Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Page 2: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Transformational

Programmes and their

impact on the business

of Project Management

Stephen Wells RIBA

Director

Public Sector Programmes

Mace Group

Page 3: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Global presence

Page 4: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Services

Page 5: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Our values

Page 6: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Safety moment

4 Mace Information Handling Classification: Confidential

Page 7: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Client focus

Page 8: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

The Shard London, UK

Page 9: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Heathrow Terminal 5 London, UK

Page 10: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Queen Elizabeth Olympic Park London, UK

Page 11: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Mace

9 Mace Information Handling Classification: Confidential

Page 12: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1 Mace Information Handling Classification: Confidential

Programme

Management experience

Page 13: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Programme Management benefits

13 Mace Information Handling Classification: Confidential

Page 14: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Programme Management commissions

14 Mace Information Handling Classification: Confidential

Page 15: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Sector innovation - The Jump Factory

15 Mace Information Handling Classification: Confidential

Page 16: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Programme Management experience

16 Mace Information Handling Classification: Confidential

Page 17: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

The Olympic Games - the world’s biggest event

• 205 countries

• 5,000 Olympic Family

• 17,800 athletes & team officials

• 22,000 media

• 8 million tickets sold

The Paralympic Games - two weeks later

• 147 countries

• 1,000 Paralympic Family

• 4,000 athletes & team officials

• 4,000 media

• 2 million tickets sold

100,000 workforce including volunteers

4 billion global audience

Page 18: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Programme Summary

• 250 hectare Olympic Park (27.5 million square feet)

• Olympic Games: 26 sports in 34 venues with 10,500 athletes

• Paralympic Games: 20 sports in 21 venues with 4,200 athletes

• Budget £9.33 billion (US $14.35 billion); max monthly spend £150m (US

$230m)

• Started on site June 2006

• Handover for test events June 2011; 12 months before the Games

Page 19: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

CLM Delivery Partner

Supply Chain

Strategic Relationships for delivery: ODA and London 2012

Page 20: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Mace role as Delivery Partner

From October 2006 until December 2012 Mace were part of the CLM JV who

were contracted as Delivery Partner providing programme and project

management services:

• Cost

• Schedule

• Design Management

• Risk

• Project Controls

• Reporting

• Assurance

• Sustainability

Project Management Partner to the London Legacy Development Corporation

from January 2013 on-going

Page 21: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Blank

Page 22: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Blank

Page 23: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Olympic Park, April 2006

Page 24: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

2012

London 2012: Timeline of Olympic Park

Site preparation

Deconstruction / Transformation

2007

Legacy

Build infrastructure

2008 - 11

Build venues

2008 - 11

Test events

2011 - 12

2012-13 2013 - 2025

2012

London 2012 Olympic and Paralympic Games

Page 25: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

London 2012: Infrastructure

Demolition Soil remediation Bridges and highways

Primary substation Energy centre Sewer and pumping station

Page 26: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

London 2012: Venues

Page 27: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

• 1 programme

• 19 major projects

• 15,000+ site workers

• 950 planning applications

• 4,400 unique design interfaces

• 2 site entry points (plus rail head)

• 869 critical Tier 2 and 3 suppliers

• 1,890 engineering technical reviews

• 304 environmental monitoring points

• 135,000 formal documents controlled

• 120 NEC3 contracts, 149 JCT contracts

• 529 delivery vehicle movements each day

• 151 critical stakeholder delivery milestones

• 1,400 unique principal contractor boundaries

• 37,000 engineering drawings (and 35,000 revisions)

• 96 Tier 1 suppliers (29,000 contract communications)

• 79 Business Close Out Reports

• 27,000 activities and milestones in integrated plan

• 0.008 rolling Accident Frequency rate at completion

• 1 key date: 27 July 2012

529 vehicle movements

each day

London 2012 in numbers

1 Key date

Page 28: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

London 2012: the results

• £630m of unexpended Funders’ contingency returned through rigorous

contingency management

• £50m efficiency savings through enabling work projects

• £120m+ of value engineering savings on infrastructure projects

• £100m+ of procurement gains through flexible procurement strategies

• Other savings through robust contract administration

• Robust project controls system

• Programme delivery management system accredited to ISO9001

Page 29: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Olympics 2012 Transformation

2014 Legacy 2030

Legacy Transformation

Page 30: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Legacy Transformation 2014

30

Page 31: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Legacy Transformation 2017

31

Page 32: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Legacy Transformation 2017

32

Page 33: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1 Mace Information Handling Classification: Confidential

The benefits of our approach to

Integrated Programme Management

Page 34: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

The benefits of our approach

34 Mace Information Handling Classification: Confidential

Page 35: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Supporting the programme

Page 36: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Programme Management solutions

36 Mace Information Handling Classification: Confidential

Page 37: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Mace Innovation – Programme Management Delivery System

37 Mace Information Handling Classification: Confidential

Page 38: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

PDMS – Controls Framework

Page 39: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Baseline Report

• Developed from Brief or Business Case

• Basis of Performance monitoring

• Change Control

SCHEDULE SCOPE

BASELINE REPORT

RISK BUDGET &

COST

Page 40: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Reporting & Performance - Dashboards

MoJ data from

existing systems

(Viewpoint)

Tier 1 / Supply

Chain data

Internal PDMS

info feeds

Assurance

Validation

Assurance

Validation

Assurance

Validation

Page 41: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Reporting & Performance

Data Collection Time performance – Project milestones / interface milestones

Cost & progress performance – budget / change management, earned value

Quality performance by KPIs for design, BIM, HSQE, client & stakeholder targets

Risk Management

Data Analysis Focused dashboard reporting

Management Action Direct management attention

Informed decision making

Find and tackle issues early

Drive performance across all sites

Page 42: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

Continuous improvement

• Lessons Learnt Database allows all users to search a central knowledge base, enabling cost savings

and efficient delivery by learning from prior experience

• User forums can be implemented, allowing a network of colleagues in diverse locations to interact and

work collaboratively

42

Page 43: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

The benefits of our approach

43 Mace Information Handling Classification: Confidential

Page 44: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1

The benefits of our approach

44 Mace Information Handling Classification: Confidential

Page 45: Mace Information Handling Classification: …obudagroup.hu/wp-content/uploads/2016/08/01_wells... · 2012-07-27  · 2012 London 2012: Timeline of Olympic Park Site preparation Deconstruction

Mace Information Handling Classification: Unrestricted/Restricted/Confidential delete as appropriate in Slide Master 1