machetanz elementary garrett burtner, mccool carlson green architects
TRANSCRIPT
Machetanz ElementaryGarrett Burtner, McCool Carlson Green Architects
Machetanz Elementary Garrett Burtner, McCool Carlson Green Architects
• Flex spaces• MPR Commons• Grades by Floor• Entry control• Passive supervision• Energy efficiency• Community-centered
21st Century Prototype
First Floor – Primary Grades
Second Floor – Intermediate Grades
Machetanz Elementary Garrett Burtner, McCool Carlson Green Architects
• Oriented for Solar Exposure• Compact Building Volume • Building Envelope Design• Daylighting and Reliting• Big Fan – Temp Inversion• Condensing Boilers• Advanced Lighting Controls• Building Automation• “Tuning” the Systems• 3rd Party Verification (LEED)
Machetanz Efficiency Story
Machetanz Elementary Garrett Burtner, McCool Carlson Green Architects
Site PlanNew residential development
Machetanz Elementary Garrett Burtner, McCool Carlson Green Architects
Light and Air
Machetanz Elementary Garrett Burtner, McCool Carlson Green Architects
Building Envelope
Machetanz Elementary Garrett Burtner, McCool Carlson Green Architects
Building Envelope
Machetanz Elementary Garrett Burtner, McCool Carlson Green Architects
• LEED Silver• 1st LEED School in AK• Projected 50% better than baseline • Performed 70% better than baseline• Valued by the community• Feels and smells good inside• My kids liked it• Award-winning educational planning• Will likely be repeated
Results
Machetanz Elementary Garrett Burtner, McCool Carlson Green Architects
• Projected vs. BaselineResults
Machetanz Elementary Garrett Burtner, McCool Carlson Green Architects
• Projected vs. ActualResults
2010 Actual Energy Used:Natural Gas = 34,625 ccf x $.81 = $28,038
Machetanz Natural Gas Usage
Machetanz Elementary Garrett Burtner, McCool Carlson Green Architects
• Projected vs. ActualResults
2010 Actual Energy Used:Natural Gas = 34,625 CCF x $1.04 = $36,010
Electricity = 331,040 KWH x $.14 = $46,345
Total Estimated Cost = $82,355
Projected Cost = $170,774
Baseline Model Cost = $313,981
Machetanz Electricity Usage
Machetanz Elementary Garrett Burtner, McCool Carlson Green Architects
• Architect – MCG• Owner – MSBSD• Ed Planner – Brain Spaces• Contractor – Collins• M/E Design – AMC• Structural/ Civil – PND• Interior – Spiral Design• LEED – MCG• Photos – Kevin Smith
A Team Effort