Aim
To achieve a greater
understanding and appreciation of
HMS Lancaster’s Pall Rochem
Reverse Osmosis Plants
Objectives
Understand basic Reverse Osmosis theory. Recognize plant components. Learn basic operations of the RO plant. Appreciate cleaning & maintenance
procedures.
Water Production Rates
27 25 23 21 19 17 15 13 11 9 7 5 30%
20%
40%
60%
80%
100%
120%
FM 161FM 161 162FM 161 162 163
Temperature °C
Per
form
ance
Pro
du
ctio
n %
Component - ControlsConductivityMeters2000µS & 50µS
VK121Sea Water / Tank
Cleaning Tank level
VK120Operating / Cleaning Mode
1. Pressure Permeate Line 0-10bar2. Feed Water into DT Modules 0-10bar3. Feed Water pressure into HP Pp 0-100bar4. Feed Water to Cartridge Filter 0-10bar5. Feed Water to Pump 0-10bar
1. Start2. Stop3. Cleaning4. Service5. Fault6. RO2
Flow Indicators(Small) Clean(Large) Made
Component - Controls
PLC
Control program is stored on a microchip called EEPROM.
The program is loaded in to the memory RAM.
The plant then receives I/O signals which change the throttle Vv and relays.
Component – LP Feed
1 • Filter Pump• Centrifugal Pump supplying 2.5 to 4.5bar
2• Bag Filter – 50µ Sediment Particles• RN Mod Filter Chamber - 10µ Sediment
Particles
3 • Cartridge Filter - 5µ Sediment Particles • (Maximum of 2.5bar)
Component – Modules
FM161 FM162
SEAWATER
DRINKING WATER (MADE) PERMEATE
OVERBOARD
Sea Temp 15°C (-10°C) 30% Production Lose
Component – Modules
FM161 FM162 FM163
SEAWATER
DRINKING WATER (MADE) PERMEATE
OVERBOARD
Sea Temp 8°C
Component – Modules
FM161 FM162 FM163 FM260
SEAWATER
DRINKING WATER (MADE) PERMEATE
OVERBOARD
DEMIN (CLEAN)
Starting Checks
1 • Check the system is correctly opened up from the Sea tube to the Aft BKD.
2 • Shut 3x Module Vv’s.
3 • Place VK120 in the operating position.• Place VK121 is in the Sea Water position.
Starting Checks
4• Ensure the plant dosing pump is switched
on.• Drain the cleaning tank VK111.
5 • Check that the LP Feed Vv (behind the cartridge filters) is open.
6 • Open the Discharge to Bilge until Conductivity is below 2000µS.
Rinse Routine
1 • Press Stop. Stop light will flash and cleaning tank level will rise.
2• Stop light will stop flashing. Place VK121
to Cleaning Tank. Place VK120 to Operating Mode.
3 • Press Start. When cleaning tank reaches zero plant will shut down.
Types of Cleaner & Inhibitor D
Cleaner A – Organic Sediment and Fouling - 4 Weekly
5L 5L 5L 5L
Cleaner C – Iron Fouling - 4 Monthly
2.5L
2.5L
2.5L
2.5L
2.5L
2.5L
2.5L
2.5L
Summary
Difference between Osmosis and Reverse Osmosis theory.
Plant components including controls, LP feed, HP pump, throttle Vv, module configuration, dosing.
Operations such as starting, stopping, faults and lamp tests.
Cleaners and inhibitors.