MacroProcess: Process Owner:
Work System OwnerEd Curry
Work System Enabling LeaderDane Theodore, Director
Priority Processes Owner Dennis Bonny, Project Mgr.
April 21, 2009
Revision 2
Manage Facilities Construction
Process Improvements
R TE NC EI IP
R TE NC EI IPGOVERNOR’S
STERLING AWARDGOVERNOR’S
STERLING AWARD
00 72 00 72
D. BonnyMANAGE FACILITIES
CONSTRUCTION
CCC HIGH SCHOOLBAYSIDE HIGH SCHOOL
REVISION LOG
SECTION NUMBER REVISION DATE REVISION DESCRIPTION
10
11
6
13
14
18
3/16/09
3/16/09
4/21/09
4/21/09
4/21/09
4/21/09
Macro PCS Baseline Update
KWP6 & 7 PCS Baseline Update
KWP6 & 7 DMAIC Storyboard Lite
Project Closeout Activity CountermeasureMatrix
Project Closeout Activity CountermeasureAction Plan Matrix
EZDMAIC 20 Checkpoint Review
MacroProcess: Process Owner:
D. BonnyMANAGE FACILITIES
CONSTRUCTION
D. BonnyMacro
Process: Process Owner:
Table of Contents1. Cover Sheet2. Table of Contents3. Internal and External Customers4. Macro Flow Chart5. Key Work Process 6& 7 Flow Chart6. DMAIC Lite Storyboard - Check Points 1-187. Priority Process Selection Matrix Form8. Key-In-Process Measures Determination System Form9. BPS Process Management System10. Macro Process Control System Form11. Key Work Process 6 & 7 Process Control Form12. Macro Countermeasure Matrix13. Project Closeout Activities (KWP6 & KWP7) Countermeasure Matrix14. Countermeasure Action Plan Matrix15. Action Plan(s) for Root Causes16. Document Tree17. Key Work Process Indicator Data18. EZDMAIC 20 Checkpoint Review
MANAGE FACILITIES CONSTRUCTION
MacroProcess: Process Owner:
ESCC INTERNAL CUSTOMERSSchool Board
SuperintendentArea SuperintendentsDistrict AdministrationSchool Administration
ECSS EXTERNAL CUSTOMERSState of Florida
Florida Department of EducationLocal Government Agencies
Parents / GuardiansStudents
D. BonnyMANAGE FACILITIES
CONSTRUCTION
ISSUENOTICE TOPROCEED
NEED PROJECTCONSTRUCTED
PERFORM SUBSTANTIAL COMPLETION ACTIVITIES
SELECTCONTRACTOR
PERFORM PRE-CONSTRUCTION ACTIVITIES
?
?
?
?
?
?
?
?
PRE-CONSTRUCTIONREQUIREMENTS MET?
BOARD APPROVED?
CONSTRUCTIONCLOSEOUT COMPLETE?
SUBSTANTIAL COMPLETION
REACHED?
TEMPORARY CONEEDED?
YES
YES
YES
NO
NO
NO
YES
YES
NO
NO
NEED ISMET
OBTAIN CFI
DELIVERABLES:
D1. Certificate of Occupancy (CO)
D2. Projects Constructed per BPS Design Specifications, Florida Building Code, and State Requirements for Educational Facilities
D3. Certificate of Final Inspection (CFI)
D4. As-Built Project Plans
Q1 - Actual Sales Tax Savings / Possible Sales Tax Savings (%)
Q2 - Construction Critical Path Milestones (% Variance from Construction Schedule)
Q3 - Construction Budget vs. Actual Construction Costs (% Variance)
Q4 - Construction-Related SESIR Incidents
Q5 - Construction Safety JLA Security Incidents
Q6 - Warranty Actions
P2 - Construction Critical Path Milestones
P3 -
P4 - Cumulative Sales Tax Savings as a % of Construction Cost
P5 - Monthly Construction Budget vs. Actual Construction Cost Variance
P6 - Construction-Related School Environmental Number of Safety Incident Report (SESIR) Incidents Involving Students and School Staff
P7 - Number of Construction Worker Safety Incidents
P8 - Number of Jessica Lundsford Act (JLA) Incidents
Cumulative Use of Estimated Contingency Funds as a Percent (%) of Cumulative Construction Costs
P1 - Pre-Construction Activity Milestones
P10 - Construction Closeout Activity Milestones
P9 - Substantial Completion Activity Milestones
P11 - Administrative Closeout Activity Milestones
P12 - Number Warranty Requests
? ADMINISTRATIVE
CLOSEOUT COMPLETE?
NO
YES
PERFORM ADMINISTRATIVE CLOSEOUT ACTIVITIES
PROJECT VALUE <$200K?
APPROVE CONTRACTOR BY BOARD
BOARDAPPROVAL
REQUIRED?
D1
D2
D3
D4
OBTAINTEMPORARY
CO
MANAGE PROJECT
HAS THE CONTRACTOR REQUESTED SUBSTANTIAL COMPLETION INSPECTION?
YES
YES
YES
NO
NO
NO
PERFORM CONSTRUCTION CLOSEOUT ACTIVITIES
KWP1
KWP2
KWP3
KWP4
KWP5
KWP6
KWP7
WHO
STEP
MacroProcess: Process Owner:
OBTAIN CO
START WARRANTY
QUESTION
NEED
PERFORM
PERFORM
APPROVE
SELECT
QUESTION
QUESTION
ISSUE
QUESTION
MANAGE
OBTAIN
QUESTION
QUESTION
START
OBTAIN
QUESTION
QUESTION
MANAGED
QUESTION
PERFORM
PERFORM
MANAGEFACILITIES CONSTRUCTION D. THEODORE
BPS FACILITIES SERVICES CONTRACTOR
BPS SCHOOL BOARD
FACILITIES SERVICES / Robert J. Wiebel & Dennis Bonny 10/30/08
NEED TO CLOSEOUT CONSTRUCTION
CONTRACT
NEED ISMET
Deliverables: D1 - Closeout Documents per Item #2 of Procedural Guidance. D2 - Architect Closeout Documents per Item #2 of Procedural Guidance D3 - CM Closeout Documents per Item #2 of Procedural Guidance. D4 - Owner Training & Video Training / Instruction D5 - Final Closeout Amendment W/ Attachments for Board Approval
?
?
?
?
?
PUNCH LISTCOMPLETED?
HVAC TEST &BALANCE COMPLETE?
OWNER TRAININGCOMPLETE?
AUDITACCEPTABLE?
OTHER CM/A&ECLOSEOUT DOCS
ACCEPTABLE?
YES
YES
YES
YES
YES
NO
NO
NO
NO
NO
PREPARE & SUBMIT CM/ A&E CLOSEOUT
DOCUMENTS
REVIEW OTHER CM/A&ECLOSEOUT DOCUMENTS
REVIEW CM/A&ECLOSEOUT DOCUMENTS
COMPLETE PUNCH LIST
PERFORM EQUIPMENT SYSTEMS TRAINING
CONDUCT AUDIT
BOARD APPROVAL
RELEASE FUNDS
CM/A&E PROVIDE INFO
PREPARE FINALAMMENDMENT &
PRESENT TOBOARD
P1 - # CLOSEOUT DOCS SUBMITTED
P2 - # CLOSEOUT DOCS REVIEWED
WHO
STEP
KWP6 &KWP7Process: Process Owner:
SCHOOL CM / AE / DBBPS FACILITIES
PREPARE &SUBMIT
QUESTION
QUESTION
REVIEW
QUESTION
REVIEW
NEED
COMPLETE
PERFORM
QUESTION
MANAGED
PROVIDE
QUESTION
APPROVAL
RELEASE
PREPARE
CONDUCT
PERFORM CONSTRUCTION
CLOSEOUT ACTIVITIES
FACILITIES SERVICES: ROBERT J. WIEBEL / DENNIS BONNY 11/21/08
Q1 - CONSTRUCTION CLOSEOUT DOCUMENT REVIEW MILESTONES COMPLETED
Q2 - CLOSEOUT DOCUMENTS REVIEWED AND APPROVED IN 5 BUSINESS DAYS OR LESS
Q3 - OWNER TRAINING / INSTRUCTION MILESTONECOMPLETED
Q4 - CONSTRUCTION AUDIT MILESTONES COMPLETED
Q5 - BOARD AMENDMENT PREPARATION AND APPROVAL MILESTONES COMPLETED
D. BONNY
Facilities Construction DMAIC Lite 4/22/2009 Page 1
INSTRUCTIONS: Please return your completed DMAIC Storyboard, along with your Process Control System (both flow chart and indicator information) and your completed Action Plan (see “Improve” checkpoint #10), via email to [email protected] and copy Steve Muzzy on all emails. Thank you, Bob Seemer, President & COO, Electronic Training Solutions, Inc. Priority Process Name: Manage Facilities Construction
Work System / Leader: Dane Theodore Revision: 1 Date: 4/21/09
Macro DMAIC “Lite” Storyboard
DEFINE
1. Describe how the linkage between the process Q measures and the District’s KPIs (or strategic objective measures) was established and confirmed.
In order to achieve the milestones identified in the 2008/2009 BPS Strategic Plan (KPI 16), as it related to “Safe and Healthy Learning and Work environment and the Ten (10) Year Facilities Improvement Plan, the design of facilities must utilize a structured approach to controlling the cost of construction, the implementation of the construction schedule and a safe construction site. In light of this structured construction approach, constant monitoring of cost, schedule and safety at all levels is imperative. Six (6) Q Measures have been developed to collect cost and schedule data:
i. , Q1 - Actual Sales Tax Savings / Possible Sales Tax Savings (%),
ii. Q2 - Construction Critical Path Schedule Milestones (% Variance from Schedule),
iii. Q3 - Construction Budget vs. Actual Costs (% Variance),
iv. Q4 - Construction-Related SESIR Incidents,
v. Q5 - Construction Worker Safety and JLA Incidents, and
vi. Q6 - Warranty Actions.
2. Explain which process Q measure(s) will be improved.
In order to identify the Q Measure to improve, a Facilities Construction Priority Process Selection Matrix and a Key-In-Process Measures Determination form were created. See attachments. After analyzing the data contained in each attachment, it was determined that Q Measure Q2 will be improved by improving key in-processes Construction Closeout Activity Milestones” and “Administrative Closeout Activity Milestones”. These two activities together are classified as “Project Closeout Activities”.
3. Develop a theme statement which will focus your process improvement efforts. The theme statement must be consistent with the measure in checkpoint #2, above.
Actual Project Completion Date exceeds the Contractual Project Completion Date by a variance that ranges between minus (-) 22.75 days to plus (+) 65.33 days during fiscal years 04 - 08
Facilities Construction DMAIC Lite 4/22/2009 Page 2
DMAIC “Lite” Storyboard
MEASURE
4. List up to five (5) potential problem areas in this process and the associated P measure(s) for each.
Pre-construction activities take longer than estimated.
Substantial completion activities take longer than estimated.
Construction closeout activities take longer than estimated.
Administrative closeout activities take longer than estimated.
5. Select the most significant problem or opportunity and develop a problem statement which answers the questions:
What? When? Gap between actual and targeted values?
Problem: Construction and Administration closeout activities take excessive time to complete. Contractors are consistently late in completing HVAC commissioning and project turnover. Problem Statement: Closeout for projects scheduled for completion in 2007, were impacted by incomplete and / or improperly commissioned HVAC work which precluded the project’s final completion be achieved within the scheduled 90 day period after substantial completion. Gap: Four projects were completed in 2007 with a completion variance that ranged between minus (-) 20 days to plus (+) 121 days. That is a 141 day range. Final completion average gap for all projects is 22.25 days.
(Hint: You may want to refer to the six sigma DMAIC course material, checkpoint #9 of the “Measure” step, as you develop your problem statement.)
Facilities Construction DMAIC Lite 4/22/2009 Page 3
DMAIC “Lite” Storyboard
ANALYZE
6. List up to five (5) potential causes of the selected problem from checkpoint #5 in the “Measure” step.
Untimely delivery of HVAC equipment.
Longer than scheduled delays in HVAC commissioning.
Lack of coordination between CM / HVAC sub / TC sub-sub.
Test and Balance contractor start date slipped.
TC sub did not complete scope of work timely.
7. List the root causes and describe the approach used to select them from among the others.
Root Causes Approach Used To Select Root Cause
A. Equipment delivery CPM schedule slipped, adjacent task durations shortened
B. Longer commissioning duration Milestone date missed
C. Coordination issues Poor communication and follow through
D. T & B start date Report submissions late
E. TC not complete Maintenance unable to monitor systems, excessive utility usage
Facilities Construction DMAIC Lite 4/22/2009 Page 4
DMAIC “Lite” Storyboard
IMPROVE
8. List the countermeasure(s) you considered for implementation for each selected root cause from the “Analyze” step.
A) CM’s CPM schedule to include long lead equipment submittal / approval / fabrication and delivery dates with logic ties to related milestones.
B) Hire commissioning agent, conduct commissioning meetings at key intervals during construction.
C) Modify relationship between HVAC sub and TC sub-sub. TC to be contracted directly with CM.
D) Include T & B sub in commissioning meetings, explore alternatives for component testing.
E) CM to monitor closely work of TC subcontractor and TC subcontractor schedule.
9. Determine the “effectiveness x feasibility” score for each countermeasure, and note the highest scores.
Countermeasure Effectiveness Feasibility Overall Action
A 5 4 20 Yes
B 5 4 20 Yes
C 5 5 25 Yes
D 5 5 25 Yes
E 5 5 25 Yes
10. Develop an action plan for each countermeasure to be implemented which shows the following: What (description of countermeasure) When (projected start and end dates) Who (accountable person) Which organizations need to support you Estimated cost to implement
See attached Countermeasure Action Plan Matrix.
(Remember: Email your action plan(s) with this completed DMAIC “Lite” Storyboard, per instructions on page 1.)
Facilities Construction DMAIC Lite 4/22/2009 Page 5
DMAIC “Lite” Storyboard
CONTROL
11. Briefly explain how you know the root causes were reduced or eliminated.
Equipment deliveries would occur timely, which will help eliminate schedule slippage.
12. Briefly explain how you know the problem was reduced.
Schedule slippage was eliminated from specific durations where this process was used.
13. Briefly explain how you know the theme measure was improved.
More work will be completed, verified and / or corrected prior to substantial completion.
14. Explain how you will prevent this problem from recurring.
Continue to follow through with the established process, measure results and modify accordingly based upon said results or project specific requirements.
15. Identify which other BPS locations should consider implementing your countermeasures.
Maintenance, for certain capital projects, ET and CTE for planning activities with Facilities.
16. Identify what other BPS locations could learn from this project.
Maintenance.
17. List the remaining problem areas in this process.
No process is full-proof, especially processes such as these that can be disrupted by human error, which is the major component for this process to fail.
18. List the key lessons learned from this process improvement.
Project closeout is not just a milestone; it is a continuous process that requires thought, commitment and incremental task completion by the team throughout the project’s duration.
ATTACHMENT A
Facilities Construction DMAIC Lite 12/18/2008 Page 7
FACILITIES CONSTRUCTION
PRIORITY PROCESS SELECTION MATRIX FORM Selection Factor
Key Work Processes Importance x Gap = Point Score Priority Rank
Select Contractor 5 1 5 3
Approve Contractor By Board 5 1 5 3
Perform Pre-Construction Activities 5 2 10 2
Manage Project 5 1 5 3
Perform Substantial Completion Activities 5 2 10 2
Perform Construction Closeout Activities 5 3 15 1
Perform Administrative Closeout Activities 5 3 15 1
Perform Warranty Administration 5 1 5 3
SCALE: 5 = Extreme 4 = High 3 = Moderate 2 = Low 1 = None
ATTACHMENT A
Facilities Construction DMAIC Lite 12/18/2008 Page 8
KEY IN-PROCESS MEASURES DETERMINATION FORM
Outcome Measures In-Process Measures
Q1 - Actual Sales Tax Savings / Possible Sales Tax Savings (%)
1. Cumulative Sales Tax Savings as a % of Construction Cost
1. Pre-Construction Activities Milestones
2. Construction Critical Path Milestones
3. Substantial Completion Activity Milestones
4. Construction Closeout Activity Milestones
Q2 - Construction Critical Path Schedule Milestones (% Variance from Schedule)
5. Administrative Closeout Activity Milestones
1. Cumulative Use of Estimated Contingency Funds as a Percent (%) of Cumulative Construction Costs
Q3 - Construction Budget vs. Actual Costs (% Variance) 2. construction Budget vs. Actual Construction Cost
Variance
Q4 - Construction-Related SESIR Incidents 1. Number of Construction-Related School
Environmental Safety Incident Report (SESIR) Incidents Involving Students and School Staff
1. Number of Construction Worker Safety Incidents Q5 - Construction Worker Safety and JLA Incidents
2. Number Jessica Lundsford Act (JLA) Incidents
Q6 - Warranty Actions 1. Number of Warranty Requests
BPS Process Management System
Work System: Manage Facilities Construction Leader: Dennis Bonny
Owner Members Priority Processes Name Email Name Email
1.
2.
3. KWP1 Select Contractor
4.
1.
2.
3. KWP2 Approve Contractor By Board
4.
1.
2.
3. KWP3 Perform Pre-Construction Activities
4.
1.
2.
3. KWP4 Manage Project
4.
1.
2.
3. KWP5
Perform Substantial Completion Activities
4.
BPS Process Management System
Work System: Manage Facilities Construction Leader: Dennis Bonny
Owner Members Priority Processes Name Email Name Email
1.
2.
3. KWP6
Perform Construction Closeout Activities
4.
1.
2.
3. KWP7
Perform Administrative Closeout Activities
4.
WORK IN PROGRESS
Macro Process Control System Process Name: Facilities Construction Process Owner: Dane Theodore
Process Customer: The School Board of Brevard County, representing staff, students, parents and the community Critical Customer Requirements:
Current Sigma Level: TBD Process Purpose: Facilities Project Construction Outcome Indicators: Q1 – Q6 Process and Quality Indicators Checking / Indicator Monitoring
Process Indicators
Control Limits Data to Collect
Timeframe (Frequency) Responsibility
Quality Indicators
Specs/ Targets
What is Checking Item or Indicator Calculation
When to Collect Data?
Who will Check?
Contingency Plans / Miscellaneous Actions Required for Exceptions Procedure References
P1 Pre-Construction Activity Schedule Milestones
Target: 100% of activities completed by scheduled
milestone date Baseline: 10 days
Completion status of required tasks at schedule milestones At least monthly Director
Project Mgr. Review/analyze situation and request that the Contractor provide a recovery action plan.
P2 Construction Critical Path Schedule Milestones
Target: 100% of activities completed by scheduled
milestone date Baseline: 5 days
Completion status of required tasks at schedule milestones At least monthly Director
Project Mgr. Review/analyze situation and request that the Contractor provide a recovery action plan.
P3 Cumulative Use of Estimated Contingency Funds as a Percent (%) of Cumulative Construction Costs
Target: ≤ 2.5% Baseline: 2%
Cumulative use of estimated contingencies – Cumulative Construction Costs At least monthly Director
Project Mgr. Analyze contingency budget and look for possible project scope reductions.
P4 Cumulative Sales Tax Savings as a % of Construction Cost
Target: ≥ 1% Baseline: 1.25%
Cumulative sales tax savings from owner direct purchase records
and cumulative construction cost At least monthly Director
Project Mgr. Review/analyze situation and request that the Contractor provide a recovery action plan.
P5 Monthly Construction Budget vs. Actual Construction Cost Variance.
Target +/- 2.5% Baseline -.9% - 1.4% Construction Budget and construction costs Monthly
Director
Project Manager Review / analyze situation and request CM to investigate potential changes in the scope of work to maintain budget.
P6 Construction-Related SESIR Incidents Involving Students and School Staff
Target: 0 Baseline: 0 # of Incidents At least monthly Director
Project Mgr. Review Contractor’s Safety Plan and meets with Contractor’s Safety Director.
P7 Construction Worker Safety Incidents Target: 0 Baseline: 3 # of Incidents At least monthly Director
Project Mgr. Review Contractor’s Safety Plan and meets with Contractor’s Safety Director.
P8 Jessica Lunsford Act (JLA) Incidents Target: 0 Baseline: 0 # of Incidents At least monthly Director
Project Mgr. Review Contractor’s Safety Plan and meets with Contractor’s Safety Director.
P9 Substantial Completion Activity Milestones
Target: 100% of activities completed by scheduled
milestone date Baseline: 120 days
Completion status of required tasks at schedule milestones At least monthly Director
Project Mgr. Review/analyze situation and request that the Contractor provide a recovery action plan.
P10 Construction Closeout Schedule Milestones
Target: 100% of activities completed by scheduled
milestone date Baseline: 120 days
Completion status of required tasks at schedule milestones At least monthly Director
Project Mgr. Review/analyze situation and request that the designer develop a recovery action plan.
P11 Administrative Closeout Schedule Milestones
Target: 100% of activities completed by scheduled
milestone date Baseline: 120 days
Completion status of required tasks at schedule milestones At least monthly Director
Project Mgr. Review/analyze situation and request that the designer develop a recovery action plan.
P12 Warranty Requests Target: 0 Baseline: 18 # of requests End of Warranty
Period Director
Project Mgr. Use number of warranty requests as a performance indicator during contractor selection process.
And
WORK IN PROGRESS
Macro Process Control System Process Name: Facilities Construction Process Owner: Dane Theodore
Process Customer: The School Board of Brevard County, representing staff, students, parents and the community Critical Customer Requirements:
Current Sigma Level: TBD Process Purpose: Facilities Project Construction Outcome Indicators: Q1 – Q6 Process and Quality Indicators Checking / Indicator Monitoring
Process Indicators
Control Limits Data to Collect
Timeframe (Frequency) Responsibility
Quality Indicators
Specs/ Targets
What is Checking Item or Indicator Calculation
When to Collect Data?
Who will Check?
Contingency Plans / Miscellaneous Actions Required for Exceptions Procedure References
Q1 Actual Sales Tax Savings / Possible Sales Tax Savings (%)
Target: +/- 1% Baseline: 1.25%
Total sales tax savings from ODP records and possible sales tax savings for purchases >
$5,000 Administrative
Closeout Director
Project Mgr. Meet with Contractor and review Owner Direct Purchase program. Develop a plan of action to increase STS.
Q2 Construction Critical Path Schedule Milestones (% Variance from Schedule)
Target: + 0% to - ∞ Baseline: 5 days
Completion status of required tasks at schedule milestones
Administrative Closeout
Director Project Mgr.
Review/analyze situation and request that the Contractor provides a recovery schedule.
Q3 Construction Budget vs. Actual Costs (% Variance)
Target: ± 2.5% Baseline: -0.9% - 1.4%
Construction budget and total construction cost
Administrative Closeout
Director Project Mgr.
Do not use Contractors who do not meet the 2.5% construction cost target.
Q4 Construction-Related SESIR Incidents Target: 0 Baseline: 0 # of Incidents Administrative
Closeout Director
Project Mgr. Do not use Contractors who have a safety program that allows construction-related SESIR incidents.
Q5 Construction Worker Safety and JLA Incidents
Target: 0 Baseline: 0 # of Incidents Administrative
Closeout Director
Project Mgr. Do not use Contractors who have a safety program that allows excessive construction worker safety incidents.
Q6
Warranty Actions Target 0 Baseline: 0 # of requests and responsiveness Warranty Period Director
Project Manager Do not use Contractor with an unreasonable record of warranty requests and / or lack of responsiveness.
Approved:
Date:
Rev #:
Rev Date:
And
WORK IN PROGRESS
KWP6 & KWP7 Process Control System Process Name: Facilities Construction Process Owner: Dane Theodore
Process Customer: The School Board of Brevard County, representing staff, students, parents and the community Critical Customer Requirements:
Current Sigma Level: TBD Process Purpose: Perform Construction Closeout Activities Outcome Indicators: Q1 – Q4 Process and Quality Indicators Checking / Indicator Monitoring
Process Indicators
Control Limits Data to Collect
Timeframe (Frequency) Responsibility
Quality Indicators
Specs/ Targets
What is Checking Item or Indicator Calculation
When to Collect Data?
Who will Check?
Contingency Plans / Miscellaneous Actions Required for Exceptions Procedure References
P1 Punchlist completion Target: 100% of tasks
completed by scheduled milestone date
Baseline: 120 days
Completion status of required tasks at schedule milestones At milestone Director
Project Mgr. Review/analyze situation and request that the Contractor provide a recovery action plan.
P2 HVAC Turnover Meeting Target: Completed by
scheduled milestone date Baseline: 120 days
Completion status of required tasks at schedule milestones At milestone Director
Project Mgr. Review/analyze situation and request that the Contractor provide a recovery action plan / reschedule meeting.
P3 Closeout document submission Target: 100% of completed and
submitted by scheduled milestone date
Baseline: 120 days
Completion status of required tasks at schedule milestones At milestone Director
Project Mgr. Review/analyze situation and request that the Contractor provide a recovery action plan / reschedule submission.
P4 Owner Training Target: 100% of activities completed by scheduled
milestone date Baseline: 60 days
Completion status of required tasks at schedule milestones At milestone Director
Project Mgr. Review/analyze situation and request that the Contractor provide a recovery action plan / reschedule submission.
P5 Financial Audit Target: Complete by milestone
date Baseline: 45 days
Review construction costs At milestone
Director Project Manager
Review/analyze audit results and request Contractor comply with auditor’s request for information, if necessary. Provide date for compliance.
P6 Final Amendment for Board Target: Complete by Board
Agenda deadline Baseline: 5 days
Review audit, contract, previous amendments As required for Board Agenda
Director Project Mgr. Prepare and / or revise Amendment to coincide with Board schedule.
Q1 Review documents for specification / contract compliance.
Target: 100% of documents are compliant
Baseline: 5 days Documents complete and compliant Prior to audit Director
Project Mgr. P3
Q2 Owner training Target: 100% of scheduled
training performed Baseline: 60 days
Confirmation included in closeout documentation Prior to audit Director
Project Mgr. P4
Q3 Audit Status Target: completed by scheduled
milestone date Baseline: 45 days
Review auditor report Weekly Director Project Mgr.
Review completion date and accelerate / reschedule as needed to coincide with Board meetings
Q4 Amendment preparation, and execution Target: Complete and in queue
for signature Baseline: 30 days
Review Final Amendment As required for Board Agenda
Director Project Mgr. Prepare and / or revise Amendment to coincide with Board schedule.
Approved:
Date:
Rev #:
Rev Date:
And
Countermeasures Matrix ____________________________Countermeasures Matrix ____________________________
EFFECTIVENESS X FEASIBILITY = OVERALL ACTION
PROBLEM
ROOT CAUSE
COUNTER-MEASURE
PRACTICALMETHODS
Longer than scheduled delays in HVAC commissioning.
Construction and Administration closeout activities take excessive time to complete. Contractors are consistently late in completing HVAC commissioning and project turnover.
Untimely delivery of HVAC equipment.
Lack of coordination between CM / HVAC sub / TC sub-sub.
Test and Balance contractor start date slipped.
TC sub did not complete scope of work timely.
CM's CPM schedule to include long lead equip. Submittal / approval / fabrication and delivery dates with logic ties to related milestones.
Hire commissioning agent, conduct commissioning meetings at key intervals during construction.
Owner to hire commissioning agent and conduct commissioning meetings.
Modify relationship between HVAC sub and TC sub-sub. TC to be contracted directly with CM.
Include T & B sub in commissioning meetings, explore alternatives for component testing.
CM to monitor closely work of TC subcontractor and TC subcontractor schedule.
Use CM staff to develop long lead equipment schedule.
Use CM resources to improve relationship between HVAC and TC Subcontractors.
Use CM resources to schedule commissioning meetings.
Use CM resources to monitor TC subcontractor work.
5
5
5
5
5
4
4
5
5
5
20
20
25
25
25
Yes
Yes
Yes
Yes
Yes
Scale: 1 = Negligble 2= Somewhat 3= Moderate 4= Very 5 = Extreme
KWP6/7 PERFORM PROJECTCLOSEOUT ACTIVITY
DMAIC LITE STORYBOARD – IMPROVE – CHECKPOINT 10
Macro / KWP 6 & 7 Countermeasure Action Plan COUNTERMEASURE
PROJECTED START DATE
PROJECTED END DATE
ACCOUNTABLE PERSON
SUPPORT ORGANIZATION ESTIMATED COST
A) CM’s CPM schedule to include long lead equipment submittal / approval / fabrication and delivery dates with logic ties to related milestones.
July 2008 June 2009 Construction Manager (CM)
CM, A/E, Subcontractor and vendor.
The cost of CM staff time to implement.
B) Hire commissioning agent, conduct commissioning meetings at key intervals during construction.
July 2008 June 2009 Construction Manager (CM)
CM, A/E, Subcontractor and vendor.
Cost to implement is variable dependant upon scope of work and size of project, anywhere from $5K to $150K.
C) Modify relationship between HVAC sub and TC sub-sub. TC to be contracted directly with CM.
July 2008 June 2009 Construction Manager (CM)
HVAC, T & B subs, and the CA.
This may actually save money by eliminating the mark-up on the TC sub’s amount which is typically included in the HVAC sub’s scope of work.
DMAIC LITE STORYBOARD – IMPROVE – CHECKPOINT 10
Countermeasure Action Plans (Continued) COUNTERMEASURE
PROJECTED START DATE
PROJECTED END DATE
ACCOUNTABLE PERSON
SUPPORT ORGANIZATION ESTIMATED COST
D) Include T & B sub in commissioning meetings, explore alternatives for component testing.
July 2008 June 2009 Construction Manager (CM)
HVAC, TC Sub, Elec., T & B subs and the CA.
The cost of adding the T&B Sub to the meeting notice and agenda by CM Staff.
E) CM to monitor closely work of TC subcontractor and TC subcontractor schedule.
July 2008 June 2009 Construction Manager (CM) TC Sub The cost of CM staff to
monitor TC Sub work.
Longer than scheduled durations / delays in HVAC commissioning Date:
Implement procedures to include sub's in commissioning meetings Owners:
Meeting scheduling
1 2 3 4 5 6 7 8 9 10 11 12 Comments
Scheduled
Completed
Scheduled
Completed
Scheduled
Completed Until process complete
Facilities Construction KWP6 & KWP7 Project Closeout Activities Action Plan # 1
Root Cause:
Countermeasure:
Practical Method:
SBBC PM, CM, CA, sub's.
29-Jul-08
CM
CM / M, E, TC, T&B sub' /
Commissioning Agent / Owner
CM / M, E, TC, T&B sub' /
Commissioning Agent / Owner
CM to dessiminate information and coordinate sub' activities
CM to invite subcontractors and Owner to discuss plan
3
WeekNo. Task Accountable
Person
1
2
CM to determine meeting schedule and agenda based upon revised CPM schedule
Equipment delivery timing Date:
Include additional milestones and durations for purchase / submittal / approval / fabrication for long lead equipment Owners:
CPM Schedule
1 2 3 4 5 6 7 8 9 10 11 12 Comments
Scheduled
Completed
Scheduled
Completed
Scheduled
Completed Monitor through completion
3
WeekNo. Task Accountable
Person
1
2
Discuss overall schedule with CM / subcontractors and vendors
CM
Owner / CM / M, TC, E subs'
Review schedule and update as needed
Build schedule using input from overall schedule meeting
Facilities Construction KWP6 & KWP7 Project Closeout Activities Action Plan #2
Root Cause:
Countermeasure:
Practical Method:
SBBC PM / CM
29-Jul-08
CM / M, TC, E subs
Coordination issues between CM, HVAC and TC subcontractors Date:
Modify contractual relationship to allow closer communication between CM and TC sub. Owners:
Contract Agreement
1 2 3 4 5 6 7 8 9 10 11 12 Comments
Scheduled
Completed
Scheduled
Completed
Scheduled
Completed Continuous through completion
3
WeekNo. Task Accountable
Person
1
2
CM to negotiate with TC subcontractor directly. Input provided by A/E / Owner / M sub
CM / TC sub
CM / M, E, CA sub's / Owner
Include TC sub in direct communication with CM' activities and directives.
CM to enter into a contract directly with TC sub.
Facilities Construction KWP6 & KWP7 Project Closeout Activities Action Plan #3
Root Cause:
Countermeasure:
Practical Method:
CM / CM's subs / SBBC PM
29-Jul-08
CM / A/E / Owner / M sub / TC sub
MANAGE FACILITIESCONSTRUCTION
MANAGE FACILITIESDESIGN
D. Bonny
Process Improvement
Document TreeMacro
Process: Process Owner: Document Title:
MACRO DMAIC LITE STORYBOARD
MACRO PCS
MACRO FLOWCHART
MACRO PRIORITY PROCESSSELECTION MATRIX FORM
MACRO KEY IN-PROCESSMEASURES DETERMINATION
SYSTEMS FORM
MACRO DMAIC LITE STORYBOARD
MACRO PRIORITY PROCESSSELECTION MATRIX FORM
KWP6 & KWP7 PROJECTCLOSEOUT FLOW CHART
KWP6 & KWP7 ACTION PLAN(s)
KWP6 & KWP7COUNTERMEASURE
MATRICES
KWP6 & KWP7 INDICATOR DATA
KWP3 DMAIC LITE STORYBOARD
KWP5 DMAIC LITE STORYBOARD
KWP3 PRIORITY PROCESSSELECTION MATRIX FORM
KWP5 PRIORITY PROCESSSELECTION MATRIX FORM
KWP3 PER-CONSTRUCTION ACTIVITIES FLOW
CHART
KWP5 PERFORMSUBSTANTIAL COMPLETION
FLOW CHART
KWP3 ACTION PLAN(s) KWP5 ACTION PLAN(s)
KWP3COUNTERMEASURE
MATRIX
KWP5COUNTERMEASURE
MATRIX
KWP3 INDICATOR DATA KWP5 INDICATOR DATA
Note 1: May be required if flow chart has internal work processin addition to individual steps.
Note 1Note 1
Key Work Processes 1 - 7
1st DMAIC Lite Storyboard 2nd DMAIC Lite Storyboard 3rd DMAIC Lite Storyboard
Contract VS. Actual Completion Variance Analysis
-5.00%
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
Reporting Years
Varia
nce
Perc
enta
ge
Contract vs. Actual Completion Date Variance Target Baseline
Contract vs. Actual Completion DateVariance
26.54% 5.12% 2.54% 5.32% -2.40%
Target 0.00% 0.00% 0.00% 0.00% 0.00%
Baseline 7.43% 7.43% 7.43% 7.43% 7.43%
FY 03/04 FY 04/05 FY 05/06 FY 06/07 FY 07/08
Baseline = 7.43%
Target = 0.0%
Project Completion Variance (Days) Analysis
-30.00
-20.00
-10.00
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
Reporting Years
Sche
dule
Var
inac
e (D
ays)
Project Completion Variance (Days) Target Baseline
Project Completion Variance (Days) 65.33 12.75 11.60 22.25 -22.75
Target 0.00% 0.00% 0.00% 0.00% 0.00%
Baseline 17.84 17.84 17.84 17.84 17.84
FY 03/04 FY 04/05 FY 05/06 FY 06/07 FY 07/08
Target = Zero (0) Variance
Baseline = 17.84 Days
FY 03 / 04 Project Completion Variance Analysis
-100
-50
0
50
100
150
Number of Construction Projects
Sche
dule
Var
ianc
e (D
ays)
Variance Baseline Target
Variance 96 67 120 67 96 115 96 94 67 67 67 67 67 94 95 67 47 5 67 96 -25 67 34 -65
Baseline 65.3 65.3 65.3 65.3 65.3 65.3 65.3 65.3 65.3 65.3 65.3 65.3 65.3 65.3 65.3 65.3 65.3 65.3 65.3 65.3 65.3 65.3 65.3 65.3
Target 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Baseline = 65.3 Days
Target = Zero (0) Variance
FY 04 - 05 Project Completion Variance Anaylsis
-10
-5
0
5
10
15
20
25
Number of Construction Projects
Sche
dule
Var
ianc
e (D
ays)Variance Target Baseline
Variance 13 9 20 9
Target 0 0 0 0
Baseline 12.75 12.75 12.75 12.75
1 2 3 4
Baseline = 12.75 Days
Target = Zero (0) Variance
FY 05-06 Project Completion Variance Analysis
-10
-5
0
5
10
15
20
25
30
35
40
Number of Construction Projects
Sche
dule
Var
ianc
e (D
ays)Variance Target Baseline
Variance 1 6 19 0 0 0 16 5 34 35
Target 0 0 0 0 0 0 0 0 0 0
Baseline 11.6 11.6 11.6 11.6 11.6 11.6 11.6 11.6 11.6 11.6
1 2 3 4 5 6 7 8 9 10
Target = Zero (0) Variance
Baseline = 11.60 Days
FY 06-07 Project Completion Varinace Analysis
-40
-20
0
20
40
60
80
100
120
140
Number of Construction Projects
Sche
dule
Var
inac
e (D
ays)
Variance Target Baseline
Variance 121 -12 -20 0
Target 0 0 0 0
Baseline 22.25 22.25 22.25 22.25
1 2 3 4
Target = Zero (0) Variance
Baseline = 22.25 Days
FY 07-08 Project Completion Variance Analysis
-110
-90
-70
-50
-30
-10
10
30
Number of Construction Projects
Sche
dule
Var
inac
e (D
ays)Variance Target Baseline
Variance -90 9 9 -19
Target 0 0 0 0
Baseline -22.75 -22.75 -22.75 -22.75
1 2 3 4
Baseline = -22.75 Days
Target = Zero (0) Variance
EEZZ DDMMAAIICC 2200 CCHHEECCKKPPOOIINNTTSS DDEEFFIINNEE MMEEAASSUURREE AANNAALLYYZZEE IIMMPPRROOVVEE CCOONNTTRROOLL
PPllaann DDoo CChheecckk AAcctt
EZDMAICSM is a registered Service Mark of ets Inc. ~ Copyright 2009, ets Inc. Page 1
Macro Process Name: Manage Facilities Construction Key Work Process: KWP6 & 7 – Project Completion Closeout
Work System / Leader: Ed Curry Process Owner: DGT / DB DMAIC Status: Improve Cycle: Yes - 4/21/09 Refine Cycle: No
DEFINE
1. The stakeholder and need were identified. Yes: X No: Rating: 5 Comment: Internal and external customers were identified.
2. An indicator measuring our performance in meeting the need was developed. Yes: X No: Rating: 4
Comment: Q Measure Q1 was developed. Tracking has been partially implemented as many of the projects have achieved substantial completion. Minimal data exists from previous projects.
3. A theme statement consistent with the indicator was selected. Yes: X No: Rating: 5 Comment: Yes the theme statement is consistent with Q1 and In Process indicators.
Rating Legend:
5 = Checkpoint Fully Satisfied / 4 = Meets Most Criteria of Checkpoint / 3 = Meets Minimal Requirement of Checkpoint 2 = Checkpoint Somewhat/Partially Satisfied / 1 = Checkpoint Not Addressed
EEZZ DDMMAAIICC 2200 CCHHEECCKKPPOOIINNTTSS DDEEFFIINNEE MMEEAASSUURREE AANNAALLYYZZEE IIMMPPRROOVVEE CCOONNTTRROOLL
PPllaann DDoo CChheecckk AAcctt
EZDMAICSM is a registered Service Mark of ets Inc. ~ Copyright 2009, ets Inc. Page 2
MEASURE
4. The theme was stratified from various viewpoints and a significant problem was chosen. Yes: X No: Rating: 5
Comment: The theme statement developed resulting from a brainstorming session where Q 1 surfaced as a core problem.
Theme Statement: Actual Project Completion Date exceeds the Contractual Project Completion Date by a variance that ranges between minus 22.75 days to plus 65.33 days during fiscal years 04 - 08
5. A target for improvement was established based on the stakeholder's need and its impact on the theme indicator was determined. Yes: X No: Rating: 5
Comment: In the world of facility construction, bringing a project in on schedule is a great achievement. Taking this into consideration, the target for improvement has been established where the Contractual Project Completion Date equals the Actual Project Date. See attached charts.
6. A problem statement that addressed the gap between the actual and target values was developed. Yes: X No: Rating: 5
Comment: The gap was established by reviewing FY 03/04 through FY 07/08 facility construction data and project records.
Problem Statement: Closeout for projects scheduled for completion in 2007, were impacted by incomplete and / or improperly commissioned HVAC work which precluded the project’s final completion be achieved within the scheduled 90 day period after substantial completion. Gap: Four projects were completed in 2007 with a completion variance that ranged between minus (-) 20 days to plus (+) 121 days. That is a 141 day range. Final completion average gap for all projects is 22.25 days.
Rating Legend:
5 = Checkpoint Fully Satisfied / 4 = Meets Most Criteria of Checkpoint / 3 = Meets Minimal Requirement of Checkpoint 2 = Checkpoint Somewhat/Partially Satisfied / 1 = Checkpoint Not Addressed
EEZZ DDMMAAIICC 2200 CCHHEECCKKPPOOIINNTTSS DDEEFFIINNEE MMEEAASSUURREE AANNAALLYYZZEE IIMMPPRROOVVEE CCOONNTTRROOLL
PPllaann DDoo CChheecckk AAcctt
EZDMAICSM is a registered Service Mark of ets Inc. ~ Copyright 2009, ets Inc. Page 3
ANALYZE
7. Potential causes most likely to have the greatest impact on the problem were selected. Yes: X No: Rating: 5
Comment: Four potential causes were identified. Three were chosen as the most effective and countermeasures were developed.
Untimely delivery of HVAC equipment.
Longer than scheduled delays in HVAC commissioning.
Lack of coordination between CM / HVAC sub / TC sub-sub.
Test and Balance contractor start date slipped.
TC sub did not complete scope of work timely
8. A relationship between the root causes and the problem was verified with data. Yes: No: X Rating: -2
Comment: Not entirely as the causes from past projects were unavailable, and current projects have not cycled through. Data will be available to analyze when current projects are completed at the end of FY 08/09.
9. Root causes were selected and the impact of each root cause on the gap was determined. Yes: No: X Rating: - 2
Comment: Not entirely as the causes from past projects were unavailable, and current projects have not cycled through. Data will be available to analyze when current projects are completed at the end of FY 08/09.
Rating Legend:
5 = Checkpoint Fully Satisfied / 4 = Meets Most Criteria of Checkpoint / 3 = Meets Minimal Requirement of Checkpoint 2 = Checkpoint Somewhat/Partially Satisfied / 1 = Checkpoint Not Addressed
EEZZ DDMMAAIICC 2200 CCHHEECCKKPPOOIINNTTSS DDEEFFIINNEE MMEEAASSUURREE AANNAALLYYZZEE IIMMPPRROOVVEE CCOONNTTRROOLL
PPllaann DDoo CChheecckk AAcctt
EZDMAICSM is a registered Service Mark of ets Inc. ~ Copyright 2009, ets Inc. Page 4
IMPROVE
10. Countermeasures were selected to address verified root causes. Yes: X No: Rating: 4
1. Comment: Four countermeasures were selected based upon implementation. A) CM’s CPM schedule to include long lead equipment submittal / approval / fabrication and delivery dates with logic ties to related milestones.
B) Hire commissioning agent, conduct commissioning meetings at key intervals during construction.
C) Modify relationship between HVAC sub and TC sub-sub. TC to be contracted directly with CM.
D) Include T & B sub in commissioning meetings, explore alternatives for component testing.
E) CM to monitor closely work of TC subcontractor and TC subcontractor schedule.
11. The method for selecting the appropriate practical methods was clear and considered effectiveness and feasibility. Yes: X No: Rating: 4
Comment: Refer to countermeasure matrix and action plans for details.
Root Cause Effectiveness Feasibility Overall Action
A 5 4 20 Yes
B 5 4 20 Yes
C 5 5 25 Yes
D 5 5 25 Yes
E 5 5 25 Yes
IMPROVE
12. The action plan reflected accountability, schedule, and cost, and was implemented. Yes: X No: Rating: 5
Comment: All three action plans that were developed incorporated showing accountability, schedule and associated cost. See attached Countermeasure Action Plan Matrix.
Rating Legend:
5 = Checkpoint Fully Satisfied / 4 = Meets Most Criteria of Checkpoint / 3 = Meets Minimal Requirement of Checkpoint 2 = Checkpoint Somewhat/Partially Satisfied / 1 = Checkpoint Not Addressed
EEZZ DDMMAAIICC 2200 CCHHEECCKKPPOOIINNTTSS DDEEFFIINNEE MMEEAASSUURREE AANNAALLYYZZEE IIMMPPRROOVVEE CCOONNTTRROOLL
PPllaann DDoo CChheecckk AAcctt
EZDMAICSM is a registered Service Mark of ets Inc. ~ Copyright 2009, ets Inc. Page 5
CONTROL
13. [Results] The effect of countermeasure on the root causes was demonstrated. Yes: No: X Rating: 2
Comment: Due to project cycle constraints, this could not effectively be determined. Data will be available to analyze when current projects are completed at the end of FY 08/09.
14. [Results] The effect of countermeasures on the problem was demonstrated. Yes: No: X Rating: 2
Comment: Due to project cycle constraints, this could not be effectively determined. Data will be available to analyze when current projects are completed at the end of FY 08/09.
15. [Results] The improvement target was achieved and causes of significant variation were addressed. Yes: No: X Rating: 2
Comment: Due to project cycle constraints, this could not be effectively determined. Data will be available to analyze when current projects are completed at the end of FY 08/09.
16. [Results] The effect of countermeasures on the theme indicator representing the stakeholder’s need was demonstrated. Yes: X No: Rating: 4
Comment: Based upon the ability to address the need, and implementation of countermeasures and action plans, the stakeholders theme was addressed.
CONTROL
17. [Standardization] A method was established to document, permanently change, and communicate the revised process or standard, and was implemented. Yes: X No: Rating: 4
Comment: This is currently in progress and will become standardized through a series of Department Policy Directives.
18. [Standardization] Specific areas for replication were identified, and an action plan was developed to promote organizational learning. Yes: No: X Rating: 2
Comment: Not at this time. Pursuant to analysis upon full cycle, and with necessary modifications, standardization will be implemented.
19. [Future Plans] Any remaining problems of the theme were addressed. Yes: No: X Rating: 5
Comment: No remaining problems at this time.
Rating Legend:
5 = Checkpoint Fully Satisfied / 4 = Meets Most Criteria of Checkpoint / 3 = Meets Minimal Requirement of Checkpoint 2 = Checkpoint Somewhat/Partially Satisfied / 1 = Checkpoint Not Addressed
EEZZ DDMMAAIICC 2200 CCHHEECCKKPPOOIINNTTSS DDEEFFIINNEE MMEEAASSUURREE AANNAALLYYZZEE IIMMPPRROOVVEE CCOONNTTRROOLL
PPllaann DDoo CChheecckk AAcctt
EZDMAICSM is a registered Service Mark of ets Inc. ~ Copyright 2009, ets Inc. Page 6
CONTROL
20. [Future Plans] Lessons learned, P-D-C-A of the ets Six Sigma DMAIC Method, and team growth were assessed and documented. Yes: X No: Rating: 4
Comment: Future plans will include utilization of the DMAIC process when a potential problem is identified. This process along with lessons learned, brainstorming and other team activities related to process and quality improvement will be the focus for identifying and resolving future situations.
Rating Legend:
5 = Checkpoint Fully Satisfied / 4 = Meets Most Criteria of Checkpoint / 3 = Meets Minimal Requirement of Checkpoint 2 = Checkpoint Somewhat/Partially Satisfied / 1 = Checkpoint Not Addressed