NOx  and  PM10  will  be  cumulatively  considerable.    While  mitigation  will  be 

incorporated to reduce such impacts, cumulative air quality impacts are still considered 

to be significant and unavoidable. 

 

There  is one  residence  identified  adjacent  to Road  209 between Highway  41  and  the 

Project  site.    This  residence  will  be  exposed  to  a  project‐related  traffic  noise  level 

increase  of  approximately  16  dB  Ldn  following  commencement  of  operations  at  the 

Project site.   Mitigation measures have been  identified  that may reduce  this  impact  to 

below a level of significance.  However, it is not possible to state with certainty that the 

property  owner will use  the  funds  to mitigate  any noise  impacts.   To  the  extent  the 

owner of  the  residence  located  approximately  300  feet  from  the  centerline of CR  209 

chooses not to spend the money for the purposes for which it was intended, the impact 

would remain significant and unavoidable. 

 

The Project could be inconsistent with the Noise Element of the Madera County General 

Plan.    The Noise  Element,  of  the General  Plan,  establishes  standards  to  protect  the 

public from harmful noise levels.  General Plan Policy 7.A.2 requires that transportation 

noise  sources be mitigated  so as not  to exceed 60dB Ldn within outdoor activity areas 

and 45 dB Ldn in interior spaces of existing or planned noise sensitive land uses. Project 

traffic is expected to exceed this standard at one existing residence on County Road 209.  

All  feasible  mitigation  will  be  incorporated  into  the  Project  to  meet  the  County’s 

standards.  It is unknown at this time whether such noise impacts will be reduced to a 

less  than  significant  level.    Therefore,  this  impact  is  considered  significant  and 

unavoidable. 

 

The Project will exacerbate an existing substandard LOS at the intersection of SR 41 and 

Avenue 15.  There are no feasible mitigation measures to mitigate the Project’s impact at 

the  intersection  of  SR  41  and Avenue  15.    Installation  of  all‐way  stop  control  is  not 

feasible due to the significant delays that would result on SR 41.  The addition of lanes 

is not feasible since it would not alleviate the delays for stop‐controlled vehicles turning 

across  traffic  from Avenue 15  to SR 41.   Finally,  traffic signal warrants are not clearly 

 

RESOURCE DESIGN TECHNOLOGY, INC. S-9

Page 21: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

satisfied and would cause new delays on the SR 41 mainline, rendering the installation 

of  traffic  signals  an  infeasible  mitigation.    Therefore,  this  impact  is  considered 

significant and unavoidable.   Eventually, as traffic volumes  in the region  increase as a 

result of  further development, warrants  for  traffic  signals are expected  to be  satisfied 

and traffic signals will be required to be installed by future development projects.  The 

Project can mitigate its equitable share of the impact with payment of an equitable share 

contribution as discussed  later  in  this report.   The Project might also be subject  to  the 

Fee Program, discussed in the Introduction.  At locations other than the intersection of 

SR 41 and Avenue 15, the impact of the projected Project traffic is less than significant.   

 

To mitigate  the  impacts of  traffic, County  and Applicant have  entered  into  the Road 

Construction, Maintenance and Reimbursement Agreement, Madera County Contract 

No. 8511‐C‐2008 (see Appendix P).   This Agreement obligates MQI to pay the costs of 

reconstructing  and    maintaining  209  (subject  to  the  right  of  partial  reimbursement 

should County create an “Area of Benefit” whereby properties generating traffic having 

a per‐vehicle certified gross vehicle weight of 80,000 lbs or greater, will be assessed their 

fair  share of costs).    In addition  the agreement obligates MQI  to pay $0.05 per  ton of 

shipped material toward road maintenance costs for roads other than 209.   

 

The Agreement  fully mitigates  the  impacts  to  reconstruct,  repair  and maintain  209.  

However, as  to any other roads  impacted by  the Project, as  the County  is required  to 

give ‘primary consideration’ to spending these maintenance funds on roads in the area, 

but  is not required  to do so,  the wear and  tear  impact on  local  roads, other  than 209, 

remains significant and unavoidable.  

 

The Applicant shall contribute an equitable share of  the cost of construction of  future 

improvements as required under  the Fee Program  (if applicable), which  is attached  in 

Appendix  N  to  the  DREIR.    If  the  Fee  Program  is  not  applicable,  equitable  share 

percentages  are  presented  in  the  traffic  impact  study  included  in Appendix D. Cost 

estimates for improvements shall be provided by Caltrans or Madera County. 

 

The Project will  contribute  traffic  to  cumulative  significant  impacts  to  road  segments 

that will require equitable fair share regarding the following mitigations: 

 

SR 41 between Road 209 and Road 406: widen to four lanes; 

SR 41 between SR 145 and Road 209: widen to four lanes; 

SR 41 between Avenue 15 and SR 145: convert to four‐lane freeway; 

 

RESOURCE DESIGN TECHNOLOGY, INC. S-10

Page 22: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

SR 41 between Avenue 12 and Avenue 15: convert to four‐lane freeway; and 

SR 145 between SR 41 and Road 400: widen to four lanes. 

 

All of  these  improvements have been  identified  in  the County’s  recently adopted Fee 

Program  (Appendix N, see Tables 1, 2, and 3).   The County  is committed  to ensuring 

that  those  improvements coincide with  the Project’s anticipated contribution  to  traffic 

on these segments, to the extent feasible. 

 

If  mitigation  measures  are  implemented,  this  impact  will  be  less  than  significant.  

However,  it  cannot  be determined  at  this  time whether  these measures will  be  fully 

funded; therefore, this impact remains significant and unavoidable. 

 

SUMMARY OF IMPACTS AND MITIGATION MEASURES  

Detailed  evaluations  were  completed  for  a  wide  array  of  environmental  issues 

identified  for  study  through  the  scoping  process.    The  previous  EIR  evaluated  each 

potential  impact  to  the  environmental  resources,  identified  significance  relative  to 

established  standards,  and  determines  appropriate mitigation  as  necessary  to  avoid 

impacts or reduce them to less than significant levels.  As discussed above, the DREIR 

evaluated those impact results from Changes to the Project, the Judicial Decisions, and 

New Legislative Mandate regarding greenhouse gases.  Table S‐1, Summary of Impacts 

and Mitigation Measures,  summarizes  the  results of  these  evaluations.   Changes  that 

have  been made  to  the  Impacts  and Mitigation Measures  in  the DREIR  to  the  prior 

Impacts  and Mitigation Measures  are  shown  as underlined  (new  text)  and  strike‐out 

(deleted text). 

 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. S-11

Page 23: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

TABLE S-1 SUMMARY OF IMPACTS AND MITIGATION MEASURES 

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation AESTHETICS Impact 3.2-1: The Project Could Have an Adverse Effect on a Scenic Vista Mitigation Measure 3.2‐1 

To minimize an engineered appearance, final slopes of the high wall at the 

north wall of the Quarry shall not be graded to a uniformly flat surface.   A 

plan  shall  be  submitted  showing  areas  of  planned  aggregate  material 

removal  from  the  north  wall  of  the  Quarry  slopes  and  showing  the 

proposed mined surface and the rock material to remain in place.  A plan 

shall  be  submitted  to  the  Planning  Director  sixty  (60)  days  before 

operations begin and material is removed from the North Wall.   The Plan 

shall include a written description of areas planned for aggregate removal, 

operation  and  final  slopes,  areas  to  remain  in  place,  and  a  graphical 

depiction  of  final  slopes.   Operations  shall not  begin  on  the North Wall 

until the Operator has received approval from the Planning Director. 

LS  LS 

Impact 3.2-2: Proposed Mining and Processing Operations Could Result in Both Temporary and Permanent Alteration of the Visual Quality or Character of the Site and its Surroundings

Mitigation Measures 3.2‐2a 

All processing facilities and asphalt silos shall be painted to conform to the 

color of the existing environment.  All colors and materials shall be subject 

to  review  and  approval  by  the Planning Director.   The processing plant 

and associated facilities shall maintain the designated color throughout the 

life of the mine. 

 

Mitigation Measures 3.2‐2b 

To blend with  the  rural character of  the site,  the office and storage  tanks 

shall be painted an earthtone color blending with the natural environment.  

All  colors  and materials  shall  be  subject  to  review  and  approval  by  the 

Planning Director.   The colors shall be submitted to the Planning director 

for approval 60 days before construction or placement of  the silos, office, 

and storage tanks. 

 

Mitigation Measures 3.2‐2c 

Upon inspection by the County, if it is determined the approved paint has 

deteriorated  to  a  point where  the  underlying material  or  base  paint  is 

visible,  the  Applicant  shall  repaint  that  portion  of  the  structure  or  the 

entire  structure  depending  on  the  severity  of  the  deterioration with  the 

approved paint color. 

PS  LS 

 

RESOURCE DESIGN TECHNOLOGY, INC. S-12

Page 24: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-13

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation Impact 3.2-3: The Project Could Result in Extended Lighting from Nighttime Loading and Hauling

Operations Mitigation Measure 3.2‐3 

Exterior  lighting shall be designed and maintained  in a manner such that 

glare and reflections are contained within the boundaries of the parcel, and 

shall  be  hooded  and  directed  downward  and  away  from  adjoining 

properties  and  public  rights‐of‐way.    The  use  of  blinking,  flashing  or 

unusually high intensity or bright lights shall not be allowed.  All lighting 

fixtures shall be appropriate to the use they are serving, in scale, intensity 

and height.   Further,  all  exterior  lighting will be designed,  installed  and 

operated as required by the Planning Director.  Lighting plans and design 

shall be submitted  to  the Planning Director  for approval 60 days prior  to 

installation and use of exterior lighting fixtures on the Project site. 

PS  LS 

Impact 3.2-4: The Project, in Combination with other Cumulative Development, could Contribute to an Alteration of the Visual Character of the Project Site, and to Visual Incompatibility with Surrounding Land Uses in the Vicinity of the Project Site

None required.  LS  LS 

Impact 3.2-5: The Project, in Combination with other Cumulative Development, could have a Substantial Adverse Effect on a Scenic Vista

See Mitigation Measure 3.2‐1.  LS  LS 

Impact 3.2-6: The Project, in Combination with other Cumulative Development, could Create Nighttime Light and Glare that may Adversely Affect Day or Nighttime Views in the Area

None required.  LS  LS 

AGRICULTURAL RESOURCES Impact 3.3-1: Conversion of Prime Farmland, Unique Farmland, or Farmland of Statewide

Importance None required.  LS  LS 

Impact 3.3-2: The Project Could Be Inconsistent With Agricultural General Plan Policies and Agricultural Zoning

None required.  LS  LS 

Impact 3.3-3: The Project Would Contribute to the Premature Cancellation of Williamson Act Contract

Mitigation Measure 3.3‐3 

The Applicant shall rescind Land Conservation Contract Number 2350‐C‐

76  in accordance with Government Code §§ 51256, 512561 and 51282 and 

simultaneously  place  the  conservation  easement  parcel  under  a 

conservation easement. 

On October  24,  2006,  pursuant  to  Board  of  Supervisor’s Resolution No. 

2006‐225,  the  County  approved  a  cancellation  of  the  Williamson  Act 

contract  on  a  52.29‐acre  portion  of  the  Project  site.    The  balance  of  the 

Project  site  remains  subject  to  a Williamson  Act  Contract,  for  which  a 

Notice  of  Non‐Renewal  was  recorded  on  November  29,  2003,  and 

therefore, on March 1, 2014, the balance of the property will no  longer be 

encumbered by  the Williamson Act  contract.    In addition, on August 28, 

PS  LS 

Page 25: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-14

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation 2008, the California Department of Conservation entered into a Williamson 

Act  Cancellation  Agreement  with  the  Applicant  and  notified  Madera 

County of the Agreement and the agreed valuation (see Appendix E). 

Impact 3.3-4: Changes in the Environment That Could Adversely Affect the Productivity of Agricultural Lands

Dust Emissions 

See Mitigation Measure 3.4‐5a through 3.4‐5q 

 

Stormwater Runoff 

See Mitigation Measures 3.9‐5a and 3.9‐5b 

 

Groundwater 

See Mitigation Measures 3.9‐5a and 3.9‐5b 

PS  LS 

Impact 3.3-5: The Project, In Combination with Other Cumulative Development, Could Result in the Conversion of Agricultural Lands

See Mitigation Measures 3.3‐3, 3.4‐5a through 3.4‐5q, 3.9‐5a, and 3.9‐5b  PS  LS 

AIR QUALITY Impact 3.4-1: The Project Could Conflict with or Obstruct Implementation of the Applicable Air

Quality Plans as Provided in the SJVUAPCD’s Guide for Assessing and Mitigating Air Quality Impacts

None required.  LS  LS 

Impact 3.4-2: The Project Could Violate Air Quality Standards or Contribute Substantially to Existing or Projected Air Quality Violations for ROG, NOx Emissions

Mitigation Measure 3.4‐2a  

The asphalt plant  shall meet Best Available Control Technology  (BACT), 

including  incorporating a  low NOx burner with  flue gas  recirculation, or 

meeting  any more  stringent  requirement  of  the  SJVUAPCD’s Rules  and 

Regulations,  including  achieving  the  lowest  achievable  emission  rate  for 

propane‐fueled asphalt plants of a similar BTU rating.  The purpose of this 

mitigation measure is to ensure that assumptions used to estimate Project 

emissions are  incorporated  into the Project, and to ensure that the Project 

reduces combustion emissions  to  the extent  feasible.   The Applicant shall 

demonstrate  compliance  by  submitting  a  copy  of  the  Authority  to 

Construct permit to the Planning Director within 30 days of receipt. 

 

Mitigation Measure 3.4‐2b  

A fabric filter shall be installed to control PM10 emissions from the asphalt 

batch  plant  and  meet  the  BACT  requirements  of  the  SJVUAPCD.  The 

purpose of  this mitigation measure  is  to ensure  that assumptions used  to 

estimate Project emissions are incorporated into the Project, and to ensure 

that  the  Project  reduces  PM10  emissions  to  the  extent  feasible.    The 

Applicant  shall  demonstrate  compliance  by  submitting  a  copy  of  the 

Authority  to Construct permit  to  the Planning Director within 30 days of 

receipt. 

SU  SU 

Page 26: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-15

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation Mitigation Measure 3.4‐2c  

A pollution control system  that controls  fugitive emissions  from  the silos 

on the asphalt batch plant during silo filling operations shall be  installed.  

The purpose of this mitigation measure is to ensure that assumptions used 

to  estimate  Project  emissions  are  incorporated  into  the  Project,  and  to 

ensure that the Project reduces PM10 emissions to the extent feasible.   The 

Applicant  shall  demonstrate  compliance  by  submitting  the Authority  to 

Construct to the Planning Director within 30 days of receipt. 

 

Mitigation Measure 3.4‐2d 

CARB  diesel  fuel  shall  be  used  for  all  vehicles.    The  purpose  of  this 

mitigation measure is to ensure that assumptions used to estimate Project 

emissions are  incorporated  into the Project, and to ensure that the Project 

reduces  combustion  emissions  to  the  extent  feasible. The Applicant  shall 

maintain  records  of  all  fuel  purchases,  and  submit  certification  of 

compliance in writing to the Planning Director annually.  Records shall be 

maintained  for  five  years  and  provided  to  the  Planning  Director  upon 

request. 

 

Mitigation Measure 3.4‐2e  

The Operator shall obtain emission offsets for stationary source emissions 

over  the  applicable  emissions  offset  thresholds  for  the  SJVUAPCD.  The 

Operator shall obtain emission offsets from a location near the project site 

or  considered  acceptable  by  the  SJVUAPCD.    The  purpose  of  this 

mitigation measure is to ensure that assumptions used to estimate Project 

emissions  are  incorporated  into  the  Project.    The  Applicant  shall 

demonstrate  compliance by  submitting  the Authority  to Construct  to  the 

Planning Director within 30 days of receipt. 

 

Mitigation Measure 3.4‐2f  

The  Operator  shall  only  use  heavy‐duty  off  road  equipment  (such  as 

bulldozers)  that meet vehicle emissions  standards  in effect at  the  time of 

issuance  of  the  certificate  of  occupancy  by  the Madera County Planning 

and  Building  Inspection  Department.    The  purpose  of  this  mitigation 

measure  is  to ensure  that assumptions used  to estimate Project emissions 

are  incorporated  into  the Project,  and  to  ensure  that  the Project  reduces 

combustion emissions  to  the extent  feasible. The Operator  shall  submit a 

vehicle  inventory and submit certification of compliance  in writing to the 

Planning Director annually. 

 

Mitigation Measure 3.4‐2g  

All  vehicles  shall  be maintained  in  accordance with  the manufacturers’ 

recommendations, and all stationary equipment maintained in compliance 

with  emissions  limitations  established  by  a  permit  issued  by  the 

Page 27: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-16

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation SJVUAPCD.    The  purpose  of  this mitigation measure  is  to  ensure  that 

assumptions used  to estimate Project emissions are  incorporated  into  the 

Project, and to ensure that the Project reduces combustion emissions to the 

extent  feasible.  The  Applicant  shall  maintain  records  of  equipment 

maintenance activities, and submit certification of compliance in writing to 

the Planning Director annually.  Records shall be maintained for five years 

and provided to the Planning Director upon request. 

Impact 3.4-3: The Project Could Increase CO Concentrations Above the Applicable Standard for CO Emissions

None required.  LS  LS 

Impact 3.4-4: The Project Could Have the Potential to Expose the Public to Toxic Air Contaminants None required.  LS  LS 

Impact 3.4-5: The Project Could Generate Additional PM10 Emissions from Fugitive Dust Emissions and Expose Sensitive Receptors to Substantial Pollution Concentrations

Mitigation Measure 3.4‐5a 

All disturbed areas,  including  storage piles, which are not being actively 

utilized for mining or processing purposes, shall be effectively stabilized of 

dust emissions using water, chemical stabilizer/suppressant, covered with 

a tarp or other suitable cover or vegetative ground cover. 

 

Mitigation Measure 3.4‐5b 

All  on‐site  unpaved  roads  and  off‐site  unpaved  access  roads  shall  be 

effectively  stabilized  of  dust  emissions  using  water  or  chemical 

stabilizer/suppressant. 

 

Mitigation Measure 3.4‐5c 

All  land  clearing, grubbing,  scraping,  excavation,  land  leveling, grading, 

cut  and  fill  activities  shall  be  effectively  controlled  of  fugitive  dust 

emissions utilizing application of water or by presoaking. 

 

Mitigation Measure 3.4‐5d 

When materials  are  transported off‐site,  all material  shall be  covered, or 

effectively wetted to limit visible dust emissions, and at least six inches of 

freeboard space from the top of the container shall be maintained. 

 

Mitigation Measure 3.4‐5e 

All  operations  shall  limit  or  expeditiously  remove  the  accumulation  of 

mud or dirt from adjacent public streets at the end of each workday. (The 

use of dry rotary brushes is expressly prohibited except where preceded or 

accompanied by sufficient wetting to limit the visible dust emissions.) (Use 

of blower devices is expressly forbidden.) 

 

 

 

PS  LS 

Page 28: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-17

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation Mitigation Measure 3.4‐5f 

Following  the addition of materials  to, or  the  removal of materials  from, 

the surface of outdoor storage piles, said piles shall be effectively stabilized 

of  fugitive  dust  emissions  utilizing  sufficient  water  or  chemical 

stabilizer/suppressant. 

 

Mitigation Measure 3.4‐5g 

Trackout  shall be  immediately  removed when  it extends 50 or more  feet 

from the site and at the end of each workday. 

 

Mitigation Measure 3.4‐5h 

Limit traffic speeds on unpaved roads to 15 mph. 

 

Mitigation Measure 3.4‐5i 

Install erosion control measures  to prevent silt runoff  to public roadways 

from sites with a slope greater than one percent. 

 

Mitigation Measure 3.4‐5j 

Suspend excavation activity when winds exceed 20 mph. 

 

Mitigation Measure 3.4‐5k 

Regardless of windspeed, Applicant must  comply with Regulation VIII’s 

20 percent opacity limitation. 

 

Mitigation Measure 3.4‐5l 

Use  of  alternative  fueled  or  catalyst  equipped  diesel  construction 

equipment, as feasible. 

 

Mitigation Measure 3.4‐5m 

Minimize idling time (i.e., 10 minute maximum). 

 

Mitigation Measure 3.4‐5n 

To  the  extent  practicable,  limit  the  hours  of  operation  of  heavy‐duty 

equipment and/or the amount of equipment in use. 

 

Mitigation Measure 3.4‐5o 

If  feasible,  replace  fossil‐fueled  equipment  with  electrically  driven 

equivalents (provided they are not run via a portable generator set). 

 

Mitigation Measure 3.4‐5p 

Curtail  excavation  activities  during  periods  of  high  ambient  pollutant 

concentrations; this may  include ceasing of excavation activity during the 

peak‐hour of vehicular traffic on adjacent roadways. 

 

Page 29: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-18

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation Mitigation Measure 3.4‐5q 

Implement  activity  management  (e.g.  rescheduling  activities  to  reduce 

short‐term impacts). 

Impact 3.4-6: The Project Could Create or Subject Sensitive Receptors to an Objectionable Odor Mitigation Measure 3.4‐6 

Prior  to constructing  the asphaltic batch plant,  the Applicant shall obtain 

permits  to construction and operate  from  the San  Joaquin Valley Unified 

Air  Pollution  Control  District  and  incorporate  best  available  control 

technology  (BACT)  in accordance with SJVUAPCD  regulations Toxic Air 

Contaminants.   These BACT’s may  include  the  installation of blue smoke 

filters. 

PS  LS 

Impact 3.4-7: The Project-Related Traffic, in Conjunction with Other Cumulative Development, Could Increase CO Levels at Local Intersections

None required.  LS  LS 

Impact 3.4-8: Implementation of the Project, in Combination with Other Projects, Could Result in an Increased Toxic Air Contaminant Risk Level for Sensitive Receptors

None required.  LS  LS 

Impact 3.4-9: Project Emissions, in Combination with Other Development in the County, Could Contribute to the Degradation of Air Quality

See Mitigation Measures 3.4‐2a through 3.4‐2g, 3.4‐5a through 3.4‐5q, and 

3.4‐6. 

SU  SU 

BIOLOGICAL RESOURCES Impact 3.5-1: Implementation of the Project could Result in the Loss of Valley Elderberry Longhorn

Beetle and their Habitat Mitigation Measure 3.5‐1 

Prior  to any ground disturbing activities within  the 100  foot buffer zone, 

the Applicant or their representative shall initiate consultation pursuant to 

the Federal Endangered Species Act with USFWS.   Section 7 Consultation 

shall occur  if  the US Army Corps of Engineers  (ACOE)  is  involved with 

this Project through a section 404 permit.   Section 10 Consultation will be 

required  if  there  is  no  ACOE  involvement  with  this  Project.    Specific 

mitigation  measures  on  the  Valley  Elderberry  Longhorn  Beetle  will  be 

developed during this process, but may include the following: 

 

A qualified biologist shall survey all Elderberry shrubs with one or 

stems measuring one inch or greater in diameter at ground level for 

the presence of  the Valley Elderberry Longhorn Beetle  and  beetle 

exit holes. 

Elderberry  shrubs with one or more  stems measuring one  inch  in 

diameter must be transplanted if they cannot be avoided. 

Each Elderberry stem measuring one inch in diameter or greater at 

ground  level  that  is adversely affected  (transplanted or destroyed) 

must  be  replaced,  in  the  conservation  area,  with  Elderberry 

 

PS  LS 

Page 30: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-19

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation seedlings  or  cuttings  at  a  ration  designated  in  the  1999  USFWS 

Conservation Guidelines for the Valley Elderberry Longhorn Beetle. 

Elderberry plants with no  stems measuring one  inch or greater  in 

diameter at ground level may be removed with mitigation. 

 

These matters  are  addressed  in  the  U.S.  Army  Corps  of  Engineers  404 

Permit,  dated  January  12,  2009,  2005‐673  (See  Appendix  H),  which 

incorporates provisions of the July 1, 2008 U.S. Department of Interior Fish 

& Wildlife Service Biological Opinion. 

Impact 3.5-2: Implementation of the Project could Result in the Loss of the special status plant species Ewan’s Larkspur

Mitigation Measure 3.5‐2a 

The  Operator  shall  implement  an  education  program  for  all  on‐site 

personnel. Prior to commencement of operations on the site and thereafter 

on  an  annual  basis,  training  shall  include:    a)  how  to  identify  sensitive 

biological resources likely to be found on the site and b) how to implement 

appropriate  measures  to  protect  said  resources.    The  Operator  shall 

maintain a record of compliance with this mitigation measure and submit 

annually  a  record  of  compliance  to  the  Madera  County  Planning 

Department. 

 

Mitigation Measure 3.5‐2b 

The  Operator  shall  retain  a  qualified  botanist  to  map  and  quantify 

populations of special status plant species located within areas that would 

be disturbed during  the subsequent  five‐year period.   Surveys have been 

conducted during the appropriate season and three known populations of 

Ewan’s  larkspur  (two  adjacent  to  County  Road  209  and  one  located 

adjacent to the proposed mine access road) have been mapped.  Cover and 

density data shall be collected prior  to disturbance and these populations 

shall  be  transplanted  to  a  similar  habitat  in  the  proposed  Conservation 

Easement parcel  in  consultation with  the California Native Plant Society 

and  CDFG.    The  Operator  shall monitor  and  document  the  success  of 

transplantation for five years.   These data shall be  included  in the annual 

and five‐year monitoring reports, required in Mitigation Measures 3.5‐34a 

and b, to be submitted to the Madera County Planning Department.  

PS  LS 

Impact 3.5-3: Direct and Indirect Impacts to the Western Pond Turtle and other Listed Reptiles and Amphibians

Mitigation Measure 3.5‐3a 

A preconstruction survey for western pond turtle shall be conducted three 

days  prior  to  the  onset  of  construction  activities  in Hildreth Creek  and 

every subsequent day while activities occur in Hildreth Creek. The survey 

area shall encompass a 100‐foot radius of the area to be effected.  If juvenile 

or adult turtles are found within the survey area, the individuals should be 

PS  LS 

Page 31: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-20

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation moved at  least 500  feet downstream  in suitable habitat.    If a  turtle nest  is 

found within  the  survey  area,  construction  activities  shall not  take place 

within 30 meters (100 feet) of the nest until the turtles have hatched, or the 

eggs have been moved to an appropriate location.   Furthermore, one‐way 

barrier  fencing  shall be  constructed within  100  feet of Hildreth Creek  to 

prevent  turtles  from moving  into  the construction area  to nest, hibernate, 

or  aestivate,  while  allowing  turtles  already  in  the  construction  area  to 

move  back  to water.    Placement  of  the  fencing  shall  occur  during mid‐

summer  in  the  year  prior  to  construction  activities  being  initiated  if 

schedule allows (i.e., some activities such as construction of the new arch 

culvert and lengthening of the culvert 1.5 miles south of the mine entrance 

may occur during year 2006, precluding placement of  the  fencing during 

the prior summer. 

Impact 3.5-4: Direct and Indirect Impacts to the Golden Eagle and its Habitat Mitigation Measure 3.5‐4a 

Prior to the commencement of construction or quarry activities within 0.25 

mile of any cliffs or escarpments located on or adjacent to the Project site, 

the Applicant shall retain a qualified biologist  to conduct a raptor survey 

of potential nesting  sites.   Surveys  shall be conducted within  the nesting 

season  (January‐August)  and  no  more  than  30  days  prior  to 

commencement of activities.    If an active nest  is  found  to be present,  the 

Applicant  shall  confer  with  CDFG  to  establish  an  avoidance  and 

monitoring program. 

 

Mitigation Measure 3.5‐4b 

If any raptor nests are observed,  the Applicant shall maintain a 0.25 mile 

buffer  area  around  the  nest.    No  construction,  operation  of  heavy 

equipment, machinery, mining, or blasting shall take place within the 0.25 

mile buffer until the biologist has determined that all young have fledged, 

are capable of foraging independently, or the nest has been abandoned. 

PS  LS 

Impact 3.5-5: Direct and Indirect Impacts to the Red Tail Hawk and its Habitat None required.  LS  LS 

Impact 3.5-6: Direct and Indirect Impacts to the Merlin None required.  LS  LS 

Impact 3.5-7: Direct and Indirect Impacts to Protected Species of Nesting Birds Mitigation Measure 3.5‐7 

Tree  removal  shall  not  occur during  the  nesting  season  (March  through 

August).    If  tree  removal  is  planned  during  the  nesting  season  (March 

through August),  the Applicant shall hire a qualified biologist  to conduct 

preconstruction  surveys  for nesting and  feeding areas  raptors, migratory 

bird species, and other wildlife species no more than thirty (30) days prior 

to  construction  in  or  removal  of  areas  containing  Blue  or  Interior  Live 

Oaks.   The surveys shall be conducted during  the nesting season  (March 

through  August).    If  any  protected  species  are  observed,  the  qualified 

PS  LS 

Page 32: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-21

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation biologist, shall recommend a buffer area around the nest.  No construction, 

operation of heavy  equipment, machinery, mining, or blasting  shall  take 

place within  the buffer until  the biologist has determined  that  all young 

have fledged and are capable of foraging  independently.   The buffer area 

shall be delineated with orange construction fencing. 

Impact 3.5-8: Direct and Indirect Impacts to Protected Species of Migratory Birds See Mitigation Measure 3.5‐7.  PS  LS 

Impact 3.5-9: Direct or Indirect Impacts to Upland Habitat Areas Adjacent to Wetlands and Riparian Areas that are Critical to the Feeding and Nesting of Wildlife Species

See Mitigation Measure 3.5‐7 and Mitigation 3.3‐3.  PS  LS 

Impact 3.5-10: Direct or Indirect Impacts to Special-Status Plants not Observed Within the Project Site During the Biological Assessments

None required.  LS  LS 

Impact 3.5-11: Direct and Impact Impacts to “Waters of the U.S.” Located Within the Project Site Mitigation Measure 3.5‐11a 

The appropriate Clean Water Act section 404 permit shall be obtained from 

the ACOE  prior  to  the  discharge  of  any  dredged  or  fill material within 

jurisdictional wetlands or waters of the U.S.  The Project shall comply with 

any  compensatory mitigation  for  loss of wetlands and waters of  the U.S. 

required by the ACOE. 

 

These matters  are  addressed  in  the  U.S.  Army  Corps  of  Engineers  404 

Permit,  dated  January  12,  2009,  2005‐673,  under  its  Special  Condition  3  

(see Appendix H). 

 

Mitigation Measure 3.5‐11b 

Clean Water Act Section 401 Water Quality Certification shall be obtained 

from  the  Regional  Water  Quality  Control  Board  prior  to  Project 

construction. 

 

See  the  CA  Regional Water  Quality  Control  Board,  Section  401 Water 

Quality Certification, dated July 17, 2008 (see Appendix K). 

 

Mitigation Measure 3.5‐11c 

Notification of Streambed Alteration  shall be  submitted  to  the California 

Department  of  Fish  and  Game  and  a  Streambed  Alteration  Agreement 

shall be obtained prior to any modification of drainage channels. 

 

See  the CA Department  of  Fish & Game  Section  1602  Stream Alteration 

Agreement No. 2007‐0209‐R4, Hildreth Creek ‐ Madera County, dated June 

13, 2008  (see Appendix L). 

 

 

 

PS  LS 

Page 33: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-22

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation Mitigation Measure 3.5‐11d 

Construction activities  that will  impact drainages and other waters of  the 

U.S.  shall  be  conducted  during  the  dry  season  (typically  May  to 

November) to minimize erosion. 

 

Mitigation Measure 3.5‐11e 

Appropriate sediment control measures shall be in place prior to the onset 

of  Project  construction  and  shall  be  monitored  and  maintained  until 

construction activities have ceased.  Temporary stockpiling of excavated or 

imported material shall occur only in approved construction staging areas.  

Excess  excavated  soil  shall  be  used  on  site  or  disposed  of  at  a  regional 

landfill or other appropriate  facility.   Stockpiles  that are  to remain on  the 

site through the wet season shall be protected to prevent erosion (e.g. silt 

fences, straw bales). 

 

Stormwater runoff and erosion from overburden and aggregate stockpiles, 

quarrying areas, construction activities, and any other ground disturbing 

activities shall be controlled  through  the  implementation of a program of 

erosion  control  Best  Management  Practices  (BMPs)  and  engineered 

sediment  control  structures.   Erosion  control BMPs may  include, but  are 

not  limited  to,  the application of straw mulch; seeding with  fast growing 

grasses;  and  the  construction  of  berms,  silt  fences,  hay  bale  dikes, 

stormwater detention basins, and other energy dissipaters. 

 

Mitigation Measure 3.5‐11f 

The Applicant will create riparian protection zones, including the bed and 

bank of both low and high flow channels and associate riparian vegetation, 

surrounding Hildreth  creek  and  drainages within  the  Project  site.    The 

buffers,  as measured  from  the  top  of  the  bank  of unvegetated  channels, 

will be 100 feet in width and 50 feet in width as measured from the outer 

edge from canopy of riparian vegetation.  Impacts to riparian habitat shall 

also be mitigated on a 3‐to‐1 basis consistent with Madera County General 

Plan Policy.  (See Madera County General Plan policy 5.D.4.) 

 

Mitigation Measure 3.5‐11g 

If Mitigation Measure 3.5‐11f is not feasible (i.e., in areas where the Project 

encroaches within 100 feet of the creek bank), the Operator shall replace or 

restore any wetlands, streams or associated vegetation damaged as a result 

of  Project  activities.    The  Operator  shall  replace  or  restore  disturbed 

wetlands and streams as near to the Project area as feasible on no less than 

a  1.2‐to‐1  basis.    Future  Corps  permits  or  CDFG  Streambed  Alteration 

Agreements may require higher replacement ratios.  Prior to disturbance of 

any wetlands or streambeds, the Operator shall submit a restoration plan.  

The Plan shall be consistent with any  required Corps permits and CDFG 

Page 34: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-23

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation Streambed  Alteration  Agreements.    The  compensatory  wetlands/ 

streambeds  shall  be  constructed,  per  the  requirements  of  the  submitted 

Restoration Plan, as soon as possible, but no  later  than one year after  the 

disturbance  occurs,  unless  a  qualified  biologist  determines  that  this will 

not  be  feasible  and  proposes  an  alternative  timeframe  acceptable  to  the 

Director  of  the  Madera  County  Planning  Department.    Compensatory 

wetlands/streambeds shall be similar in scope and biological complexity to 

the  original  wetlands/streams.  The  design  and  construction  of  these 

wetlands shall be performed under the supervision of a qualified biologist 

or  wetlands  restoration  specialist.    Compensatory  wetlands  shall  be 

monitored by a qualified biologist or wetlands restoration specialist  for a 

period  of  up  to  five  years  or  until  it  is  determined  by  said  biologist  or 

restoration specialist that restoration is complete and self‐sustaining.   The 

Operator shall be responsible for all restoration and monitoring costs. (See 

Madera County General Plan policy 5.D.6.) 

Impact 3.5-12: Over The Projected 53-Year Life of the Project, it is Estimated 993 Trees will be Removed as a Result of Quarry and Construction Activities

Mitigation Measure 3.5‐12a 

Removal  of  oak  trees  shall  limited  to  the minimum  number  as  feasible, 

defined more specifically as those trees occurring within the direct impact 

area  of  the  Quarry,  plant  site,  and  roads  associated  with  the  mine 

construction and operation.   Trees outside of  the direct  impact zone shall 

be protected. 

 

Mitigation Measure 3.5‐12b 

To  protect  oak  trees  intended  to  remain  undisturbed  during  vegetation 

clearing,  a  4‐foot‐tall,  brightly  colored  (usually  orange  or  yellow), 

temporary  fence  shall be  installed  at  a distance of  1.5  times  the distance 

from the trunk to the outer extent of the canopy or drip line of the tree.  No 

encroachment  into  the  fenced  areas  shall  be permitted  and  fencing  shall 

remain in place until all vegetation‐clearing activities have ceased. 

 

Mitigation Measure 3.5‐12c 

Any  tree  roots  to be  severed  should be  the maximum distance  from  the 

trunk.  Any roots over one inch in diameter that are damaged as a result of 

construction activities  should be  traced back  and  cleanly  cut behind  any 

split, cracked, or damaged area. 

 

Mitigation Measure 3.5‐12d 

Oak  trees  to  be  removed  shall  be  replaced  according  to  an  oak  tree 

replacement  program  developed  by  a  qualified  International  Society  of 

Arboriculture Certified Arborist.  An oak tree replacement assessment and 

plan for the Madera Ranch Project is included as Appendix D of the FEIR, 

and  recommendations  developed  therein  shall  be  adhered  to  and  shall 

PS  LS 

Page 35: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-24

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation include the establishment (i.e. planting, monitoring, maintenance) of native 

oak trees in the proposed 132 acre Conservation Easement parcel discussed 

in Section 3.3 of the Draft EIR at a ratio of 2.7 to 1 of planted and preserved 

trees to trees removed as a result of Project activities. 

Impact 3.5-13: Quarry and Construction Activities will Disturb Cumulatively Approximately 130 Acres of Vegetation Over the 53-Year Life of the Project

None required.  LS  LS 

CULTURAL RESOURCES Impact 3.6-1: Disturbance of Subsurface Archaeological, Historic, or Cultural Resources Mitigation Measure 3.6‐1a 

The Applicant shall train field personnel in identification procedures, prior 

to  implementing  the  quarry  operation.    The  training materials  shall  be 

prepared by a professional archaeologist and shall provide a review of the 

natural and cultural history of  the Project area, archaeological sensitivity, 

most likely locations of buried cultural materials, and specific instructions 

on how to address such discoveries and what immediate actions to take in 

the event  that materials are,  in  fact, unearthed.    Instructional materials or 

artifacts  are  to  be  kept  on‐site  and  under direction  of  identified  specific 

individuals.    Part  of  the  annual  report  shall  identify  the  responsible 

individuals. 

 

Mitigation Measure 3.6‐1b 

If  buried  resources,  such  as  chipped  stone,  historic  debris,  building 

foundations, or human bone are inadvertently discovered during ground‐

disturbing activities, work should stop  in that area and within 100 feet of 

the  find until  a  qualified  archaeologist  can  assess  the  significance  of  the 

find  and,  if  necessary,  develop  appropriate  treatment  measures  in 

consultation with appropriate agencies. 

LS  LS 

Impact 3.6-2: The Project Could Disturb Human Remains Mitigation Measure 3.6‐2 

If  human  remains  are discovered during Project  construction, work will 

stop at the discovery location and any nearby area reasonably suspected to 

overlie adjacent to human remains (Public Resources Code, Section 7050.5).  

The Madera County coroner will be contacted to determine if the cause of 

death must be investigated. 

 

If the coroner determines that the remains are of Native American origin, it 

is necessary to comply with state laws relating to the disposition of Native 

American burials, which  fall within  the  jurisdiction of  the NAHC  (Public 

Resources Code, Section 5097).   The coroner will contact the NAHC.   The 

descendants or most likely descendants of the deceased will be contacted, 

and work will not resume until they have made a recommendation to the 

landowner or the person responsible for the excavation work for means of 

treating  and disposing  of, with  appropriate dignity,  the  human  remains 

LS  LS 

Page 36: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-25

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation and  any  associated  grave  goods,  as provided  in Public Resources Code, 

Section  5097.98.   Work  may  resume  if  NAHC  is  unable  to  identify  a 

descendant or the descendant failed to make a recommendation. 

Impact 3.6-3: The Project, in Conjunction with the Expected Future Buildout in Madera County, could Significantly Impact Historic, Archaeological, Paleontological, Geologic or Human Resources

None required.  LS  LS 

GEOLOGY AND SOILS Impact 3.7-1: Ground Rupture of a Known Earthquake Fault or Liquefaction None required.  LS  LS 

Impact 3.7-2: Ground Shaking None required.  LS  LS 

Impact 3.7-3: Erosion and the Loss of Topsoil See Mitigation Measures3.5‐11a through 3.5‐11g  PS  LS 

Impact 3.7-4: Landslide and Slope Stability Mitigation Measure 3.7‐4 

The purpose of this mitigation measure is to ensure that the Project will not 

create unstable slopes  that could adversely affect neighboring properties, 

reclamation  of  the  site,  or  endanger  quarry  employees. An  engineering 

geologist,  meeting  Madera  County  qualification  requirements,  shall  be 

retained,  at  the  Applicant’s  expense,  to  implement  a  slope  stability 

monitoring  and  testing  program.  This  program  shall  be  implemented 

concurrent with  the  initiation of Phase 2 quarrying.     Said geologist shall 

evaluate the stability of each quarry face, prior to the operator proceeding 

to  the next  face. Further quarrying below  the existing bench  shall not be 

allowed until evidence, meeting the satisfaction of the Planning Director, is 

submitted  that demonstrates  that  the proposed  final  slopes of 1:1 will be 

globally  stable.  If  the  evidence  is  inconclusive,  quarrying  shall  only 

proceed  in  a manner  that  allows  final  reclamation  slopes  of  an  overall 

slope angle not to exceed 2:1 (overall slope is the combined average slope 

of benches and faces). This mitigation measure shall remain in effect for the 

life  of  the Project  or until  the Planning Director,  based upon  substantial 

evidence, determines that additional monitoring is no longer warranted. 

PS  LS 

Impact 3.7-5: Expansive Soil None required.  LS  LS 

Impact 3.7-6: The Project, In Combination with Other Cumulative Projects, Could Result in Soil Erosion

See Mitigation Measures 3.5‐11a through 3.5‐11g  PS  LS 

Page 37: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-26

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation HAZARDS AND HAZARDOUS MATERIALS Impact 3.8-1: The Project Could Create a Significant Hazard to the Public or the Environment Through Reasonably Foreseeable Upset and Accident Conditions Involving the Release of Hazardous Materials into the Environment Mitigation Measure 3.8‐1a 

The  Applicant  will  use  above  ground  storage  tanks  that  have  been 

approved  by  the U.S. Environmental Protection  agency when  storing  all 

petroleum  products  and  other  regulated  substances.   The  above  ground 

tanks shall be double walled and meet all ballistic and flame impingement 

requirements  in CFC Article 79.   The containment structures shall not be 

equipped with any valves or drains. 

 

Mitigation Measure 3.8‐1b 

Project  site  equipment  and  servicing materials  shall  be maintained  in  a 

neat and orderly manner  to aid  in accounting  for and detecting potential 

sources  of  contamination.    Non‐functional  equipment,  scrap  metal, 

construction debris  (other  than material  intended  for use  in  the  recycling 

plant), used batteries and tires, and similar objects shall be removed from 

the  site  on  a  regular  basis  and  disposed  of  at  appropriately  licensed 

facilities.  Spare equipment such as heavy equipment parts, conveyor belts, 

tires  and  other  replacement  or  extra  equipment  pieces,  shall  be  stored 

indoors whenever possible  to  avoid  surface water  contamination.   Spare 

parts  containing  petroleum  products  (i.e.,  lubricants,  hydraulic  oil,  etc.) 

shall  be  stored  using  Best  Management  Practices  (BMP’s)  to  prevent 

contamination  of  soil  or  storm  water  runoff.  Storage  areas  shall  be 

inspected  by  the  Operator  monthly.  Any  petroleum  leaks  shall  be 

documented  and  cleaned  up.    Leaking  equipment  shall  be  repaired. 

Inspection and monitoring documentation shall be retained for a minimum 

of five years and be available to County staff during site inspections. 

 

Mitigation Measure 3.8‐1c 

An  impervious  concrete washout  area  shall  be  used  to  collect washout 

from haul  trucks. The silts and mud  from  the washout shall be  recycled. 

Only  the  designated washout  area  shall  be  used  for  this  purpose.  The 

washout  area  shall  be  constructed  in  such  a manner  that  storm water, 

beyond  the  immediate washout  area,  shall  not  flow  into  or  out  of  this 

facility. It shall be of adequate size to contain all washout material plus the 

maximum amount of  rain expected  to  fall  in a  three‐day period.   Trucks 

shall not track washout material beyond the impervious containment area. 

 

Mitigation Measure 3.8‐1d 

All  delivery,  maintenance,  and  repair  trucks  containing  petroleum 

products  will  be  required  to  comply  with  the  Department  of 

Transportations  regulations  for  transport  of  hazardous  materials.    All 

PS  LS 

Page 38: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-27

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation trucks  carrying petroleum products will be equipped with quick connect 

couplings and  automatic  shut‐off valves  to prevent  spills,  and will  carry 

appropriate absorbent materials to contain and recover spillage. 

 

Mitigation Measure 3.8‐1e 

A Hazardous Materials Business Plan (Business Plan) will be developed for 

the  Project  site  to  address  the  potential  hazards  to  the  public  and 

environment  associated  with  the  transport,  use  or  storage  of  these 

hazardous materials.   The Business Plan will be submitted  to  the Madera 

County  Environmental  Health  Division  and  Madera  County  Fire 

Department for approval. 

 

Business  identification  form  that  provides  information  of  the 

Applicant,  type  of  business,  and  contact  persons  for  the  Project 

site; 

A Chemical Inventory that lists the names, uses, forms, quantities, 

storage  locations,  and  physical  and  health  categories  of  the 

chemicals stored on‐site; and 

Emergency Response Plan and Procedures, including: 

‐ Notification procedures  in  the event of a  release of hazardous 

material  that  causes  a  present  or  potential  hazard  to  public 

health or the environment 

‐ Procedures  for  mitigation  the  release  or  potential  release  of 

hazardous  materials  to  minimize  the  harm  or  damage  to 

persons, property, or environment 

‐ Creation, training and implementation of evacuation plans and 

procedures 

‐ Detailed facility map. 

 

Mitigation Measure 3.8‐1f 

Spare equipment such as heavy equipment parts, conveyor belts, tires, and 

other replacement or extra equipment pieces will be kept within the plant 

area.   Parts  containing or  coated with petroleum products will be  stored 

using  Best  Management  Practices  to  prevent  soil  or  storm  water 

contamination.    All  used  oil  and  similar  petroleum  products  or  spent 

solvents  will  be  collected  and  transported  in  accordance  with  the 

applicable Madera County Department of Environmental Health Services, 

Department of Toxic Substances Control, Regional Water Quality Control 

Board and Integrated Waste Management Board regulations. 

 

Mitigation Measure 3.8‐1g 

Upon completion of the Project, all hazardous materials and above ground 

storage  tanks will be  removed and  the  site will be  cleaned of hazardous 

material as part of the Reclamation Plan. 

Page 39: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-28

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation Impact 3.8-2: The Project Create a Significant Hazard to the Public or the Environment Through the

Routine Transport, Use, or Disposal of Hazardous Materials See Mitigation Measures 3.8‐1(a‐e).  PS  LS 

Impact 3.8-3: The Project Could Emit Hazardous Emissions or Handle Hazardous or Acutely Hazardous Materials, Substances, or Waste Within One-Quarter Mile of an Existing or Proposed School

None required.  LS  LS 

Impact 3.8-4: The Project Could Impair Implementation of or Physically Interfere with an Adopted Emergency Response Plan or Emergency Evacuation Plan

Mitigation Measure 3.8‐4 

Prior  to  the  initiation  of mining  or  operational  activities,  the Applicant 

shall  contact  the  local  Madera  County  Sheriff,  who  serves  as  Madera 

County  Emergency  Services  Director,Fire  Department  regarding  an 

adopted  Emergency  Response  or  Emergency  Evacuation  plan.    The 

Applicant  shall  develop  a  site  specific  Emergency  Response  and 

Emergency Evacuation Plan that will be submitted to the Fire Department 

for review and approval. 

PS  LS 

Impact 3.8-5: The Project Could Expose People or Structures to a Significant Risk of Loss, Injury or Death Involving Wildland Fires, Including Where Wildlands are Adjacent to Urbanized Areas or Where Residences Are Intermixed With Wildlands

Mitigation Measure 3.8‐5a 

Maintain  around  and  adjacent  to  such  building  or  structure  a  firebreak 

made by removing and clearing away,  for a distance of not  less  than 100 

feet on each  side  thereof or  to  the property  line, whichever  is nearer, all 

flammable vegetation or other combustible growth.  This subdivision does 

not  apply  to  single  specimens of  trees, ornamental  shrubbery, or  similar 

plants which  are used  as ground  cover,  if  they do not  form  a means  of 

rapidly  transmitting  fire  from  the  native  growth  to  any  building  or 

structure. 

 

Mitigation Measure 3.8‐5b 

Maintain around and adjacent to any such building or structure additional 

fire  protection  or  firebreak  made  by  removing  all  brush,  flammable 

vegetation, or combustible growth which is located from 30 feet to 100 feet 

from  such  building  or  structure  or  to  the  property  line,  whichever  is 

nearer, as may be required by the director if he finds that, because of extra 

hazardous conditions, a firebreak of only 100 feet around such building or 

structure is not sufficient to provide reasonable fire safety.  Grass and other 

vegetation  located more  than 30  feet  from such building or structure and 

less than 18  inches  in height above the ground may be maintained where 

necessary to stabilize the soil and prevent erosion. 

 

 

 

PS  LS 

Page 40: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-29

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation Mitigation Measure 3.8‐5c 

Remove that portion of any tree which extends within 10 feet of the outlet 

of any chimney or stovepipe. 

 

Mitigation Measure 3.8‐5d 

Maintain any tree adjacent to or overhanging any building free of dead or 

dying wood. 

 

Mitigation Measure 3.8‐5e 

Maintain  the  roof of  any  structure  free of  leaves, needles, or other dead 

vegetative growth. 

 

Mitigation Measure 3.8‐5f 

Provide and maintain at all times a screen over the outlet of every chimney 

or  stovepipe  that  is  attached  to  any  fireplace,  stove, or other device  that 

burns  any  solid  or  liquid  fuel.    The  screen  shall  be  constructed  of 

nonflammable material with openings of not more  than one‐half  inch  in 

size. 

 

Mitigation Measure 3.8‐5g 

Except  as provided  in  Section  18930  of  the Health  and  Safety Code,  the 

director  may  adopt  regulations  exempting  structures  with  exteriors 

constructed entirely of nonflammable materials, or  conditioned upon  the 

contents  and  composition  of  same,  he  may  vary  the  requirements 

respecting the removing or clearing away of flammable vegetation or other 

combustible growth with respect to the area surrounding said structures. 

No such exemption or variance shall apply unless and until the occupant 

thereof, or  if  there be no occupant,  then  the owner  thereof,  files with  the 

department, in such form as the director shall prescribe, a written consent 

to the inspection of the interior and contents of such structure to ascertain 

whether the provisions hereof and the regulations adopted hereunder are 

complied with at all times. 

Impact 3.8-6: The Project Could Have a Cumulative Impact on Public Health and Safety, Hazardous Materials, and Hazardous Waste Management

None required.  LS  LS 

HYDROLOGY AND WATER QUALITY Impact 3.9-1: The Project Could Cause the Water Levels and Pumping Rates in Adjacent Private Wells

to Decline During the Operational Life of the Quarry None required.Mitigation Measure 3.9‐1a 

Monitoring  of  water  levels  will  be  conducted  by  the  Applicant  on  a 

semiannual basis for two three‐year periods during the operational  life of 

the Quarry.   The first three‐year period will occur at the beginning of the 

Project.   The second three‐year period will occur when the rate of Quarry 

dewatering exceeds the rate of water production from the wells.  Based on 

PSLS  LS 

Page 41: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-30

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation the aquifer test data previously measured at the site (Cleath & Associates, 

2001),  a  three‐year  period  should  be  sufficient  to  identify  any  potential 

effects on  the water  levels  in  surrounding wells  from Quarry operations.  

Semiannual monitoring of water  levels will occur  in  each of  the Madera 

Ranch  wells  and  in  private  wells  adjacent  to  the  Project  boundary  for 

which  the  owners  agree  to  participate  in  the  mitigation  monitoring 

program.  An impact will be considered to have occurred if the water level 

data  in  any  private  declines  to  a  level where  insufficient water  can  be 

produced  for  the  normal,  pre‐impact  uses  of  the  property  owner.    To 

demonstrate  an  impact,  the  water‐level  decline  must  be  shown  to  be 

related to quarry operations (i.e. groundwater pumping or pit dewaering) 

and  not  related  to  other  outside  influences  (e.g.  drought,  increased 

pumping  by  a  neighbor,  or  a  subsequent  project  in  the  area  that  also 

potentially  affects  groundwater  resources)  by  a  qualified  registered 

professional.  If an impact occurs and is demonstrated to be related to the 

Project,  then Madera Ranch,  Inc. will provide  the affected well owner or 

well owners with replacement water equivalent to the loss of production in 

the private well or wells. 

 

The owner or operator at the time the impact occurs may implement one or 

more of the following, as appropriate and at  its discretion, to provide the 

replacement supply: 

 

1. Rehabilitate or deepen the private well, and/or install a new pump, 

to restore the prior pumping rate; or 

2. Provide an incremental replacement of water equivalent to the 

amount of the reduced rate of pumping by the affected party, by 

providing a connection to the water system for the Project; or 

3. Provide a full replacement water supply to the affected party by 

providing a connection to the water system for the Project. 

 

Based on  the previously‐collected  aquifer  test data  (Cleath & Associates, 

2001), pumping  rates  in  the Madera Ranch wells may decline  some over 

time.   However,  adequate  volumes  of water will  be  available  from  the 

existing Madera  Ranch wells  and/or  from  future Quarry  dewatering  to 

replace  any  lost  production  from  adjacent  private wells.   Due  to water‐

quality  issues, however, the replacement water can only be used for non‐

consumptive uses, such as  landscape  irrigation, clothes and car washing, 

bathing  for  adults  and  similar  uses.   Water  for  consumptive  uses must 

come from the remaining production of the private well or, if inadequate, 

through Mitigation Measure 3.9‐1b, described below. 

 

 

Page 42: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-31

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation Mitigation Measure 3.9‐1b 

If  Mitigation  Measure  3.9‐1a  is  implemented,  and  any  remaining 

production  from  an  affected  private well  is  insufficient  for  consumptive 

uses, then Madera Ranch, Inc. shall provide the affected party, or parties, 

with bottled water or potable water from some other source that is verified 

to  meet  state  and  federal  drinking  water  standards  to  supply  the 

consumptive  use.    Consumptive  uses  are  considered  drinking,  food 

preparation and cooking, and bathing of  infants and young children  that 

may ingest water while bathing.   

Impact 3.9-2: The Project Could Cause the Water Levels and Pumping Rates in Adjacent Private Wells to Decline After the Operational Life of the Quarry

None required.Mitigation Measure 3.9‐2a 

After  the  completion  of  the  Quarry  operations,  the  Applicant  or  then‐

current Operator will conduct monitoring of water levels on a semiannual 

basis for a period of three years.  Based on the aquifer test data previously 

measured at the site (Cleath & Associates, 2001), a three‐year period should 

be  sufficient  to  identify  any  potential  effects  on  the  water  levels  in 

surrounding wells after Quarry operations have ceased.   The semiannual 

monitoring  of water  levels will  occur  in  any  remaining Madera  Ranch 

wells  and  in  adjacent  private  wells  for  which  the  owners  agree  to 

participate  in  the  mitigation  monitoring  program.    In  addition,  the 

Applicant  or  subsequent  owner will  provide  a mechanism  to  provide  a 

replacement  supply  of  water  to  a  private  well  owner  if  an  impact  is 

demonstrated to occur to any private well.   An impact will be considered 

to have occurred  if  the water  level data  in any private declines  to a  level 

where insufficient water can be produced for the normal, pre‐impact uses 

of the property owner.  To demonstrate an impact, the water‐level decline 

must be shown to be exclusively or primarily related to evaporation from 

the reclaimed Quarry lake and not related to other outside influences (e.g. 

drought, increased pumping by a neighbor, or a subsequent project in the 

area  that  also  potentially  affects  groundwater  resources)  by  a  qualified 

registered  professional.    If  an  impact  occurs  and  is  demonstrated  to  be 

related  to  evaporation  from  the  reclaimed  Quarry  lake,  then  Madera 

Ranch,  Inc.  or  any  subsequent property  owner will provide  the  affected 

well owner or well owners with replacement water equivalent to the  loss 

of  production  in  the  private  well  or  wells,  or  will  establish  a  fund 

accessible  to  the County  to provide  replacement water, using one of  the 

following measures, at the Owner’s or Counties discretion: 

 

1. Rehabilitate or deepen the private well, and/or install a new pump, to restore the prior pumping rate; or 

2. Provide an incremental replacement of water equivalent to the 

amount of the reduced rate of pumping by the affected party, by 

providing a connection to the water system for the Project; or 

PSLS  LS 

Page 43: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-32

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation 3. Provide a full replacement water supply to the affected party by 

providing a connection to the water system for the Project. 

 

Adequate  volumes  of  water  are  anticipated  to  be  available  from  any 

remaining Madera Ranch wells or  from  the  future reclaimed Quarry  lake 

to replace any lost production from adjacent private wells.  Due to water‐

quality  issues, however, the replacement water can only be used for non‐

consumptive uses, such as  landscape  irrigation, clothes and car washing, 

bathing  for  adults  and  similar  uses.   Water  for  consumptive  uses must 

come from the remaining production of the private well or, if inadequate, 

through Mitigation Measure 3.9‐2b, described below. 

 

Mitigation Measure 3.9‐2b 

The Applicant shall provide a mechanism such that, if Mitigation Measure 

3.9‐2a  is  implemented,  and  any  remaining  production  from  an  affected 

private well  is  insufficient  for  consumptive  uses,  then  the  affected well 

owner, or owners, will be provided with bottled water or potable water 

from some other source that is verified to meet state and federal drinking 

water  standards  to  supply  the  consumptive use.   Consumptive uses  are 

 

considered drinking, food preparation and cooking, and bathing of infants 

and young children that may ingest water while bathing.   

Impact 3.9-3: The Project Could Cause an Increase in Surface-Water Runoff That Could Cause an Increased Potential for Flooding in Areas Downstream of the Quarry During the Operational Life of the Quarry

None required. Mitigation Measure 3.9‐3a 

Any  increases can be mitigated by diverting a portion of  the runoff  from 

the Plant area  into  the Mine.   The diversion can be effected by placing a 

multiport  orifice  plate  in  the  excavated  channel  to meter  the  continuing 

flow  in  the  channel  to  stock pond.   An overflow weir  can  then be  set  to 

divert the excess flow rate in the channel down a pipeline to the Mine. 

LSPS  LS 

Impact 3.9-4: The Project Could Cause an Increase or Decrease in Surface-Water Runoff That Could Affect Areas Downstream of the Quarry After the Operational Life of the Quarry

None required.  LS  LS 

Impact 3.9-5: The Project Could Cause a Permanent Pond to be Created in the Mine Excavation Area after the Operational Life of the QuarryDegradation of Groundwater and/or Surface-Water Quality

Mitigation Measure 3.9‐5a 

The site is to be reclaimed using native vegetation along with a minimum 

of 1 foot of overburden and 4 inches of topsoil shall spread on all benches 

and  the  excavation  floor.   A  performance  standard  of  not more  than  22 

acre‐feet per year of  infiltration,  through water‐bearing  fractures, will be 

monitored by the County.As part of the Project approvals and permitting, 

the  Applicant  shall  be  required  by  the  Central  Valley  Regional Water 

PS 

LS 

LS 

Page 44: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-33

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation Quality Control Board to prepare a Stormwater Pollution Prevention Plan 

to  comply  with  Basin  Plan  limits  for  water  quality  and  discharge  of 

sediment and suspended solids.  Compliance with the requirements in the 

Stormwater Pollution Prevention Plan, along with Mitigation Measure 3.9‐

5b, will prevent any future degradation of surface‐water quality related to 

the  Project.    To  verify  compliance  with  this  mitigation  measure,  the 

operator will be required to conduct monitoring and sampling as required 

in the Stormwater Pollution Prevention Plan.  The monitoring results must 

be reported to the Regional Water Quality Control Board and the County. 

 

Mitigation Measure 3.9‐5b 

All  fuel and chemical storage areas and all equipment maintenance areas 

should  be  placed  on  bermed  concrete  surfaces.  If  the  bermed  concrete 

surfaces drain to a sump, the sump should be cleaned and the waste fluids 

handled  and  disposed  of  in  compliance  with  all  applicable  laws  and 

regulations.  If  the  bermed  concrete  surfaces  do  not  drain  to  a  sump, 

routine  cleaning  should  be  conducted  to  prevent  the  surface  from 

becoming  slippery.    The  cleaning  solutions  and  wash  water  should  be 

handled  in  the  same  manner  as  the  sump  fluids.    Verification  of 

compliance  with  this  mitigation  measure  will  occur  through  routine 

inspections by the County. 

Impact 3.9-6: The Project Could Cause Degradation of Groundwater and/or Surface-Water Quality Mitigation Measure 3.9‐6a 

As  part  of  the  Project  approvals  and  permitting,  the Applicant  shall  be 

required by  the Central Valley Regional Water Quality Control Board  to 

prepare a Stormwater Pollution Prevention Plan to comply with Basin Plan 

limits  for water quality and discharge of sediment and suspended solids.  

Compliance with the requirements in the Stormwater Pollution Prevention 

Plan,  along  with  Mitigation  Measure  3.9‐6b,  will  prevent  any  future 

degradation  of  surface‐water  quality  related  to  the  Project.    To  verify 

compliance with this mitigation measure, the operator will be required to 

conduct monitoring and sampling as required in the Stormwater Pollution 

Prevention Plan.  The monitoring results must be reported to the Regional 

Water Quality Control Board and the County. 

 

Mitigation Measure 3.9‐6b 

All  fuel and chemical storage areas and all equipment maintenance areas 

should  be  placed  on  bermed  concrete  surfaces.  If  the  bermed  concrete 

surfaces drain to a sump, the sump should be cleaned and the waste fluids 

handled  and  disposed  of  in  compliance  with  all  applicable  laws  and 

regulations.  If  the  bermed  concrete  surfaces  do  not  drain  to  a  sump, 

routine  cleaning  should  be  conducted  to  prevent  the  surface  from 

becoming  slippery.    The  cleaning  solutions  and  wash  water  should  be 

handled  in  the  same  manner  as  the  sump  fluids.    Verification  of 

PS  LS 

Page 45: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-34

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation compliance  with  this  mitigation  measure  will  occur  through  routine 

inspections by the County. 

LAND USE AND PLANNING Impact 3.10-1: The Project will not Physically Divide an Established Community None required.  LS  LS 

Impact 3.10-2: The Project may be Inconsistent with the Land Use Element of the Madera County General Plan

See Mitigation Measures 3.3‐3, 3.4‐2 and 3.4‐9 of Air Quality and 3.11‐3 of 

Noise and Vibration. 

PS  LS 

Impact 3.10-3: The Project may be Inconsistent with the Transportation and Circulation Element of the Madera County General Plan

See Mitigation Measures  3.12‐1  and  3.12‐2  of  the  Traffic  section  of  this 

Draft EIR. 

PS  LS 

Impact 3.10-4: The Project may be Inconsistent with the Public Facilities and Services Element of the Madera County General Plan

None required.  LS  LS 

Impact 3.10-5: The Project may be Inconsistent with the Cultural and Recreational Resources Element of the Madera County General Plan

See Mitigation Measure 3.6‐1 of the Cultural Resources section of this Draft 

EIR. 

PS  LS 

Impact 3.10-6: The Project may be Inconsistent with the Agricultural and Natural Resources Element of the Madera County General Plan

See Mitigation Measures 3.4‐2  through 3.4‐6 of  the Air Quality section of 

the Draft, Mitigation Measures 3.5‐11, 3.5‐12, 3.5‐13 of Biological Resources 

section of  this Draft EIR and Mitigation Measure 3.11‐3 of  the Noise and 

Vibration section of this Draft EIR. 

PS  LS 

Impact 3.10-7: The Project may be Inconsistent with the Health and Safety Element of the Madera County General Plan

See Mitigation Measure 3.7‐4 of Geology and Soils section of this Draft EIR.  PS  LS 

Impact 3.10-8: The Project may be Inconsistent with the Noise Element of the Madera County General Plan

Mitigation Measure 3.11‐3  SU  SU 

Impact 3.10-9: The Project may be Inconsistent with O’Neal Area Plan Goals and Policies Mitigation Measure 3.3‐3 of the Agricultural Resources section of this Draft 

EIR. 

PS  LS 

Impact 3.10-10: The Project may be Inconsistent with Certain Zoning Ordinance Regulations None required.  LS  LS 

Impact 3.10-11: The Project Could Result in Cumulative Growth Impacts None required.  LS  LS 

NOISE AND VIBRATION Impact 3.11-1: The Project Could Result in Excessive Noise fromNoise Impacts Associated with On-Site

Activities (Mining, Processing, Asphalt, and Load Out) None required.  LS  LS 

Page 46: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-35

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation Impact 3.11-2: The Project Could Result in Excessive Blasting Noise and VibrationNoise and Vibration

Impacts Associated with Blasting Mitigation Measure 3.11‐2 

The Operator shall hire a blasting consultant to develop a blasting program 

that provides for minimum off‐site noise and vibration  levels,  in addition 

to conducting blasting during a recurring mid‐day period. If blasting loads 

exceed  7,000  pounds  of ANFO,  or  the  equivalent,  a  blasting  consultant 

shall develop a blasting program which  results  in vibration  levels of  less 

than 0.1  inches per  second and noise  levels of 80 dBA Lmax or  less at  the 

nearest residences.   The plan shall be submitted to the County for review 

prior to commencement of blasting activities on the Project site. 

LSPS  LS 

Impact 3.11-3a: The Project Could Result in anNoise Impacts Due to Project-Related Increases in Existing Off-Site Traffic Noise Levels

Mitigation Measure 3.11‐3a 

Prior to off‐site sales of material, to the extent feasible, the Applicant shall 

implement adequate noise  reduction measures,  including but not  limited 

to  setbacks,  barriers,  vegetation,  sound  absorbing  materials,  and/or 

rubberized asphalt, to reduce potential noise impacts to the one residence 

identified adjacent to Road 209 between Highway 41 and the Project site to 

below the level of significance. 

There  is one  receptor, a  residence on  the Wagner Family Trust  (Wagner) 

property, which could be impacted by the Project.  In an effort to mitigate 

any  noise  impact  at  the  residence  to  a  less  than  significant  level,  the 

Applicant entered into a “Compensation and Grazing Agreement Waiving 

Potential Noise Impacts to Residents for Mining and Asphalt Project Truck 

Traffic, between Madera Quarry, Inc. and the Wagner Family Trust”, dated 

February 2009 (see Appendix F). 

SU 

 

SU 

 

Impact 3.11-3b: Noise Impacts Due to Project-Related Increases in Existing Off-Site Traffic Noise Levels None required.  LS  LS 

Impact 3.11-4a: Noise Impacts Due to Project-Related Increases in Cumulative Increase in Existing Off-Site Traffic Noise Levels

Mitigation Measure 3.11‐4a 

See Mitigation Measure 3.11‐3 

There  is one  receptor, a  residence on  the Wagner Family Trust  (Wagner) 

property, which could be impacted by the Project.  In an effort to mitigate 

any  noise  impact  at  the  residence  to  a  less  than  significant  level,  the 

Applicant entered into a “Compensation and Grazing Agreement Waiving 

Potential Noise Impacts to Residents for Mining and Asphalt Project Truck 

Traffic, between Madera Quarry, Inc. and the Wagner Family Trust”, dated 

February 2009 (see Appendix F). 

SU 

 

SU 

 

Impact 3.11-4b: Noise Impacts Due to Project-Related Increases in Cumulative Off-Site Traffic Noise Levels

None required.  LS  LS 

Page 47: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-36

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation TRAFFIC Impact 3.12-1: The Project Could Result in Increased Vehicle Trips or Traffic Congestion, Including

Substandard LOS Mitigation Measure 3.12‐1a 

Intersection  improvements  shall  be  constructed  by  the  Applicant  with 

oversight by Caltrans or by Caltrans  at  the Applicant’s  expense prior  to 

opening  day  at  the  intersection  of  State  Route  41  and  Road  209.    The 

required improvements shall include: 

 

a) Separate eastbound left‐turn and right‐turn lanes; 

b) A northbound left‐turn lane with a minimum of 280 feet of storage 

plus deceleration distance; 

c) A northbound receiving/acceleration lane for eastbound left turns, 

the  length  of  which  shall  be  determined  based  on  design‐level 

studies; and  

d) A  southbound  receiving/acceleration  lane  for  eastbound  right 

turns.   All  improvements  shall  be  designed  in  accordance with 

Caltrans  standards  and  will  require  a  Caltrans  encroachment 

permit. 

 

Mitigation Measure 3.12‐1b 

 

a) Readable signs shall be installed for trucks leaving the site stating 

the  truck  route  that  is  required  to  be  utilized  upon  exiting  the 

project site. 

b) If  the County  requires,  the Applicant has agreed  to pay  for signs 

located on public roads specifying the designated haul route. 

PS  LS 

Impact 3.12-2: The Project Could Result in Increased Vehicle Trips or Traffic Congestion During Reconstruction of Road 209

Mitigation Measure 3.12‐2 

Traffic  control  shall be  implemented by  the Applicant with oversight by 

the County of Madera at the Applicant’s expense during construction. 

 

a) Traffic  control  plans  conforming  to  the  most  recent  County  of 

Madera  and  Caltrans  standards  shall  be  implemented  during 

construction; 

b) Access  for  local  traffic  (residents)  shall be maintained at all  times.  

At least one lane of travel shall be maintained in each direction, or 

traffic  control  shall  provide  for  one  lane  of  travel  controlled  by 

flagmen or pilot car; 

c) Signs should be installed prior to construction informing drivers of 

the pending construction and possible closure dates; and 

d) Access for regional traffic (non‐local/non‐resident) shall be provided 

via alternate routes, including Roads 208, 400, and 406. 

PS  LS 

Page 48: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-37

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation Impact 3.12-3: The Project Could Result in Truck Trips on Roads That Are

Not Suitable For Heavy Truck Traffic    

Mitigation Measure 3.12‐3a 

The Applicant  shall  inform  and/or  post warning  signs  at  the  exit  of  the 

Project site that inform all transporters and delivery vehicles that Road 406 

and Road 208 shall not be utilized  to  transport any material  to and  from 

the proposed Project site. 

 

Mitigation Measure 3.12‐3b 

If the County requires, the Applicant has agreed to pay for signs located on 

public roads specifying the designated haul route. 

PS  LS 

Impact 3.12-34: The Project Contributes Traffic to Intersections and Road Segments That Will Require Upgrades With or Without the Project

Mitigation Measure 3.12‐34a 

Contribute  an  equitable  share  of  the  cost  of  construction  of  future 

improvements if requested by Caltrans or Madera County.  Equitable share 

percentages shall be calculated using the equation presented above and the 

traffic  volumes  presented  in  the  Figures  included  in  this  report.    Cost 

estimates  for  improvements  shall  be  provided  by  Caltrans  or  Madera 

County. Contribute an equitable share of the cost of construction of future 

improvements as required under the Fee Program (if applicable), which is 

attached  in  Appendix  N  to  the  DREIR.    If  the  Fee  Program  is  not 

applicable, equitable share percentages are presented  in the traffic  impact 

study  included  in Appendix D. Cost estimates  for  improvements shall be 

provided by Caltrans or Madera County. 

 

The Project will contribute traffic to cumulative significant impacts to road 

segments  that  will  require  equitable  fair  share  regarding  the  following 

mitigations: 

 

SR 41 between Road 209 and Road 406: widen to four lanes; 

SR 41 between SR 145 and Road 209: widen to four lanes; 

SR  41  between  Avenue  15  and  SR  145:  convert  to  four‐lane 

freeway; 

SR  41  between Avenue  12  and Avenue  15:  convert  to  four‐lane 

freeway; and 

SR 145 between SR 41 and Road 400: widen to four lanes. 

 

All of  these  improvements have been  identified  in  the County’s  recently 

adopted Fee Program (Appendix N, see Tables 1, 2, and 3).  The County is 

committed to ensuring that those improvements coincide with the Project’s 

anticipated contribution to traffic on these segments, to the extent feasible. 

 

PS  LSSU 

Page 49: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT Summary

 

RESOURCE DESIGN TECHNOLOGY, INC. S-38

Level of Significance

Impacts and Mitigation Measures Before

Mitigation After

Mitigation Mitigation Measure 3.12‐4b  

In  order  to mitigate  the  impacts  of  traffic,  County  and Applicant  have 

entered  into  the  Road  Construction,  Maintenance  and  Reimbursement 

Agreement, Madera County Contract No. 8511‐C‐2008  (see Appendix P).  

This  Agreement  obligates  MQI  to  pay  the  costs  of  reconstructing  and  

maintaining  209  (subject  to  the  right  of  partial  reimbursement  should 

County create an “Area of Benefit” whereby properties generating  traffic 

having a per‐vehicle certified gross vehicle weight of 80,000 lbs or greater, 

will  be  assessed  their  fair  share  of  costs).    In  addition  the  agreement 

obligates  MQI  to  pay  $0.05  per  ton  of  shipped  material  toward  road 

maintenance costs for roads other than 209.   

 

The  Agreement  fully  mitigates  the  impacts  to  reconstruct,  repair  and 

maintain 209.  However, as to any other roads impacted by the Project, as 

the County  is  required  to give  ‘primary consideration’  to  spending  these 

maintenance  funds on roads  in  the area, but  is not required  to do so,  the 

wear  and  tear  impact on  local  roads, other  than  209,  remains  significant 

and unavoidable. 

NEW LEGISLATIVE MANDATE Impact 4.0-1: Project Actions Could Conflict with Implementation of State Goals for Reducing GHG

Emissions and Thereby Have an Adverse Effect on Global Climate Change Mitigation Measures 

See Mitigation Measures 3.4‐3 and 3.5‐12d of  the DEIR and FEIR.   These 

measures are also provided in the Summary section of this DREIR. 

PS  LS 

Impact 4.0-2: Project Emissions, in Combination with Other Development in the County, Could Contribute to Greenhouse Gases

None required.  LS  LS 

Page 50: MADERA QUARRY PROJECT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.0 INTRODUCTION

Page 51: MADERA QUARRY PROJECT

 

 

 

 

 

 

 

 

 

 

1.0 INTRODUCTION  

 

 

1.1 EIR PURPOSE, USE, AND SCOPE  

This  Draft  Revised  Environmental  Impact  Report  (DREIR)  has  been  prepared  in 

accordance with  the California  Environmental Quality Act  (CEQA)  (Public Resource 

Code,  Section  21000,  et.  seq.)  and  the  State Guidelines  for  implementation  of CEQA 

(Title 14, California Code of Regulations, Section 15000,  et.  seq.).   This DREIR will be 

used  by Madera County  (County)  in  its  consideration  of  the Madera Quarry Project 

(Project)  as  proposed  by Madera  Quarry,  Inc.  (Applicant  or  Operator).    Except  as 

modified by this DREIR, this document incorporates the Draft EIR (DEIR) and Final EIR 

(FEIR), dated June 2005 and February 2006, respectively.   Digital versions of the DEIR 

and FEIR are attached  to  this DREIR and hard copies are available  for viewing at  the 

Madera County Planning Department at the following location: 

 

Madera County Planning Department 

2037 W. Cleveland Avenue, Mail Stop G  

Madera, California 93637 

(559) 675‐7821 

 

Another  unrelated  entity  named Madera Ranch  has  been  involved  in  litigation with 

Madera County (County).  Therefore, the Applicant changed its name and the name of 

the  Project  to  avoid  confusion with  the  other  entity.    The Madera Ranch  name was 

accidentally utilized in some of the Scoping materials prepared and circulated as part of 

the DREIR preparation process.   However,  the County and environmental  consulting 

firm  informed  the  public  of  the  mistaken  nomenclature  during  the  public  scoping 

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-1

Page 52: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 1.0 Introduction

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-2

meeting, which  is discussed  in greater detail  in Section 1.1.6, below.   The Applicant  is 

now called Madera Quarry Inc., and the Project name is Madera Quarry Project. 

 

1.1.1 Purpose and Use  

The purpose of an EIR is to provide objective planning and environmental information 

to  guide  and  assist decision makers,  lead  agency  staff,  responsible  agencies,  and  the 

public in their evaluation of the potential environmental effects that may result from the   

implementation  of  the  Project  and  in  the  evaluation  of  alternatives  and  mitigation 

measures  that may reduce or eliminate  those  impacts.   This DREIR,  together with  the 

previously  circulated  EIR:    (1) provide  a  detailed  project  description;  (2)  discuss  the 

existing  environmental  setting;  (3)  identify  and  evaluate  potential  environmental 

impacts  of  the  Project,  the  cumulative  effects  of  the  Project,  and  other  existing  or 

proposed  activities  in  the  vicinity;  (4)  provide  feasible  mitigation  measures  to 

substantially  lessen  or  avoid  environmental  impacts;  and  (5)  identify  various 

alternatives to the Project to substantially lessen or avoid environmental impacts. 

 

Madera  County  is  the  CEQA  Lead  Agency,  and  carries  primary  responsibility  for 

preparing  this  EIR.    The  County  is  also  responsible  for  the  implementation  of  the 

California Surface Mining and Reclamation Act (SMARA) and the approval of proposed 

projects in accordance with Section 19.01 of the Madera County Code.  The County will 

use this document in its consideration of the primary land use entitlements needed for 

implementation  of  the  Project.    Other  agencies  could  also  use  this  document  in 

consideration of various permits, as needed. 

 

1.1.2 Nature and Background of Project  

Madera  Quarry,  Inc.  proposes  to  develop  a  new  hard  rock  quarry  and  associated 

aggregate processing facilities in central Madera County.  The processing facilities will 

be  located  on  a  28‐acre  portion  of  one  of Madera  Quarry,  Inc’s  parcels,  while  the 

aggregate material will be mined from an approximately 77.8‐acre portion of the same 

parcel (these acreages are the net acres to be disturbed in the construction of the mine 

and processing  areas).   Table  2.0‐1 of  the Project Description of  the DEIR provides  a 

detailed description of the processing facilities.  The Project will be located on a 540‐acre 

parcel, being one of the four owned by Madera Quarry, Inc, which total approximately 

1,000 acres.  The entire property is currently primarily used for rangeland cattle grazing.  

The  Project  is  located  about  16 miles  northeast  of  the  City  of Madera  in  the  lower 

granitic  foothills of  the western slope of  the southern Sierra Nevada Mountains.   The 

Page 53: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 1.0 Introduction

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-3

topography  is  variable,  ranging  from  flat  and  gently  rolling  hills  to  steep,  boulder‐

strewn fields.  The area has some history of rock quarries, the most visible of which can 

be seen to the east of County Road 209 just south of the Project site. 

 

As proposed, the Project would result in the mining, processing, and off‐site transport 

of a maximum of 900,000 tons of aggregate material annually for up to 50 years.  Project 

support  facilities  associated  with  the  quarry  would  include  aggregate  processing 

equipment, a hot mix asphalt plant, an administration complex and various stockpiles, 

sediment ponds, etc.   A  two‐lane paved mine access road would be constructed  from 

the  processing  area  to  County  Road  209  (a  distance  of  about ¼ mile).    Substantial 

upgrading, reconstruction, and realignment of County Road 209 from the mine entrance 

south about 4.5 miles to the intersection of Highway 41 would also be a component of 

the  Project.    Further,  the  Applicant  will  construct  left‐turn,  acceleration,  and 

deceleration  lanes  at  the  intersection  of  County  Road  209  and  Highway  41.    The 

Applicant will perform  improvements on Highway 41 between County Road 209 and 

Highway  145  and  on  County  Road  209  from  the  Project  Site  to  the  intersection 

of County  Roads  209  and  406  as more  fully  discussed  in  Section  2.2.4  of  this Draft 

Revised Environmental Impact Report. 

 

1.1.3 CEQA and Litigation Process  

The initial application was submitted in October 2002.  The County conducted a Public 

Scoping Meeting on October 27, 2003.  The County then circulated the DEIR for public 

review  from  late  June  through early August 2005.   The FEIR  (consisting of  the DEIR, 

minor  revisions  thereto,  and  the Responses  to Comments) was prepared  in February 

2006.   After  a  series  of Planning Commission  and Board  of  Supervisor  hearings,  the 

County’s Board approved the Project and certified the FEIR as adequate. 

 

Opponents  to  the  Project  filed  a  Petition  for Writ  of  Mandate  and  Complaint  for 

Injunctive  and Declaratory Relief  regarding  the  adequacy  of  the  FEIR.    The County 

prevailed  in  the Madera County Superior Court.   However, on October  24, 2008,  the 

Court  of  Appeal  for  the  Fifth  Appellate  District  (Court  of  Appeal)  reversed  the 

judgment and remanded the matter to the Madera County Superior Court.   The Court 

of Appeal  concluded  that  there were deficiencies  in  the FEIR’s hydrology mitigation 

measures, traffic mitigation measures, cumulative noise impact evaluation, cumulative 

impact evaluation, and required that the County to consider whether it was obligated to 

provide  an  SB  610  Water  Supply  Assessment  (WSA)  to  the  extent  the  Project,  as 

Page 54: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 1.0 Introduction

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-4

mitigated, involved the construction and operation of a public water system.  A copy of 

the Court of Appeal’s opinion (Opinion) is provided in Appendix A‐1. 

The Court of Appeal upheld the County’s actions on the following matters: 

 

The  FEIR  was  not  required  to  assess  economic  impacts  on  neighboring 

landowners  due  to  the  potentially  significant  impact  on  the  water  levels  in 

private wells. 

Adequacy  of  the  EIR’s  analysis  of  the  impacts  on  biological  resources  and 

wildlife habitat due  to  an  alleged  incorrect methodology  relation  to California 

Tiger Salamander. 

Adequacy  of  the  EIR’s  analysis  of  impacts  on  air  quality  due  to  an  alleged 

incorrect methodology. 

Adequacy  of  the  EIR’s  analysis  of  impacts  on  aesthetics  due  to  an  alleged 

improper deferral of a mitigation relating to lighting and glare. 

Adequacy of the analysis of growth‐inducing impacts. 

Finding of general plan  consistency  regarding no  substantial adverse  effect on 

property values; and  

SMARA determinations. 

 

On  January  20,  2009,  Judge  Charles  A. Wieland  of  the  Superior  Court  for Madera 

County  issued  the  Judgment Granting Petition  for a Writ of Mandate  (Judgment).   A 

copy of the Judgment is provided in Appendix A‐2. The Judgment ordered the County:  

 

To vacate its approval of Conditional Use Permit Nos. 2002‐20 and 2006‐001; 

To vacate its certification of the Final EIR and to revise those portions of the EIR 

(including sections describing impacts to surface water and groundwater, noise, 

traffic, and cumulative impacts) which were found to be inadequate by the Court 

of Appeal, consistent with the Opinion; 

To determine whether SB 610 applies in the context of any mitigation measures 

which may be proposed for the Project in the Revised EIR; 

To  update  any  of  the  remaining  chapters  or  portions  of  the  EIR  as may  be 

necessary, using the criteria set forth in CEQA Guidelines Section 15162 (14 CCR 

Section 15162);  

To  recirculate  a  revised  draft  Environmental  Impact  Report  as  required  by 

CEQA, and to provide responses to comments within a revised Final EIR prior to 

re‐approving the Project; and 

Page 55: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 1.0 Introduction

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-5

To evaluate the Project’s consistency with the Madera County General Plan and 

zoning ordinance(s) prior to any re‐approval of the Project. 

 

Finally in the Judgment, the trial court: 

 

Upheld the County’s Williamson Act determinations; and   

Retained jurisdiction over the County’s proceedings. 

 

The Opinion and the Judgment shall collectively be referred to as the Judicial Decisions. 

 

1.1.4 Changes to the Project Subsequent to Prior EIR Resulting from the Applicant’s Consultants’ Studies Done in Response to the Judicial Decisions

 

Water  for  the  Project will  now  come  from  two wells, Well No.  1  and Well No.  10 

(constructed in 2008), and when available, from dewatering the excavation site.  To limit 

dewatering  to  the  inflow  of  22  acre‐feet  per  year,  fractures  in  the mine  area will  be 

grouted.   

 

In  response  to  the  Judicial  Decisions,  described  in  Section  1.1.3,  above,  substantial 

additional  hydrology  studies  have  been  completed.    These  included  a  groundwater 

study by Kenneth D. Schmidt and Associates (KDS) and a surface water report, by Blair, 

Church & Flynn  (BCF).    In addition,  the groundwater analysis was peer‐reviewed by 

Luhdorff & Scalmanini, Consulting Engineering (LS).   These studies took  into account 

actual  groundwater  pumping  information  from wells  on  the  Project  site,  as well  as 

information from monitored wells on‐site and off‐site.   

 

The DEIR and FEIR concluded that when the mine site was reclaimed, a permanent lake 

would be created in the prior excavation area.  Based upon the KDS and LS reports, this 

DREIR  concludes  that when  the mine  site  is  reclaimed,  no  permanent  lake will  be 

created  in  the  prior  excavation  area,  as  evapotranspiration  and  evaporation  will 

consume all surface and groundwater coming into the reclaimed excavation area.  Both 

during and after mining, surface water  (but not process water which will be  retained 

on‐site) coming across the plant area, will be directed to the mine area where it will be 

captured by a channel and directed to the existing stock pond. A diversion feature will 

be made part  of  this  bypass  channel  so  that  there will  be no  significant  increases  to 

downstream  run‐off  volume  of  surface water.    Figure  3.9‐3  shows  the  approximate 

location of  the Plant bypass  channel.   As before, no processed water, either  from  the 

plant or mine areas, will be discharged from the Project. 

Page 56: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 1.0 Introduction

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-6

While the mine reduces operations during the winter months, water may accumulate in 

the excavation site from winter rains.  In that event, when the mine increases operations 

in the spring, any standing water will be pumped to the adjoining stock pond, with any 

excess over historical flows being used to irrigate adjoining pasture land. 

 

On October  24, 2006, pursuant  to Board of Supervisor’s Resolution No. 2006‐225,  the 

County approved a cancellation of the Williamson Act contract on a 52.29‐acre portion 

of the Project site.   The balance of the Project site remains subject to a Williamson Act 

Contract, for which a Notice of Non‐Renewal was recorded on November 29, 2003, and 

therefore, on March 1, 2014, the balance of the property will no longer be encumbered 

by the Williamson Act contract. 

 

When  the Project was  first processed with  the County,  the Applicant’s engineers had 

provided an estimate of  the acreage  to be encompassed by  the mine and plant areas.  

The engineers  ‘squared off’ any areas  to be disturbed.   This resulted  in  the mine area 

and plant areas being  listed as 86 and 32 acres,  respectively.   The disturbed areas  for 

each have now been calculated to be 77.8 acres for the mine and 28 acres for the plant 

and administration site.  The project site had been listed as 108 acres (which includes 1.7 

acres  for  the on‐site access road).   However, construction and operation of  the Project 

will include the disturbance of 121 acres.   If 131, 86, and 35 acres are referenced in the 

original  EIR,  it  is  to  refer  to  the  gross  acreage  and  not  the  areas  permitted  to  be 

disturbed,  which  are  121,  77.8,  and  35  acres  (see  Figure  1.0‐1,  Current  Acreage 

Calculations). 

 

As  noted  in  Section  1.1.3,  the  original  project’s  approval was  vacated.    Actions  by 

various  agencies,  agreements  between  the  Applicant  and  private  parties  and 

governmental  agencies,  the  judicial  decisions  and  reports  of  consultants  have  been 

issued  all  of  which  affect  the  consideration  of  the  Project,  as  modified.    Those 

documents are referenced in Table 1.0‐1, Table of Appendices. 

 

See Section 1.1 for the location of hard copies of the appendices.  A CD containing all of 

the appendices is included with this DREIR.  

The Court of Appeal found deficiencies  in four general areas, hydrology,  traffic, noise 

and  cumulative  impacts.    As  to  hydrology,  the  court  found  the  3‐day  pump  tests 

described in the DEIR to be adequate.  It then found certain mitigation measures to be  

 

 

Page 57: MADERA QUARRY PROJECT
Page 58: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 1.0 Introduction

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-8

infeasible or ineffective.  The most significant deficiency in the FEIR, as identified in the 

Opinion, was in regard to hydrology.  The following summarizes what has occurred in 

response and modifications made as a result of any subsequent studies. 

 

First, in accordance with its existing monitoring program, the Applicant has monitored 

22  wells in the vicinity of the Project.  Eight of the monitored wells are located on the 

Project Site,1 while 12 wells are owned and operated by private parties, each of whom 

consented to the monitoring program.2  By undertaking 18‐, 16‐, and 35‐day pumping of 

Ranch Wells No. 1, 5 & 10  for aquifer  testing, and pumping Ranch Well No. 1  for 17 

months of irrigation, the Applicant was able to obtain significantly better data as to the 

effects of groundwater pumping than was previously available from the 3‐day aquifer 

pump tests undertaken by Cleath and Associates.   

 

The  results of  the KD study, which was peer‐reviewed by LS, demonstrate  that  there 

will be no adverse impacts to neighboring private wells. With the incorporation of three 

mitigation measures,  the  Project will  not  have  a  significant  environmental  effect  on 

groundwater or surface water.  The mitigations are to:  1) keep downsteam areas from 

being  adversely  affected  from    surface water  run‐off  by  limiting  the  run‐off  to  pre‐

project  volumes;  2) during  reclamation,  overburden,  topsoil,  and planting will  occur 

within the quarry to enhance evapotranspiration that will be undertaken to prevent the 

creation of a permanent lake within the quarry; and 3) manage water on‐site so that it 

does not become contaminated with processing and blasting chemicals (this mitigation 

is unchanged from the FEIR).   

 

Mitigation Measure 3.9‐2 of the FEIR called for the possible creation of a water system 

to serve one or more property owners.  The Court of Appeal determined that if a water 

system was  to  be  created,  the  Board would  need  to  decide whether  a  SB  610 water 

supply assessment  should be undertaken.   As  the Project no  longer  contemplates  the 

establishment  of  a  community water  system,  there  is  no  need  for  an  SB  610 Water 

Supply Assessment. 

 

 

1  Two  of  the wells  are  non‐operating without  any  pumps.   When  constructed  by Madera Quarry’s 

predecessor, they were mistakenly believed to be on the Madera Quarry property. 2  After 15 and 17 months of monitoring, two of the private parties withdrew their consent to have their 

wells monitored.

Page 59: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 1.0 Introduction

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-9

TABLE 1.0-1 TABLE OF APPENDICES

 No. Description A‐1  Fifth District Court of Appeal Opinion, Case No. F053661, Gray v. County of Madera 

A‐2  Judgment  Granting  Petition  for Writ  of  Mandate  on  Remand,  Madera  Co.  Case  No. 

SCV005567, Gray v. County of Madera 

B‐1   Notice of Preparation 

B‐2  Scoping letters 

C‐1  Technical Memorandum, Review of ʹHydrogeologic Conditions At and Near the Proposed 

Madera Quarry,ʹ Luhdorff & Scalmanini, Consulting Engineers, dated October 28, 2009 

C‐2  Hydrogeologic Conditions At and Near the Proposed Madera Quarry, Kenneth D. Schmidt 

and Associates, Groundwater Quality Consultants, Fresno, California, dated October 2009 

C‐3  Madera  Quarry  Surface Water  Hydrology  Report,  Blair,  Church  &  Flynn,  Consulting 

Engineers, dated October 2009 

C‐4  Wellco Drilling, Inc., Letter to Madera Quarry, Inc, dated September 23, 2009 

D  Traffic  Impact  Study  for  Proposed  Madera  Quarry,  Peters  Engineering  Group,  dated 

October 13, 2009 

E  Department of Conservation Letter to Madera County Assessorʹs Office, with Williamson 

Act Cancellation Valuation Agreement Attached, all dated August 28, 2008 

F  Compensation and Grazing Agreement Waiving Potential Noise Impacts to Residents for 

Mining and Asphalt Project Truck Traffic, between Madera Quarry, Inc. and the Wagner 

Family Trust, dated February 2009 

G  Conservation  Easement  Deed,  Madera  County  Contract  No.  8512‐C‐2008,  dated 

January 15, 2008 

H  U.S. Army Corps of Engineers Permit, dated  January 12, 2009, 2005‐673  (includes  July 1, 

2008 U.S. Department of Interior Fish & Wildlife Service Biological Opinion) 

I  U.S.  Department  of  Interior,  Fish  &  Wildlife  Service,  Comments  on  Avoidance 

Minimization and Compensation Measures, dated December 17, 2007 

J‐1  CA Office of Historic Preservation, Historic Properties Comment Letter to USACOE, dated 

November 13, 2008 

J‐2  Cultural  Resources  Inventory  and  Evaluation  Report  for  The  Madera  Ranch  Quarry 

Project, Madera County, California, Pacific Legacy, dated June 2008 

J‐3  Supplemental Cultural Resources Inventory and Evaluation Report for The Madera Ranch 

Quarry Project, Pacific Legacy, dated September 2008 

K  CA Regional Water Quality Control Board, Section 401 Water Quality Certification, dated 

July 17, 2008 

L  CA Department of Fish & Game Section 1602 Stream Alteration Agreement No. 2007‐0209‐

R4, Hildreth Creek ‐ Madera County, dated June 13, 2008 

M  Analysis of Greenhouse Gas Emissions, Madera Quarry, Inc., Madera County, California, 

October 1, 2009 

N  Madera County Road Impact Fee Program Update, November 2009 

O‐1  Acoustical Terminology 

O‐2  Continuously Measured Hourly Noise Levels 

Page 60: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 1.0 Introduction

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-10

No. Description O‐3  Madera Quarry Noise Source Data 

O‐4  FHWA‐RD‐77‐108 Highway Traffic Noise Prediction Model 

P  Road  Construction,  Maintenance  and  Reimbursement  Agreement,  Madera  County 

Contract No. 8511‐C‐2008,dated January 15, 2008  

Q  Traffic Mitigation Agreement Capital Deferment, Madera County Contract No.  8513‐C‐

2008,dated January 15, 2008 

 

 

1.1.5 County Approach to DREIR  

As  discussed  above  in  Section  1.1.3,  Judicial Decisions  determined  that  only  limited 

portions  of  the  Final  EIR  were  inadequate.    The  County  and  the  EIR  author  have 

accepted  the direction of  the Appellate Court, and  the subsequent Writ  issued by  the 

Trial  Court,  as  set  forth  in  the  Judicial  Decisions.    This  DREIR  will  address  the 

deficiencies outlined above, minor revisions in background conditions and components 

of  the  Project.    Based  on  a  review  of  the  previously  circulated  FEIR,  the  County 

determined  to evaluate  those  issues outlined  in  the  Judicial Decisions, any changes  to 

the Project which resulted from the studies undertaken to address the Judicial Decisions 

and  anything  mandated  by  changed  legislation,  such  as  the  Project’s  impacts  on 

greenhouse gas emissions. Other sections of the FEIR which were found to be adequate 

in the Judicial Decisions are anticipated to be largely left intact. 

  

On December 23, 2008, the County circulated a Notice of Preparation of a Draft Revised 

Environmental Impact and Notice of Scoping Meeting.  A scoping meeting was held on 

January 16, 2009 at 6:00 p.m. at the Coarsegold Community Center.  A brief summary of 

the NOP and Scoping Process is provided in Section 1.1.6, below. 

 

1.1.6 Notice of Preparation  

A Notice of Preparation (NOP) for the EIR was distributed to the State Clearinghouse, 

responsible  agencies,  interested  groups  and  individuals,  and  surrounding  property 

owners on December 23, 2008,  for a 30‐day comment period.   Copies of  the NOP and 

mailing list are included in Appendix B‐1, Notice of Preparation and Mailing List.  One‐

hundred and  thirty  letters were received  in response  to  the NOP and are  included as 

Appendix B‐2, Written NOP and Scoping Comments.   

 

Page 61: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 1.0 Introduction

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-11

The NOP advised: 

 

“The Court of Appeal concluded  that  there were deficiencies regarding specified 

EIR’s  hydrology  mitigation  measures,  traffic  mitigation  measures  cumulative 

noise impact evaluation, cumulative impact evaluation, and whether SB 610 was 

applicable to hydrology mitigation measures. 

 

A  summary of  the Final EIR’s  impact  evaluations and mitigation measures are 

provided  in  Table  S‐1,  Summary  of  Impacts  and  Mitigation  Measures 

Attachment  A,  hereto.    However,  based  on  the  Court  of  Appeal’s  decision 

discussed above, the nature and extent of impacts and mitigation will be updated 

consistent with  the decision  in  the revised EIR, and  therefore could be different 

than provided in Attachment A.” 

 

The  Court  of  Appeal  determined  that  many  of  the  sections  of  the  EIR  were  not 

defective.   It was expected that any comments would be  limited to areas noted by the 

Court of Appeal to be deficient  in the EIR, or matters of changed circumstance or  law 

(i.e.,  AB  32,  mandatory  greenhouse  gas  analysis).    This  DREIR  will  not  address 

comments  that address matters  for which  the  courts determined  either  the EIR  to be 

adequate and/or  the actions of  the Madera Board of Supervisors  to be proper  (at  the 

time  of  the  Scoping meeting,  the Amended  Judgment Granting  Petition  for Writ  of 

Mandate had not yet been  entered, but  it  incorporated  the directions of  the Court of 

Appeal). 

 

1.1.7 Public Scoping Meeting  

A Public Scoping Meeting was held at 6:00 p.m. on January 16, 2009 at the Coarsegold 

Community  Center  in  Coarsegold,  California.    The  EIR  Consultant  described  the 

Project.    County  staff  and  its  EIR  Consultant  then  solicited  public  comments  and 

concerns  to be  considered  in  the analysis  for  this EIR.   Thirty‐four people  signed  the 

attendance  list,  and  approximately  80  people  attended.    Written  comments  were 

accepted  from  governmental  agencies,  a  non‐profit  organization  and  various  private 

parties.    

 

1.1.8 DREIR Scope  

The  Judicial  Decisions  outlined  those matters  of  which  this  DREIR  would  need  to 

adequately  address  to  comply with CEQA  requirements.    Based  on  a  review  of  the 

Page 62: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 1.0 Introduction

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-12

previously  circulated FEIR,  the County determined  to  evaluate  the  issues outlined  in 

the Judicial Decisions as well as the Project’s impacts on greenhouse gas emissions. An 

overview of the scoping process completed for this Project is provided in Sections 1.1.6 

and 1.1.7. 

 

 This DREIR contains the following sections: 

 

Summary (substantially revised since the FEIR); 

Section 1.0:  Introduction (superseding 2006 DEIR); 

Section 2.0:   Revisions  to Project Description  in Response  to  Judicial Decisions, 

Entitlements,  and Contracts Subsequent  to  the FEIR  (amendment  to DEIR and 

FEIR); 

Section 3.1:   Revisions  to Hydrology and Water Quality Section  in Response  to 

Judicial Decisions (replaced previous version); 

Section  3.2:   Revisions  to Noise  and Vibration  Section  in Response  to  Judicial 

Decisions (replaced previous version); 

Section  3.3:    Revisions  to  Traffic  Section  in  Response  to  Judicial  Decisions 

(replaced previous version);  

Section 4.0:  New Legislative Mandate; and 

Section 5.0:  List of Preparers. 

 

1.1.9 Effects Found Not to be Significant  

As  required  by  CEQA,  this  DREIR  focuses  on  expected  significant  or  potentially 

significant  environmental  effects  (CEQA  Guidelines  Section  15143).    As  previously 

stated, a previous EIR was prepared  for  the Project  to  identify  issues  to be evaluated.  

The  Judicial Decisions  refined  the  list of environmental  issues  to be evaluated  in  this 

DREIR.   

 

Some of  the  impacts analyzed  in  this DREIR are considered  to be  less  than significant 

and  require  no  mitigation.    Other  impacts  (i.e.,  those  that  are  considered  to  be 

potentially  significant)  can  be  reduced  to  a  less  than  significant  level  with  the 

implementation of  the proposed mitigation measures.    Seven  impacts  are  considered 

significant and unavoidable.  All of the impacts analyzed in this DREIR, including those 

considered  to  be  less  than  significant,  are  summarized  in  Table  S‐1,  Summary  of 

Impacts and Mitigation Measures, in the Summary section of this document. 

 

Page 63: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 1.0 Introduction

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-13

1.1.10 Areas of Controversy  

CEQA  Guidelines  Section  15123(b)(2)  requires  a  discussion  of  areas  of  controversy 

known to the Lead Agency, including issues raised by agencies and the public.  While 

many of the  issues raised during the scoping process may be considered controversial 

to the public, the following are the primary areas of controversy for this Project: 

Aesthetics:   Impacts associated with  the visual quality and character of  the site 

and its surroundings were evaluated in the previous EIR.  The Judicial Decisions 

upheld  the  FEIR’s  evaluation  of  aesthetics  issues.    Further,  the  County  has 

carefully evaluated the comments made during the NOP and scoping process on 

the DREIR and has determined  that  the previous EIR adequately evaluates  the 

Project’s  impacts  regarding  aesthetics  issues.  No  changes  to  the  Project  are 

proposed that would alter the analysis or conclusions of the FEIR. 

 

Agricultural  Resources:    The  significance  of  potential  agricultural  resources 

impacts and appropriate mitigation measures were  reviewed  in  the FEIR.   The 

Judicial Decisions upheld  the FEIR’s  evaluation of agricultural  resource  issues.  

Further, the County has carefully evaluated the comments made during the NOP 

and scoping process on the DREIR and has determined that the DEIR and FEIR 

adequately evaluate the Project’s impacts regarding agricultural resource issues.  

No  changes  to  the  Project  are  proposed  that  would  alter  the  analysis  or 

conclusions of the FEIR. 

 

In  addition,  on  August  28,  2008,  the  California  Department  of  Conservation 

entered  into a Williamson Act Cancellation Agreement with  the Applicant and 

notified  Madera  County  of  the  Agreement  and  the  agreed  valuation  (see 

Appendix E). 

 

Also,  on  January  15,  2008,  a  Conservation  Easement Deed was  executed  and 

presented to the County of Madera as Madera County Contract No. 8512‐C‐2008 

(see Appendix G). 

 

Air Quality:   The  significance of potential air quality  impacts and appropriate 

mitigation measures were evaluated in the FEIR.  The Judicial Decisions upheld 

the  FEIR’s  evaluation  of  air  quality  issues.   Based  on  a desire  to  evaluate  the 

Project’s  impacts  to  greenhouse  gas  emissions,  the  County  has  decided  to 

prepare  a new  section  to  address AB  32/SB  375,  containing  a Greenhouse Gas 

Page 64: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 1.0 Introduction

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-14

CEQA  evaluation.    Section  4.0,  New  Legislative  Mandate  includes  the 

Greenhouse Gas analysis as part of this DREIR. 

 

Biological Resources:   The significance of potential biological resources impacts 

and appropriate mitigation measures were reviewed in the DEIR and FEIR.  The 

Judicial Decisions upheld the FEIR’s evaluation of biological resource issues.  No 

changes to the Project are proposed that would alter the analysis or conclusions 

of the FEIR. 

 

Further, the County has carefully evaluated the comments made during the NOP 

and scoping process on the DREIR and has determined that the FEIR adequately 

evaluates the Project’s impacts regarding biological resource issues.    

 

As  the Project affected Waters of  the United States,  it was  required  to obtain a 

Section 404 permit from the US Army Corps of Engineers, and as a condition of 

issuance,  the US  Fish  and Wildlife  Service  issued  a  biological  opinion  on  the 

Project.  On January 12, 2009, the US Army Corps of Engineers issued its Section 

404 permit SPK‐2005‐673.  

 

On December 17, 2007,  the U.S. Dept. of  the  Interior, Fish and Wildlife Service 

issued  its  Biological  Opinion  regarding  Avoidances,  Minimization,  and 

Compensation Measures for Madera Ranch Quarry Project (see Appendix I). 

 

Cultural  Resources:    The  FEIR  performed  an  extensive  cultural  resource  site 

review at two sites affected by the Project.  Potential impacts to these sites were 

evaluated  in  the previous DEIR  and  FEIR.   The  Judicial Decisions upheld  the 

FEIR’s  evaluation  of  cultural  resource  issues.   No  changes  to  the  Project  are 

proposed that would alter the analysis or conclusions of the FEIR.   Further, the 

County  has  carefully  evaluated  the  comments  made  during  the  NOP  and 

scoping  process  on  the DREIR  and  has  determined  that  the  FEIR  adequately 

evaluates the Project’s impacts regarding cultural resource issues.    

 

However, to obtain the Section 404 permit from the USACOE, an approval of a 

cultural  resources  analysis was  required  from  the  State  of California Office  of 

Historic Preservation, which issued its approval letter on November 13, 2008 (see 

Appendix J‐1). 

 

Page 65: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 1.0 Introduction

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-15

The  reports  are  a Cultural Resources  Inventory  and Evaluation Report  for  the 

Madera Ranch Quarry Project, and a  supplemental  report,  issued  in  June 2008 

and September 2008, respectively (see Appendices J‐2 and J‐3).   

 

Geology  and  Soils:    Impacts  and  subsequent mitigation measures  regarding 

geology and  soils were  evaluated  in  the FEIR.   The Project opponents did not 

challenge  issues  related  to  geology  and  soils  issues.    Further,  the County  has 

carefully evaluated the comments made during the NOP and scoping process on 

DREIR  and  has  determined  that  the  FEIR  adequately  evaluates  the  Project’s 

impacts  regarding  geology  and  soil  issues.    No  changes  to  the  Project  are 

proposed that would alter the analysis or conclusions of the FEIR. 

 

Hazards  and Hazardous Material:    The  significance  of  potential  impacts  and 

appropriate mitigation measures  for  hazardous  and  hazardous materials were 

evaluated in the FEIR. The Project opponents did not challenge issues related to 

hazards  and  hazardous  materials  issues.    Further,  the  County  has  carefully 

evaluated  the  comments made  during  the  NOP  and  scoping  process  on  the 

DREIR  and  has  determined  that  the  FEIR  adequately  evaluates  the  Project’s 

impacts regarding hazards and hazardous materials issues. 

 

However, regarding Mitigation Measure 3.8‐4, by letter of December 29, 2008, the 

Madera  County  Fire  Department  noted  that  the  County  Emergency  Services 

Director should have been noted in place of the Fire Department.   Accordingly, 

this mitigation measure will be modified to read as follows: 

 

Mitigation Measure 3.8‐4 

Prior  to  the  initiation  of mining  or  operational  activities,  the Applicant  shall 

contact  the Madera County Sheriff, who  serves  as Madera County Emergency 

Services  Director,  regarding  an  adopted  Emergency  Response  or  Emergency 

Evacuation plan.  The Applicant shall develop a site specific Emergency Response 

and Emergency Evacuation Plan  that will be submitted  to  the Fire Department 

for review and approval. 

 

Hydrology  and Water Quality:    To  address  the matters  noted  in  the  Judicial 

Decisions,  substantial  additional  testing  and  analysis was  undertaken  by  the 

Applicant.   The revised Hydrological analysis contained in Appendices C‐1, C‐2 

Page 66: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 1.0 Introduction

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-16

and C‐3 is contained in Section 3.1, Revisions to Hydrology and Water Quality in 

Response to Judicial Decisions. 

 

When the Project was initially approved, one of the mitigations provided for the 

establishment  of  a water  system  to  supply water  from  the  Project  to  affected 

neighboring properties.  Through the litigation, petitioners asserted both that the 

Project  itself and the potential construction of a public water system to provide 

replacement water to neighboring properties necessitated the preparation of a SB 

610  Water  Supply  Assessment.    The  Court  of  Appeal  rejected  the  former 

argument, noting:   

 

“Finally,  appellants  contend  that  the  County  violated  Water  Code, 

sections  10910‐10914,  otherwise  known  as  Senate  Bill  No.  610  (“SB 

610”) by failing to prepare a water supply assessment for the Project. SB 

610, however, requires a water supply assessment only if a “public water 

system” is impacted by the Project. A “public water system” is defined to 

mean “a system  for the provision of piped water to the public  for human 

consumption  that has 3000 or more  service connections.”  (Wat. Code, § 

10912, subd. (c).) Here, the water that will be used for the mine is not part of a public water system.

 

As  to  the argument  that  the potential  replacement public water  supply  system 

would trigger the requirements of SB 610, the Court concluded: 

 

“Appellants also contend that the amendment to Mitigation Measure 3.9‐

1b, which  could  require  the  construction  of  a water  system  for  use  by 

affected neighbors would require a water supply assessment under SB 610.  

We  agree…  Thus,  the  County must  do  a  water  supply  assessment  or 

provide substantial evidence to explain why it did not have to comply with 

SB 610.”(App. A‐1, pp.36‐37) 

 

As  a  result  of  the  expanded  analysis  contained  in  the  Subsequent Hydrology 

Reports, this DREIR concludes that impacts to neighboring wells will be less than 

significant.    Therefore,  no  water  system  is  proposed,  and  no  water  supply 

assessment need be prepared. 

 

Land Use:   Impacts associated with the land use were evaluated in the previous 

DEIR and FEIR.  The Judicial Decisions upheld the FEIR’s evaluation of land use 

Page 67: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 1.0 Introduction

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-17

issues.  Further, the County has carefully evaluated the comments made during 

the  NOP  and  scoping  process  on  the  DREIR  and  has  determined  that  the 

previous  EIR  adequately  evaluates  the  Project’s  impacts  regarding  land  use 

issues. No changes  to  the Project are proposed  that would alter  the analysis or 

conclusions of the FEIR.   

 

While upholding the CEQA evaluation regarding land use issues, the Judgment 

required  the  County  to  evaluate  the  Project’s  consistency  with  the  Madera 

County General Plan  and  zoning  ordinance(s) prior  to  any  re‐approval  of  the 

Project.    The  County  will  perform  this  evaluation  and  include  in  its  staff 

presentation to the Planning Commission and Board of Supervisors.  

Noise:  Section 3.2, Revisions to Noise Section in Response to Judicial Decisions, 

is  a  part  of  this  DREIR.    The  Project’s  impacts  were  evaluated  in  terms  of 

potential  impacts  from  on‐site  mining  and  processing  activities  and  off‐site 

traffic.    The  Project  will  comply  with  County  on‐site  noise  and  vibrations 

standards.   However,  there will be a noise  impact  to one  residence on County 

Road  209, which  is presently owned by  the Wagner Trust.   The Owner of  the 

subject property has  entered  into  a  recorded  agreement with  the Applicant  in 

which the Owner has been compensated in connection with the noise impacts of 

the Project.   However, it is not possible to state with certainty that the property 

owner will use the funds to mitigate any noise impacts.  To the extent the owner 

of  the  residence  located  approximately  300  feet  from  the  centerline  of CR  209 

chooses not to spend the money for the purposes for which it was intended, the 

impact would remain significant and unavoidable. 

 

There are no other potential significant noise  impacts and  reference  is made  to 

Section 3.2 for a full discussion of all noise issues. 

 

Traffic:    On  October  13,  2009,  Peters  Engineering  Group  prepared  a  Traffic 

Impact  Study  (see Appendix D).   The  results  of  the  study  are  incorporated  in 

Section 3.3, Revisions  to Traffic Section  in Response  to  Judicial Decisions.   The 

study notes impacts in the future from increased traffic for which there might not 

be  feasible  mitigation  measures.    If  not  mitigated,  those  impacts  will  be 

significant and unavoidable.   These  include  the possibility  that  funds  collected 

from  the  Project  for  its  fair  share  of  any  future  improvements might  not  be 

expended.    In  addition,  there  will  be  a  lowering  of  Level  of  Service  to  an 

unacceptable level at intersections where traffic warrants will not be met to allow 

Page 68: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 1.0 Introduction

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-18

for  signalization.    The  County  recently  adopted  the  “Madera  County,  Road 

Impact Fee Program Update, November 2009”.  A full discussion of these matters 

is provided in Section 3.3. 

 

On  January  15,  2008, Applicant  and County  entered  into  two  agreements  (see 

Appendix  P  and  Q),  being  the  1)  Road  Construction,  Maintenance  and 

Reimbursement Agreement (Construction Agreement), and 2) Traffic Mitigation 

Agreement  Capital  Deferment  (Mitigation  Agreement),  respectively.    The 

Construction Agreement pertains to the obligations to pay for the reconstruction 

and maintenance of County Road 209, and  the payment of a $0.05 per  ton  fee 

with the proceeds being used by the County for the maintenance of roads other 

than  209.    The  Mitigation  Agreement  pertains  to  the  construction  of 

improvement on State Hwy. 41 south of its intersection with County Road 209. 

 

Mandatory Findings of Significance:  The Project was evaluated in terms of the 

mandatory findings of significance, particularly with regard to  impacts that are 

individually  limited, but potentially “cumulatively considerable”, as defined by 

CEQA. 

 

1.1.11 Disposition of Issues Raised and Remaining Areas of Controversy  

After applying CEQA standards of significance  to  the entire range of adverse  impacts 

that  would  result  from  implementation  of  the  Project,  seven  significant  and 

unavoidable  impacts  have  been  identified  through  systematic  analysis  of  potential 

Project effects.  These impacts are related to air quality, noise, land use, and traffic. 

 

1.1.12 Document Availability The basic Project CUP Application (No. 2002‐20) and technical documents that were, in 

part, used in the preparation for this DEIR and FEIR were submitted by the Applicant 

to the County in October 2002, January 2003, and June 2004.  In 2009, the Applicant also 

submitted  technical  reports  that were prepared  in  response  to  the  Judicial Decisions 

Additionally,  more  detailed  design  information  has  been  recently  submitted.    The 

Application and  supporting documents, as well as  the  June 2005 DEIR and February 

2006 FEIR, are on file and available for public review at the following location: 

Page 69: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 1.0 Introduction

 

RESOURCE DESIGN TECHNOLOGY, INC. 1.0-19

Madera County  

Planning Department 

2037 W. Cleveland Avenue, Mail Stop G 

Madera, California  93637 

 

1.2 DREIR PUBLIC REVIEW  

This DREIR  is distributed  for a 45‐day period of  review and  comment by  the public, 

responsible  agencies,  organizations,  and  other  interested  parties.    All  comments  or 

questions about the EIR should be addressed to: 

 

Matthew Treber 

Madera County Planning Department 

2037 W. Cleveland Avenue, Mail Stop G  

Madera, California 93637 

(559) 675‐7821 

 

Comments may also be received by e‐mail at:  matthew.treber@madera‐county.com. 

 

Following  the public  review period,  comments  and written  responses  on  the DREIR 

will be used to prepare a Final Revised EIR and made available for public review prior 

to consideration of the Project by the County.  One or more public hearings will be held 

by the County prior to certification of the Final EIR. 

 

Page 70: MADERA QUARRY PROJECT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  

 

 

 

 

 

 

 

 

 

2.0 REVISIONS TO PROJECT DESCRIPTION IN RESPONSE TO JUDICIAL DECISIONS, ENTITLEMENTS, AND CONTRACTS SUBSEQUENT TO THE FEIR

Page 71: MADERA QUARRY PROJECT

 

 

 

 

 

 

 

 

 

 

2.0 REVISIONS TO PROJECT DESCRIPTION IN RESPONSE TO JUDICIAL DECISIONS, ENTITLEMENTS, AND CONTRACTS SUBSEQUENT TO THE FEIR

 

 

 

2.1 INTRODUCTION  

Section 2.0 of  the Draft EIR  (DEIR)  contains a detailed project description.   The basic 

components of the Project have not changed in any significant manner.  However, as a 

result  of  the Opinion  of  the Court  of Appeals  and  Judgment  of  the  Superior Court 

(Judicial Decisions),  additional  technical  reports  have  been  prepared  in  the  areas  of 

hydrology, traffic, and noise.  The noise technical information appears in Section 3.2 and 

its appendices.  The hydrology and traffic technical reports are included as Appendices 

C‐1, C‐2, C‐3, and D.  Due to the implementation of AB 32 and SB 375, Section 4.0, New 

Legislative  Mandates,  has  been  added.    This  new  section  contains  an  analysis  of 

greenhouse gas (GHG) pertaining to the Project.  The consultant’s report is included as 

Appendix M.   

 

In  addition,  since  the  original  approval  of  the  Project  and  before  the  entry  of  the 

Judgment, additional entitlements and contractual rights all to facilitate the Project have 

been obtained.  They are referenced below in Table 2.0‐1, Contracts and Entitlements. 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 2.0-1

Page 72: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 2.0 Project Description

This  section will provide  information on  those minor  changes  to  the Project and will 

enumerate the above‐referenced entitlements and agreements, which are reproduced in 

the  appendix  to  the  Draft  Revised  Environmental  Impact  Report  (DREIR).    For  a 

complete  description  of  the  Project,  this  section  should  be  read  in  conjunction with 

Section 2.0 of the June 2005 DEIR. 

 

2.2 MINOR CHANGES TO PROJECT AS DEFINED IN DEIR  

2.2.1 Affected Acreage Recalculated  

When  the  Project  was  first  processed  with  the  County,  the  Applicant’s  engineers 

provided an estimate of  the acreage  to be encompassed by  the mine and plant areas.  

The engineers  ‘squared off’ any areas  to be disturbed.   This resulted  in  the mine area 

and plant areas being  listed as 86 and 35 acres,  respectively.   The disturbed areas  for 

each area have now been more precisely calculated  to be 77.8 acres  for  the  top of  the 

mine, and 28 acres for the plant and administration site.  The Project site had previously 

been  listed  as  131  acres.    However,  construction  and  operation  of  the  Project  will 

include  the  disturbance  of  121  acres.    If  131,  86,  and  35  acres  are  referenced  in  the 

original  EIR,  it  is  to  refer  to  the  gross  acreage  and  not  the  areas  permitted  to  be 

disturbed, which are 121, 77.8, and 28 acres (see Figure 1.0‐1). 

 

2.2.2 Modifications Resulting from Hydrology, Groundwater, and Surface Water Studies

 

The Final EIR (FEIR) presumed, on  the basis of  limited 3‐day aquifer pump tests, that 

there  was  a  possibility  of  a  potential  significant  impact  on  the  production  of 

neighboring wells.  To mitigate what could be a significant decline in water, mitigation 

measures were  adopted.    For  various  reasons  set  forth  in  the Opinion,  the Court  of 

Appeal  rejected  these measures.    Therefore,  additional  extensive  hydrology  studies 

were commissioned.   

 

These  additional  hydrology  studies  included  a  groundwater  study  by  Kenneth  D. 

Schmidt  and Associates  (KSD)  and  a  surface water  report  by Blair, Church &  Flynn 

(BCF).    In  addition,  the  ground  water  analysis  was  peer‐reviewed  by  Luhdorf  & 

Scalmanini, Consulting Engineering (LS) (see Section 3.2 and its referenced appendices 

for a full discussion.) 

     

 

RESOURCE DESIGN TECHNOLOGY, INC. 2.0-2

Page 73: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 2.0 Project Description

As a result of these studies, the following modifications have been added:  

 

1. Water from the Project will come from Ranch Wells Nos. 1 and 10 (constructed in 

2008), rather than from Nos. 1 and 5.  As before, when available, water will come 

from dewatering from the quarry; 

2. Fractures within the quarry will be grouted, as needed, to limit water infiltration 

to 22 acre‐feet per year; and 

3. A small channel will be constructed on a north bench to capture rain runoff and 

direct it to the existing stock pond. 

 

In addition, there will be no permanent lake formed after mining activities cease.  As a 

result of these modifications and more detailed analysis, the KDS, LS, and BCF reports 

concluded that will be no adverse impact to the production of neighboring wells.   

 

However, the FEIR concluded that the development and operation of the Project could 

have a potentially  significant effect on neighboring domestic wells and  the  supply of 

available water to neighboring agricultural properties.    The FEIR then listed a series of 

mitigation measures  (see DEIR p.  3.9‐36),  including  improving  (deepening)  the well, 

replacing  equipment,  and,  if  necessary,  providing  a  replacement water  supply  from 

project wells or another source of water.  Both the methodology of the FEIR’s hydrology 

analysis  and  the  feasibility  and  effectiveness  of  the  mitigation  measures  were 

challenged during the public hearing process and in the ensuing litigation.     

 

This DREIR contains an entirely new and expanded groundwater hydrology evaluation 

(see  Section  3.1).   This  analysis  concludes  that  the  Project  will  have  less  than  a 

significant  affect  on  neighboring  domestic wells,  on  both  an  individual  project  and 

cumulative level. 

 

Where  it  is  properly  determined  that  there  are  less  than  significant  impacts  from  a 

project, CEQA does not require the identification or imposition of mitigation measures.  

Nonetheless,  due  to  the  concerns  of  neighboring  property  owners,  to  determine 

whether impacts to neighboring domestic wells and water supplies occur due to Project 

operations,  the Applicant  suggests  that  the County  include  the  following use permit 

condition: 

 

Adopt a well monitoring program  similar  to  that proposed by KDS at pp.106‐

108.    In general,  this would be a  continuation of  the well monitoring program 

that has been  in effect during  the  testing by KDS.     This  includes continuing  to 

 

RESOURCE DESIGN TECHNOLOGY, INC. 2.0-3

Page 74: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 2.0 Project Description

 

RESOURCE DESIGN TECHNOLOGY, INC. 2.0-4

use flow meters on the 10 private wells previously monitored, as well as adding 

transducers to 4 of these wells.   Pumping rates, pumpage and well water levels 

will be monitored.   Consent of the private owners would be required.   Costs of 

the monitoring shall be borne by the Operator.  The frequency of the monitoring 

would  be  reconsidered  after  two  years  and  be  subject  to modification  by  the 

County Director of Resource Management.   

 

An  impact  will  be  considered  to  be  deemed  imminent  if  there  has  been,  or 

threatens to be, a substantial reduction in the water level or well production for 

the normal, pre‐Project uses of the property owner.  To demonstrate a substantial 

reduction, the water‐level decline must be shown, or threatened, to be related to 

quarry  operations  and  not  related  to  other  outside  influences  (e.g.  drought, 

increased pumping by a neighbor, or a subsequent project  in  the area  that also 

potentially affects groundwater resources) by a qualified registered professional.  

If a substantial reduction occurs, or appears imminent, and is demonstrated to be 

related to the Project, then the Operator shall take the following serial actions to 

restore the quantity and quality of production that existed before commencement 

of the Project.   

 

- Undertake to determine if the well is functioning properly; 

- Rehabilitate by lowering the existing pump, or installing a new   pump;  

- Deepen the well; and if still not successful; and 

- Construct a new well. 

 

If  at  anytime  during  the  above  actions  it  appears  likely  that  there  will  be 

insufficient  yields  of water  from  the  existing  owner’s well,  then  the Operator 

shall provide interim water by having BeZak Water1 or other licensed company 

deliver potable water  to  the owner’s water  tank.    If  the owner does not have a 

water storage tank,  the Operator shall cause a 2,500‐gallon tank  to be delivered 

for water  storage while  the  restoration  actions  are  being  undertaken.    Bezak 

Water  presently  procures water  from  the Hillview Water Co., which  supplies 

water to Oakhurst, CA. 

 

A September 23, 2009  letter  to Madera Quarry,  Inc., by Wellco of Raymond, CA,  is  in 

Appendix C‐4.  It notes that in the 10 years since Wellco has constructed 18 wells within 

3‐mile  radius  of Madera Quarry,  it  has  always  been  successful  in  constructing wells 

sufficient for the needs of his customers.   Wellco notes that  it will take between 2 to 4 

1  State Lic. No. 84284, P.O. Box 541, Mariposa, CA 95338, (209) 966‐4244 

Page 75: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 2.0 Project Description

days “to successfully drill a well with the 3 mile radius of the Madera Quarry property, 

which would yield adequate volumes for domestic use.” 

 

2.2.3 Modified Phasing Plan  

Phasing, as noted in the FEIR, is modified to limit mining until March 1, 2014 to a 52.29‐

acre portion of  the Madera Quarry property.   Pursuant  to County action, a 52.29‐acre 

portion  of  the Project was  approved  for  termination  of  the Williamson Act  contract, 

pursuant  to a  cancellation procedure.   Until  contract  is  terminated on March 1, 2014, 

pursuant  to  the Notice of Non‐Renewal  recorded on November 29, 2003, mining and 

processing will  occur  only  from  this  52.29‐acre  portion  of  the  Project.    Figure  2.0‐1, 

Mining Plan Alternate 2, depicts  the 52.29 acres within  the 121‐acre quarry and plant 

site,  and  Figure  2.0‐2, Assessor’s  Parcel,  depicts  that  parcel  as  it will  be  noted  as  a 

separate assessor’s parcel. 

 

2.2.4 Additional Traffic Contributions Resulting from 2006 Hearing Process  

Based on commitments made by the Applicant during the 2006 public hearing process, 

the Applicant will perform the following: 

 

Highway 41 Improvements 

The Applicant will increase Highway 41 improvements above and beyond what 

is adequate in mitigating the traffic concerns on Highway 41 to a level that is less 

than significant.   The Applicant will construct a south bound lane on Highway 

41 from its intersection with Road 209 to the intersection of Highway 41 and 145.  

This  improvement  is  in  addition  to  what  the  Department  of  Transportation 

required  for  this  Project.    Applicant  shall  undertake  this  construction  after 

County has obtained any required clearances. The Applicant will also post lights 

if  permitted  under  the Department  of  Transportation warning  travelers  about 

slow moving trucks exiting Road 209 onto Highway 41.   

County Road 209 Improvements 

The Applicant will  increase mitigation  above  and  beyond what was  adequate 

and  sufficient  under  the  Environmental  Impact  Report  for  the  Project.    The 

Applicant has agreed to resurface Road 209 from the entrance of the Project site 

up to its intersection with Road 406.  

 

RESOURCE DESIGN TECHNOLOGY, INC. 2.0-5

Page 76: MADERA QUARRY PROJECT
Page 77: MADERA QUARRY PROJECT
Page 78: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 2.0 Project Description

2.3 ENTITLEMENTS AND CONTRACTS OBTAINED SUBSEQUENT TO THE FEIR

Table 2.0‐1  itemizes  those agreements and  entitlements  entered  into and obtained, as 

the case may be, from the prior approval of the Project until the issuance of this DREIR.  

Several of these are permits which were originally listed in DEIR Table 2.0‐3, Potential 

Permits, Approvals and Processes, Madera Ranch Quarry Project. 

 

 

TABLE 2.0-1 CONTRACTS AND ENTITLEMENTS

   Agreements and Entitlements Date 1  Department of Conservation Letter  to Madera County Assessorʹs 

Office,  with  Williamson  Act  Cancellation  Valuation  Agreement 

(Appendix E). 

August 28, 2008 

2  Compensation  and Grazing Agreement Waiving  Potential Noise 

Impacts to Residents for Mining and Asphalt Project Truck Traffic, 

between  Madera  Quarry,  Inc.  and  the  Wagner  Family  Trust, 

(Appendix F). 

February 2009 

3  Conservation Easement Deed, Madera County Contract No. 8512‐

C‐2008, (Appendix G). 

January 15, 2008 

4  U.S. Army Corps  of Engineers Permit,  2005‐673  (includes  July  1, 

2008 U.S. Department of Interior Fish & Wildlife Service Biological 

Opinion), (Appendix H). 

January 12, 2009 

5  U.S. Department of Interior, Fish & Wildlife Service, Comments on 

Avoidance Minimization and Compensation Measures, (Appendix 

I). 

December 17, 2007 

6  California  Office  of  Historic  Preservation,  Historic  Properties 

Comment Letter to USACOE, (Appendix J‐1). 

November 13, 2008 

7  California  Regional  Water  Quality  Control  Board,  Section  401 

Water Quality Certification, (Appendix J‐2). 

July 17, 2008 

8  California  Department  of  Fish  &  Game  Section  1602  Stream 

Alteration Agreement No. 2007‐0209‐R4, Hildreth Creek  ‐ Madera 

County, (Appendix J‐3). 

June 13, 2008 

9  California  Regional  Water  Quality  Control  Board,  Section  401 

Water Quality Certification, (Appendix K). 

July 17, 2008 

10  California  Department  of  Fish  &  Game  Section  1602  Stream 

Alteration Agreement No. 2007‐0209‐R4, Hildreth Creek – Madera 

County, (Appendix L). 

June 13, 2008 

11  Compensation  and Grazing Agreement Waiving  Potential Noise 

Impacts to Residents for Mining and Asphalt Project Truck Traffic, 

between  Madera  Quarry,  Inc.  and  the  Family  Wagner  Trust, 

(Appendix F). 

February, 2009 

 

RESOURCE DESIGN TECHNOLOGY, INC. 2.0-8

Page 79: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 2.0 Project Description

 

RESOURCE DESIGN TECHNOLOGY, INC. 2.0-9

  Agreements and Entitlements Date 12  Road Construction, Maintenance and Reimbursement Agreement, 

Madera County Contract No. 8511‐C‐2008, (Appendix P). January 15, 2008 

13  Traffic Mitigation Agreement Capital Deferment, Madera County 

Contract No. 8513‐C‐2008, (Appendix Q). January 15, 2008 

 

Page 80: MADERA QUARRY PROJECT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.0 REVISIONS TO ENVIRONMENTAL SECTIONS

Page 81: MADERA QUARRY PROJECT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.1 REVISIONS TO HYDROLOGY AND WATER QUALITY SECTION IN RESPONSE TO JUDICIAL DECISIONS

Page 82: MADERA QUARRY PROJECT

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-1

 

 

 

 

 

 

 

 

 

 

3.1 REVISIONS TO HYDROLOGY AND WATER QUALITY

SECTION IN RESPONSE TO JUDICIAL DECISIONS1  

 

 

3.9.1 Summary  

Upon reviewing the Court of Appeals Opinion and the Judgment of the Superior Court 

(Judicial  Decisions)  regarding  hydrology,  the  Applicant  devised  a  plan  that  would 

attempt to definitively determine what impact, if any, quarry pumping would have on 

neighboring wells.    The  plan,  by  necessity,  involved  extensive  testing  that went  far 

beyond  the  limited  3‐day  pump  test  upon which  earlier  determinations  in  the  2006 

Draft  Environmental  Impact  Report  (DEIR)  were  made.    Kenneth  D.  Schmidt  and 

Associates  (KDS)  performed  all  testing  with  regard  to  groundwater  issues.    Blair, 

Church &  Flynn  (BCF)  undertook  an  analysis  of  Project  impacts,  if  any,  on  surface 

water.    Finally,  Luhdorff  and  Scalmanini  (LS)  peer‐reviewed  all  of  the  KDS 

undertakings and findings, and performed independent modeling to verify the validity 

of KDS’ findings.  

 

The plan  included  the construction of a new 900  foot‐deep Project well.   Ranch wells 

and  a  sufficient  number  of  neighboring  wells  were  also  constructed  to  determine 

whether  impacts would  occur  under  Project  operations were monitored  under  two 

distinct  pumping  scenarios.    First,  in  order  to  determine  whether  there  would  be 

impacts, aquifer testing was performed while pumping from several ranch wells.  Then, 

1 These subsections will all reference 3.9 to keep this consistent with the numbering of the EIR. 

Page 83: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

during  one  12‐month  period, more water was  pumped  for  irrigation  purposes  than 

would be used for the Project.  

 

KDS projected that potential neighboring well drawdowns during operations would be 

small (compared to the feet of water standing in the wells, for example, one well would 

have a drawdown of   20  feet and  the  rest between 13 and no effect  (see Figure 3.9‐5, 

Maximum  Projected Drawdowns  in Wells During Mining), with  drawdowns  during 

reclamation being  even  smaller  (the well with a drawdown of 20  feet during mining 

will be between 5 and 13 feet;  the rest will be less than 5 feet, with the vast majority of 

them  incurring  no  effect  (see  Figure  3.9‐6,  Projected  Drawdowns  in Wells  During 

Reclamation Phase).   KDS notes  that even  though  the  irrigation pumping during one 

annual period was 110 percent of what would be pumped  for  the Project, no adverse 

impacts were noted on any private wells  in  the vicinity.   LS determined  that wells on 

adjoining property will “discharge at  essentially  the  same  capacities prior  to, during, 

and after the proposed project is operational.”   

 

3.9.2 Introduction  

When  the  Project  was  initially  approved,  the  groundwater  hydrology  analysis  was 

primarily based upon a 3‐day pump test.  Both the Judicial Decisions and LS found that 

a  3‐day  pump  test  is  adequate.    Based  largely  on  the  3‐day  pump  test  and  an 

extrapolation of  its  results,  the DEIR author assumed  that  the Project would  result  in 

potential  significant  impacts  to  adjacent  wells.    Accordingly,  various  mitigation 

measures were adopted  to  reduce  those  impacts  that were assumed  to be potentially 

significant to a less than significant level.  The Court of Appeal ruled that 1) there was 

no  substantial  evidence  that  the measures were  feasible  or  effective;  2)  the  impacts 

associated with implementing some or all of the mitigation measures were not analyzed 

in  the EIR; and 3)  the measure which contemplated  the possible  formation of a water 

system improperly deferred formulation of specific mitigation strategies until after the 

Project was approved. 

 

This section describes the hydrology  information obtained since the publication of the 

June 2005 DEIR.  For more detail, please refer to:  

 

Review  of  ‘Hydrogeologic  Conditions  At  and  Near  The  Proposed Madera  Quarry’, October 28, 2009, Luhdorff & Scalmanini (see Appendix C‐1); 

Hydrological  Conditions  at  and  Near  the  Proposed Madera  Quarry,  October  2009, Kenneth D. Schmidt and Associates (see Appendix C‐2); and 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-2

Page 84: MADERA QUARRY PROJECT
Page 85: MADERA QUARRY PROJECT
Page 86: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

Madera Quarry  Surface Water Hydrology  Report, October  2009,  Blair,  Church & Flynn (see Appendix C‐3).   

 

(Collectively,  this  DEIR  refers  to  the  above‐referenced  studies  and  the 

“Subsequent Hydrology Reports”). 

 

As will be noted below, the Subsequent Hydrology Reports provide factual data from 

pump  tests,  ranch  and  private well monitoring,  and  both  groundwater  and  surface 

water modeling supporting a determination  that  the Project, as described herein, will 

not result in significant impacts to neighboring operating wells. 

 

Ranch Well No. 10, a new Project supply well, was constructed  in 2008.   Well No. 10, 

along with Ranch Well No. 1, and water which occurs  from dewatering, will provide 

water for the operations of the Project.  Figure 3.9‐1, Locations of Wells Used For Well 

No.  10  Aquifer  Test,  depicts  the  location  of  the  following:    1)  the  entire  1,000‐acre 

Madera Quarry, Inc. property in which the 121‐acre mine, plant site, and the proximity 

of  the Oakwood Subdivision  is  shown; 2)  ranch wells 1, 3, 5, 6, 7, and 10; and 3)  the 

neighboring private wells that were subject to the 2008 monitoring.  

 

The  location of  the  ranch and private wells  that were monitored  for  the 2005 aquifer 

tests  is  attached  as Figure  3.9‐2, Locations  of Quarry Wells  and Wells Used  for  2005 

Aquifer Tests). 

 

The Operator will grout water‐bearing fractures, as needed, to reduce the infiltration of 

water  into  the  quarry  to  no more  than  22  acre‐feet per  year.  This will  eliminate  the 

creation of a permanent lake during the post‐mining phase (see Section 3.9.3.3, “Inflow 

Post Mining Will Not Cause Formation of Lake”).  Grouting of water‐bearing fractures 

is common in hard rock quarries, and provides reliable long‐term protection from water 

infiltration.  The specific grouting method and means of application will be determined 

based upon information obtained during excavation, but a performance standard of not 

more than 22 acre‐feet per year will be imposed and monitored by the County.    

 

As  initially proposed and approved, a bypass  channel was  included  in  the Project  to 

route  surface  run‐off,  from  the  275  acres  (which  BCF  describes  as  Tributary No.  1) 

around  the mine  and  into  its  natural  pre‐project  drainage  course.   As will  be  noted 

below, to mitigate against any  impacts during the Project from surface water volumes 

during 2‐year 24‐hour events, a plant bypass channel on a high bench on the south side 

of the excavation would be constructed.   There will be an overflow mechanism in this 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-5

Page 87: MADERA QUARRY PROJECT
Page 88: MADERA QUARRY PROJECT
Page 89: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

channel  that will divert excess surface runoff  into  the excavation site.   The  location of 

the two bypass channels is depicted on Figure 3.9‐3, Plan View of Project Site. 

 

These  changes  to  the  Project will  eliminate  the  possibility  of  significant  impacts  to 

neighboring wells and prevent excessive surface water being discharged off‐site.   This 

DREIR  concludes,  on  the  basis  of minor  changes  to  the  Project  and  the  Subsequent 

Hydrology Reports, that there will not be significant  impacts to groundwater supplies 

at adjoining operating wells during either during or post‐mining.   As a  result, CEQA 

does not require the identification and evaluation of mitigation measures.   

3.9.3 Existing Setting and During and Post-Mining Conditions  

The prior DEIR had a  section under  this heading.   However,  it  included  information 

which also addressed during and post‐mining phases of  the Project.   For  example,  it 

contained  a  discussion  of  the  lake  that was  expected  to  be  created.    Based  on  the 

Applicant’s plan to grout fractures as necessary to limit inflow to 22 acre‐feet per year, 

and based  further upon  the  results of  the Subsequent Hydrology Reports,  the DREIR 

concludes  that  the Project will no  longer  cause  a permanent  lake  to be  created post‐

mining.   

 

Where  the prior DEIR’s extensive discussion of Existing Setting does not conflict with 

the following, it is incorporated into this DREIR.  

 

3.9.3.1 Surface Water Quantity  

To  analyze  the  surface water  impacts of  the Project,  as  it was  revised  to  address  the 

Judicial Decisions,  BCF  undertook  a  surfacewater  hydrology  Report  (Appendix C‐3, 

Madera Quarry Surface Water Hydrology Report). 

 

BCF analyzed  two scenarios;  the During Project and Post‐Project differences  from  the 

Pre‐Project  conditions.   BCF determined discharge  rates and volume  rate  changes  for 

average 2‐, 10‐ and 100‐year events, as well as the differences in annual base flow.   Its 

findings are noted as: 

“During Project Compared  to Pre‐Project Condition  ‐ Except  for  the  2‐Year  24‐Hour  event,  the  peak  discharge  rates  increase  when  the  during‐project  condition  is 

compared to the pre‐project condition.  For the 2‐Year 24‐Hour event, the peak discharge 

rate  decreases  by  2‐percent.    For  the  10‐Year  24‐Hour  event,  the  peak  discharge  rate 

increases by 15‐percent and by 3‐percent for the 100‐Year 24‐Hour event. 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-8

Page 90: MADERA QUARRY PROJECT
Page 91: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

The runoff volume  for  the 2‐Year 24‐Hour event  increases by 22  ‐percent,  the 10‐Year 

24‐Hour event  increases by 9‐percent, and the 100‐Year 24‐Hour event decreases by 1‐

percent. 

 

The  mean  annual  runoff  volume  will  increase  by  12‐percent  due  to  the  increased 

imperviousness of the plant area. 

 

The estimated base flow will decrease by 3‐percent as a result of an overall reduction in 

the  watershed  area  due  to  removal  of  the  mine  [sic:    during  the  post‐reclamation 

scenario]. 

 

Mitigation Measures  ‐ The  increases  in  the peak discharge  rates and  runoff volumes 

that occur  for  the during project  condition are  the  result of  increased  runoff  rates and 

volumes from the Plant area.  These increases can be mitigated by diverting a portion of 

the  runoff  from  the Plant  area  into  the Mine.   The diversion  can  be  easily  effected  by 

placing a multiport orifice plate in the excavated channel to meter the continuing flow in 

the channel to stock pond.  An overflow weir can then be set to divert the excess flow rate 

in the channel down a pipeline to the Mine. 

 

Post  Project  Compared  to  Pre‐Project  Condition  ‐  The  decrease  in  the  peak 

discharge rates of the post project condition compared to the pre‐project condition varies 

from 2‐percent for the 2‐Year 24‐Hour event to 2‐percent for the 10‐Year 24‐Hour event 

and to 3‐percent for the 100‐Year 24‐Hour event. 

 

The decrease in runoff volume varies from 3‐percent for the 2‐Year 24‐Hour event to 3‐

percent for the 10‐Year 24‐Hour event and to 3‐percent for the 100‐Year 24‐Hour event. 

 

The mean  annual  runoff  volume will  decrease  by  4‐percent  as  a  result  of  an  overall 

reduction  in  the  watershed  area  due  to  removal  of  the  mine  [sic:  during  the  post‐

reclamation scenario]. 

 

The  estimated  base  flow  will  decrease  by  3‐percent  due  to  an  overall  reduction  in 

watershed area due to removal of the mine [sic:  during the post‐reclamation scenario].”  

(BCF 21‐22). 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-10

Page 92: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

3.9.3.2 Surface Water Quality  

As  in  the  prior DEIR, which  is  included  in Volume  II  to  this DREIR  in CD  format, 

available  on  the  County’s  website  (http://www.madera‐county.com/rma/ 

planningdept/), and available in hard copy for viewing at: 

 

Madera County Planning Department 

2037 W. Cleveland Avenue, Mail Stop G  

Madera, California 93637 

(559) 675‐7821 

 

3.9.3.3 Groundwater Quantity  

For a discussion of groundwater conditions at the Project site, please see the prior DEIR, 

which is attached to this DREIR in a CD format and available on the County’s website: 

http://www.madera‐county.com/rma/planningdept/  and  available  in  hard  copy  (as 

modified as revised by Appendix C‐2 of this DREIR) for viewing at: 

 

Madera County Planning Department 

2037 W. Cleveland Avenue, Mail Stop G  

Madera, California 93637 

(559) 675‐7821 

 

Pumpage (Domestic)  

For 18 days in October 2005, a long‐term aquifer test was conducted on Ranch Well #1 

(see Figure 3.9‐1  for  the  location of  this well).    It  indicated a sustainable yield, absent 

recharge, of 127 gpm.  At that time, ten private wells were being monitored.  The largest 

drawdown  of  any  of  the  private wells was  less  than  3  feet.    This  indicated  a  poor 

hydraulic connection between Well #1 and all but two of the private wells.  Eight of the 

wells showed a drawdown of less than 1 foot.  It was noted that there would have been 

drawdown during the aquifer test in October, as well water levels decline in the fall. 

 

From October 31  to November 15, 2005, a period of 16 days, a  long‐term aquifer  test 

was conducted on Well #5.  Well #5 is located in the intended excavation area as shown 

on Figure 3.9‐1.  This test indicated a long‐term yield of 23 gpm, absent recharge.  Ten 

private wells were monitored, with only one having a drawdown of over 1 ‐foot.  This 

was  the Graham‐West well,  indicating a drawdown of 2.1  feet.   The other nine wells 

indicated no hydraulic connection to Well #5. 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-11

Page 93: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

Then,  in  2008,  for  a  period  of  35  days,  there  was  sustained  pumping  of  a  newly 

constructed well, Ranch Well #10  (see Figure 3.9‐1  for  the  location of  this well).   The 

results indicated that this well would have a 55 gpm sustainable yield, in the absence of 

recharge.   Twelve private wells were  then monitored.   However, one of  those wells, 

listed  as  Ranch Well  #2,  is  a  non‐operating well  located  on  property  owned  by  the 

Wagner Family Trust, which has no pump in it.  Other than Ranch Well #2, nine of the 

private  wells  showed  no  observable  drawdown.    Two  of  the  wells  showed  an 

observable drawdown of 3 and 6 feet (see Figure 3.9‐2). 

 

From April 16, 2008 to December 2, 2008, Harris flowmeters were installed on 11 private 

wells.    They  indicated  an  average  per‐day  consumption  of  1,250  gallons  each.    This 

would further indicate a demand of 90 acre‐feet per year for the 63 developed lots in the 

Oakview  Subdivision  (except where noted,  all  following numerical  references  in  this 

section are to the KDS report, which is attached to this DREIR at Appendix C‐2). 

 

For a numerical summary of the Aquifer Tests for Wells No. 1, 5 & 10, see Figures 3.9‐7, 

3.9‐8, and 3.9‐9 (Table 10 Summary of Aquifer Tests). 

 

Appendix B of Appendix C‐2 contains  the construction data  for 50 area private wells 

(see Figure 3.9‐4, Location of Private Wells in Vicinity).  Five of them are in the range of 

260 to 320 feet deep.  The remaining 44 wells are between 400 and 1,175 feet deep.   

 

This data  regarding neighboring well depths  is at variance with  the DEIR, 3.9‐19, but 

believed reliable as KDS had access to well driller information for the neighboring wells 

on which he reported in KDS (Appendix C‐2 to this DREIR). 

 

During the reclamation phase, there would be only two wells having a drawdown that 

would exceed 5 feet.  These would be drawdowns of approximately 7 and 13 feet.  (104) 

 

Pumpage (Irrigation)  

During  two drought years  (2007‐08 and 2008‐09), portions of  the ranch were  irrigated 

utilizing  water  from Well  #1.    During  this  time,  various  private  wells  were  being 

monitored.  

 

Between July 2007 and December 2007, 32 acre‐feet were pumped from this well onto 20 

adjoining acres.   From August 2008  to  July 2009, 61.7 acre‐feet was pumped  from  the 

same well (see 76‐80). 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-12

Page 94: MADERA QUARRY PROJECT
Page 95: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

These amounts represent 60 and 110 percent, respectively, of  the 55 acre‐feet per year 

water demand  for  the Project.   The report notes  that  this pumpage occurred “with no 

obvious adverse impacts on private wells in the vicinity.” (106) 

 

Groundwater Inflow to Excavation Site  

Dewatering During Excavation  

Water producing fractures will be grouted to limit inflow to 22 acre‐feet per year. 

 

During mining, groundwater  inflow  could  accumulate  in  the winter when  the 

facility is closed.   When the operations start up in the spring, any accumulation 

of water can be pumped and used either as process water or pumped for use as 

irrigation water.  This is affirmed by LS, p.7:  

 

“As  noted  above,  KDSA  concludes  that  grouting  of  fractures  in  the 

proposed  excavation will  impede  groundwater  inflow  to  a  rate  of  about 

20,000 gpd (14 gpm), which could be used to meet some of the estimated 

plant process water requirements during mining.   Our understanding  is 

that the quarry could make use of some of all of that water for part of its 

plant process water  requirements; alternatively,  it may  simply discharge 

the groundwater  inflow, as well as any  inflow  from precipitation,  to  the 

existing stock pond and then use it for irrigation on its lands adjacent to 

the mining  operation.    In  either  case,  there would  not  be  a  permanent 

accumulation  of  ponded  water  in  the  bottom  of  the  excavation  during 

mining.” 

 

Inflow During Reclamation  

“[T]he water coming  into  the grouted excavation  (about 20 acre‐feet per 

year)  would  be  consumed  by  evapotranspiration  of  native  plants.    A 

permanent  lake  would  not  form,  because  the  plant  evapotranspiration 

would consume the precipitation and groundwater inflow, except for short 

periods of high precipitation  in winter.   There would be some  temporary 

ponding in the bottom of the excavation in the winter.” (103‐104)  

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-14

Page 96: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

Intended Source of Project Water  

Until  dewatering  occurs,  pumping will  be  from  a  combination  of Wells  #1  and  #10.  

Although they have a sustainable yield of 127 gpm and 55 gpm, respectively, at startup 

they will be pumped at 25 gpm and 10 gpm, respectively.  This will supply the 55 acre‐

feet per year mine project consumption. 

 

When  dewatering  commences,  the  14  gpm  and  20  acre  feet  per  year  yield  from 

dewatering will allow the pumping from Wells #10 and #1 to be reduced. (97) 

 

Drawdowns in Wells   

“Wells No. 1 and 10 would be pumped at a combined total of 35 gpm, until water 

from the limited dewatering of the excavation becomes available.  Because greater 

drawdowns in private domestic wells in the vicinity would generally result from 

pumping of Well No. 10 than from pumping of Well No. 1, more water would be 

pumped  from the  latter well.   In order to produce a total of 35 gpm, Well No. 1 

would be  initially pumped at 25 gpm, or about  twenty percent of  its  long‐term 

yield. Well No.  10  would  be  initially  pumped  at  10  gpm,  also  about  twenty 

percent  of  its  long‐term  yield.    The  results  of  the  groundwater  monitoring 

program proposed  in a  later section of  this report would be used  to manage  the 

pumping  rates  from  these wells,  if necessary,  so  as  to minimize drawdowns  in 

private wells in the vicinity …” 

 

Any private well situated on a major  lineament similar to Well No. 1 and No. 10 will, 

prior to dewatering, have a projected drawdown of 

  

“…30’ at a distance of 5,000’, and 20’ at a distance of 9,000’,  from Well No. 1.  

There is only one private well (Graham East) that is apparently located along the 

same  lineament  as Well  No.  1.    A  maximum  drawdown  of  about  20  feet  is 

projected at this well.” (97‐99) 

 

There will be smaller drawdowns “to the north that are not along major lineaments or 

fracture zones that pass through Wells No. 1 or 10.” (100).  Figures 3.9‐5 and 3.9‐6 show 

the projected drawdowns both during mining and reclamation phases and the location 

of neighboring wells.  Figures 3.9‐7 through 3.9‐9, Table 10 Summary of Aquifer Tests, 

shows a summary of the three above‐noted aquifer tests. 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-15

Page 97: MADERA QUARRY PROJECT
Page 98: MADERA QUARRY PROJECT
Page 99: MADERA QUARRY PROJECT
Page 100: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

Inflow Post Mining Will Not Cause Formation of Lake  

As noted in “Groundwater Inflow to Excavation Site”, above, KDS concluded that other 

than for short periods of high precipitation during the winter when temporary ponding 

might occur, standing water will not occur at the bottom of the pit.  This condition, if it 

occurs, will be temporary in nature.   Thus, contrary to the conclusion of the DEIR, the 

DREIR concludes that a permanent lake will not form at the excavation site after mining 

activities cease because grouting and the reclaimed vegetative surface that will enhance 

evapotranspiration, which has been calculated in Appendix C‐1.   

 

Utilizing  the groundwater  inflow quantity provided by KDS and precipitation data at 

the gauged rates at  the Madera California  Irrigation Management  Information Service 

(CIMIS), LS undertook  to more extensively model whether a pond might  form  in  the 

excavation site after mining concludes.  LS analyzed utilizing average annual data and 

then performed a second calculation based upon monthly precipitation.  LS conclusions 

are that 1) on an annual basis there will be no surplus of water to allow for the creation 

of a lake, but 2) there will a few months when up to 5 inches of water might pool before 

it evaporates.  LS calculations were modeled assuming “the excavation, covering a total 

of about 78 acres, will be reclaimed by placing 12 inches of unconsolidated overburden 

and 4 inches of topsoil on the entire area.” (For all references on this issue see LS, App. 

C‐1) 

 

“Within the excavation, most of that water (after interception of a small fraction 

by the vegetation itself) will combine with groundwater inflow and tend to fill the 

pore space of the reclaimed overburden and topsoil, up to the limits of their water 

holding  capacity, with  any  surplus  then  accumulating  as  ponded water  on  the 

ground  surface.   A  combination  of  evapotranspiration  by  the native  vegetation 

and  evaporation  from  any  ponded water  surface will  then  tend  to  remove  the 

inflow from groundwater and precipitation.  Two water budgets were prepared to 

examine the balance, or imbalance, between inflows and outflows, one at the scale 

of average annual conditions and a second on a monthly time steps to account for 

seasonal variations  in both precipitation  and  evapotranspiration, which  in  turn 

can be  expected  to  result  in  seasonal variations  in  soil moisture, ponded water, 

and plant growth… 

 

On an average annual basis, the combined inflows from groundwater (22 afy) and 

total  precipitation  (105  afy)  represent  a  total water  supply  of  127  afy  for  the 

native  vegetation  to  be  planted  on  the  78  acres  of  reclaimed  surfaces  of  the 

excavation… 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-19

Page 101: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

In summary, at the scale of total available water over a year, native vegetation can 

be  expected  to  consumptively  use  all  the  inflow,  with  the  net  result  that  no 

surplus will remain to accumulate as a lake at the bottom of the excavation.” 

 

“The monthly water budget was prepared to examine whether evapotranspiration 

would cumulatively utilize all available water, as suggested by the average annual 

budget above, and also to examine whether there would be seasonal periods when 

surplus water would be expected to pond in the excavation… 

 

Commencing in January: 

 

“the  combined  inflows would  exceed  the  combination  of  evapotranspiration  by 

native vegetation and the moisture holding capacity of the reclaimed overburden 

and topsoil, resulting in a ponding of up to about 5 inches of water in March and 

April.    In  subsequent  months,  the  combined  inflows  would  be  less  than 

consumption by the native vegetation…” 

 

3.9.3.4 Groundwater Quality The  quality  of  the  groundwater was  analyzed  for  the  original DEIR  and  afterwards 

when  the  use  of  Project water was  considered  as  a  possible  supply  for  neighboring 

properties.  However, as that is no longer part of the Project or any of its contemplated 

mitigations,  the  subsequently  obtained  groundwater  quality  information  is  provided 

only as non‐essential information.   

 

Table 11 of KDS shows chemical analysis from ranch wells taken in 2001, 2004 and 2008 

on Well Nos. 1, 4, 5, and 10.  It does not include the analysis from the prior DEIR for the 

following reasons.  “BSK (2004) collected water samples from Quarry Wells Nos. 1‐8 on 

June 10, 2004.   However, only a small amount of water was pumped  from each well, 

and the results are not considered as representative as those provided on Table 11.”  

 

As reported by KDS, arsenic levels were in excess of MCL for Well Nos. 4 and 10 and 

fluoride exceeded MCL on wells 1, 5, and 10. 

 

An analysis of various private wells was performed and those results are indicated on 

Tables 12, 13, and 14.   The 2004 BSK analysis was  considered  representative as  those 

“wells were in use and were pumped from about 10 to 15 minutes before collecting the 

samples…” (84) 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-20

Page 102: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

In the 2004 test, arsenic exceeded MCL on 2 of 10 wells and fluoride exceeded MCL on 1 

well.  For the 2009 test, arsenic was elevated on 2 of the 10 wells, fluoride on 1 of 10, and 

alpha activity was elevated on 1 of the 10 wells. 

 

3.9.4 Standards of Significance, Environmental Consequences, and Mitigation Measures

 

3.9.4.1 Standards of Significance  

Appendix  G  of  the  CEQA  Guidelines  for  Implementation  of  the  California 

Environmental Quality Act (CEQA) provides guidance for assessing the significance of 

potential  environmental  impacts.   Relative  to hydrology  and water  quality,  a Project 

will normally have a significant effect on the environment if it will: 

 

Violate any water quality standards or waste discharge requirements; 

Substantially  deplete  groundwater  supplies  or  interfere  substantially  with 

groundwater recharge such that there would be a net deficit in aquifer volume or 

a lowering of the local groundwater table level (e.g., the production rate of pre‐

existing nearby wells would drop to a level that would not support existing land 

uses or planned uses for which permits have been granted);  

Substantially  alter  the  existing  drainage  pattern  of  the  site  or  area,  including 

through  the  alteration  of  the  course  of  a  stream  or  river,  in  a manner, which 

would result in substantial erosion or siltation on‐ or off‐site; 

Substantially  alter  the  existing  drainage  pattern  of  the  site  or  area,  including 

through the alteration of the course of a stream or river, or substantially increase 

the rate or amount of surface runoff in a manner which would result in flooding 

on‐ or off‐site; 

Create or contribute runoff water, which would exceed the capacity of existing or 

planned stormwater drainage systems or provide substantial additional sources 

of polluted runoff;  

Otherwise substantially degrade water quality; 

Place housing within a 100‐year flood hazard area as mapped on a federal Flood 

Hazard  Boundary  or  Flood  Insurance  Rate  Map  or  other  flood  hazard 

delineation map; 

Place within  a  100‐year  flood  hazard  area  structures, which would  impede  or 

redirect flood flows; 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-21

Page 103: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

Expose people or structures to a significant risk of loss, injury or death involving 

flooding, including flooding as a result of the failure of a levee or dam; or 

Inundation by seiche, tsunami, or mudflow. 

 

Significant  impacts could also  result  if Project elements conflict with adopted County 

policies that relate to groundwater. 

 

State Water Resources Control Board Resolution 68‐16 is also an applicable criterion for 

assessing the impact of the Project on groundwater resources.  This resolution requires 

maintenance of existing water quality unless demonstrated  that a  change will benefit 

the people of  the  state, will not unreasonably  affect present or potential water users, 

and will not result in lower water quality than prescribed by other state policies. 

 

3.9.4.2 Impacts and Mitigation Measures  

Impact 3.9-1: The Project Could Cause the Water Levels and Pumping Rates in Adjacent Private Wells to Decline During the Operational Life of the Quarry

 

Based  upon  the  Subsequent Hydrology  Reports,  it  is  possible,  that  water  levels  in  adjacent 

private wells could decline.   However, the level of decline would not cause a significant impact 

on pumping rates to adjacent wells.  This impact is less than significant.   

 

The Applicant has estimated that Quarry operations will require 55 acre‐feet/year 

of water  for  consumptive  uses.    An  independent  assessment  of water  usage 

conducted  as  part  of  this  analysis  indicates  that  the  Quarry  operations  will 

require at least 30 acre‐feet/year of water.  

 

Two types of ranch well pumping support the conclusion of less than significant 

impact.   KDS undertook  constant  head  tests  of Ranch Wells Nos.  1,  5  and  10 

while monitoring  several neighboring private wells.   KDS determined  that  the 

sustainable  yield  of  No.  1  is  127  gpm  and  55  gpm  for  No.  10.    KDS  then 

determined the approximate effect on the selected private wells near the Project 

that were made available for monitoring.  They calculated a drawdown effect of 

pumping 25 gpm and 10 gpm (the amount necessary to serve the Projects needs 

of 55 acre‐feet/year) from Nos. 1 and 10.  This was then plotted on a contour map 

depicting  all  of  the  neighboring wells,  not  just  those  that were  subject  to  the 

monitoring.   He undertook  the  same analysis  considering  the  excavation  site’s 

dewatering of approximately 22 acre‐feet/year. 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-22

Page 104: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

The wells were shown in proximity to the lineaments along which Nos. 1 and 10 

exist.   As  indicated,  the effects are expected  to be  larger  to  those private wells 

more distant  from  the Project along  those  lineaments  than  those  that are off  to 

the side of either lineament. 

 

KDS concluded that the potential drawdown in each well to be anywhere from 1 

to 13 feet, except the Graham East well, which could experience a drawdown of 

up to 20 feet.      

 

LS reviewed KDS and replicated the project impacts.  In doing so, LS determined 

that KDS’s determination was supported by the data.   

 

“Thus, our independent assessment would be that the combined effects of 

proposed  project  pumping  and  excavation  dewatering,  as  presented  by 

KDSA  in  its Figure 31, and also as  itemized  (about 20  feet)  for a single 

well  (Graham East) along  the  lineament associated with Quarry Well 1, 

are notably conservative.” (LS 6)

In other words, LS believed the projected effect on the Graham East well would 

most likely be less than 20 feet. 

 

However, even using KDS’s ‘conservative’ results, LS noted that impacts of  

 

“less than 10 feet in almost all cases and up to a maximum of about 20 feet in one 

well,  are  not  sufficient  to  cause  a  notable  change  in  pumping  capacity  for  the 

types of  typical deepwell submersible pumps  that are used  in private wells near 

the proposed project site.   Thus, the nearby private well owners could anticipate 

their respective individual water supply wells to discharge at essentially the same 

capacities prior to, during, and after the propose project is operational.” (LS 6) 

 

LS did note that increasing the pumping depth by 20 feet would be expected to 

occasion an increase in energy use of 50 kWh per year, or about $10‐15.   This is 

based upon  the  average  of  1.4  acre‐feet/year water usage determined  by KDS 

from the meters in the Oakwood subdivision adjacent to the Project.  

 

LS concluded on this topic with,  

 

“The  range  of potential pumping  and dewatering  impacts presented by KDSA, 

less than 10 feet in almost all cases and up to a maximum of about 20 feet in one 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-23

Page 105: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

well,  are  not  sufficient  to  cause  a  notable  change  in  pumping  capacity  for  the 

types of deepwell submersible pumps that are typically used in private wells like 

those near  the  proposed  project  site.    .  . As  a  closing  comment  on  the  topic  of 

pumping impacts on private wells, it is noteworthy that all the pumping impacts 

estimated by KDSA are numerically small, leading to the expectation that private 

pump  capacities  will  be  practically  unaffected,  and  pumping  costs  will  be 

minimally increased as discussed above.” (LS 6) 

 

Level of Significance Before Mitigation:  Less than Significant 

 

Mitigation Measures:  None Required 

  

Impact 3.9-2: The Project Could Cause the Water Levels and Pumping Rates in Adjacent Private Wells to Decline After the Operational Life of the Quarry

 

Once excavation and mining ceases, there will no  longer be Project demand for 

55 acre‐feet/year of water.  Water will continue to flow into the former excavation 

site at the rate of 22 acre‐feet/year.  As this draw on the groundwater is less than 

during  excavation  and  mining  there  will  be  no  significant  effect  on  the 

neighboring wells’ water  levels or pumping  rates as a  result of  reclamation, or 

after the operational life of the quarry. 

 

Level of Significance Before Mitigation:  Less than Significant 

 

Mitigation Measures:  None Required 

 

Impact 3.9-3: The Project Could Cause an Increase in Surface Water Runoff That Could Cause an Increased Potential for Flooding in Areas Downstream of the Quarry During the Operational Life of the Quarry

 

The  Project might  result  in more  surface‐water  run‐off  in  areas  downstream  of  the Quarry 

because,  at  times,  there  will  be  an  increase  in  surface  run‐off.    This  impact  is  potentially 

significant. 

 

As part  of  the Project,  the  intermittent  stream  that  currently  runs  through  the 

Quarry area will be diverted through a bypass channel around the north side of 

the Quarry pit.   Therefore, normal  surface  flows  from upstream of  the Quarry 

area will not  be  affected.   A  small  bypass  channel will  be  installed  on  a high 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-24

Page 106: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

bench on the south side of the mining area to divert surface flows to the existing 

stock pond, which pond, at times, then creates downstream surface run‐off.  BCF 

determined downstream discharge  rates and volumes  for mean conditions and 

for 2‐, 10‐, and 100‐year 24‐hour events.   There  is one situation which causes a 

downstream  impact from  increased surface volumes.   The 2‐year 24‐hour event 

would cause a downstream increase of 22 percent of surfacewater volume.   

 

”The envelope of precision of hydrologic modeling is approximately 10 to 

20‐percent, meaning that numbers that fall within this range are generally 

considered to be equivalent.  All of these changes in flow rates or volumes 

are at or within that envelope of precision except the increase in the 2‐year 

24‐hour peak discharge rate in the during project condition, which can be 

mitigated  as  discussed  below.  …These  increases  can  be  mitigated  by 

diverting a portion of the runoff from the Plant area into the Mine.ʺ (BCF 

22). 

 

Level of Significance Before Mitigation:  Potentially Significant 

 

Mitigation Measures:  Mitigation Measure 3.9‐3 

 

Any increases can be mitigated by diverting a portion of the runoff from the Plant area 

into  the Mine.   The diversion can be effected by placing a multiport orifice plate  in  the 

excavated  channel  to  meter  the  continuing  flow  in  the  channel  to  stock  pond.    An 

overflow weir can then be set to divert the excess flow rate in the channel down a pipeline 

to the Mine. 

 

Level of Significance After Mitigation:  Less than Significant 

 

Impact 3.9-4: The Project Could Cause an Increase or Decrease in Surface-Water Runoff That Could Affect Areas Downstream of the Quarry After the Operational Life of the Quarry

The  Project  might  result  in more  surfacewater  run‐off  in  areas  downstream  of  the  Quarry 

because,  at  times,  there  will  be  an  increase  in  surface  run‐off.    This  impact  is  potentially 

significant. 

“The decrease  in  the peak discharge rates of  the post project condition compared  to  the 

pre‐project condition varies from 2 percent for the 2‐year 24‐hour event to 2 percent for 

the 10‐year 24‐hour event and to 3 percent for the 100‐year 24‐hour event. 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-25

Page 107: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

The decrease  in  runoff volume varies  from 3 percent  for  the 2‐year 24‐hour  event  to 3 

percent for the 10‐year 24‐hour event and to 3 percent for the 100‐year 24‐hour event. 

 

The mean  annual  runoff  volume will  decrease  by  4  percent  as  a  result  of  an  overall 

reduction in the watershed area due to removal of the mine. 

 

The  estimated  base  flow  will  decrease  by  3  percent  due  to  an  overall  reduction  in 

watershed area due to removal of the mine.”  

 

Level of Significance Before Mitigation:  Less than Significant 

 

Mitigation Measure:  None Required 

 

Impact 3.9-5: The Project Could Cause a Permanent Pond to be Created in the Mine Excavation Area After the Operational Life of the Quarry

 

As needed to meet the performance standard, the Operator will grout the water‐

bearing fractures within the quarry.  The performance standard of not more than 

22  acre‐feet  per  year  of  infiltration,  through  water‐bearing  fractures,  will  be 

monitored by  the County.   KS noted  that  this volume of water coming  into  the 

grouted  excavation  (about  20  acre‐feet/year)  would  be  consumed  by 

evapotranspiration of native plants.   

 

“A permanent lake would not form, because the plant evapotranspiration 

would consume the precipitation and groundwater inflow, except for short 

periods  of  high  precipitation  in  the  winter.    There  would  be  some 

temporary ponding  in the bottom of the excavation  in the winter.” (103‐

104) 

 

LS modeled the inflow of groundwater and surface water on an annual average 

and  then  modeled  based  on  monthly  data.    Using  the  monthly  model,  LS 

determined  that, with  the  site  being  reclaimed with  1  foot  of  overburden,  4 

inches of topsoil and native vegetation, a permanent pond will not be created.  At 

most  there might be  temporary ponding of 5  inches of water  in  the excavation 

floor from March until the water evaporates in May. 

 

Level of Significance Before Mitigation:  Potentially Significant 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-26

Page 108: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-27

Mitigation Measures:  Mitigation Measure 3.9‐5 

 

The site  is  to be reclaimed using native vegetation along with a minimum of 1 

foot of overburden and 4  inches of  topsoil  shall  spread on all benches and  the 

excavation floor.  A performance standard of not more than 22 acre‐feet per year 

of infiltration, through water‐bearing fractures, will be monitored by the County. 

 

Level of Significance After Mitigation:  Less than Significant 

  

Impact 3.9-6: The Project Could Cause Degradation of Groundwater and/or Surface-Water Quality2

 

Activities  such  as  blasting,  ground  disturbance,  onsite  storage  of  petroleum  products,  and 

operation storage, maintenance, and repair of construction equipment could cause degradation of 

groundwater and/or surface water quality.  This impact is potentially significant.  

 

The Project will involve the blasting of the bedrock to produce material suitable 

to  be  crushed  into  aggregate.    The  blasting will  typically  involve  the  use  of 

compounds  containing  ammonium,  nitrate,  and  fuel  oils.    These  compounds 

could migrate to groundwater through exposed fractures in the Quarry pit if not 

stored, handled, and used properly.   The Quarry dewatering will  tend  to draw 

any compounds that reach groundwater back to the Quarry, where they will be 

extracted during dewatering.  Under certain conditions, however, such as heavy 

winter rains or a curtailment of Quarry operations, these compounds could reach 

groundwater and not be captured by the Quarry dewatering. 

 

The  Project  includes  extensive  ground  disturbance  and  onsite  storage  of 

petroleum products and other hazardous materials.   As discussed above, future 

operations may also involve the operation of an asphalt batch plant.  The asphalt 

batch plant will use asphaltic  tars, which are generally  insoluble.   Solvents and 

cleaners may be used  for  cleaning and maintenance of  the asphalt batch plant 

operations and delivery trucks.  These proposed operations increase the potential 

for contamination of surface‐water runoff and groundwater.  Operation, storage, 

maintenance,  and  repair  of  construction  equipment will  occur  as  part  of  the 

Project.   These activities will require  the use,  transport,  transfer, and storage of 

fuels,  lubricants, and cleaners.   Spills or  leaks of  these petroleum products and 

other hazardous materials  could affect  surface‐water or groundwater quality  if 

2 This impact statement is unchanged from the DEIR. 

Page 109: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

not  properly  stored  and  handled.    California  State Water  Resources  Control 

Board Resolution 68‐16  requires  that  existing water quality be maintained and 

that further degradation of water quality be prevented.   This resolution  is often 

referred  to  as  the  “non‐degradation  policy”  and  prohibits  the  degradation  of 

surface‐water or groundwater quality. 

 

 Level of Significance Before Mitigation:  Potentially Significant 

 

Mitigation Measures: 

 

Mitigation Measure 3.9‐6a 

As part of the Project approvals and permitting, the Applicant shall be required 

by  the  Central  Valley  Regional  Water  Quality  Control  Board  to  prepare  a 

Stormwater  Pollution  Prevention  Plan  to  comply  with  Basin  Plan  limits  for 

water quality and discharge of sediment and suspended solids.  Compliance with 

the  requirements  in  the  Stormwater  Pollution  Prevention  Plan,  along  with 

Mitigation Measure 3.9‐7b, will prevent any future degradation of surface‐water 

quality related to the Project.  To verify compliance with this mitigation measure, 

the operator will be required to conduct monitoring and sampling as required in 

the  Stormwater  Pollution  Prevention  Plan.    The  monitoring  results  must  be 

reported to the Regional Water Quality Control Board and the County. 

 

Mitigation Measure 3.9‐6b 

All  fuel and chemical storage areas and all equipment maintenance areas should 

be placed on bermed concrete surfaces. If the bermed concrete surfaces drain to a 

sump, the sump should be cleaned and the waste fluids handled and disposed of in 

compliance  with  all  applicable  laws  and  regulations.  If  the  bermed  concrete 

surfaces do not drain to a sump, routine cleaning should be conducted to prevent 

the  surface  from  becoming  slippery.    The  cleaning  solutions  and  wash  water 

should  be  handled  in  the  same  manner  as  the  sump  fluids.    Verification  of 

compliance with  this mitigation measure will occur  through routine  inspections 

by the County. 

   

Level of Significance After Mitigation:  Less than Significant 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-28

Page 110: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.1 Revisions to Hydrology and Water Quality Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.1-29

3.9.5 Cumulative Impacts and Mitigation Measures  

As of the time of issuance of the Notice of Preparation (December 23, 2008), there were 

no pending applications for, nor any existing large‐scale aggregate mining or industrial 

activities  in  the  area  near  the  Project  that  would  utilize  significant  quantities  of 

groundwater,  or  result  in  significant  surface‐water  runoff.    Therefore,  there  are  no 

cumulative impacts related to hydrology and water quality from the Project. 

 

Page 111: MADERA QUARRY PROJECT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.2 REVISIONS TO NOISE AND VIBRATION SECTION IN RESPONSE TO JUDICIAL DECISIONS

Page 112: MADERA QUARRY PROJECT

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-1

 

 

 

 

 

 

 

 

 

 

3.2 REVISIONS TO NOISE AND VIBRATION SECTION IN RESPONSE TO JUDICIAL DECISIONS1

 

 

 

3.11.1 Introduction  

The revisions to the DEIR and FEIR were specifically undertaken to address and respond to 

the Court’s opinion  that  the original noise evaluation did not consider  the potentially 

significant cumulative noise impacts associated with off‐site Project related traffic noise 

increases.2  Figure 3.11‐1 (Site Plan, Noise Measurement Locations, and Receiver Locations) 

shows the general orientation of the Project site and proposed on‐site uses.  This section 

also  includes  pertinent  data  regarding  current  baseline  traffic  and  general  ambient 

conditions.  The revisions to the original section include the following: 

 

This section includes an updated Environmental Setting to discuss changes in land 

use and noise environments since the original noise analysis was prepared for this 

project.  This update was based on review of the recent Tesoro Viejo Specific Plan 

EIR,  current aerial photographs, and discussion with Madera County Planning 

Department Staff. 

This  section  includes  an  expanded discussion of project  significance  criteria  in 

response  to  the  Court’s  ruling, with  particular  attention  to  the  thresholds  of 

significance for findings of noise impacts related to Project‐related cumulative noise  

 

1  These subsections will all reference 3.11 to keep this consistent with the numbering of the DEIR and FEIR. 

2  This section is based on the previous noise analysis prepared for this project (Environmental Noise Analysis, 

Madera Ranch Quarry Project, Bollard & Brennan,  Inc.,  July 2004), with revisions by Bollard Acoustical 

Consultants, Inc. 

Page 113: MADERA QUARRY PROJECT
Page 114: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-3

level increases.  Specifically, these revisions include a discussion of the thresholds 

recommended  by  the  Federal  Interagency Commission  on Noise  (FICON)  for 

assessing  impacts  associated with Project‐related noise  increases,  and how  the 

FICON standards are more conservative than the standards previously utilized to 

assess Project noise impacts.   

This section includes an expanded discussion of applicable Madera County noise 

standards.  These revisions discuss the distinction between residences constructed 

on residentially‐zoned properties versus residences constructed on agriculturally‐

zoned properties.   

 

This section includes an expanded discussion of off‐site Project‐related traffic noise impacts 

for both existing and cumulative conditions, and reassessment of the impact statements 

contained  in  the previous study relative  to  the FICON standards and actual distances 

between  the  roadway centerlines and  residential structures.    In  the previous analysis, 

impacts  associated with  the  Project‐related  traffic  noise  increases were  assessed  at  a 

standardized distance of 100 feet from the roadway centerlines, to generally reflect worst‐

case conditions.   In response  to  the Court’s opinion  that  the FEIR failed to adequately 

address Project  traffic noise  impacts,  this section  includes a more  focused  traffic noise 

impact assessment at the actual distances to residences in cases where those distances are 

greater  than  the  100‐foot  reference distance.   More  specifically,  the previous  analysis 

utilized a reference position of 100 feet from centerline to assess noise impacts to existing 

residences  located  along Highways  41  and  145,  and County Road  209,  regardless  of 

whether there were any existing residences constructed that close to the roadway.  This 

section recognizes that along several roadway segments utilized by Project traffic, there is 

either no residence at all, or the existing residential structures are located beyond the 100‐

foot reference distance.  Review of aerial photographs within 10 miles of the intersection of 

State Routes 145 and 41 indicated that there were no apparent residential structures within 

100 feet of the roadway centerline.  The traffic noise impact statements were revised, where 

applicable, to account for these actual distances. 

 

3.11.2 Noise and Vibration Fundamentals and Terminology  

3.11.2.1 Background on Noise and Vibration  

Sound is defined as any pressure variation in air that the human ear can detect.  If the 

pressure variations occur frequently enough (at least 20 times per second), they can be 

heard and are called sound.  The number of pressure variations per second is called the  

Page 115: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-4

frequency of sound, and is expressed as cycles per second, called Hertz (Hz).  Appendix  

O‐1, Acoustical Terminology, contains definitions of acoustical terminology used in this 

section. 

 

Measuring sound directly in terms of pressure would require a very large and awkward 

range of numbers.  To avoid this, the decibel scale was devised.  The decibel scale uses the 

hearing threshold (20 micropascals of pressure) as a point of reference, defined as 0 dB.  

Other sound pressures are then compared to the reference pressure, and the logarithm is 

taken to keep the numbers in a practical range.  The decibel scale allows a million‐fold 

increase in pressure to be expressed as 120 dB.  Another useful aspect of the decibel scale is 

that changes in levels (dB) correspond closely to human perception of relative loudness.  

Noise is often described as unwanted sound.  Figure 3.11‐2, Typical A‐Weighted Sound 

Levels of Common Noise, illustrates common noise levels associated with various sources. 

 

Vibration  is  like noise  in that  it  involves a source, a transmission path, and a receiver.  

While vibration is related to noise, it differs in that in that noise is generally considered to 

be pressure waves  transmitted  through  air, whereas vibration usually  consists of  the 

excitation of a structure or surface.  As with noise, vibration consists of an amplitude and 

frequency.    A  person’s  perception  to  the  vibration will  depend  on  their  individual 

sensitivity  to vibration, as well as  the amplitude and  frequency of  the source and  the 

response of the system which is vibrating. 

 

Vibration can be described in terms of acceleration, velocity, or displacement.  A common 

practice is to monitor vibration measures in terms of peak particle velocities in inches per 

second.  Standards pertaining to perception as well as damage to structures have been 

developed for vibration levels defined in terms of peak particle velocities.  For this Project, 

vibration is a concern primarily during blasting and excavation.  An assessment of mining‐

related vibration levels is contained within this section. 

 

3.11.2.2 Effects of Noise on People  

The perceived  loudness of  sounds  is dependent upon many  factors,  including  sound 

pressure level and frequency content.  However, within the usual range of environmental 

noise levels, perception of loudness is relatively predictable, and can be approximated by 

weighing the frequency response of a sound level meter by means of the standardized A‐ 

weighing  network.    There  is  a  strong  correlation  between A‐weighted  sound  levels 

(expressed as dBA) and community response to noise.  For this reason, the A‐weighted  

Page 116: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-5

sound level has become the standard tool of environmental noise assessment.  All noise 

levels reported in this section are in terms of A‐weighted levels in decibels. 

 

 

FIGURE 3.11-2 TYPICAL A-WEIGHTED SOUND LEVELS OF COMMON NOISE SOURCES

  Loudness Ratio Level A-Weighted Sound Level (dBA)

     128    130 Threshold of pain  

  

 

 

64  

120 Jet aircraft take‐off at 100 feet  

 

 

 32 

 110 Riveting machine at operators position 

 

 

 

 16 

 100 Shotgun at 200 feet 

 

   

 

 8 

 90 Bulldozer at 50 feet 

 

   

 

 4 

 80 Diesel locomotive at 300 feet 

 

   

 

 2 

 70 Commercial jet aircraft interior during flight 

 

   

 

 1 

 60 Normal conversation speech at 5‐10 feet 

 

   

 

 1/2 

 50 Open office background level 

 

   

 

 1/4 

 40 Background level within a residence 

 

   

 

 1/8 

 30 Soft whisper at 2 feet 

 

 

 

  

1/16  

 

 20 

 

 

Interior of recording studio 

 

 

Community noise is commonly described in terms of the ambient noise level, which is 

defined as the all‐encompassing noise level associated with a given noise environment.  A 

common statistical tool to measure the ambient noise level is the average, or equivalent, 

sound level (Leq) over a given time period (usually one hour).  The Leq is the foundation of 

Page 117: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-6

the Day‐Night Average Level noise descriptor, Ldn, and shows very good correlation with 

community response to noise. 

 

The Day‐Night Average Level (Ldn) is based upon the average noise level over a 24‐hour 

day, with a +10 decibel weighing applied to noise occurring during nighttime (10:00 p.m. to 

7:00 a.m.) hours.  The nighttime penalty is based upon the assumption that people react to 

nighttime noise  exposures  as  though  they were  twice  as  loud  as daytime  exposures.  

Because Ldn represents a 24‐hour average, it tends to disguise short‐term variations in the 

noise environment.   Ldn‐based noise standards are commonly used to assess noise impacts 

associated with traffic, railroad, and aircraft noise sources. 

 

The Madera County noise standards, which are discussed in detail later in this section, are 

expressed  in  terms  of  the  Ldn  descriptor  as well  as  in  terms  of  hourly  performance 

standards.    In  addition  to  applying  the County’s  noise  standards  to  this Project,  the 

California Environmental Quality Act  (CEQA) requires  that noise  impacts be assessed 

relative to ambient noise levels that are present without the Project.  As a result, ambient 

noise surveys were conducted, and comparisons of Project to No‐Project noise levels were 

used  to  assess  noise  impacts  (in  addition  to  comparison  to  Madera  County  noise 

standards).  Specifically, individual maximum (Lmax) noise levels and hourly average (Leq) 

noise levels, both with and without the Project, were compared so that the assessment of 

noise impacts was not based solely on an assessment of Project‐generated noise in terms of 

24‐hour  averages  (Ldn),  but  also  on  short‐term  fluctuations  in  the  ambient  noise 

environment. 

 

It should be noted that audibility is not a test of significance according to CEQA.  If this 

were the case, any project which added any audible amount of noise to the environment 

would be considered unacceptable according to CEQA.  Because every physical process 

creates noise, whether by the addition of a single vehicle on a roadway, or by a tractor in an 

agricultural field, the use of audibility alone as significance criteria would be unworkable.  

CEQA requires a substantial increase in noise levels before noise impacts are identified, not 

simply an audible change.  The discussion of what constitutes a substantial change in noise 

environments, both existing and cumulative, is provided in the Regulatory Setting section 

of this section. 

 

Page 118: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-7

3.11.3 Affected Environment  

3.11.3.1 Project Location and Description  

Please see the Project Description, Section 2.0 of the DEIR, for a comprehensive narrative on 

the Project.  In short, the Project proposes to develop the Madera Quarry property as a new 

hardrock quarry.  The Project site is located in central Madera County, California, about 2 

miles west of State Highway 41, 4 miles north of State Highway 145, and 16 miles northeast 

of the City of Madera.  The Project would be located on approximately 125 acres of the 540‐

acre Madera Quarry, which  is zoned for agricultural use.   Associated with the Quarry 

would  be  an  aggregate  processing  facility,  asphalt  processing  plant,  administration 

complex, parking areas, on‐site haul road, and various other stockpile and   processing 

areas.  The Project would also include construction of a two‐lane paved haul road from the 

processing area west about ¼‐mile out to County Road 209.  As proposed, the Project also 

would include substantial upgrading and realignment of Road 209 to meet County and 

Caltrans standards. 

 

The maximum proposed aggregate production during the Project life would be 900,000 

tons per year marketed.  Mining would continue for up to 50 years, through several mining 

phases, with mining‐related noise levels decreasing with increasing depth into the mining 

pit due to shielding by pit walls.  A total of about 45 million tons of marketable material 

would be mined over the life of the Project.  At the conclusion of aggregate production, a 

reclamation phase would extend the total Project lifespan to about 53 years. 

 

Typical mine operating hours would be  from 6:00 a.m.  to 7:00 p.m., Monday  through 

Friday (13 hours per day).  Hauling of material from the processing facilities would also 

take place Monday through Friday, from 6:00 a.m. to 7:00 p.m.  The asphalt processing 

plant would operate from 6:00 a.m. to 7:00 p.m. on normal operating days.  Operations 

would  normally  occur  5  days  per  week;  however,  extended  operations,  including 

Saturdays, could occur sporadically to meet customer demands.  

 

Certain public agency projects (such as Caltrans road improvement projects) may operate 

during nighttime hours to prevent traffic congestion associated with lane closures and 

heavy vehicle operations.  In addition, emergency road repairs may be made necessary by 

natural disasters (e.g., flooding), or other unforeseen events.  These road improvement or 

repair  projects  accordingly  require  materials  to  be  supplied  at  night.    The  asphalt 

processing plant and truck loadout could periodically operate 24 hours per day, and up to 

Page 119: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-8

7 days per week  for  limited periods  to  service  these projects.   The duration of  these 

expanded hours of operation would depend on the duration of the projects being supplied. 

However, excavation from the mine area and rock crushing operations would occur only 

during daylight hours. 

 

Operations  would  take  place  year‐round.    However,  according  to  the  Applicant, 

construction tends to be slow during the months of December and January because of 

seasonal storms and holidays.  The Madera Quarry would be open to serve customer needs 

during these months, but hours of operation and production rates would likely be less than 

during the remainder of the year. 

 

3.11.3.2 Land Uses in the Project Vicinity  

Land uses in the immediate vicinity of the Project site consist of primarily of open grazing 

lands and large rural‐residential properties.  Agricultural uses are not considered to be 

noise‐sensitive.  The nearest noise‐sensitive uses to the Project site consist of residences 

constructed on agricultural properties to the west, north, and east of the Project site.  The 

approximate  locations of  the nearest  identified representative noise‐sensitive areas are 

identified on Figure 3.11‐1.  

 

3.11.3.3 Description of Existing Ambient Noise Environment in 2004  

The ambient noise environment in the immediate Project vicinity at the time the original 

noise analysis was prepared  for  this Project was defined primarily by natural sounds, 

(wind, cattle, birds,  insects, etc.), but also by sporadic  local  traffic and occasional high 

altitude aircraft over flights of the area.  

 

To quantify the ambient noise environment in the Project vicinity in 2004, continuous and 

short term noise level measurements were conducted at five locations on and around the 

Project site on April 19‐20, 2004.  That measurement period represented a typical weekday 

period during normal spring/fall‐like atmospheric conditions.  The noise measurement site 

locations are identified in Figure 3.11‐1.  

 

Larson Davis Laboratories (LDL) Model 820 precision integrating sound level meters were 

used for the noise level measurement survey.  The meters were calibrated before and after 

use with  an  LDL Model CAL200  acoustical  calibrator  to  ensure  the  accuracy  of  the 

Page 120: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-9

measurements.  The equipment used meets all pertinent specifications of the American 

National Standards Institute. 

 

The numerical summaries of the ambient noise level measurements are provided in Table 

3.11‐1, Ambient Noise Measurement Survey Summaries (April 19‐20, 2004).  The Table 

3.11‐1 data include daytime and nighttime, average and maximum noise levels, as well as 

the Ldn values computed from the hourly average noise levels.  Graphical depictions of the 

2004 ambient noise environments at the measurement sites for the Sunday and Monday 

periods monitored are shown in Appendix O‐2, Continuously Measured Hourly Noise 

Levels. 

 

 

TABLE 3.11-1 AMBIENT NOISE MEASUREMENT SURVEY SUMMARIES (APRIL 19-20, 2004)

 Daytime

(7 a.m. to 10 p.m.) Nighttime

(10 p.m. to 7 a.m.)

Site Location Average

(Leq) Maximum

(Lmax) Average

(Leq) Maximum

(Lmax) Computed

Ldn A  P/L next to Elevated Res. to West.  44  49‐71  45  42‐76  51 

B  40762 Rd. 406 ‐ Pfoutz Residence  43  53‐79  37  42‐68  45 

C  41259 Rd. 406 ‐ Harris Residence  49  58‐81  47  47‐83  54 

D N/E Corner of Project Site ‐  

White Residence 46  50‐80  34  34‐69  45 

E  Eastern Boundary of Project Site   40  54  –  –  – 

Source: Bollard & Brennan, Inc. 

Notes: 

1. Noise measurement locations are identified on Figure 3.11‐1. 

2. Averages shown are the logarithmic mean for the period. 

3. Maximum levels shown are the range of maximum levels measured during each hour of the day or 

nighttime period. 

4. Site E was monitored as a short‐term site during daytime hours, so no nighttime data was collected 

at this location.  

 

 

The Table 3.11‐1 data indicate that the 2004 ambient noise environment on the Project site 

and at the nearest residences during the survey period consisted of fairly low noise levels.  

The measured levels are consistent with what would be expected of rural, agricultural 

areas removed from major roadways, and which are not significantly affected by other 

local noise sources.  

Page 121: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-10

The Table 3.11‐1 data indicate that the 2004 ambient noise environment on the Project site 

and at the nearest residences during the survey period consisted of fairly low noise levels 

with  brief  periods  of  elevated maximum  noise  levels.    A wide  range  of measured 

maximum noise levels were recorded at each site, indicating that during certain hours of 

the day and night there were no appreciably loud events, while during other hours there 

were.    The  measured  levels  are  consistent  with  what  would  be  expected  of  rural, 

agricultural areas removed from major roadways, and that are not significantly affected by 

other local noise sources.  

 

3.11.3.4 Description of Existing Ambient Noise Environment in 2009  

Review of current aerial photography indicates that no new noise‐sensitive receptors have 

been constructed closer to the project site than those which existed during the 2004 ambient 

noise surveys.  This observation was confirmed by Madera County Planning Department 

Staff (pers. comm., Matt Treber, January 28, 2009). 

 

Because there have not been appreciable changes  in  land use  in the  immediate Project 

vicinity, ambient noise conditions quantified through extensive monitoring in 2004 are 

believed to remain representative of current conditions in the immediate Project vicinity.  

Because ambient conditions general increase over time due to general increases in traffic 

volumes associated with growth  in  the region,  it  is highly unlikely  that ambient noise 

conditions in the immediate Project vicinity decreased between the 2004 ambient noise 

surveys and current conditions.  As a result, the 2004 data likely provides a conservative 

baseline condition against which current Project noise impacts are evaluated.  

 

It is worthy of note that ambient noise monitoring data contained in Table 4.10‐4 of the 

Tesoro Viejo Specific Plan EIR3  indicate  that average and maximum noise  levels were 

generally similar to those shown above in Table 3.11‐1.  Although the project sites are not 

contiguous, they are in the same general region and provide additional context pertaining 

to ambient noise conditions. 

 

3  http://www.madera‐county.com/rma/archives/uploads/1221158005_Document_upload_15_ 

sec4.10_noise.pdf 

Page 122: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-11

3.11.3.5 Description of Current Ambient Vibration Environment  

Because no significant vibration sources or industrial operations were identified within the 

Project vicinity, the ambient vibration environment is considered to be negligible both at 

the Project site and at the nearest sensitive land uses. 

 

3.11.4 Regulatory Setting  

3.11.4.1 Local Jurisdictional Guidelines  

In California, cities and counties are required to adopt a noise element as part of their 

general plan.  Cities and counties can also adopt noise control requirements within their 

zoning ordinances or as a separate noise ordinance.   The Project  is  located  in Madera 

County, which has both a Noise Ordinance and a Noise Element.  

 

3.11.4.2 Madera County General Plan Noise Element  

County General Plan Noise Level Standards  

The Madera County General Plan Noise Element establishes acceptable noise level limits 

for both transportation and non‐transportation noise sources.  The primary objective of the 

noise element is to prescribe policies that lead to the preservation and enhancement of the 

quality  of  life  for  the  residents  of Madera  County  by  securing  and maintaining  an 

environment free from hazardous and annoying noise. 

 

For residential uses affected by transportation noise sources (off‐site traffic in this case), the 

noise element identifies 60 dB Ldn as acceptable.  This is consistent with State of California 

standards  recommended  for  transportation  noise  sources.    Policy  7.A.1  specifically 

prohibits the creation of new residences in areas where noise due to transportation noise 

sources would exceed 60 dB Ldn in outdoor activity areas or 45 dB Ldn within residences.   

 

It should be noted that many of the land uses located in the immediate Project vicinity are 

agriculturally zoned, and agricultural uses are not considered to be noise sensitive.  For the 

purposes  of  assessing  noise  impacts  for  this  Project,  however,  residences  located  on 

agriculturally designated properties are considered to be noise sensitive.  Even though the 

residence is considered to be noise sensitive, the agriculturally zoned property containing 

the  residence  is  not,  so  noise  impacts  are  evaluated  in  this  study  at  the  residences 

Page 123: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-12

themselves where  the  noise  sensitivity  exists,  rather  than  at  the  property  line  of  the 

agriculturally designated parcel, which is not considered to be noise sensitive.  

 

For  residences  affected  by non‐transportation noise  sources,  such  as noise‐producing 

activities that will occur at the Project site, the County Noise Element establishes noise 

standards.  For this Project, the evaluation period is considered to be the worst‐case hour 

during which all on‐site equipment would be operating, including maximum truck traffic 

generation.  The Madera County noise standards that may be applicable to this Project are 

provided  in  Table  3.11‐2,  Madera  County  Noise  Element  Performance  Standards 

Applicable to Land Uses Affected by Heavy Industrial Uses. 

 

 

TABLE 3.11-2 MADERA COUNTY NOISE ELEMENT PERFORMANCE STANDARDS

APPLICABLE TO LAND USES AFFECTED BY HEAVY INDUSTRIAL USES  

Land Use Daytime Standard

(7 am to 10 pm) Nighttime Standard

(10 pm to 7 am) Agricultural   65  60 

Residential   60  55 

Source:  Madera County Noise Element Table 7.A.4 

 

 

The recently updated Madera County noise standards summarized  in Table 3.11‐2 are 

ambiguous  in  that  they do not  specify  the noise  level descriptor  associated with  the 

numeric  standard.   Given  the magnitude of  the  standard,  it  is assumed  that  they are 

intended to represent average noise levels (Leq) that are not to be exceeded at the property 

line of the receiving use.   

 

County General Plan Vibration Thresholds  

Madera County is in the process of updating its General Plan Policies 7.A.9 and 7.A.10 to 

establish a vibration level threshold of 0.1 inches per second at areas considered sensitive 

to vibration.  This level is considered the threshold at which annoyance can be expected. 

 

Page 124: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-13

3.11.4.3 Madera County Noise Ordinance  

Section 9.58.020 of the Madera County Code contains general noise regulations for noise 

sources located within Madera County.  This section contains general regulations geared 

towards residences, schools, generation of motor vehicles, horns, etc., but does not contain 

numeric noise level standards for use in evaluating the compatibility of new projects with 

its surroundings.  Therefore, the County Noise Element standards (described above) and 

the CEQA guidelines (described below) are used to assess noise impacts for this Project. 

 

3.11.4.4 Noise Level Increase Significance Criteria  

It is generally recognized that an increase of at least 3 dB for similar noise sources is usually 

required before most people will perceive a change in noise levels, and an increase of 6 dB 

is required before the change will be clearly noticeable (Egan 1988).  

 

The Federal Interagency Commission on Noise (FICON) has developed a graduated scale 

for use in the assessment of project‐related noise level increases.  Table 3.11‐3, Significance 

of Chances  in Cumulative Noise Exposure, was developed by FICON  as  a means of 

developing thresholds for impact identification for project‐related noise level increases.  

The FICON standards have been used extensively in recent years by the authors of this 

section in the preparation of the noise sections of Environmental Impact Reports that have 

been certified in many California Cities and Counties.  

 

The rationale for the graduated scale used in the FICON standards is that test subject’s 

reactions  to  increases  in noise  levels varied depending on  the  starting  level of noise.  

Specifically, with  lower ambient noise environments, such as those below 60 dB Ldn, a 

larger  increase  in  noise  levels was  required  to  achieve  a  negative  reaction  than was 

necessary in more elevated noise environments. 

 

It should be noted that the use of the FICON standards for this analysis represent a change 

from  the  previous  noise  analysis.    This  change  was  implemented  to  provide more 

conservative thresholds for assessment of significance of project‐related noise increases.  

The previous analysis utilized a 3 dB threshold for a finding of noise impact, whereas the 

FICON standards, which are based on Federal research, utilize thresholds of 1.5 to 5 dB for 

significance criteria, depending on no‐project noise environments.  So where the lowest  

 

Page 125: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-14

threshold considered in the previous assessment was 3 dB, in this revised assessment using 

the FICON standards, that threshold has been lowered to 1.5 dB. 

 

The use of the FICON standards is also considered conservative relative to thresholds used 

by other agencies in the State of California.  For example, the California Department of 

Transportation (Caltrans) requires a project‐related traffic noise level increase of 12 dB for  

a finding of significance, and the California Energy Commission (CEC) considers project‐

related noise  level  increases  between  5‐10 dB  significant, depending  on  local  factors.  

Therefore,  the  use  of  the  FICON  standards, which  set  the  threshold  for  finding  of 

significant noise impacts as low as 1.5 dB, provide a very conservative approach to impact 

assessment for this Project. 

 

 

TABLE 3.11-3 SIGNIFICANCE OF CHANCES IN CUMULATIVE NOISE EXPOSURE

 Ambient Noise Level Without Project (Ldn) Increase Required for Significant Impact

Less than 60 dB  +5.0 dB or more 

60 to 65 dB  +3.0 dB or more 

Greater than 65 dB  +1.5 dB or more 

Source:  Federal Interagency Committee on Noise (FICON) 

 

 

Based on the FICON research, as shown in Table 3.11‐3, a 5 dB increase in noise levels due 

to a project is required for a finding of significant noise impact where ambient noise levels 

without  the project are  less  than 60 dB Ldn.   Where pre‐project ambient conditions are 

between 60 and 65 dB Ldn, a 3 dB increase is applied as the standard of significance.  Finally, 

in areas already exposed  to higher noise  levels, specifically pre‐project noise  levels  in  

excess  of  65  dB  Ldn,  a  1.5  dB  increase  is  considered  by  FICON  as  the  threshold  of 

significance.  This scale indicates that in quieter noise environments, test subjects tolerated 

a higher increase in noise levels due to a project before the onset of adverse noise impacts 

than did test subjects in louder environments.   

 

According to the FICON Study, “if screening analysis shows that noise‐sensitive areas will 

be at or above DNL 65 dB and will have an  increase of DNL 1.5 dB or more,  further 

analysis should be conducted”.  The FICON Study also reported the following: “Every 

change in the noise environment does not necessarily impact public health and welfare.”  

 

Page 126: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-15

3.11.5 Impacts and Mitigation Measures  

3.11.5.1 CEQA Environmental Checklist for Noise  

Criteria for determining the significance of noise and vibration impacts were developed 

based on information contained in the California Environmental Quality Act Guidelines 

(State CEQA Guidelines, Appendix G).  According to those guidelines, a project may have 

a significant effect on the environment if it will satisfy the following conditions: 

 

a. Exposure  of  persons  to  or  generation  of  noise  levels  in  excess  of  standards 

established in the local general plan or noise ordinance, or applicable standards of 

other agencies? 

b. Exposure  of  persons  to  or  generation  of  excessive  groundborne  vibration  or groundborne noise levels? 

c. A substantial permanent  increase  in ambient noise  levels  in  the project vicinity 

above levels existing without the project? 

d. A substantial temporary or periodic increase in ambient noise levels in the project 

vicinity above levels existing without the project? 

e. For a project located within an airport land use plan or, where such a plan has not 

been adopted, within two miles of a public airport or public use airport, would the 

project expose people residing or working  in the project area to excessive noise 

levels? 

f. For a project within  the vicinity of a private airstrip, would  the project expose 

people residing or working in the project area to excessive noise levels? 

 

3.11.5.2 Application of CEQA Guidelines to the Proposed Project – Standards of Significance  

The following specific standards were applied to the CEQA guidelines shown above for the 

assessment of project‐related noise and vibration impacts.   

 

a. Exterior noise levels of 60 dB Ldn at the building facades of residences constructed on 

agricultural properties for off‐site traffic noise sources, and the standards shown in 

Table 7.A.4 of  the Madera County Noise Element  for on‐site activities,  such as 

excavation and processing. 

b. Vibration impacts associated with blasting are considered significant if vibration 

levels within existing residential structures exceed 0.1 in/sec (ppv). 

Page 127: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-16

c. A substantial permanent increase in ambient noise levels is defined in Table 3.11‐3  

as being 1.5 to 5 dB, depending on pre‐project ambient noise levels.  A statement 

regarding  the  specific  noise  thresholds  to  use  for  finding  of  significant  noise 

increases due to the various aspects of the Project follows:    

 

For the assessment of impacts at the nearest residences due to average noise level 

increases  associated with  on‐site  activities,  Table  3.11‐1  indicates  that  existing 

average noise  levels at  the nearest  residences are  relatively quiet, with average 

daytime  levels ranging from 43‐49 dB Leq, and nighttime average levels ranging 

from  34‐47 dB Leq.   Given  these  low  ambient  levels,  the FICON  thresholds  for 

finding of  significant noise  impacts  indicate  that a 5 dB  increase would apply.  

Given  the  low pre‐Project ambient noise  levels, average daytime and nighttime 

noise level standards of 45 dB Leq and 40 dB Leq, respectively, would be appropriate 

for the assessment of noise impacts associated with on‐site activities affecting the 

nearby residences.  These standards are essentially 5 dB lower (more protective) 

than those recommended by the County in Table 3.11‐2.  Therefore, compliance with 

these standards would ensure compliance with the County’s noise standards.   

 

For the assessment of noise impacts at the nearest residences due to maximum noise 

level increases associated with on‐site activities, Table 3.11‐1 shows that daytime 

maximum noise levels at the nearest residences to the Project site routinely exceeded 

70 dB, with maximum noise levels generated by existing local activities measured  

in the mid to upper 70s and low 80s at some locations.  As a result, it appears that 

the application of the County’s 70 dB maximum daytime noise level standard and  

65 dB maximum nighttime standard would be a conservative means of assessing 

impacts  associated with  on‐site  activities  at  the  nearest  residences,  and  those 

standards are therefore applied to this Project. 

 

For the assessment of noise  impacts due to off‐site traffic  increases, particularly 

Project‐generated heavy truck traffic, the FICON standards shown in Table 3.11‐3 

are also used, with the appropriate significance threshold determined by the pre‐

Project traffic noise levels along the various roadways.  

 

d. A substantial temporary or periodic increase in ambient noise levels in the project 

vicinity above levels existing without the Project, defined in Table 3.11‐3 as being 

1.5  to  5  dB,  depending  on  pre‐project  levels.    The  thresholds  for  substantial 

Page 128: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-17

temporary  increases  are  the  same  as  those  described  above  in  Item  “c”  for 

permanent increases. 

 

e. Because this Project is not located within an airport land use plan or within 2 miles 

of a public airport or public use airport, item “e” of the CEQA guidelines shown 

above would not apply to this Project.  This approach is consistent with the DEIR 

and FEIR. 

 

f. Because this Project is not within the vicinity of a private airstrip, item “f” of the 

CEQA guidelines shown above would not apply to this Project.  This approach is 

consistent with the DEIR and FEIR. 

 

3.11.5.3 Methodology for Assessing Noise Impacts Associated with On-Site Equipment  

The major noise  sources  identified  for  this Project are  the aggregate mining activities 

(including blasting), aggregate crushing and screening activities (including truck load‐out), 

asphalt processing plant operations, and off‐site truck traffic.  The noise emissions of these 

various noise sources were obtained from Bollard Acoustical file data for similar sources 

and from published acoustical literature. 

 

Table 3.11‐4, Major Noise Producing Equipment and Associated Noise Levels, shows the 

noise levels for the various operations proposed at the Project site in terms of average and 

maximum noise levels.  These noise levels were obtained from Bollard Acoustical noise 

level measurements conducted at the Baldwin Construction Stoney Creek and Hallwood 

facilities, from file data for similar noise sources and from the Dry Creek Surface Mine Project 

EIR (SC#94112033, 12/95), the Kaweah River Rock Company’s Surface Mining Permit Project  

EIR  (SC#89032709 4/98), and  from  the Kaweah River Basin  Investigation Feasibility Study  

DEIR (6/96) and the Teichert Lincoln Aggregate Facility EIR (12/2000).  Appendix O‐3, Madera 

Quarry Noise Source Data, contains the linear octave band sound power levels for each of 

these operations.   

 

Distances  from  the  noise producing  equipment  shown  in Table  3.11‐4  to  the  nearest  

existing residence vary for each major component of the project.   To predict Project‐related 

noise levels at the nearest representative residences to the Project site, 14 representative 

residential receiver locations were identified as shown in Figure 3.11‐1.  Noise levels were 

computed at  those  locations using  the Environmental Noise Model  (ENM), which  is a 

sophisticated  three‐dimensional noise prediction model. The ENM  takes  into account 

Page 129: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-18

multiple noise sources and  locations,  topographic relief, vegetative ground cover, and 

atmospheric effects, in predicting noise levels at multiple receiver locations.   

 

 

TABLE 3.11-4 MAJOR NOISE-PRODUCING EQUIPMENT AND ASSOCIATED NOISE LEVELS

 Approximate Noise Level, dBA

@ 100 ft. Reference Dist. Equipment Type Maximum (Lmax) Average (Leq)

Excavation (including drilling but not blasting)  90  85 

Processing Equipment  85  80 

Asphalt Processing Plant  85  80 

Truck Load Out: On‐Site Traffic  75  65 

Notes:  Average noise  levels  represent  any  1‐hour period  and  assume  continuous  operation  of  the 

excavation and plant operations and maximum truck loadout conditions (100 trips in the peak 

hour). 

 

 

USGS Topographic maps, aerial photographs, and project grading plans were used  to 

digitize the locations of proposed noise sources, sensitive receptors, and the ground in 

between  the  sources  and  receivers.    Because  there  is  considerable  topographic  relief 

between the noise sources (especially as the mining equipment descends into the mining 

pit),  the  digitization  of  elevation  contours was  a  critical  component  of  this  analysis.  

Mining‐related noise levels were predicted for three scenarios; the equipment operating at 

the existing elevation during initial excavation and site preparation, the mining equipment 

operating half way into the pit, and the mining equipment operating near the base of the 

pit.  The asphalt and aggregate processing plants were located as indicated on the Project 

site plans.  As noted previously, the ENM Model can predict noise levels under a variety of 

atmospheric  conditions.   A  general description  of  the  effects  of  varying  atmospheric 

conditions is provided below. 

 

Atmospheric conditions can influence the transmission of sound over distance.  Changes  

in temperature, humidity, cloud cover, wind, and temperature inversions can all affect the 

propagation of sound from source to receiver.  These effects become more pronounced 

with increasing distance between the noise source and receptor, and were included in the 

analysis of Project‐related noise sources associated with the Project.  

 

Page 130: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-19

Temperature and relative humidity affect the transmission of sound by influencing both 

the density of air and the extent by which it is agitated.  For example, in high heat and 

humidity  conditions,  the  air  is  dense  and  agitated,  so  it  will  absorb  more  sound.  

Conversely, during cool and dry conditions, sound will encounter  less resistance as  it 

passes through air, and therefore it will carry further.  This explanation is a simplification, 

as  the relationship between  temperature, relative humidity, and sound propagation  is  

more complicated, in addition to being frequency dependent.   

 

During windy conditions over open level ground, wind gradients almost always exist.   

This is due to the friction between the moving air and the ground.  Due to these gradients, 

the speed of sound varies with height above ground.  This condition tends to refract, or 

bend, sound waves upward or downward, depending on whether the receiver is upwind 

or downwind from the source.   

 

At locations upwind from the sound source, wind gradients bend sound rays upward, 

thereby  reducing  sound  levels  at  the  receiver.   Conversely, downwind  locations will 

experience higher sound levels due to wind gradients bending sound rays downward.   

 

This analysis recognizes that wind speeds in the Project vicinity vary.  During such windy 

conditions, however, ambient noise levels in the community also increase.  This increase is 

due to the effects of wind passing through trees, over grasslands, and around structures. 

Once wind speeds exceed 5 mph, these effects become apparent, and ambient noise levels 

increase proportionately with wind speeds.   This distinction  is  important  in that noise 

impacts evaluated for this Project are identified relative to ambient noise levels.  So while 

windy  conditions will  tend  to  increase  Project‐related  noise  levels  in  the  downwind 

direction, at wind speeds exceeding 5 mph, this increase is expected to be masked by noise 

generated by the wind itself. 

 

Temperature gradients almost always exist due to heat exchange between the ground and 

the atmosphere.  As with wind gradients, temperature gradients tend to refract, or bend,  

sound waves upward or downward, depending on whether the gradient is positive or 

negative. 

 

During normal temperature lapses, air temperature decreases with increasing elevation.  

During  these conditions, warmer air near  the ground can cause sound waves  to bend 

upward, thus decreasing sound levels at the ground.  Conversely, air temperatures can 

become inverted, and sound will tend to focus and bend toward the ground. 

Page 131: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-20

It is recognized that temperature gradients can have a substantial effect on the propagation 

of sound over large distances.  The differences between a clear, calm summer day and  

night can range from 5‐10 at distances in excess of 1,000 feet from the noise source under 

ideal inversion conditions.   However, the actual level will depend on the strength and 

ceiling of the inversion.  

 

Project‐generated noise levels associated with various combinations of the atmospheric 

conditions described  above were  evaluated  for various operating  scenarios using  the  

ENM. Those operating scenarios are shown in Table 3.11‐5, Scenarios Evaluated for the 

Madera Quarry Project.  

 

The results of the ENM modeling effort are shown in Table 3.11‐6, Predicted Project Noise 

Levels from On‐Site Sources.  It should be noted that the Table 3.11‐6 data are intended to 

be representative of worst‐case operating conditions with respect to noise generation.  That 

is because all equipment associated with  the plant area was assumed  to be operating 

continuously and concurrently, and operations at the mining site were assumed to consist 

of maximum equipment operating during excavation.  These worst‐case operations are 

expected to be present only for as long as it takes to clear a sufficient amount of material to 

provide line‐of‐sight shielding to the operating equipment in the mining area.  Once the 

mining equipment is depressed in the pit, Project‐generated noise levels are predicted to  

be substantially attenuated, as indicated by Scenarios 4 and 5. 

 

 

TABLE 3.11-5 SCENARIOS EVALUATED FOR THE MADERA QUARRY PROJECT

 Scenario # Operations

1  Processing Equipment 

2  Asphalt Processing Plant 

3  Mining Top Surface  (Equipment at Elev 880) 

4  Mining Mid‐Point     (Equipment at Elev 600) 

5  Mining Base of Pit    (Equipment at Elev 350) 

6  Load Out & On‐Site Truck Traffic 

7  Combined Processing, Asphalt, Mining (880 ft), and Load Out 

8  Combined Processing, Asphalt, Mining (600 ft), and Load Out 

9  Combined Processing, Asphalt, Mining (350 ft), and Load Out 

Source:  Bollard Acoustical 

 

 

Page 132: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-21

TABLE 3.11-6 PREDICTED PROJECT NOISE LEVELS FROM ON-SITE SOURCES (LEQ, DB)

 Scenario

Receiver 1 2 3 4 5 6 7 8 9 1  22  25  25  14  6  6  29  27  27 

2  18  20  24  14  6  6  26  23  22 

3  26  24  11  11  11  12  28  28  28 

4  26  28  28  19  12  16  32  31  30 

5  14  15  20  12  3  4  22  19  18 

6  18  24  18  13  7  10  26  25  25 

7  19  26  26  18  14  12  30  27  27 

8  12  14  14  15  14  4  18  19  18 

9  13  12  17  15  15  0  19  18  18 

10  14  13  18  15  14  0  20  19  18 

11  18  16  21  18  17  0  24  22  22 

12  18  17  23  17  15  4  25  22  22 

13  24  33  36  30  17  15  38  35  34 

14  20  28  34  24  15  15  35  30  29 

Notes:  A description of analysis scenarios is provided in Table 3.11‐5. 

 

 

The Table 3.11‐6 data was generated assuming a typical spring/fall condition.  Specifically, 

the data were modeled assuming a 70 degree Fahrenheit (°F) average daytime temperature, 

and 30 percent relative humidity.  The model was also run with the above scenarios for 

winter conditions at 40°F and 50 percent humidity, as well as summer conditions at 90°F 

and 20 percent humidity.   The results of that analysis indicate that the predicted noise 

levels shown in Table 3.11‐6 are approximately 2 dB louder under winter conditions at the 

nearest residences, and 2 dB quieter at those same positions under summer conditions.  

Under low wind conditions, the noise levels shown in Table 3.11‐6 will be incrementally 

higher downwind, and incrementally lower upwind.  With higher winds, the wind will 

create it own noise, thereby masking the downwind increase in noise from the Project.  

Finally, Project noise levels are expected to be approximately 5 dB higher than those shown 

in Table 3.11‐6 under typical temperature inversion conditions.  

 

The Table 3.11‐6 data indicate that projected Madera Quarry noise levels would satisfy the 

recommended daytime and nighttime 45 dB and 40 dB Leq exterior noise level standards, 

respectively, at every identified existing noise‐sensitive area in the project vicinity under a 

variety of operating scenarios.    

 

Page 133: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-22

The reasons the predicted noise levels are well below the project’s standards of significance 

are due to the considerable distance between the proposed operations and noise‐sensitive 

areas, and because of significant existing and proposed intervening topography between 

the project site and those areas.  

 

3.11.5.4 Methodology for Assessing Blasting Noise and Vibration Impacts  

In addition to the aforementioned mining and processing noise sources, it will be necessary 

to  conduct blasting  to  free  the aggregate  resources  for  subsequent excavation.   Noise 

sources associated with blasting consist of rock drills and the shot itself.  The noise levels 

generated by the rock drills are dependant on drill type, but are predicted to be generally 

similar to the noise levels generated by excavation equipment, and are included in the 

levels described in the previous section pertaining to on‐site noise sources. 

 

Noise  generated  by  aggregate  shots  are more  variable, depending  on  the  amount  of  

charge‐material used, the number of holes and the depth of those holes, timing delays, and 

other factors.  There tends to be misconceptions regarding what an aggregate blast looks 

and sounds like, due in part to the types of explosions which are frequently seen in movies. 

 In reality, aggregate shots are designed to transfer the energy of the shot into the ground, 

rather than have it vent into the atmosphere sending rocks flying.   

 

Based on Bollard Acoustical observations of various aggregate shots in recent years, it is 

our opinion that aggregate shots are characteristic of muted thunder claps, rather than fiery 

explosions.   Based on BAC’s experience, maximum noise  levels during blasting at  the 

nearest residences are expected to be in the range of the measured existing noise levels  

reported in Table 3.11‐1 due to the considerable distances between the blasting areas and 

nearest residences, and substantial topographic shielding.   

 

With respect to blast induced vibration, the type, sizes, number, depth and timing delay 

sequence  of  the  charges,  as well  as  the  geology  of  the  surrounding  area, will  all  be  

variables which will affect  the  transmission of  that vibration  from  the site.   Bollard & 

Brennan Data collected at the San Rafael Rock Quarry of a blast in August of 2000, was 

used to generally estimate the magnitude of vibration which can be expected off‐site.  That 

blast consisted of 7,000 lbs of ANFO distributed in 17 holes each timed to detonate in a 

sequence, rather than all together.  The measured Peak Particle Velocity of that shot at a 

distance of 1,400 feet was 0.05 inches per second.  Given the assumption that vibration 

energy is radiating away from the blast site proportional to inverse square law, the level of 

Page 134: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-23

vibration energy present at 3,000 feet from the mining area would be less than it would be 

at 1,400 feet.  The resulting PPV then at the nearest identified sensitive areas is estimated to 

be well below the thresholds for both annoyance (0.1 inches/second PPV), with even higher 

levels required for damage to structures.  

 

3.11.5.5 Methodology for Assessing Off-Site Truck Traffic Noise Levels  

To assess Project‐related  traffic noise  impacts,  traffic noise  levels are predicted at  the 

nearest representative residential receptors in terms of distances from the centerlines of  

the local roadway network to those nearest residences.  This approach represents a change 

in noise impact assessment relative to the previous noise analysis prepared for this Project 

by providing a more focused impact assessment at actual residences.  Noise impacts are 

identified at existing noise‐sensitive areas if the noise level increases which result from the 

Project exceed the significance thresholds described previously in this section. 

 

To  describe  existing  and  projected  noise  levels  due  to  traffic,  the  Federal Highway 

Administration Highway Traffic Noise Prediction Model (FHWA RD‐77‐108) was used.  

The model is based upon the Calveno reference noise factors for automobiles, medium 

trucks and heavy  trucks, with consideration given  to vehicle volume, speed, roadway 

configuration, distance to the receiver, and the acoustical characteristics of the site.  The 

FHWA  model  was  developed  to  predict  hourly  Leq  values  for  free‐flowing  traffic 

conditions.  To predict traffic noise levels in terms of Ldn, it is necessary to adjust the input 

volume to account for the day/night distribution of traffic. 

 

Traffic volumes for future conditions and scenarios are contained in the Transportation 

Section of  this EIR.   A  listing of  the FHWA Model  input data  for  future conditions  is 

provided in Appendix O‐4, FHWA‐RD‐77‐108 Highway Traffic Noise Prediction Model.  

Table  3.11‐7,  Project‐Related  Changes  in  Existing  Traffic  Noise  Levels  at  Existing 

Residences, and Table 3.11‐8, Project‐Related Changes in Cumulative Traffic Noise Levels, 

show the predicted existing and cumulative traffic noise levels for the Project, respectively, 

relative to no‐project conditions.  This Table is provided in terms of Ldn at the approximate 

distances (in feet from roadway centerline) to existing residences.  

 

 

Page 135: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-24

TABLE 3.11-7 PROJECT-RELATED CHANGES IN EXISTING TRAFFIC NOISE LEVELS AT EXISTING RESIDENCES

 Ldn (dB)

Roadway Section Distance from C/L to

nearest Residence, Ft. Existing Existing

+ Project dB Road 209  SR 41 to Project Site  300  47.5a  55.8  +8.3 

North of Road 209  100  67.9  68.1  +0.2 

Road 209 to SR 145  No Residences along this segment  N/A 

SR 41 

South of SR 145  100  67.2  68.4  +1.2 

West of SR 41  100  62.7  64.8  +2.1 SR 145 

East of SR 41  200  54.7  55.3  +0.6 

Source:  Bollard & Brennan, Inc., using FHWA RD‐77‐108 with inputs from the Traffic Section, updated for 

distance by Bollard Acoustical Consultants. 

Notes: 

Existing no‐project noise levels at the nearest residence on Road 209 between SR 41 and the Project site are 

predicted to reach a practical minimum of approximately 47.5 dB Ldn.  This level is based on the measured 

ambient noise monitoring  results shown  for remote receiver  locations  in  the  immediate project vicinity 

(Table 3.11‐1) with  consideration of  the  contribution of Highway 41  to background noise  levels at  this 

location. 

 

 

For example, the nearest identified residence to County Road 209 is located approximately 

300 feet from the centerline of that roadway.  As a result, noise impact assessment at that 

location rather  than at a  theoretical distance of 100  feet provides a more accurate and 

realistic assessment of Project noise impacts.  Although noise levels from traffic on County 

Road 209 without the Project would be below the indicated 47.5 dB Ldn value identified for 

no‐project conditions at  this residence,  the  level of 47.5 dB Ldn assumed  for no‐project 

conditions at that residence represents a practical minimum noise exposure for all sources 

of ambient noise.  The use of this level is supported by the noise level data shown in Table 

3.11‐1  for  remote  locations  removed  from  significant  roadway  noise  sources,  and 

consideration of the contribution of Highway 41 traffic noise levels to the overall ambient 

noise conditions at this residence.  

 

 

Page 136: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-25

TABLE 3.11-8 PROJECT-RELATED CHANGES IN CUMULATIVE TRAFFIC NOISE LEVELS

 Ldn (dB)

Roadway Section Distance (ft) Cumulative Cum. + Project Difference

Road 209  Nearest Residence to Roadway  300  47.5a  55.8  +8.3 

North of Road 209  100  70.0  70.1  +0.1 

Road 209 to SR 145  No residences along this segment  N/A 

SR 41 

South of SR 145  100  69.6  70.3  +0.7 

West of SR 41  100  64.7  65.3  +0.6 SR 145 

East of SR 41  200  59.3  59.6  +0.3 

Source:  Bollard & Brennan, Inc., using FHWA RD‐77‐108 with inputs from the Traffic Section, updated for 

distance by Bollard Acoustical Consultants. 

Notes: 

Cumulative no‐project noise levels at the nearest residence on Road 209 between SR 41 and the Project site 

are predicted to reach a practical minimum of approximately 47.5 dB Ldn.  This level is based on the measured 

ambient noise monitoring  results shown  for  remote  receiver  locations  in  the  immediate project vicinity 

(Table 3.11‐1) with  consideration of  the  contribution of Highway 41  to background noise  levels at  this 

location. 

 

 

3.11.5.6 Methodology for Assessing Construction Noise Impacts  

During  the  construction  phases  of  the  Project,  including  noise  generated  by  the 

reconstruction of portions of County Road 209, noise from construction activities would 

add to the noise environment in the immediate Project vicinity.   Activities involved in 

construction would generate maximum noise levels ranging from 85 to 90 dB at a distance 

of 100 feet.  Construction activities, including construction of County Road 209, would be 

temporary in nature and are reported to occur only during normal daytime working hours.  

 

Noise would also be generated during the construction phase by increased truck traffic on 

area  roadways.   A  significant  project‐generated  noise  source would  be  truck  traffic 

associated with transport of heavy materials and equipment to and from the construction 

site.  This noise increase would be of relatively short duration, and are proposed to occur 

only during daytime hours. 

 

Page 137: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-26

3.11.5.7 Specific Project Impacts and Noise Mitigation Measures   

Impact 3.11-1: Noise Impacts Associated with On-Site Activities (Mining, Aggregate Processing, Asphalt Processing, and Loadout)

 

Scenario  7  of  Table  3.11‐6  indicates  that  average  noise  levels  generated  by 

excavation (excluding blasting – see Impact 3.11‐2), aggregate processing, asphalt 

processing, and heavy truck load out from the site, are predicted to range from 18  

to 38 dB Leq during worst case mining operations (i.e., those at existing grade before 

the equipment descends into the mine pit).  Once the equipment descends into the 

pit, average noise levels are predicted to be reduced as the excavation equipment 

becomes shielded by the pit walls.   Although noise from on‐site operations will 

occasionally be audible at the nearest residences, the predicted noise levels would 

not constitute a significant  increase  in ambient conditions.   For this reason, and 

because the predicted levels would satisfy the Noise Element standards of Madera 

County, this impact is considered less than significant. 

 

Level of Significance Before Mitigation:  Less than Significant 

 

Mitigation Measures:  None Required 

 

Impact 3.11-2: Noise and Vibration Impacts Associated with Blasting  

Noise and vibration associated with blasting  is dependant on several variables.  

Based  on  the  data  used  to  assess  impacts  for  this  Project,  and  the  substantial 

distances between the area where the shots will occur and the nearest residences, 

blasting  noise  and  vibration  levels  are  not  predicted  to  significantly  exceed 

background noise levels or Madera County standards.  Provided blast parameters 

are of an equal or lower magnitude that those reported in the methodology section 

(7,000 lbs of ANFO distributed in 17 holes each timed to detonate in a sequence, 

rather than all together), this impact is considered to be less than significant.  If, 

however, more intensive blast parameters than those shown above are proposed, 

this impact would be considered potentially significant.    

 

Level of Significance Before Mitigation:  Potentially Significant 

 

Page 138: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-27

Mitigation Measures:  Mitigation Measure 3.11‐2 

 

If blasting loads exceed 7,000 pounds of ANFO, or the equivalent, a blasting consultant shall 

develop a blasting program which results  in vibration  levels of  less  than 0.1  inches per 

second and noise levels of 80 dBA Lmax or less at the nearest residences.  The plan shall be 

submitted to the County for review prior to commencement of blasting activities on the 

Project site.  

 

Level of Significance After Mitigation:  Less than Significant 

 

Impact 3.11-3: Noise Impacts Due to Project-Related Increases in Existing Off-Site Traffic Noise Levels

 

The Table 3.11‐6 data indicate that the Project‐related traffic noise level increase  

over no‐project levels will range from 0.2 to 3.8 dB Ldn.  The FICON methodology 

dictates that a finding of significant noise impact would be 5 dB where no‐project 

noise levels are below 60 dB Ldn, 3 dB where no‐project noise levels range from 60 to 

65 dB Ldn, and 1.5 dB where no‐project noise levels exceed 65 dB Ldn.   

 

Noise Impacts Along State Route 145  

Table 3.11‐6 shows that the SR 145 existing traffic noise levels without the Project 

range from 60‐65 dB Ldn west of SR 41, and less than 60 dB Ldn at existing residences 

east of SR 41.  As a result, the Project would be subject to significance thresholds of 3 

dB west of SR 41, and 5 dB east of SR 41.  Because the predicted Project‐related noise 

increases for this roadway are 2.1 dB west of SR 41, and 0.6 dB east of SR 41, which 

do not exceed the above‐described significance thresholds, noise impacts along this 

roadway for existing plus project conditions are predicted to be less than significant. 

This conclusion is consistent with the findings of the previous noise analysis. 

 

Noise Impacts Along State Route 41  

Table 3.11‐6 shows that the SR 41 existing traffic noise levels without the Project 

exceed 65 dB Ldn at a 100‐foot reference distance from the centerline.  Note that there 

are no residences located along this roadway between SR 145 and County Road 209 

to be affected, so there are no noise impacts along that segment of SR 41.  At existing 

residences north of CR 209, or south of SR 145, the Project would be subject to a 

Page 139: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-28

significance  threshold  of  1.5  dB.    Because  the  predicted  Project‐related  noise 

increases for this roadway range from 0.2 dB North of CR 209, and 1.2 dB south of 

SR 145, which do not exceed the 1.5 dB significance threshold, noise impacts along 

this  roadway  for  existing plus project  conditions  are predicted  to be  less  than 

significant.  This conclusion is consistent with the findings of the previous noise 

analysis. 

 

Noise Impacts Along County Road 209  

Finally, Table 3.11‐6 shows that the County Road 209 existing traffic noise  level 

without the Project would be less than 60 dB Ldn at the nearest residence located 300 

feet from that roadway.  As a result, the Project would be subject to a significance 

threshold of 5 dB along this roadway.  Although the predicted Project‐related noise 

increase for this roadway segment were shown in the previous noise study to be 

approximately 16 dB at a reference position 100 feet from the centerline, no noise‐

sensitive land uses exist at that distance.   

 

Impact 3.11-3a: Noise Impacts Due to Project-Related Increases in Existing Off-Site Traffic Noise Levels

 

At the nearest residence, located 300 feet from the roadway centerline, the predicted 

Project‐related traffic noise level increase is estimated to be approximately 8.3 dB 

Ldn, as indicated in Table 3.11‐6.  Because this increase exceeds the 5 dB significance 

threshold, noise impacts at this nearest identified residence to County Road 209 for 

existing plus project conditions would have been predicted to be significant.  This 

conclusion is consistent with the findings of the previous noise analysis, but with a 

diminished severity of impact. 

 

However, a Memorandum of Agreement Regarding Noise Impacts and Covenant 

Running with the Land became effective February 13, 2009 between the Applicant 

and the owner of this small vacant residence (see Appendix F, Compensation and 

Grazing Agreement Waiving Potential Noise Impacts to Residents for Mining and 

Asphalt Project Truck Traffic, Between Madera Quarry, Inc. and the Wagner Family 

Trust).  The agreement underlying the memorandum will require the Applicant pay 

to the owner the sum of $142,600 at such time as Applicant procures all entitlements 

to undertake the Project.   

 

Page 140: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-29

Section 4.A of the agreement (see Appendix F of this DREIR) provides: 

 

Waiver of Noise Impact, Creation of Noise Easement and Covenant 

Running  with  the  Land.    The  Grazing  Consideration  and  Cash 

Consideration are tendered in exchange for Trust agreeing that any noise 

impacts  to  the Residence  depicted  on  Exhibit  ʺAʺ  (or  any  replacement 

residence constructed within a 100 foot radius of the Residence), in specific, 

shall be deemed impacts for which it has been compensated.  MQI and Trust 

intend  that  this  Agreement,  and  the  covenants  created  herein,  shall 

constitute covenants running with the land (the Trust Property and Project 

Site traffic), and/or an easement or servitude attached to the land as defined 

in California Civil Code Section 1462, so as to bind and benefit successors, 

heirs and assigns of the parties.  

 

As long as the property owner either a) ceases using this building as a residence; or 

b) uses the payment to attenuate any sound impacts that would be visited upon it, 

then  the  Impact will be  fully mitigated.    ’Mitigation’,  as defined  in  the CEQA 

Guidelines (Section 15370), includes compensating for the impact by replacing or 

providing substitute resources or environments.  The funds payable to the property 

owner  under  the  agreement would,  if  properly  utilized,  provide  the  type  of 

compensation set forth in Section 15370.  However, it is not possible to state with 

certainty that the property owner will use the funds to mitigate any noise impacts.  

To the extent the owner of the residence located approximately 300 feet from the 

centerline of CR 209 chooses not to spend the money for the purposes for which it 

was intended, the impact would remain significant and unavoidable.  

 

Level of Significance Before Mitigation:  Significant 

 

Mitigation Measures:  Mitigation Measure 3.11‐3a 

 

There is one receptor, a residence on the Wagner Family Trust (Wagner) property, which 

could be impacted by the Project.  In an effort to mitigate any noise impact at the residence to 

a  less  than  significant  level,  the Applicant  entered  into a “Compensation and Grazing 

Agreement Waiving Potential Noise Impacts to Residents for Mining and Asphalt Project 

Truck Traffic, between Madera Quarry, Inc. and the Wagner Family Trust”, dated February 

2009 (see Appendix F).  

 

Page 141: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-30

Level of Significance After Mitigation:  As there is no assurance that Wagner will 

use the compensation to make noise reducing improvements to the residence, this 

impact will remain as significant and unavoidable. 

 

Impact 3.11-3b: Noise Impacts Due to Project-Related Increases in Existing Off-Site Traffic Noise Levels

 

The next closest residence to CR 209 was identified as being approximately 600 feet 

from the centerline of that roadway.   Due to this considerable distance, existing 

County Road 209 traffic noise levels without the Project would be less than 60 dB Ldn 

at  that  residence.   As  a  result,  the  Project would  be  subject  to  a  significance 

threshold of 5 dB along this roadway.  At the 600‐foot distance from the centerline, 

the  predicted  Project‐related  traffic  noise  level  increase  is  estimated  to  be 

approximately  3.8  dB  Ldn.    Because  this  increase  does  not  exceed  the  5  dB 

significance  threshold, noise  impacts at  this next nearest  identified residence  to 

County Road 209, located approximately 600 feet from the roadway centerline, for 

existing plus project  conditions  are predicted  to  be  less  than  significant.   This 

conclusion  is different  from  the  findings of  the previous noise  analysis, which 

assessed noise impacts at 100 feet, rather than at the actual location of the nearest 

residences to CR 209. 

 

Level of Significance Before Mitigation:  Less than Significant 

 

Mitigation Measures:  None Required 

 

3.2.5.8 Cumulative Noise Impacts  

Impact 3.11-4: Noise Impacts Due to Project-Related Increases in Cumulative Off-Site Traffic Noise Levels

 

The Table 3.11‐7 data indicate that the Project‐related traffic noise level increase over 

no‐project levels will range from 0.1 to 3.8 dB Ldn.  The FICON methodology dictates 

that a finding of significant noise  impact would be 5 dB where no‐project noise 

levels are below 60 dB Ldn, 3 dB where no‐project noise levels range from 60 to 65 dB 

Ldn, and 1.5 dB where no‐project noise levels exceed 65 dB Ldn.   

 

Page 142: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-31

Noise Impacts Along State Route 145  

Table 3.11‐7 shows that the cumulative SR 145 traffic noise levels without the Project 

range from 60‐65 dB Ldn west of SR 41, and less than 60 dB Ldn at existing residences 

east of SR 41.  As a result, the Project would be subject to significance thresholds of 3 

dB west of SR 41, and 5 dB east of SR 41.  Because the predicted Project‐related noise 

increases for this roadway are 0.6 dB west of SR 41, and 0.3 dB east of SR 41, which 

do not exceed the above‐described significance thresholds, noise impacts along this 

roadway  for Cumulative  Plus  Project  conditions  are  predicted  to  be  less  than 

significant.  This conclusion is consistent with the findings of the previous noise 

analysis. 

 

Noise Impacts Along State Route 41  

Table 3.11‐7 shows that the cumulative SR 41 traffic noise levels without the Project 

exceed 65 dB Ldn at a 100‐foot reference distance from the centerline.  Note that there 

are no residences located along this roadway between SR 145 and County Road 209 

to be affected, so there are no noise impacts along that segment of SR 41.  At existing 

residences north of CR 209, or south of SR 145, the Project would be subject to a 

significance  threshold  of  1.5  dB.    Because  the  predicted  Project‐related  noise 

increases for this roadway range from 0.1 dB North of CR 209, and 0.7 dB south of 

SR 145, which are well below the 1.5 dB significance threshold, noise impacts along 

this roadway for Cumulative Plus Project conditions are predicted to be less than 

significant.  This conclusion is consistent with the findings of the previous noise 

analysis. 

 

Noise Impacts Along County Road 209  

Finally, Table 3.11‐7 shows that the County Road 209 existing traffic noise  level 

without the Project would be less than 60 dB Ldn at the nearest residence located 300 

feet from that roadway.  As a result, the Project would be subject to a significance 

threshold of 5 dB along this roadway.  Although the predicted Project‐related noise 

increase for this roadway segment were shown in the previous noise study to be 

approximately 16 dB at a reference position 100 feet from the centerline, no noise‐

sensitive land uses exist at that distance.   

 

Page 143: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-32

Impact 3.11-4a: Noise Impacts Due to Project-Related Increases in Cumulative Off-Site Traffic Noise Levels

 

At the nearest residence, located 300 feet from the roadway centerline, the predicted 

Project‐related traffic noise level increase is estimated to be approximately 8.3 dB 

Ldn, as indicated in Table 3.11‐7.  Because this increase exceeds the 5 dB significance 

threshold, noise impacts at this nearest identified residence to County Road 209 for 

existing plus project conditions would have been predicted to be significant.  This 

conclusion is consistent with the findings of the previous noise analysis, but with a 

diminished severity of impact. 

 

However, a Memorandum of Agreement Regarding Noise Impacts and Covenant 

Running with the Land became effective February 13, 2009 between the Applicant 

and the owner of this small vacant residence (see Appendix F, Compensation and 

Grazing Agreement Waiving Potential Noise Impacts to Residents for Mining and 

Asphalt Project Truck Traffic, Between Madera Quarry, Inc. and the Wagner Family 

Trust).   The agreement underlying the memorandum will require the Applicant  

pay  to  the  owner  the  sum  of  $142,600  at  such  time  as Applicant  procures  all 

entitlements to undertake the Project.   

 

Section 4.A of the agreement (see Appendix F of this DREIR) provides: 

 

Waiver of Noise Impact, Creation of Noise Easement and Covenant Running 

with the Land.  The Grazing Consideration and Cash Consideration are tendered in 

exchange for Trust agreeing that any noise impacts to the Residence depicted on 

Exhibit ʺAʺ (or any replacement residence constructed within a 100 foot radius of 

the  Residence),  in  specific,  shall  be  deemed  impacts  for  which  it  has  been 

compensated.  MQI and Trust intend that this Agreement, and the covenants created 

herein, shall constitute covenants running with the land (the Trust Property and 

Project Site traffic), and/or an easement or servitude attached to the land as defined 

in California Civil Code Section 1462, so as to bind and benefit successors, heirs and 

assigns of the parties.   

 

As long as the property owner either a) ceases using this building as a residence; or 

b) uses the payment to attenuate any sound impacts that would be visited upon it, 

then  the  Impact will be  fully mitigated.    ’Mitigation’,  as defined  in  the CEQA 

Guidelines (Section 15370) includes compensating for the impact by replacing or 

Page 144: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-33

providing substitute resources or environments.  The funds payable to the property 

owner  under  the  agreement would,  if  properly  utilized,  provide  the  type  of 

compensation set forth in Section 15370.  However, it is not possible to state with 

certainty that the property owner will use the funds to mitigate any noise impacts.  

To the extent the owner of the residence located approximately 300 feet from the 

centerline of CR 209 chooses not to spend the money for the purposes for which it 

was intended, the impact would remain significant and unavoidable.   

 

Level of Significance Before Mitigation:  Significant 

 

Mitigation Measures:  Mitigation Measure 3.11‐4a    

 

There is one receptor, a residence on the Wagner Family Trust (Wagner) property, which 

could be impacted by the Project.  In an effort to mitigate any noise impact at the residence to 

a  less  than  significant  level,  the Applicant  entered  into a “Compensation and Grazing 

Agreement Waiving Potential Noise Impacts to Residents for Mining and Asphalt Project 

Truck Traffic, between Madera Quarry, Inc. and the Wagner Family Trust”, dated February 

2009 (see Appendix F). 

 

Level of Significance After Mitigation:  As there is no assurance that Wagner will 

use the compensation to make noise reducing improvements to the residence, this 

impact will remain as significant and unavoidable. 

 

Impact 3.11-4b: Noise Impacts Due to Project-Related Increases in Cumulative Off-Site Traffic Noise Levels

 

The next closest residence to CR 209 was identified as being approximately 600 feet 

from the centerline of that roadway.   Due to this considerable distance, existing 

County Road 209 traffic noise levels without the Project would be less than 60 dB Ldn 

at  that  residence.   As  a  result,  the  Project would  be  subject  to  a  significance 

threshold of 5 dB along this roadway.  Although the predicted Project‐related noise 

increase for this roadway segment was shown in the previous noise study to be 

approximately 16 dB at a position 100 feet from the centerline, that increase would 

not apply  to  this  residence because  it  is  located 600  feet, not 100  feet,  from  the 

roadway centerline.   At  the 600‐foot distance  from  the centerline,  the predicted 

Project‐related traffic noise level increase is estimated to be approximately 3.8 dB 

Ldn.  Because this increase does not exceed the 5 dB significance threshold, noise 

Page 145: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.2 Revisions to Noise and Vibration Section

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.2-34

impacts  at  this  next  nearest  identified  residence  to County  Road  209,  located 

approximately  600  feet  from  the  roadway  centerline  for  existing  plus  project 

conditions are predicted to be less than significant.  This conclusion is different from 

the findings of the previous noise analysis, which assessed noise impacts at 100 feet, 

rather than at the actual location of the nearest residences to CR 209. 

 

Level of Significance Before Mitigation:  Less than Significant 

 

Mitigation Measures:  None Required 

 

Page 146: MADERA QUARRY PROJECT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.3 REVISIONS TO TRAFFIC SECTION IN RESPONSE TO JUDICIAL DECISION

Page 147: MADERA QUARRY PROJECT

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-1

 

 

 

 

 

 

 

 

 

 

3.3 REVISIONS TO TRAFFIC SECTION IN RESPONSE TO JUDICIAL DECISIONS1

 

 

 

3.12.1 Introduction  

This section presents  the  results of a  traffic  impact study performed  for  the proposed 

Madera Quarry Project.   The analysis focuses on the potential traffic impacts that may 

be generated by the Project on nearby roads and intersections.  This section was revised 

to address the concerns expressed by the Court of Appeals and Superior Court (Judicial 

Decisions), as noted in Section 1.0 of this DREIR.  The Court of Appeal determined that 

the mitigation measure for paying a ‘fair share’ impact fee was an improper deferral of 

the mitigation of cumulative  traffic  impacts.   As  the baseline conditions had changed 

since the certification of the EIR, it was necessary to undertake a new traffic analysis of 

existing conditions as well as 2030 cumulative conditions.2 

 

Recently the County adopted the “Madera County Road Impact Fee Program Update, 

November 2009”  (Fee Program), which  is attached as Appendix N.   The Fee Program 

sets  forth  a  methodology  for  identifying  and  prioritizing  candidate  projects;  co‐

ordination  with  affected  agencies;  identifying  improvement  projects;  and  the 

development of base road and highway segment data.  Projects will be identified based 

on various criteria which among other items will only consider projects having LOS E 

or F.   

 

1 These subsections will all reference 3.12 to keep this consistent with the numbering of the EIR. 2 The EIR considered year 2025 cumulative conditions.

Page 148: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

3.12.2 Affected Environment  

3.12.2.1 Project Elements Affecting Traffic  

Section 6.4, Mineral Resources, of  the 1995 Madera County General Plan  states: “The 

most  significant  resources  in  terms  of  abundance,  demand,  and  economic  value,  is 

aggregate.”  The Madera Quarry Project (Project) is an aggregate mine.  The Project site 

is  located  on Road  209 northeast  of  the City  of Madera.   The Project  is  also  in  close 

proximity  to  the Fresno‐Clovis area by access of State Route  (SR) 41.   Road 209 starts 

about a half mile from the intersection of SR 41 and SR 145, the Four Corners region of 

Madera County.  From the Four Corners region traveling north toward Oakhurst on SR 

41,  SR  41  curves  to  the northeast.   At  this  curve, Road  209  starts  and  continues  in  a 

northerly direction until it reaches the Hildreth Creek about two and half miles from the 

intersection with SR 41.   Road 209  then  follows  the natural streambed continuing  in a 

predominately northerly direction.   The  existing  road  and  stream have gentle  curves 

and grades until the road crosses the creek approximately a mile along the streambed.  

From  this point, curves on Road 209 become  sharper and  the grades become  steeper.  

These geometric features continue to the Project site, approximately another mile from 

the  creek  crossing.    Road  209  then  terminates  approximately  three‐quarters  of mile 

north of the Project site, at Road 406.  Road 406 is a predominately east/west road with 

its easterly connection at SR 41 and its westerly connection at Road 400, or River Road, 

just  south  of  Hensley  Lake,  (Madera  County  Resource  Management  Agency  Road 

Department, 2004). 

 

The Project  is an aggregate mining operation  located on Road 209 approximately  two 

miles west of SR 41 and  four miles north of SR 145  in Madera County, California.   A 

vicinity map showing nearby roadways  is shown  in Figure 3.12‐1, Vicinity Map.   The 

Project consists of a proposed 121‐acre hardrock quarry with processing  facilities and 

hot mix  asphalt  plant.   Maximum  output  at  the  site will  be  900,000  tons  per  year.  

Typical operating hours will be  from  6:00  a.m.  to  7:00 p.m. Monday  through Friday.  

The  asphalt  batch  plant would  operate  from  5:00  a.m.  to  7:00  p.m.    PG&E may,  on 

occasion,  require nighttime operations  to  reduce peak power usage.   The Project will 

employ  15  to  20  persons.    The  Project  is  expected  to  realign  and/or  reconstruct  a 

majority of Road 209 between the site and SR 41. 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-2

Page 149: MADERA QUARRY PROJECT
Page 150: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

3.12.2.2 Study Area and Time Period  

The  intersections chosen for analysis and discussed  in this section were determined  in 

consultation with Madera County Road Department staff and Caltrans staff; the scope 

of  the  traffic  impact  analysis  was  agreed  upon  and  approved  by  County  Road 

Department  staff prior  to  beginning  the  study.   This  section  includes  analysis  of  the 

following intersections and road segments: 

 Study Intersections Study Roadway Segments

1.  State Route 41 / Road 209  1.  State Route 41 (Road 209 to Road 406) 

2.  State Route 41 / State Route 145  2.  State Route 41 (SR 145 to Road 209) 

3.  State Route 41 / Avenue 15  3.  State Route 41 (Ave 15 to SR 145) 

4.  State Route 41 / Road 204 / Avenue 14‐1/2   4.  State Route 41 (Road 204/Avenue 14‐1/2 to Ave 15) 

5.  State Route 41 / Avenue 12  5.  State Route 41 (Ave 12 to Road 204) 

  6.  State Route 145 (SR 41 to Road 400) 

 

The time periods of the analysis included the weekday a.m. and p.m. peak hours, which 

typically occur within  the  time periods between 7:00 and 9:00 a.m. and between 4:00 

and  6:00 p.m.   PG&E may, on occasion,  require nighttime operations  to  reduce peak 

power usage.    In addition,  the project may be  required  to serve  jobs  that do not  take 

place during  typical hours of operation under  either  scenario;  the background  traffic 

would be less than under peak traffic conditions.   The peak‐hour scenarios were to be 

analyzed for the following conditions: 

 

Existing Conditions; 

Existing Plus Project Conditions; 

Cumulative Conditions Without Project (Year 2030); and 

Cumulative Conditions With Project (Year 2030). 

 

3.12.2.3 Existing Lane Configurations  

The  existing  lane  configurations  at  each  of  the  intersections  studied  are  shown  on 

Figure 3.12‐2, Existing Lane Configurations.   

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-4

Page 151: MADERA QUARRY PROJECT
Page 152: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

3.12.2.4 Planned Improvements  

It  is anticipated that SR 41 will eventually be converted to a freeway from the current 

end  of  freeway north  of Childrens Boulevard  to north  of  SR  145.    In  the  future  it  is 

expected  that  new  interchanges  will  be  constructed  along  SR  41  at  the  following 

locations:  1) Avenue 12, 2) Avenue 15, and 3) SR 145.  With the construction of a new 

freeway,  access  would  not  be  provided  from  Avenue  14‐1/2.    At  the  other  study 

locations,  this  report assumes  that  the existing  lane configurations will be maintained 

through the year 2030, unless specific impacts requiring mitigations are identified.  The 

assumed year 2030 lane configurations and intersection control are presented in Figure 

3.12‐3, Cumulative Lane Configurations.   

 

3.12.3 Traffic Methodology  

Passenger car equivalents (PCE) represent the number of passenger cars displaced by a 

single heavy vehicle  (trucks with 3 axles or more) under certain roadway,  traffic, and 

control conditions.   The use of PCEs compensates for the operational characteristics of 

heavy  vehicles  as well  as  the  roadway  space  displaced.   Use  of  PCEs  in  the  traffic 

analysis generally  results  in  recommendations  for wider  roadways  and  intersections, 

which increase the capacity of the facilities and provide for better operating conditions 

and enhanced safety for the traveling public. 

 

The  2000  Highway  Capacity  Manual  recommends  a  PCE  factor  of  2.0  for  heavy 

vehicles, which is an average for all heavy vehicle sizes.  Based on the type of aggregate 

transfer trucks that will be utilized for this operation (i.e. 25‐ton capacity 5‐axle truck), a 

greater PCE  factor  is reasonable because  these  trucks are  long, heavy, accelerate more 

slowly, and require more distance to decelerate.  A PCE of 2.5 was applied to the Project 

traffic volumes.  The project traffic volumes, adjusted for PCEs, are presented in Figure 

3.12‐4, Opening Day Project Traffic Volumes, and Figure 3.12‐5, Ultimate Project Traffic 

Volumes. 

 

3.12.3.1 Level of Service  

The Madera County General  Plan  Background Report  provides  further  definition  of 

traffic  impacts at  signalized  intersections and  roadway  segments.   LOS  for  signalized 

intersections is defined in terms of volume‐to‐capacity (V/C) ratio as well as by delays 

for vehicles at  intersections as shown  in Table 3.12‐1, Madera County Level of Service 

Definitions for Signalized Intersections.  

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-6

Page 153: MADERA QUARRY PROJECT
Page 154: MADERA QUARRY PROJECT
Page 155: MADERA QUARRY PROJECT
Page 156: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

Since publication of the data provided in Table 3.12‐1, revisions in analysis techniques 

and  LOS  definitions  have  been  published  in  the  2000  version  of  the  Transportation 

Research  Board  Highway  Capacity  Manual  for  both  signalized  and  unsignalized 

intersections.  LOS characteristics as currently defined by the Highway Capacity Manual 

and  utilized  in  current  analysis  software  for  both  unsignalized  and  signalized 

intersections  are  presented  in  Table  3.12‐2,  Level  of  Service  Characteristics  for 

Unsignalized  Intersections,  and  Table  3.12‐3,  Level  of  Service  Characteristics  for 

Signalized Intersections, respectively. 

 

Madera  County  has  developed  a  technique  of  evaluating  the  LOS  on  the  basis  of 

“segment  capacity.”   The  segment  capacity varies by  roadway  category, as  shown  in 

Table  3.12‐4,  Capacities  per  Hour  per  Lane  for  Various  Highway  Facilities  in  the 

Madera County. 

 

The  County’s  General  Plan  Policy  Document  provides  further  guidance  on  the 

application  of  this  information  to  the Project.   According  to LOS Policy  2.A.8  in  the 

Transportation  and  Circulation  Section,  the  County  shall  develop  and  manage  its 

roadway system to maintain a minimum LOS of D on all State and County roadways.  

LOS measured for roadway segments are based on the capacities shown in Table 3.12‐4.  

In addition, if a project introduces more than 50 peak‐hour trips, then a more detailed 

and focused traffic analysis would be required.   

 

A  traffic  impact  is considered significant  if  it  renders an unacceptable  level of service 

(LOS)  on  a  street  segment  or  signalized  intersection,  or  if  it  worsens  already 

unacceptable conditions on a street or at a signalized  intersection.   According  to LOS 

Policy 2.A.8  in  the Transportation and Circulation Section of  the General Plan Policy 

Document,  the County  shall develop  and manage  its  roadway  system  to maintain  a 

minimum LOS of D on all State and County roadways. 

 

Caltrans  typically  requires  that  LOS  C  or  better  be  maintained  on  State  facilities.  

However, where an intersection experiences a LOS below C, warrants for all‐way stop 

control  or  traffic  signals  as  described  in  the  State  of  California  Department  of 

Transportation California Manual on Uniform Traffic Control Devices  for Streets and 

Highways  dated  September  26,  2006  (CMUTCD)  must  be  satisfied  before  such 

improvements are allowed.   

 

 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-10

Page 157: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

TABLE 3.12-1 MADERA COUNTY LEVEL OF SERVICE DEFINITIONS FOR SIGNALIZED INTERSECTIONS

 Level of Service Description V/C Ratio

Describes operations with very  low delay;  i.e.,  less  than 5.0 sec per 

vehicle.   This occurs when progression  is extremely  favorable, and 

most vehicles arrive during  the green phase.   Most vehicles do not 

stop at all.  Short cycle lengths may also contribute to low delay. 

<0.60 

Describes operations with delay  in  the  range of 5.1  to 15.0  sec per 

vehicle.   This generally occurs with good progression and/or short 

cycle  lengths.   More vehicles  stop  than  for LOS A,  causing higher 

levels of average delay. 

= 0.61 to 0.70 

Describes operations with delay  in the range of 15.1 to 25.0 sec per 

vehicle.    These  higher  delays  may  result  from  fair  progression 

and/or  longer cycle  lengths.   Individual cycle failures may begin to 

appear at this level.  The number of vehicles stopping at this level is 

significant,  although  many  still  pass  through  the  intersection 

without stopping. 

= 0.71 to 0.80 

Describes operations with delay  in the range of 25.1 to 40.0 sec per 

vehicle.   At  level  “D,”  the  influence  of  congestion  becomes more 

noticeable.    Long  delays  may  result  from  some  combination  of 

unfavorable  progression,  long  cycle  lengths,  or  high  v/c  ratios.  

Many  vehicles  stop,  and  the  proportion  of  vehicles  not  stopping 

declines.  Individual cycle failures are noticeable. 

= 0.81 to 0.90 

Describes operations with delay  in the range of 40.1 to 60.0 sec per 

vehicle.  This is considered to be the limit of acceptable delay.  These 

high  delay  values  generally  indicate  poor  progression,  long  cycle 

lengths, and high v/c  ratios.    Individual cycle  failures are  frequent 

occurrences. 

= 0.91 to 1.00 

Describes  operations with  delay  in  excess  of  60.0  sec  per  vehicle.  

This  is  considered  to  be  unacceptable  to  most  drivers.    This 

condition often occurs with over saturation;  i.e., when arrival  flow 

exceeds the capacity of the intersection.  It may also occur at high v/c 

ratios  below  1.00  with  many  individual  cycle  failures.    Poor 

progression and  long cycle  lengths may also be major contributing 

causes to such delay levels. 

>1.00 

Source:  Transportation Research Board, Highway Capacity Manual, 1980‐1985. 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-11

Page 158: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

TABLE 3.12-2 LEVEL OF SERVICE CHARACTERISTICS FOR UNSIGNALIZED INTERSECTIONS

 Level of Service Description Average Vehicle Delay (seconds)

A  Little or no delay.  0‐10 

B  Short traffic delays.  >10‐15 

C  Average traffic delays.  >15‐25 

D  Long traffic delays.  >25‐35 

E  Very long traffic delays.  >35‐50 

F  Stop‐and‐go conditions.  >50 

Source:  Transportation Research Board, Highway Capacity Manual, 2000. 

 

 

TABLE 3.12-3 LEVEL OF SERVICE CHARACTERISTICS FOR SIGNALIZED INTERSECTIONS

 Level of Service Description

Average Vehicle Delay (seconds)

A  Uncongested operations; all queues clear in a single cycle.  <10 

B  Very light congestion; an occasional phase is fully utilized.  >10‐20 

C  Light congestion; occasional queues on approaches.  >20‐35 

Significant  congestion  on  critical  approaches,  but 

intersection  is  functional.   Cars  required  to wait  through 

more than one cycle during short peaks.  No long‐standing 

queues formed. 

>35‐55 

Severe  congestion  with  some  long‐standing  queues  on 

critical  approaches.    Traffic  queue  may  block  nearby 

intersection(s) upstream of critical approach (es). 

>55‐80 

F  Total breakdown, stop‐and‐go conditions.  > 80 

Source:  Transportation Research Board, Highway Capacity Manual, 2000. 

 

 

TABLE 3.12-4 CAPACITIES PER HOUR PER LANE FOR VARIOUS HIGHWAY FACILITIES IN THE MADERA COUNTY

 Level of Service Freeways

Two-Lane Rural Highway

Multi-Lane Rural Highway Expressway Arterial Collector

A  700  120  470  720  450  300 

B  1,100  240  945  840  525  350 

C  1,550  395  1,285  960  600  400 

D  1,850  675  1,585  1,080  675  450 

E  2,000  1,145  1,800  1,200  750  500 

Source:  County General Plan Policy Document, reference 22. 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-12

Page 159: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

The CMUTCD presents criteria  (warrants)  for determining  the need  for  traffic signals 

and  provides  criteria  for  eight‐hour  volume,  four‐hour  volume,  peak‐hour  volume, 

pedestrian volume, coordinated systems, crash experience, and roadway network.  The 

CMUTCD also indicates that satisfaction of a traffic signal warrant or warrants shall not 

in  itself  require  the  installation  of  a  traffic  control  signal.    Significant  engineering 

judgment  is  required  by  the CMUTCD  in  the  application  of  the warrants.   A  traffic 

control  signal  should  not  be  installed  unless  an  engineering  study  indicates  that 

installing a traffic control signal will improve the overall safety and/or operation of the 

intersection. 

 

Caltrans does not  allow  installation of  a  traffic  signal  at  an unsignalized  intersection 

operating at substandard LOS  if  traffic signal warrants are not satisfied.   Under  these 

conditions,  the  only means  to  alleviate  delays  to  stop‐controlled  vehicles may  be  to 

install  a  traffic  signal.    However,  the  unsatisfied  signal  warrants  suggest  that  the 

reduction in delay for the stop‐controlled vehicles does not  justify the new delays that 

would  be  incurred  by  the major  street  traffic  (which  at  one‐way  or  two‐way  stop‐

controlled  intersections  is not currently required  to stop).   Under  these circumstances, 

Caltrans does not recommend installation of a signal. 

 

3.12.4 Traffic Impact Study  

3.12.4.1 Project Traffic Volumes  

The  trip generation estimates originated with  the Applicant and were provided  to  the 

EIR preparer.   Aggregate material produced at the Project site will typically be hauled 

in 25‐ton‐capacity  trucks.    It  is estimated  that  the Project will produce approximately 

3,825  tons  of  material  on  the  average  weekday  and  8,525  tons  of  material  on  the 

maximum  weekday.    The  trip  generation  information  is  provided  in  Table  3.12‐5, 

Project Trip Generation.  The values presented in Table 3.12‐5 include trucks accessing 

the asphalt batch plant. 

 

The peak hour  estimates do not  include  employee  traffic, which  is  expected  to occur 

during off‐peak hours.  The estimated percentage distribution of annual average project 

traffic is presented in Figure 3.12‐6, Project Traffic Distribution Percentage.  The project 

traffic volumes at  each of  the  study  intersections are presented  in Figure 3.12‐7, PCE 

Project Traffic Volumes, and Figure 3.12‐8, 2030 PCE Project Traffic Volumes.  The trip 

generation values represented in Figures 3.12‐7 and 3.12‐8 are the same.  The difference 

between the two figures is the configuration of future interchanges. 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-13

Page 160: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

TABLE 3.12-5 PROJECT TRIP GENERATION

 Time Period Entering Site Trucks Exiting Site

Average Workday 153 trucks 

20 employee vehicles 

153 trucks 

20 employee vehicles 

Maximum Workday 341 trucks 

20 employee vehicles 

341 trucks 

20 employee vehicles 

Maximum Weekday AM Peak 

Hour 50 trucks  50 trucks 

Maximum Weekday PM Peak Hour  20 trucks  20 trucks 

 

 

Construction activities  to realign and/or reconstruct Road 209 between  the project site 

and State Route 41 are expected to generate up to 190 trucks per day entering the site 

and 190 trucks per day leaving the site during construction.  A majority of these trucks 

are expected to travel only on Road 209 as the material will be generated at the project 

site  and  delivered  to  the  construction  area.    Few  of  the  truck  trips  are  expected  to 

impact State Route 41. 

 

3.12.4.2 Existing Traffic Volumes  

Existing  traffic  volumes were  determined  by  performing manual  turning movement 

counts  at  each  of  the  study  intersections.    Existing  peak  hour  turning  movement 

volumes  at  the  study  intersections  are  presented  in  Figure  3.12‐9,  Existing  Traffic 

Volumes.   Existing‐plus‐Project peak hour  traffic  volumes with PCE  adjustments  are 

presented in Figure 3.12‐10, Existing Plus Project Traffic Volumes.  

 

The results of previous 24‐hour counts were provided by Caltrans.   The results of  the 

24‐hour counts are included in Attachment 3, Traffic Count Data Sheet of Appendix D 

Traffic Impact Study. 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-14

Page 161: MADERA QUARRY PROJECT
Page 162: MADERA QUARRY PROJECT
Page 163: MADERA QUARRY PROJECT
Page 164: MADERA QUARRY PROJECT
Page 165: MADERA QUARRY PROJECT
Page 166: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

3.12.4.3 Cumulative Traffic Volumes  

Cumulative year 2030 traffic volume forecasts without the Project were estimated based 

on the cumulative 2030 Madera County travel model maintained by the Madera County 

Transportation Commission (MCTC) using an increment method.  The MCTC is located 

at 2001 Howard Road, Suite 201, Madera, California 93637.  The documentation for the 

Madera County  travel model  is presented  in documents dated November 1, 2001 and 

October 6, 2006 which are available from the MCTC by request.  The increment method 

projects  future  traffic  volumes  by  adding  the  growth  projected  by  the model  to  the 

existing traffic volumes.   

 

Printouts  showing  the  travel model  data  at  the  study  intersections  are  included  in 

Appendix  D  future  turning  movements  were  estimated  based  on  the  methods 

presented in Chapter 8 of the Transportation Research Board National Cooperative  

 

Highway Research Program Report 255 entitled “Highway Traffic Data  for Urbanized 

Area Project Planning and Design”.  Projected future traffic volumes without the Project 

are  presented  in  Figure  3.12‐11,  Cumulative  2030  No  Project  Traffic  Volumes.  

Cumulative‐with‐project  traffic  volumes  are  presented  in  Figure  3.12‐12, Cumulative 

2030 With Project Traffic Volumes.   

 

3.12.4.4 Intersection Analyses  

Intersection analyses were performed using  the Synchro 6 software  (Build 614) which 

incorporates Highway Capacity Manual methods for determining intersection delays and 

associated  levels  of  service  (LOS)  for  both  signalized  and  unsignalized  intersections.  

Build 614 is listed among the analysis software considered acceptable to Caltrans in the 

Caltrans Guide  for  the Preparation  of Traffic  Impact  Studies dated December  2002.   The 

results  of  the  analyses  are  presented  in  Tables  3.12‐6  through  3.12‐9,  Intersection 

Analysis Summary.  LOS definitions are presented in Section 3.12.3 of this section.  For 

the  existing  conditions  and  cumulative  no‐project  conditions,  deficient  intersection 

levels of service are indicated in bold type.   For Project scenarios, only Project impacts 

are indicated in bold type. 

 

The Highway Capacity Manual does not define  the overall  intersection LOS  for one‐

way  stop‐sign controlled  intersections.   Therefore,  the LOS  for  the approach with  the 

greatest delay is presented for one‐way stop‐sign controlled intersections.   

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-20

Page 167: MADERA QUARRY PROJECT
Page 168: MADERA QUARRY PROJECT
Page 169: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

TABLE 3.12-6 INTERSECTION ANALYSIS SUMMARY - EXISTING CONDITIONS

 A.M. Peak Hour P.M. Peak Hour

Intersection Control

Type Delay (sec) LOS

Peak Hour

Warrant Delay (sec) LOS

Peak Hour

Warrant SR 41 / Road 209  OWS  14.2  B  n/r  11.1  B  n/r 

SR 41 / SR 145  Signal  15.6  B  n/r  20.2  C  n/r 

SR 41 / Ave 15  OWS  42.6  E  Not met*  81.7  F  Not met* 

SR 41 / Ave 14½ / Road 204  TWS  51.6  F  Not met  53.8  F  Not met 

SR 41 / Ave 12  Signal  35.7  D  n/r  50.5  D  n/r 

Notes:  OWS:  One‐way stop control; DNE:  Does not exist; TWS:  Two‐way stop control;  n/r:   Analysis 

not required.   

*  See discussion regarding right‐turn volumes. 

 

 

TABLE 3.12-7 INTERSECTION ANALYSIS SUMMARY - EXISTING PLUS PROJECT CONDITIONS

 A.M. Peak Hour P.M. Peak Hour

Intersection Control

Type Delay (sec) LOS

Peak Hour

Warrant Delay (sec) LOS

Peak Hour

Warrant SR 41 / Road 209  OWS  22.7  C  n/r  13.6  B  n/r 

SR 41 / SR 145  Signal  15.3  B  n/r  19.3  B  n/r 

SR 41 / Ave 15  OWS  60.4  F  Not met*  94.9  F  Not met* 

SR 41 / Ave 14½ / Road 204  TWS  55.9  F  Not met  52.8  F  Not met 

SR 41 / Ave 12  Signal  37.0  D  n/r  52.1  D  n/r 

Notes:  OWS:  One‐way stop control; DNE:  Does not exist; TWS:  Two‐way stop control;  n/r:   Analysis 

not required.   

*  See discussion regarding right‐turn volumes. 

 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-23

Page 170: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

TABLE 3.12-8 INTERSECTION ANALYSIS SUMMARY – 2030 CUMULATIVE NO-PROJECT CONDITIONS

 A.M. Peak Hour P.M. Peak Hour

Intersection Control

Type Delay (sec) LOS

Peak Hour

Warrant Delay (sec) LOS

Peak Hour

Warrant SR 41 / Road 209  OWS  301.7  F  2/2  *  F  2/2 

SR 41 / SR 145  Signal  188.5  F  n/r  283.3  F  n/r 

SR 41 SB / Ave 15  Signal  7.5  A  n/r  8.7  A  n/r 

SR 41 NB / Ave 15  Signal  17.2  B  n/r  31.0  C  n/r 

SR 41 / Ave 14½ / Road 204  DNE  ‐  ‐  n/r  ‐  ‐  n/r 

SR 41 SB / Ave 12  Signal  29.3  C  n/r  36.3  D  n/r 

SR 41 NB / Ave 12  Signal  18.3  B  n/r  28.8  C  n/r 

Notes:  OWS:  One‐way stop control; DNE:  Does not exist; TWS:  Two‐way stop control;  n/r:   Analysis 

not required.   

*  Excessive delays not reported. 

 

 

TABLE 3.12-9 INTERSECTION ANALYSIS SUMMARY – 2030 CUMULATIVE WITH-PROJECT CONDITIONS

 A.M. Peak Hour P.M. Peak Hour

Intersection Control

Type Delay (sec) LOS

Peak Hour

Warrant Delay (sec) LOS

Peak Hour

Warrant SR 41 / Road 209  OWS  *  F  2/2  *  F  2/2 

SR 41 / SR 145  Signal  195.5  F  n/r  285.6  F  n/r 

SR 41 SB / Ave 15  Signal  7.6  A  n/r  8.8  A  n/r 

SR 41 NB / Ave 15  Signal  17.2  B  n/r  31.0  C  n/r 

SR 41 / Ave 14½ / Road 204  DNE  ‐  ‐  n/r  ‐  ‐  n/r 

SR 41 SB / Ave 12  Signal  29.6  C  n/r  36.4  D  n/r 

SR 41 NB / Ave 12  Signal  18.2  B  n/r  28.7  C  n/r 

Notes:  OWS:  One‐way stop control; DNE:  Does not exist; TWS:  Two‐way stop control;  n/r:   Analysis 

not required.   

*  Excessive delays not reported. 

 

 

3.12.4.5 Road Segment Analyses  

Road segment analyses were performed by determining the road segment volumes and 

the LOS based on definitions presented  in Section 3.12.3 of  this report.   The results of 

the  analyses  are  presented  in  Tables  3.12‐10  through  3.12‐13,  Road  Segment  LOS 

Summary.    For  the  existing  conditions  and  cumulative  Project  conditions,  deficient 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-24

Page 171: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

intersection  levels  of  service  are  indicated  in  bold  type.    For  Project  scenarios,  only 

Project impacts are indicated in bold type. 

 

 

TABLE 3.12-10 ROAD SEGMENT LOS SUMMARY-EXISTING CONDITIONS

 A.M. Peak Hour P.M. Peak Hour

Road and Direction Facility Type Lanes Volume LOS Volume LOS SR 41 NORTHBOUND Rd 209 to Rd 406  2‐Lane Rural Highway  1  243  C  634  D 

SR 145 to Rd 209  2‐Lane Rural Highway  1  316  C  920  E 

Ave 15 to SR 145  2‐Lane Rural Highway  1  264  C  815  E 

Ave 14½ to Ave 15  2‐Lane Rural Highway  1  344  C  1,045  E 

Ave 12 to Ave 14½  2‐Lane Rural Highway  1  373  C  1,146  F 

SR 41 SOUTHBOUND Rd 406 to Rd 209  2‐Lane Rural Highway  1  627  D  435  D 

Rd 209 to SR 145  2‐Lane Rural Highway  1  811  E  456  D 

SR 145 to Ave 15  2‐Lane Rural Highway  1  797  E  422  D 

Ave 15 to Ave 14½  2‐Lane Rural Highway  1  1,013  E  520  D 

Ave 14½ to Ave 12  2‐Lane Rural Highway  1  1,195  F  554  D 

SR 145 WESTBOUND SR 41 to Rd 400  2‐Lane Rural Highway  1  138  B  177  B 

SR 145 EASTBOUND Rd 400 to SR 41  2‐Lane Rural Highway  1  179  B  302  C 

 

 

TABLE 3.12-11 ROAD SEGMENT LOS SUMMARY – EXISTING PLUS PROJECT CONDITIONS

 A.M. Peak Hour P.M. Peak Hour

Road and Direction Facility Type Lanes Volume LOS Volume LOS SR 41 NORTHBOUND Rd 209 to Rd 406  2‐Lane Rural Highway  1  248  C  636  D 

SR 145 to Rd 209  2‐Lane Rural Highway  1  361  C  938  E 

Ave 15 to SR 145  2‐Lane Rural Highway  1  296  C  828  E 

Ave 14½ to Ave 15  2‐Lane Rural Highway  1  376  C  1,058  F 

Ave 12 to Ave 14½  2‐Lane Rural Highway  1  402  D  1,158  F 

SR 41 SOUTHBOUND Rd 406 to Rd 209  2‐Lane Rural Highway  1  632  D  437  D 

Rd 209 to SR 145  2‐Lane Rural Highway  1  856  E  474  D 

SR 145 to Ave 15  2‐Lane Rural Highway  1  829  E  435  D 

Ave 15 to Ave 14½  2‐Lane Rural Highway  1  1,045  E  534  D 

Ave 14½ to Ave 12  2‐Lane Rural Highway  1  1,224  F  566  D 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-25

Page 172: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-26

A.M. Peak Hour P.M. Peak Hour Road and Direction Facility Type Lanes Volume LOS Volume LOS

SR 145 WESTBOUND SR 41 to Rd 400  2‐Lane Rural Highway  1  148  B  181  B 

SR 145 EASTBOUND Rd 400 to SR 41  2‐Lane Rural Highway  1  189  B  306  C 

 

 

TABLE 3.12-12 ROAD SEGMENT LOS SUMMARY – CUMULATIVE 2030 NO-PROJECT CONDITIONS

 A.M. Peak Hour P.M. Peak Hour

Road and Direction Facility Type Lanes Volume LOS Volume LOS SR 41 NORTHBOUND Rd 209 to Rd 406  2‐Lane Rural Highway  1  686  E  1,409  F 

SR 145 to Rd 209  2‐Lane Rural Highway  1  813  E  1,597  F 

Ave 15 to SR 145  2‐Lane Rural Highway  1  1,491  F  2,663  F 

Ave 12 to Ave 15  Freeway  2  3,265  D  4,223  F 

SR 41 SOUTHBOUND Rd 406 to Rd 209  2‐Lane Rural Highway  1  1,252  F  1,029  E 

Rd 209 to SR 145  2‐Lane Rural Highway  1  1,422  F  1,229  F 

SR 145 to Ave 15  2‐Lane Rural Highway  1  2,396  F  2,022  F 

Ave 15 to Ave 12  Freeway  2  4,126  F  3,223  D 

SR 145 WESTBOUND SR 41 to Rd 400  2‐Lane Rural Highway  1  719  E  912  E 

SR 145 EASTBOUND Rd 400 to SR 41  2‐Lane Rural Highway  1  761  E  940  E 

 

 

TABLE 3.12-13 ROAD SEGMENT LOS SUMMARY – CUMULATIVE 2030 WITH-PROJECT CONDITIONS

 A.M. Peak Hour P.M. Peak Hour

Road and Direction Facility Type Lanes Volume LOS Volume LOS SR 41 NORTHBOUND Rd 209 to Rd 406  2‐Lane Rural Highway  1  691  E  1,411  F 

SR 145 to Rd 209  2‐Lane Rural Highway  1  858  E  1,608  F 

Ave 15 to SR 145  2‐Lane Rural Highway  1  1,523  F  2,676  F 

Ave 12 to Ave 15  Freeway  2  3,294  D  4,235  F 

SR 41 SOUTHBOUND Rd 406 to Rd 209  2‐Lane Rural Highway  1  1,257  F  1,031  E 

Rd 209 to SR 145  2‐Lane Rural Highway  1  1,467  F  1,224  F 

SR 145 to Ave 15  2‐Lane Rural Highway  1  2,428  F  2,035  F 

Ave 15 to Ave 12  Freeway  2  4,158  F  3,234  D 

Page 173: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-27

A.M. Peak Hour P.M. Peak Hour Road and Direction Facility Type Lanes Volume LOS Volume LOS

SR 145 WESTBOUND SR 41 to Rd 400  2‐Lane Rural Highway  1  729  E  916  E 

SR 145 EASTBOUND Rd 400 to SR 41  2‐Lane Rural Highway  1  771  E  944  E 

 

 

3.12.5 Standards of Significance, Environmental Consequences, and Mitigation Measures

 

3.12.5.1 Standards of Significance  

Appendix G of  the California Environmental Quality Act  (CEQA) provides guidance 

for assessing the significance of potential environmental impacts.  Relative to traffic and 

safety, a project will normally have a significant effect on the environment if it will: 

 

Cause an increase in traffic, which is substantial in relation to the existing traffic 

load  and  capacity  of  the  street  system  (i.e.,  results  in  a  substantial  increase  in 

either  the  number  of  vehicles  trips,  the  volume  to  capacity  ratio  on  roads,  or 

congestion at intersections); 

Exceed, either  individually or cumulatively, a LOS standard established by  the 

County congestion management agency for designated roads or highways; 

Substantially  increase  hazards  due  to  a  design  feature  (e.g.,  sharp  curves  or 

dangerous intersections) or incompatible uses (e.g., farm equipment); 

Result in inadequate emergency access; or 

Result in inadequate parking capacity. 

 

3.12.6 Impacts and Mitigation Measures  

3.12.6.1 Discussion of Existing and Existing-Plus-Project Analyses  

The analyses  indicated  that  three of  the study  intersections along SR 41 and all of  the 

study road segments currently experience a substandard LOS (LOS below C based on 

Caltrans’  criteria).   The deficient  study  intersections  are  the  SR  41  intersections with 

Avenue 15, Road 204 (Avenue 14‐1/2), and Avenue 12.   This supports the need for the 

planned  freeway and  interchange  improvements on SR 41 and  the need  for widening 

SR 145.   

Page 174: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

It  is noted  that  the certain  study  locations  that were  included  in  the DEIR  for Project 

were previously determined  to  operate  at deficient  levels  of  service, but  the  affected 

agencies  did  not  require  updated  traffic  analyses  since  the  DEIR  found  no  Project 

impacts and the Project generates low traffic volumes at those locations.  The previously 

deficient locations are: 

 

Intersection of SR 41 and Road 406; 

Intersection of Cleveland Avenue and SR 99 northbound ramps; 

State Route 41 road segment between Road 406 to Road 200); 

State Route 145 (Road 400 to Cleveland Avenue); and 

Cleveland Avenue (SR 145 to SR 99). 

 

With  the  addition  of  the  Project  (existing‐plus‐project)  conditions,  the  LOS  remains 

unchanged at all intersections except the intersection of SR 41 and Avenue 15.   At this 

location, a LOS F is expected for the eastbound approach. 

 

Impact 3.12-1: The Project Could Result in Increased Vehicle Trips or Traffic Congestion, Including Substandard LOS 

 

At the intersection of SR 41 and Avenue 15, the Project will exacerbate an existing substandard 

LOS.  This impact is potentially significant. 

 

The Project will exacerbate an existing substandard LOS at the intersection of SR 

41  and Avenue  15.   There  are no  feasible mitigation measures  to mitigate  the 

Project’s  impact at  the  intersection of SR 41 and Avenue 15.    Installation of all‐

way stop control is not feasible due to the significant delays that would result on 

SR 41.  The addition of lanes is not feasible since it would not alleviate the delays 

for  stop‐controlled  vehicles  turning  across  traffic  from  Avenue  15  to  SR  41.  

Finally,  traffic  signal warrants  are  not  clearly  satisfied  and would  cause  new 

delays  on  the  SR  41 mainline,  rendering  the  installation  of  traffic  signals  an 

infeasible  mitigation.    Therefore,  this  impact  is  considered  significant  and 

unavoidable.   Eventually, as traffic volumes in the region increase as a result of 

further development, warrants for traffic signals are expected to be satisfied and 

traffic  signals will  be  required  to  be  installed  by  future development projects.  

The Project  can mitigate  its  equitable  share  of  the  impact with payment  of  an 

equitable share contribution as discussed later in this report.   The Project might 

also be subject to the Fee Program, discussed in the Introduction. 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-28

Page 175: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-29

At locations other than the intersection of SR 41 and Avenue 15, the impact of the 

projected Project traffic is less than significant.   

 

Level of Significance Before Mitigation:  Significant 

 

Mitigation Measures:  No Feasible Mitigation   

 

Level of Significance After Mitigation:  Significant and Unavoidable  

 Impact 3.12-3: The Project Could Result in Truck Trips on Roads That Are Not

Suitable For Heavy Truck Traffic3  

County Road 208 and Road 406 are not suitable for the type of heavy truck traffic generated by 

the Project.  This impact is potentially significant. 

 

Because County Road 208 and Road 406 are not suitable for heavy truck traffic, 

they will not be part of the designated haul route unless specific County or local 

projects  are  located  on  these  County  roads.   Mitigation measures  have  been 

established  (see  below)  instructing  haul  trucks  leaving  the  project  site  the 

designated haul route.   

 

Level of Significance Before Mitigation:  Potentially Significant 

 

Mitigation Measures:   

 

  Mitigation Measure 3.12‐3a 

The Applicant shall  inform and/ or post warning signs at the exit of the Project 

site that inform all transporters and delivery vehicles that Road 406 and Road 208 

shall not be utilized  to  transport any material  to and  from  the proposed Project 

site. 

 

3  This  Impact  is numbered 3.12‐3  as  there  is  an  Impact  3.12‐2  in  the FEIR.   The  analysis  contained  in 

Impact  3.12‐2 was upheld by  the  Judicial Decisions  and  after  a  careful  review of NOP  and  scoping 

comments, the County determined that the DEIR and FEIR adequately addressed the issue.  The DEIR 

and FEIR  are  contained  in  a disk attached  to  the RDEIR  and  can  also be  reviewed on  the County’s 

website: http://www.madera‐county.com/rma/planningdept/planning_dept_docs.html and hard copies 

can  be  found  at  the Madera County Planning Department  at  2037 W. Cleveland Ave., Madera, CA 

93637. 

Page 176: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

Mitigation Measure 3.12‐3b  

If the County requires, the Applicant has agreed to pay for signs located on public 

roads specifying the designated haul route. 

 

Level of Significance After Mitigation:  Less than Significant 

 

3.12.7 Cumulative Impacts and Mitigation Measures  

Impact 3.12-4: The Project Contributes Traffic to Intersections and Road Segments That Will Require Upgrades With or Without the Project

 

The  Project  will  contribute  to  intersections  and  road  segments  that  are  expected  to  require 

upgrades prior to the Year 2030.  This impact is potentially significant. 

 

The future analyses without the Project (year 2030) indicate that all of the study 

intersections  and  road  segments  are  expected  to  require  improvements  to 

operate at acceptable levels of service.  Interchanges are expected to be required 

on SR 41 at Avenue 12, Avenue 15, and SR 145.  The intersection at Avenue 14½ 

will be closed. 

 

The  future  analyses  with  the  project  added  indicate  that  the  LOS  remains 

unchanged at all of the study intersections and road segments   

 

The Project will create a potentially significant impact at the intersection of SR 41 

and  Road  209  by  exacerbating  conditions  that  are  expected  to  be  deficient 

without  the  Project.    Since  Caltrans  has  indicated  that  traffic  signals  are  not 

desirable  at  the  intersection  of  SR  41  and  Road  209  due  to  the  close  spacing 

between Road 209 and SR 145, traffic signals are not recommended as a feasible 

mitigation.  Further, since the need for traffic signals at the intersection is caused 

almost  entirely by hypothetical  commercial development near  the  intersection, 

the  Project’s  share  of  the  cumulative  impact  is  minimal  and  will  become 

significant and unavoidable if the LOS at the intersection ever drops below LOS 

C.   The Project  can mitigate  its  share of  the  cumulative  significant  impacts by 

paying  an  equitable  share  of  the  cost  of  improvements  required  by  Caltrans.  

Further,  the  Fee  Program  specifies  all  potentially  significant  segments  and 

earmarks funding for required improvements. 

 

The Project  shall be  responsible only  for  its equitable  share of  the  cost of  road 

improvements. 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-30

Page 177: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

The Project will be responsible  to mitigate  its equitable share of  the cumulative 

significant  impacts  that  can  be  mitigated  with  construction  of  the  future 

interchanges  on  SR  41  at Road  209, Avenue  12, Avenue  15,  and  SR  145.   The 

Project  can mitigate  its  equitable  share  by  being  subject  to  the  Fee  Program 

and/or the payment of Caltrans traffic impact fees.  The Project can also mitigate 

its  impact  by  constructing  a  portion  of  the  improvements.    The  cost  of  the 

construction shall be credited against the Project’s equitable share.  If any of the 

mitigations are not fully funded by the Fee Program or CalTrans equitable share 

contribution  then  the  impact  at  that  location  would  remain  significant  and 

unavoidable.   

 

The  project will  contribute  traffic  to  intersections  and  road  segments  that  are 

expected to require upgrades prior to the year 2030 whether or not the Project is 

constructed.  Caltrans may request that the project contribute an equitable share 

of  the  cost  of  future  improvements  at  these  locations.    Such  contributions  are 

typically calculated using the following equation: 

 

P = The equitable share of the project’s traffic impact; 

T = The project trips generated during the peak hour of the adjacent 

State Highway facility; 

TB  =  The  forecasted  (future  with  project)  traffic  volume  on  the 

impacted State highway facility; 

TE  =  The  existing  traffic  on  the  State  Highway  facility  plus 

approved projects traffic (cumulative). 

 

In  the  FEIR,  the  Applicant  agreed  to  enter  into  a  long‐term  maintenance 

agreement with Madera County  to mitigate  for  the Project’s  impacts  to County 

roads.  The Applicant and County were to agree on a fee based on cents per ton 

of aggregate sold and other Applicant commitments to ensure that the Project’s 

impacts are mitigated to a less than significant level.   

 

The Court of Appeal noted, as follows: 

 

“……intent to make improvements but no definite commitment on when 

the  improvements  will  take  place.    Moreover,  there  is  no  substantial 

evidence that Caltrans is committed to scheduling the improvements to SR 

41 in a way that would mitigate the increase in vehicle traffic, for example 

by  scheduling  the  improvements  earlier  and more  often.    Furthermore, 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-31

Page 178: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

there  is  no  evidence  that  the  County  has  a  mitigation  plan  in  place 

involving the improvement or maintenance of the various local roadways 

because  of  the  increased  vehicle  traffic.    Thus,  the mitigation measures 

relating to traffic impacts are inadequate.”  Opinion pp. 26‐27 

 

On  January  15,  2008,  the  Applicant  and  County  entered  into  the  Road 

Construction,  Maintenance  and  Reimbursement  Agreement  (Construction 

Agreement) (see Appendix P).     In addition to various construction obligations, 

the  Construction  Agreement  requires  the  Applicant,  or  its  successor,  to  (1) 

construct improvements to County Road 209 (209) (2) maintain 209 for a distance 

of approximately 4.5 miles,  commencing at  its  intersection with State Route 41 

and terminating at Project Site entrance, and (3) pay a maintenance fee of $0.05 

per  ton, with  the  proceeds  being  used  by  the County  for  the maintenance  of 

roads  other  than  209.      Although  County  is  required  to  give  “primary 

consideration”  to utilizing  the  funds “for other  roads  in  the general vicinity of 

the quarry, such as Road 208, 406, etc.”  it  is not required  to spend  the  funds  in 

that area.   

 

Level of Significance Before Mitigation:  Potentially Significant 

 

Mitigation Measures:   

 

Mitigation Measure 3.12‐4a 

The Applicant  shall  contribute  an  equitable  share  of  the  cost  of  construction  of 

future improvements as required under the Fee Program (if applicable), which is 

attached  in Appendix N  to  the DREIR.    If  the Fee Program  is not  applicable, 

equitable share percentages are presented  in the traffic  impact study  included  in 

Appendix D. Cost  estimates  for  improvements  shall be provided by Caltrans or 

Madera County. 

 

The  Project  will  contribute  traffic  to  cumulative  significant  impacts  to  road 

segments  that  will  require  equitable  fair  share  regarding  the  following 

mitigations: 

 

SR 41 between Road 209 and Road 406: widen to four lanes; 

SR 41 between SR 145 and Road 209: widen to four lanes; 

SR 41 between Avenue 15 and SR 145: convert to four‐lane freeway; 

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-32

Page 179: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 3.3 Revisions to Traffic

 

RESOURCE DESIGN TECHNOLOGY, INC. 3.3-33

SR 41 between Avenue 12 and Avenue 15: convert to  four‐lane  freeway; and 

SR 145 between SR 41 and Road 400: widen to four lanes.  

All of these  improvements have been  identified  in the County’s recently adopted 

Fee Program (Appendix N, see Tables 1, 2, and 3).  The County is committed to 

ensuring  that  those  improvements  coincide  with  the  Project’s  anticipated 

contribution to traffic on these segments, to the extent feasible. 

 

Mitigation Measure 3.12‐4b 

To mitigate  the  impacts  of  traffic, County  and Applicant have  entered  into  the 

Road  Construction,  Maintenance  and  Reimbursement  Agreement,  Madera 

County Contract No. 8511‐C‐2008 (see Appendix P).  This Agreement obligates 

the Applicant to pay the costs of reconstructing and  maintaining 209 (subject to 

the  right  of  partial  reimbursement  should County  create  an  “Area  of Benefit” 

whereby properties generating  traffic having a per‐vehicle certified gross vehicle 

weight  of  80,000  lbs  or  greater, will  be  assessed  their  fair  share  of  costs).    In 

addition  the  agreement  obligates  the Applicant  to pay $0.05 per  ton  of  shipped 

material toward road maintenance costs for roads other than 209.   

 

The Agreement  fully mitigates  the  impacts  to  reconstruct,  repair  and maintain 

209.   However, as  to any other roads  impacted by  the Project, as  the County  is 

required to give ‘primary consideration’ to spending these maintenance funds on 

roads in the area, but is not required to do so, the wear and tear impact on local 

roads, other than 209, remains significant and unavoidable.  

  

Level  of  Significance  After  Mitigation:    If  mitigation  measures  are 

implemented,  this  impact will be  less  than  significant.   However,  it  cannot be 

determined at this time whether these measures will be fully funded; therefore, 

this impact remains significant and unavoidable. 

 

Page 180: MADERA QUARRY PROJECT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.0 NEW LEGISLATIVE MANDATE

Page 181: MADERA QUARRY PROJECT

 

 

 

 

 

 

 

 

 

 

4.0 NEW LEGISLATIVE MANDATE  

 

 

4.1 INTRODUCTION TO GREENHOUSE GAS (AB 32, SB 375)  

Subsequent  to  the  certification  of  the  FEIR,  California  passed  the  Global Warming 

Solutions Act of 2006.   This section addresses  the analysis undertaken  to comply with 

the legislation.   

 

The  Impacts  and Mitigation Measures  appearing  in  4.1.6 will be  in  addition  to  those 

already referenced in the DEIR as 3.4‐1 to 3.4‐6 (Air Quality).   

 

4.1.1 Greenhouse Gases  

Green House Gas  (GHG)  emissions  refer  to  a  group  of  emissions  that  are  generally 

believed  to  affect  global  climate  conditions.    The  glass  panes  in  a  greenhouse  allow 

radiant energy from sunlight in and reduce the amount of heat that escapes.  Similarly, 

atmospheric  gases  such  as  CO2,  methane  (CH4),  and  nitrous  oxide  (N2O)  keep  the 

average  surface  temperature of  the Earth at  inhabitable  levels.   However,  excesses  in 

GHGs  may  amplify  the  greenhouse  effect  increasing  the  surface  temperature  and 

potentially affecting  climatic  conditions around  the planet.   The  scientific  community 

largely  agrees  that  human  activities  that  cause  emissions  of  GHGs  have  and  will 

continue to contribute to global warming, although some uncertainty exists concerning 

the rate and magnitude of global warming. 

 

In  addition  to  CO2,  methane,  and  N2O,  GHGs  include  hydrofluorocarbons  (HFCs), 

perfluorocarbons (PFCs), sulfur hexafluoride (SF6), and water vapor.  Of all the GHGs, 

CO2  is  the most  abundant  climate  change  pollutant  resulting  from  human  activities, 

 

RESOURCE DESIGN TECHNOLOGY, INC. 4.0-1

Page 182: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 4.0 New Legislative Mandate

 

RESOURCE DESIGN TECHNOLOGY, INC. 4.0-2

with CO2 from fossil fuel combustion comprising 81 percent of the total GHG emissions 

in California  in 2002 and non‐fossil  fuel CO2 emissions  comprising 2.3 percent.1   The 

other GHGs are less abundant, but have higher global warming potential than CO2.  To 

account for this higher potential, emissions of other GHGs are frequently expressed in 

the  equivalent mass of CO2, denoted as CO2e.   The CO2e of methane  represented 6.4 

percent  of  the  2002 California GHG  emissions, N2O  represented  6.8 percent,  and  the 

other high global warming potential gases represented 3.5 percent of  these emissions.  

In addition, there are a number of man‐made pollutants, such as CO, nitrogen oxides, 

non‐methane volatile organic compounds (NMVOCs), and SO2 that have indirect effects 

on terrestrial or solar radiation absorption by  influencing the formation or destruction 

of other climate change emissions. 

 

4.1.2 Existing Greenhouse Gases  

In December 2006, the California Energy Commission (CEC) published the Inventory of 

California Greenhouse Gas Emissions and Sinks: 1990  to 2004.   Gases  that  trap  the heat of 

the  sun  in  the  Earth’s  atmosphere,  producing  the  green  house  effect,  are  called 

greenhouse gases (GHG).  The two major greenhouse gases are water vapor and carbon 

dioxide  (CO2).   Other GHG  include methane, ozone, chlorofluorocarbons, and nitrous 

oxide.  This report indicates that California is the second largest emitter of GHG in the 

United States next to Texas.  This is largely a result of the number of people living in the 

state, as opposed to a small state such as Rhode Island.    California is second lowest in 

the  nation  in  per  capita  CO2  emissions,  with  only  the  District  of  Columbia  lower.  

Between 1990 and 2000, California’s population grew by 4.1 million people and during 

the 1990 to 2003 period, California’s gross state product grew by 83 percent (in dollars, 

not  adjusted  for  inflation).   However,  California’s GHG  emissions  grew  by  only  12 

percent between 1990 and 2003.   The report concludes  that California’s ability  to slow 

the  rate  of  growth  of  GHG  emissions  is  largely  due  to  the  success  of  its  energy 

efficiency, renewable energy programs, and commitment to clean air and clean energy.   

 

4.2 REGULATORY SETTING  

California has responded  to  the  issue of global climate change by adopting a series of 

laws  to  reduce GHG  emissions  from  various  sources within  the  State.   These  efforts 

began  in September 2002 when  then‐Governor Gray Davis signed Assembly Bill  (AB) 

1493 requiring the development and adoption of regulations to achieve “the maximum 

1  California  Environmental  Protection  Agency,  Climate  Action  Team  Report  to  Governor 

Schwarzenegger and the Legislature, March 2006, p. 11.   

Page 183: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 4.0 New Legislative Mandate

feasible reduction of greenhouse gases” emitted by noncommercial passenger vehicles, 

light‐duty  trucks, and other vehicles used primarily  for personal  transportation  in  the 

state.  In September 2006, Governor Arnold Schwarzenegger signed into law AB 32, the 

California Global Warming Solutions Act of 2006.   AB 32 requires  the CARB  to adopt 

regulations to require the reporting and verification of statewide GHG emissions and to 

monitor and enforce compliance with  that program.   As part of  this effort,  the CARB 

will adopt a statewide greenhouse gas emissions limit equivalent to the statewide GHG 

emissions  levels  in  1990,  to  be  achieved  by  2020.    The  CARB will  adopt  rules  and 

regulations  to  achieve  the maximum  technologically  feasible  and  cost‐effective GHG 

emission reductions.  These are expected to include regulations for certain refrigerants, 

a Low Carbon Fuel Standard, and market‐based compliance mechanisms.   The statute 

further requires the CARB to monitor compliance with and enforce any rule, regulation, 

order,  emission  limitation,  emissions  reduction measure, or market‐based  compliance 

mechanism that it adopts.   

 

In October  2006, Governor  Schwarzenegger  issued  an  Executive Order  in which  he 

designated the Cal EPA Secretary with the primary responsibility for implementing AB 

32.    In  late December,  the Governor announced  the members of a blue‐ribbon Market 

Advisory  Committee  board  to  devise  approaches  to  develop  a  market  for  carbon 

trading.  More developments are likely as the Governor and the Legislature determine 

who  has  primary  responsibility  for  implementation  and  the  relationship  between 

regulations and market‐based mechanisms.  Because the intent of AB 32 is to limit 2020 

emissions to the equivalent of 1990, and the present year (2009) is near the midpoint of 

this timeframe, it is expected that the regulations would affect many existing sources of 

GHGs and not just new general development projects.  

 

In October 2007, Governor Schwarzenegger signed Senate Bill  (SB) 97, which requires 

the Governor’s Office of Planning and Research (OPR) to prepare CEQA guidelines for 

the mitigation of GHG  emissions.   OPR  is  in  the process of preparing  formal CEQA 

guidelines and requirements pursuant to SB 97, to be promulgated by January 2010.  In 

the meantime, OPR has published a Technical Advisory (June 2008) that is an “informal 

guidance  regarding  the  steps  lead agencies  should  take  to  address  climate  change  in 

their CEQA documents.”   The Technical Advisory recommends  that  in  the absence of 

regulatory  standards  for  GHG  emissions,  individual  agencies  may  conduct  each 

analysis  on  a  project‐by‐project  basis,  consistent  with  existing  CEQA  practices  and 

guidance.  

 

In January 2009, the state of California, through the OPR/SCH (Office of Planning and 

Research/State Clearinghouse), published  its  Interim Greenhouse Gas  thresholds  (see 

 

RESOURCE DESIGN TECHNOLOGY, INC. 4.0-3

Page 184: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 4.0 New Legislative Mandate

Table 4.0‐1, CARB’s Interim GHG Significance Standards for Industrial Projects, located 

in subsection 4.1.4 Standards of Significance, below).    On April 13, 2009, OPR submitted to the Secretary for Natural Resources  its proposed 

amendments  to  the state CEQA Guidelines  for greenhouse gas emissions, as required 

by Senate Bill 97  (Chapter 185, 2007).   These proposed CEQA Guideline amendments 

would provide guidance to public agencies regarding the analysis and mitigation of the 

effects of greenhouse gas emissions in draft CEQA documents.  The Natural Resources 

Agency will  conduct  formal  rulemaking  in 2009, prior  to  certifying and adopting  the 

amendments, as required by Senate Bill 97. 

 

On November  5,  2009,  the  SJVAPCD  issued  its  draft Guidance  for  Valley  Land‐use 

Agencies  in Addressing GHG  Impacts  for New Projects under CEQA.    If  and when 

adopted, the Guidance may be  implemented by Valley  land‐use agencies, should they 

elect to adopt it.  As currently drafted the Guidance contemplates 1) the development of 

Best Performance Standards (BPS) as a means of reducing or  limiting GHG emissions, 

and  2)  the  establishment  of  BPS  for  specific  categories  of  stationary  sources  and 

development projects.  It is anticipated that there will be a period of time before BPS are 

adopted for projects such as the Madera Quarry, even if the Guidance is adopted in the 

near  future by  the SJVAPCD  and  then applied  to Madera Quarry.   For development 

projects,  the  guidance  focuses  on  reduction  of  vehicle  miles  traveled  (VMT)  as  an 

important objective. 

 

4.3 STANDARDS OF SIGNIFICANCE  

With respect to Greenhouse Gases (GHG) Emissions (OPR 2009) the Project will have a 

significant air quality impact based on: 

 

The  extent  to which  the project  could help  or hinder  attainment  of  the  state’s 

goals of  reducing greenhouse gas  emissions  to 1990  levels by  the year 2020 as 

stated in the Global Warming Solutions Act of 2006; 

The extent to which the project may result in increased energy efficiency of and a 

reduction in overall greenhouse gas emissions from an existing facility;  

The  extent  to which  the project  impacts  or  emissions  exceed  any  threshold  of 

significance that applies to the project ; and 

The extent  to which  the project may  increase  the consumption of  fuels or other 

energy  resources,  especially  fossil  fuels  that  contribute  to  greenhouse  gas 

emissions when consumed.  

 

RESOURCE DESIGN TECHNOLOGY, INC. 4.0-4

Page 185: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 4.0 New Legislative Mandate

Thresholds of significance illustrate the extent of an impact and are a basis from which 

to  apply  mitigation  measures.    In  October  2008,  CARB  released  preliminary  draft 

Interim GHG thresholds for industrial projects and residential and commercial projects.  

CARB’s policy objective is to develop a threshold of significance that will result in the 

vast  majority  (about  90  percent  statewide)  of  GHG  emissions  from  new  industrial 

projects  being  subject  to  CEQA’s  requirement  to  impose  feasible  mitigation.    The 

threshold consists of a quantitative threshold of 7,000 metric tons of CO2 equivalent per 

year  (MTCO2e/yr)  for  operational  emissions  (excluding  transportation),  and  a 

performance standard for construction and transportation emissions (see Table 4.0‐1).  

 

 

TABLE 4.0-1 CARB’S INTERIM GHG SIGNIFICANCE STANDARDS FOR INDUSTRIAL PROJECTS

 CEQA Category Proposed Criteria

Exemption  Apply applicable exemption. 

Regional GHG Reduction Plan  N/A. 

Thresholds   Project < 7,000 MTCO2eq/yr from non‐transportation 

operational sources  

Meets construction & transportation performance standards. 

Performance Standards  See above. 

Offsets  Off‐site substitution allowed. 

Determination  GHG emissions significant, EIR is prepared, if meeting none of the 

above. 

Notes: These standards have been developed for industrial sources, but will be used as significance 

criteria for this project in the absence of other appropriate criteria. 

 

 

4.4 IMPACTS AND MITIGATION MEASURES  

Impact 4.0-1: Project Actions Could Conflict with Implementation of State Goals for Reducing GHG Emissions and Thereby Have an Adverse Effect on Global Climate Change

 

Mining and transport of materials associated with the Project would produce various greenhouse 

gases, which could conflict with implementation of State goals for reducing GHG emissions and 

thereby have an adverse effect on global climate change. 

 

The  Quarry  would  use  various  types  of  diesel  powered  mining  equipment 

including  drill  rig,  bulldozers,  haul  trucks,  hydraulic  shovels  and  excavators.  

The overburden would be transported to an aggregate processing area where the 

 

RESOURCE DESIGN TECHNOLOGY, INC. 4.0-5

Page 186: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 4.0 New Legislative Mandate

rock is crushed and screened.  The aggregate would be shipped to customers in 

Fresno‐Madera  consumption  region.    Transportation  costs  associated  with 

delivering  aggregate  to  the  end  user  is  one  of  the  largest  components  of 

aggregate  pricing  (California  Department  of  Conservation,  “Aggregate 

Availability in California,” (2006), p. 15 (”DOC Aggregate Report”)).   

 

The process of producing and transporting the aggregate and asphaltic concrete 

would produce various greenhouse gases. These emissions occur from two main 

categories of sources: 

 

Combustion of diesel fuel in trucks and on‐site equipment 

- On‐site equipment and mining trucks; 

- Off‐site haul (transport) trucks; 

- Employee vehicles and travel; 

- Delivery vehicles; and 

Use of electric power from the local grid. 

 

GHG  emissions  consist  primarily  of  carbon  dioxide  (CO2)  and much  smaller 

amounts  of  nitrous  oxide  (N2O2)  and  methane  (CH4).    The  greenhouse  gas 

potential  of  these  gases  varies  substantially.   However,  only  trace  amounts  of 

N2O2  and  CH4  are  released  from  diesel  combustion.  Therefore,  the  current 

analysis focuses on CO2 emissions. 

 

The  CO2  emissions  are  summarized  below  in  Table  4.0‐2,  Summary  of  GHG 

Emissions from On‐Site Equipment and Quarry Trucks.  The results indicate that 

approximate  1,216  tons  of  CO2  would  be  released  annually  from  the  on‐site 

equipment, including trucks that would haul rock from the mine to the aggregate 

processing area. 

 

In  addition  to  the  emissions  summarized  in  Table  4.0‐2,  the  facility  would 

employ  temporary  electric  generators.    These  generators would  be  on‐site  for 

approximately  six months.   As  a  result,  their  contribution  to GHG  emissions 

would negligible over the lifetime of this project. 

 

 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 4.0-6

Page 187: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 4.0 New Legislative Mandate

TABLE 4.0-2 SUMMARY OF GHG EMISSIONS FROM ON-SITE EQUIPMENT AND QUARRY TRUCKS

 Equipment Number HP Annual Hours Capacity Factor CO2 (tons/yr)

Dozers  1  370  1,800  55%  210.6 

Backhoe  1  375  1,800  55%  213.5 

Motor Grader  1  225  1,100  61%  98.4 

Hydraulic Shovel Scraper  1  450  1,800  55%  256.2 

Blast Hole Drill Rig  1  265  1,000  40%  61.0 

Water Trucks  1  300  1,800  40%  124.2 

Front‐End Loaders  3  325  1,800  55%  555. 

Misc. Accessory Equip.  1  250  1,000  40%  57.5 

Quarry Trucks  2  400      9.6 

Total  1,574 

Notes: 

1. CO2 Emission Factor: 1.15lbs; CO2/bhp‐hr Ref: EPA, AP‐42, Sec. 303, Oct. 1996 and data  from Caterpillar, 

Inc. 

2. Capacity Factor data from URBEMIS 2007 for construction equipment. 

3. Quarry Truck CO2 Emissions 

4. No. of truck trips based on 900,000 tons/yr production, 40 tons/truck load = 22,500 trips/yr 

5. 0.2 miles per round trip, total 4,500 miles/yr 

6. Emission factor (from EMFAC): 1,930 grams CO2/mile 

7. Annual emissions = (4,500 miles/yr x 1,930 gram/mi)/(454 gram/lb x 2000 lb/ton) = 9.56 tons/yr 

 

 

Off‐site emissions consist of transportation related GHG emissions and emissions 

associated with off‐site electrical power generation.  These emissions consist of: 

 

Transportation Related Emissions 

- Haul trucks transporting material to customers off‐site; 

- Employee vehicles; 

- Delivery vehicles for supplies, fuel, etc.; and 

Emissions from off‐site electric power generation. 

 

Not  all  of  these  emissions  are  “new”  emissions.    This  is  because  if Madera 

Quarry were not built, production and transport of aggregate and asphalt would 

be shifted to other, more distant quarries.  Consequently, the Project would shift 

some of the GHG emissions from other quarries.   

 

GHG  emissions  from  the  three  categories of vehicles are  summarized  in Table 

4.0‐2.   The  traffic and mileage data are  from  the February 2006 Final EIR.   The 

 

RESOURCE DESIGN TECHNOLOGY, INC. 4.0-7

Page 188: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 4.0 New Legislative Mandate

 

RESOURCE DESIGN TECHNOLOGY, INC. 4.0-8

Project’s traffic trip generation is not expected to change under the Revised EIR.  

The emissions estimate is based on average emissions for vehicles in the 2000 to 

2008 model  year  using  the  EMFAC model2.    This model  is  used  to  calculate 

emissions  from  light duty passenger  cars, medium  and heavy duty  trucks.   A 

copy of the EMFAC output is provided in Attachment 1. 

 

The  results  indicate  that 3,383  tons of GHG would be  released annually and  is 

summarized in Table 4.0‐3, Summary of Transportation‐Related Emissions.  

 

Madera  Quarry  would  use  electric  power  to  run  the  rock  crushers  and 

conveyors.    In  addition  the office buildings  and  facility  lighting would  all use 

electricity.   The generation of electric power would result  in GHG emissions at 

the point  of  generation.   A modern natural  gas  fired power plant  releases  0.5 

pounds of GHG emissions per kilowatt hour (kwh) of electric power generated. 

 

It is estimated that 3,700,000 kilowatts (kw) of power would be used annually at 

the Madera Quarry.  This translates to approximately 925 tons of GHG emissions 

annually and is summarized below in Table 4.0‐4, CO2 Emissions from Electricity 

Generation. 

 

 

TABLE 4.0-3 SUMMARY OF TRANSPORTATION-RELATED EMISSIONS

 

Maximum

Annual Trips Round Trip

Length (mile) Annual

Miles (mile) CO2

(gram/mile) (tons/yr) Employee Vehicles  10,000  20  400,000  305.0   134.4 

Haul Trucks (note 4)  36,000  49  1,764,000  1611  3129.7 

Delivery Trucks  2,250  46  207,000  521.0   118.8 

Total  3,383 

Notes: 

1. Annual tons/year = (gram/mile) x (annual miles) / (454 grams/lb)(2000 lbs/ton) 

2. Gram/mile data based on EMFAC model run for Madera County for 2000 to 2008 fleet mix.  Copy of 

EMFAC model provided in the Attachment. 

3. Traffic and mileage data from Appendix D of this DREIR, Table 16, of Traffic Study (Peters Engineering 

Group, October 13, 2009) 

4. Trip length for haul trucks based on average  one‐way trip length to Madera (23 miles) and Fresno (26 

miles) per the traffic study = 24.5 miles or 49 miles round‐trip 

2 CARB (2007) Emission Model, California Air Resources Board.  Available from: 

http://www.arb.ca.gov/msei/onroad/latest_version.htm 

Page 189: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 4.0 New Legislative Mandate

TABLE 4.0-4 CO2 EMISSIONS FROM ELECTRICITY GENERATION

 Source Usage CO2 Conversion Rate Emissions

Electricity Generation 3,700,000 kw/year 

(3.7 x 106 kw/year) 0.5 lbs/kwh  925 tons/yr 

    Total  925 tons/yr 

Notes:   

1. CO2 conversion rate from PG&E 2004Second Annual Corporate Responsibility Report, Page 66. 

2. Emissions (tons/yr) = 3.7 x 106  kwh/yr x 0.5 lb/kwh/(2000 lbs/ton) 

 

 

As part of the mitigation related to agricultural impacts, Madera Quarry Inc. will 

establish a conservation easement area to offset the loss of trees and agricultural 

use  at  the  Project  Site.    The  mitigation  includes  the  development  of  a  tree 

replacement  program  and  maintenance  of  existing  trees.    A  quantitative 

assessment of this preserve and the tree replacement program were included in 

the June 2005 DEIR.  This assessment demonstrated that loss of trees at the study 

impact area would be offset by a ratio of 4.8  to 1 as measured on an aggregate 

diameter at breast height (dbh) of trees.   

 

While a detailed analysis of CO2 absorption  in  the  impact portion of  the  study 

area  or  at  the preserve was  beyond  the  scope  of  this  analysis, we  note  that  a 

single oak tree 18” in DBH would absorb 17,800 pounds (8.9 tons) of CO2 over 50 

years or 350 pounds per year per tree.  The aggregate DBH at the impact portion 

of  the study area has been estimated  to be 10,355.5”.   This  is equivalent  to 575 

trees of 18” DBH and would have the potential to remove 201,250 pounds of CO2 

per year.   This  loss  is CO2 absorption capacity would be offset by an aggregate 

DBH of 49,772.5” at the preserve.  This translates into an equivalent of 2,765 trees 

(18” DBH) which equals a gain of 981,952 lbs/yr of CO2 absorption with the net 

reduction  of  389  tons/yr  of  CO2  as  a  result  of  the  preserve  easement.    This 

calculation is shown in Table 4.0‐5, Estimate of CO2 Sequestration. 

 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 4.0-9

Page 190: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 4.0 New Legislative Mandate

TABLE 4.0-5 ESTIMATE OF CO2 SEQUESTRATION

  Notes Units Impact Area Preserve

Total Diameter at Breast 

Height  (DBH) 1    10,355.5  49,772.5 

Equivalent Number of 18” 

DBH Trees 2    575.3  2,765.1 

CO2 sequestration per 18” DBH 

tree over 50 years 3  Lbs  17,756  17,756 

  4  Lbs/yr per tree  355.1  355.1 

Amount of CO2 sequestered  5  Lbs/yr  204,302  981,952 

  6  Tons/yr  102  491 

Net Mitigation    Tons/yr    ‐389 

Notes: 

1. Data from Appendices D and H, DEIR Madera Ranch Quarry 

2. Number of equivalent 18” DBH trees = Total DBH/18 

3. CO2 sequestration calculated using a logarithmic regression models as described by Jenkins et al. 

“National‐Scale Biomass Estimators for United States Tree Species”, Forest Science, Vol. 49, No. 1, 

Feb. 2003.  Copy attached. 

Generalized Regression Equation for Total Above Ground Biomass (bm) from oak/hardwood 

trees is: 

bm=exp(b0 + b1ln(dbh)) 

            bm = total aboveground biomass (kg) for trees 2.5 cm or higher 

            b0 , b1 emirical constants 

            dbh = diameter in cm 

4. CO2 sequestration calculated for 50 years (from note 3) / 50.  Assume growth rate = 0.25ʺ diameter per 

year.  Below ground biomass = 0.2 x above ground biomass. 

5. CO2 sequesteration (lbs/tree per year) x number of equivalent 18ʺ DBH trees (from note 2) 

Conversion pounds/year  to tons per year 

 

 

While  the  operation  of  Madera  Quarry  would  result  in  a  local  increase  in 

greenhouse gases the combined emission totals from on‐site, off‐site, and electric 

power generation would be well below California’s OPH/SCH published interim 

thresholds  for  green  house  gas  of  7,000  metric  tons/year.    Total  anticipated 

emissions associated with  the Project are 5,882  tons/year and would be  further 

reduced with CO Sequestration to 5,493 tons/year.  Therefore, this impact is less 

than significant. 

 

Level of Significant Before Mitigation:  Potentially Significant 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 4.0-10

Page 191: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 4.0 New Legislative Mandate

 

RESOURCE DESIGN TECHNOLOGY, INC. 4.0-11

Mitigation Measures:   See Mitigation Measures  3.4‐3 and  3.5‐12d of  the DEIR 

and FEIR.  These measures are also provided in the Summary section (Table S‐1) 

of this DREIR.  Level of Significant After Mitigation:  Less than Significant 

 

4.5 CUMULATIVE IMPACTS AND MITIGATION MEASURES  

Impact 4.0-2: Project Emissions, in Combination with Other Development in the County, Could Contribute to Greenhouse Gases

 

Emission  from  mining  and  transportation  resulting  from  implementation  of  the  Project,  in 

combination with other cumulative development, has  the potential  to contribute  to greenhouse 

gas. 

 

The operation of Madera Quarry would result  in a  local  increase  in greenhouse 

gases.   Regionally, however,  the operation of  the Quarry would  result  in a net 

reduction in greenhouse gases.   

 

The demand of aggregate is driven by the population.  This demand is reflected 

in the number and location of aggregate plants.  According to the 2008 California 

Geological Survey,  the average per capita demand  is between 5 and 7  tons per 

person3  for  the  period  2003  through  2007.    This means  that  the  operation  of 

Madera  Quarry  would  not  create  new  demand  for  aggregate  or  asphaltic 

concrete.  Rather, the Quarry is being built in response to increased demand due 

to increased population. 

 

According  to  studies4  on  the  environmental  costs  associated with  delivery  of 

aggregate, it is estimated that transportation costs will exceed production costs if 

travel  distances  exceed  20 miles.    Therefore,  if  aggregate  cannot  be  procured 

locally,  it would  have  to  be  procured  from  other, more  distant  sources.    This 

3  The California Dept.  of Conservation  notes  that  for  the  Fresno  P‐C Region  the  average  annual  per 

capita consumption rate from 1960 to 1997 was 6.5 tons.  Ref: “Update of Mineral Land Classification: 

Aggregate  Materials  in  the  Fresno  Production‐Consumption  Region,  California”.    Dept.  of 

Conservation, Div. Of Mines and Geology, Sacramento.     Report 99‐02  (1999) of attached DOC  letter 

dated 4/1/1999. 4  Peter  Berck,  “A Note  on  the  Environmental Costs  of Aggregate” Working  Paper No.  994, Dept.  of 

Agricultural and Resource Economics Policy, University of California, Berkeley, January 2005.

Page 192: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 4.0 New Legislative Mandate

 

RESOURCE DESIGN TECHNOLOGY, INC. 4.0-12

would lead to higher truck miles and higher emissions of various air pollutants, 

including GHG emissions. 

 

Madera  Quarry  will  provide  aggregate  within  the  Fresno  Production‐

Consumption  (P‐C) Region, primarily  to Madera County  and Northern Fresno 

County.  Currently, Madera County and Northern Fresno County are served by 

four existing quarries  in Fresno County.   A new quarry which  is  scheduled  to 

open in the summer of 2009, CMI, Sanger and the Madera Quarry are shown in 

Figure  4.0‐1,  Location  of  Alternate  Sources  of  Aggregate  in Madera  County, 

along  with  existing  quarries.    According  to  Department  of  Conservation, 

Division  of Mines  and  Geology5,  the  current  supply  of  aggregate  in  Fresno 

Production‐Consumption Region was projected to be totally exhausted by 2011.  

However, in light of the recent economic recession, it is expected that the supply 

may last as long as 2014.  

 

Specifically, the current permitted supply is as follows: 

 

Vulcan San Joaquin:  1.6 million tons per year; 

Vulcan Sanger:  2.5 million tons per year; 

Cemex San Joaquin:  1.2 million tons per year; 

Granite Coalinga:  No Specific Limit; 

Air permit allows 11 million tons (not in Fresno P‐C); 

LeGrand Asphalt:  0.5 million tons (not in Fresno P‐C); and 

CMI Sanger:   1.0 Million  tons  per  year  (scheduled  to  open  in  Summer 

2009).  

 

When  the  supply of material at Vulcan San  Joaquin and Cemex San  Joaquin  is 

exhausted,  the  remaining  permitted  annual  production  from  these  other 

(excluding Coalinga) permitted  facilities will  total  4 million  tons per  year.    In 

1997, there was a 500,000 tons shortfall  in the Fresno P‐C area.   This shortfall  is 

based on a demand of 4.7 tons per year and a production rate of 4.2 million tons 

per year.    In 1998,  this shortfall was satisfied by 500,000  tons of material being 

shipped from Coalinga6. 

5  DOC Report 99‐02 (1999), page 2 of cover letter dated 4/1/1999. 6  Ibid.

Page 193: MADERA QUARRY PROJECT
Page 194: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 4.0 New Legislative Mandate

 

RESOURCE DESIGN TECHNOLOGY, INC. 4.0-14

In 2006, the DOC updated its data regarding permitted aggregate availability in 

California7.  The DOC noted that the Fresno P‐C had only 11 percent of the next 

50 years demand under permit, making it one of the 4 lowest of the 31 regions.  

The  reserves were  less  than 10 years of demand.   This  represents a 27 percent 

drop  from  the  DOC’s  2002  calculations.    DOC  acknowledged  “Aggregate 

shortages in the Fresno area have resulted in rock being imported from Coalinga, 

a 60 mile haul.”8 

 

Once the Vulcan and Cemex San Joaquin facilities are exhausted and after CMI 

Sanger  opens  for  business,  there  will  only  be  4.0  million  tons  per  year  of 

permitted  supply9  from  Le Grand  to  the North  and  CMI  Kings  River  to  the 

South.   

 

The DOC has previously estimated the following average annual demand for the 

respective time periods: 

 

2003 to 2007:   6.48 million tons; 

2008 to 2012:   7.42 million tons; and 

2013 to 2017:   8.48 million tons. 

 

If  these  estimates  are  accurate,  without  other  permitted  facilities  coming  to 

market, the production from Madera Quarry would serve to reduce the quantity 

of material being transported from Coalinga by 900,000 tons per year.  This is not 

to say that all of Madera Quarry’s customers would otherwise transport material 

from  Coalinga.    However,  whether  it  is Madera  Quarry’s  or  other  facilities’ 

customers, Madera Quarry coming on‐line will reduce the quantity of import to 

the Fresno P‐C Region by 900,000 tons per year. 

 

Scenario 1 – 2009 to 201110  

If we assume  that  for  the period 2009  to 2011,  the majority of Madera Quarry’s 

customers are located primarily in Madera County, then aggregate shipped from 

7  Map Sheet 52, Aggregate Availability in California 2006, Department of Conservation 8  Aggregate Availability in California, 200, Map Sheet 52, Dept. of Conservation, pg. 15. 9  LeGrand’s  production  is  primarily  consumed  in  that  immediate  area,  but  for  the  purposes  of  this 

analysis all of it is assumed to be available for the Fresno P‐C Region. 10  It  is  recognized  that  the  production  at  the  Cemex  and  Vulcan  San  Joaquin  facilities might  not  be 

exhausted until  2014 due  to  the  economic downturn,  this  report  continues  to use  the data  from  the 

DOC that indicates the production at these two facilities would cease by 2011. 

Page 195: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 4.0 New Legislative Mandate

 

RESOURCE DESIGN TECHNOLOGY, INC. 4.0-15

Madera Quarry would  result  in  a  saving  of  25 miles per  trip  as  compared  to 

aggregate  shipped  from  Fresno  County.    Shipments  to  customers  in  Central 

Madera would reduce truck travel by approximately 10 miles per the October 13, 

2009  traffic study11  included  in  the EIR.   This would  lead  to a net reduction on 

GHG emissions by a minimum of 386 tons per year as shown below in Table 4.0‐

6,  Summary  of Avoided Emissions  –  Scenario  1  (2009  to  2011).   This  estimate 

assumes no change employee vehicle or delivery traffic volume or miles driven. 

 

Scenario 2 – Beyond 2011  

Beyond  2011,  the only  source of material will be  the Coalinga  facility.    In  this 

scenario,  the material would be  transported approximately 65 miles  (one‐way).  

However, a detailed analysis  that  takes  into account  the  location of population 

the  net  savings would  be  35 miles  per  one‐way  trip12.    In  this  scenario,  the 

avoided GHG  emissions would be 4,218  tons per year a  shown  in Table 4.0‐7, 

Summary of Avoided Emissions – Scenario 2 (Beyond 2011). 

 

 

TABLE 4.0-6 SUMMARY OF AVOIDED EMISSIONS – SCENARIO 1 (2009 TO 2011)

 CO2

Maximum

Annual Trips Round Trip

Length (mile) Annual Miles (gram/mile) (tons/yr)  Employee Vehicles  10,000  20  400,000  305.0  134.4 

 Off‐Site Haul Trucks  36,000  10  360,000  1611  639 

 Delivery Trucks  2,250  46  207,000  521.0  118.8 

Total  386 

Notes: 

1. Annual tons/year  = (gram/mile) x (annual miles) / (454 grams/lb)(2000 lbs/ton). 

2. Gram/mile data based on EMFAC model run for Madera County for 2000 to 2008 fleet mix.   Copy of 

EMFAC model provided in the Appendix. 

3. Traffic and mileage data from Appendix D of this DREIR, Table 16, of Traffic Study (Peters Engineering 

Group, October 13, 2009). 

 

 

11  “Traffic Impact Study, Proposed Madera Quarry”, October 13, 2009, Peters Engineering Group, Clovis, 

CA. 12  Traffic Impact Study for Proposed Madera Quarry, Peters Engineering Group, October 13, 2009. 

Page 196: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 4.0 New Legislative Mandate

 

RESOURCE DESIGN TECHNOLOGY, INC. 4.0-16

TABLE 4.0-7 SUMMARY OF AVOIDED EMISSIONS – SCENARIO 2 (BEYOND 2011)

  CO2

Maximum

Annual Trips Round Trip

Length (mile) Annual Miles (gram/mile) (tons/yr)  Employee Vehicles  10,000  20  400,000  305.0  134.4 

Haul Trucks (note 3)  36,000  70  2,520,000  1,611  4,471 

 Delivery Trucks  2,250  46  207,000  521.0  118.8 

Total:  4,218 

Notes: 

1. Annual tons/year  = (gram/mile) x (annual miles) / (454 grams/lb)(2000 lbs/ton). 

2. Gram/mile data based on EMFAC model run for Madera County for 2000 to 2008 fleet mix.   Copy of 

EMFAC model provided in the appendix. 

3. Traffic and mileage data from Appendix D of this DREIR, Table 16, of Traffic Study (Peters Engineering 

Group, October 13, 2009). 

 

 

Material  supplied by Madera Quarry  to  job  sites  in Central Madera County  to 

Southern Merced County would  lead  to  a net  savings of between 386  to  4,289 

tons/year of greenhouse gases from avoided transportation related emissions.   

 

To place the above emission in perspective, the statewide CO2 emissions in 2004 

were approximately 390 million tons.   The project emissions represent  less than 

0.001 percent of statewide emissions.    In addition,  in  January 2009,  the state of 

California  through  OPH/SCH  published  interim  thresholds  for  greenhouse 

gases.   The interim threshold for GHG is 7,000 metric tons of GHG equivalents.  

Using this threshold, GHG emissions are less than significant when compared on 

project basis or compared with regional emissions.   

 

Level of Significant Before Mitigation:  Less than Significant 

 

Mitigation Measures:  None Required 

Page 197: MADERA QUARRY PROJECT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5.0 LIST OF PREPARERS

Page 198: MADERA QUARRY PROJECT

 

 

 

 

 

 

 

 

 

 

5.0 LIST OF PREPARERS  

 

 

5.1 LEAD AGENCY STAFF  

Madera County Planning and Building Inspection Department 2037 West Cleveland Avenue 

Madera, California  93637 

 

Matthew Treber, Planner III 

 

5.2 CONSULTANTS AND OTHER INDIVIDUALS INVOLVED IN THE PREPARATION OF THE EIR

 

5.2.1 Applicant Team  

Madera Quarry, Inc. P.O. Box 994248 

Redding, California  96099 

 

Leonard Bandell, Esq., Vice President 

Kim Enderson, Executive Assistant 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 5.0-1

Page 199: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 5.0 List of Preparers

5.2.2 Applicant Team Technical Consultants  

Greenhouse Gas:  

Air Permitting Specialists

12247 Welch Road 

Wilton, California  95693 

Ray Kapahi, Principal 

Hydrology:  

Luhdorff & Scalmanini Consulting Engineers

500 First Street 

Woodland, California  95695‐4026 

Joseph C. Scalmanini, Principal 

Kenneth D. Schmidt and Associates

600 West Shaw, Suite 250 

Fresno, California  93704 

Kenneth D. Schmidt, Certified Hydrogeologist  

and Professional Geologist 

Blair Church & Flynn Consulting Engineers

451 Clovis Avenue, Suite 200 

Clovis, California  93612 

Cordie R. Qualle, Project Engineer  

and Registered Professional Engineer 

Noise:  

Bollard Acoustical Consultants, Inc.

455 Main Street, Suite 3 

Newcastle, California  95658 

Paul Bollard, President 

Transportation:  

Peters Engineering

952 Pollasky Ave. 

Clovis, California  93612 

John Rowland, Civil Engineer 

 

 

 

RESOURCE DESIGN TECHNOLOGY, INC. 5.0-2

Page 200: MADERA QUARRY PROJECT

MADERA QUARRY DRAFT REVISED ENVIRONMENTAL IMPACT REPORT 5.0 List of Preparers

 

RESOURCE DESIGN TECHNOLOGY, INC. 5.0-3

5.2.3 Peer Review, Editorial, and Formatting  

RESOURCE DESIGN TECHNOLOGY, INC. 4990 Hillsdale Circle, Suite 400 

El Dorado Hills, California  95762 

 

David E. Brown, Principal 

Bruce Steubing, Project Director 

Andrew White, Project Manager 

Jesse Hall, Graphics 

Gian Duong, Document Control Manager 

Katharina McKillip, Document Preparation 

 

 

 

Page 201: MADERA QUARRY PROJECT

 

www.resourcedesign.bizResource Design Technology, Inc. 4990 Hillsdale Circle, Suite 400, El Dorado Hills, California 95762