lwhite & czollingerrcc pavements - recent advances in the ...• drill & grout rebar into...
TRANSCRIPT
![Page 1: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/1.jpg)
- 1 -
Recent Advances in the Design & Construction of Roller Compacted
Concrete Pavements
![Page 2: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/2.jpg)
- 2 -
AGENDA
• Roller Compacted Concrete• What is it? Where has it Been Used? and Why?
• RCC Construction Process
• Recent Advances / Changes
![Page 3: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/3.jpg)
- 3 -
ROLLER COMPACTED CONCRETE IS A ZERO SLUMP CONCRETE
With A Long History Of Good Performance On Heavy Duty Pavements
• Concrete Pavement, Placed more efficiently• No Slump, low water content• Consistency of cement treated base• Placed by asphalt pavers• Compacted with vibratory rollers• No forms• No reinforcing steel • No finishing• Normal concrete strength• Low W/C ratio = limited shrinkage cracks
Roller Compacted Concrete
Pavements
• Intermodal Port/ Freight/ Manufacturing• Ports of Houston, Long Beach, LA, Jacksonville• Central Freight – Austin, TX• Honda, Kia, BMW, Saturn – GA, TN, SC• Jack Daniel’s– Lynchburg, TN• Proctor & Gamble - PA• Lowe’s– Rome, GA• Kansas City Southern, CSX, Norfolk Southern
Historical RCC Uses
Port of Houston – 2008
![Page 4: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/4.jpg)
- 4 -
• Owner: Lowe’s• Use Type: Distribution Center• Year Built: 2012• Size: 69 Acres• Volume: 65,000 CY
Project Information
• Thickness: 7” RCC / 6” Aggregate Base• Traffic: 400 Trucks / day• Paved 30 ft wide, 150 to 180 CY/ hour• RCC paving completed in 2 months, 11
days (Calendar)• Saved $3.5 M versus asphalt with concrete
dolly strips
Additional Details
PORTS, INTERMODALS & DISTRIBUTION CENTERS ARE USING RCC FOR DURABILITY, SPEED OF CONSTRUCTION, & COST SAVINGS
![Page 5: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/5.jpg)
- 5 -
Lowe’s Distribution CenterRome, GA
![Page 6: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/6.jpg)
- 6 -
USE OF RCC PAVEMENTS IN USRCC utilization began growing in early 2000’s & is now growing at a faster rate
1975 - 1999 2000-2010 2011-2013# of Projects 71 99 172
SY 2,999,771 8,933,250 4,993,296
![Page 7: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/7.jpg)
PAVEMENT TYPES & OWNERS ARE CHANGINGIndustrial Still Remains Largest Application Type, But Roadway are Increasing
5
12
7
27
9
24
13
2
16
5
29
57
11
Commercial Industrial Intermodal Port Roadway
# of Projects
Application Type
2011
2012
2013
34
17
48
15
42
15
Private Public
# of Projects
Owner Type
2011
2012
2013
![Page 8: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/8.jpg)
- 8 -
EAST WETLANDS HIKE TRAILYuma, AZ
• Owner: City of Yuma• Use Type: Trail• Year Built: 2013• Thickness: 5” RCC / Compacted
Subgrade• Quantity: 1,700 CY
Pavement Design
Information
• City Park, environmentally sensitive area
• Did not want Asphalt due to hydrocarbons
• Lacked funds for conventional concrete
• RCC made it feasible
Additional Details
![Page 9: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/9.jpg)
- 9 -
LAMESA DRIVEMIDLAND, TX
![Page 10: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/10.jpg)
- 10 -
OVER THE PAST 10 YEARS, DOT’S HAVE PAVED SHOULDERS & SURFACE ROADS USING RCC
I-85 Interchange – Lagrange, GA SR 6 – Powder Springs, GA
US 78 – Aiken, SC
I 285 – Atlanta, GA
I 385 - Greenville, SC I 75 – Tift, GA
South Carolina DOT ProjectsUS 21 Greystone
BlvdUS 25 SC 5
New StateRoad
S. BeltlineBlvd
SC 9
![Page 11: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/11.jpg)
- 11 -
I-285 SHOULDER REPLACEMENTAtlanta, GA
•35 Lane Miles of 10’ Shoulder•38500 CY of material placed•Material placed on weekends only
![Page 12: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/12.jpg)
- 12 -
![Page 13: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/13.jpg)
- 13 -
ADDITIONAL PROJECTS COMPLETED BY GDOT
![Page 14: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/14.jpg)
- 14 -
ADDITIONAL PROJECTS COMPLETED BY GDOT
![Page 15: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/15.jpg)
- 15 -
• Owner: South Carolina DOT• Use Type: US Highway • Year Built: 2009• Thickness: Milled 10” asphalt
Placed 10” RCC• Traffic: 6000 ADT, 4 lanes• Speed: 45 mph
Pavement Design
Information
• Replaced 27,500 SY in 15 days• Placed 10” RCC in 1 lift• All milled areas were paved within same
day• Maintained 1 lane open in each direction
• Transverse Joints : 20 ft, early entry saw cut within 3 hours
• Traffic re-opened within 24 hours
Additional Details
Richland Ave (US 78)Aiken, SC - 2009
![Page 16: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/16.jpg)
- 16 -
RICHLAND AV. (US 78) AIKEN, SCCompleted Project
![Page 17: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/17.jpg)
- 17 -
AGENDA
• Roller Compacted Concrete• What is it? Where has it Been Used? and Why?
• RCC Construction Process
• Recent Advances
![Page 18: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/18.jpg)
- 18 -
THE FINAL SURFACE TYPE WILL DICTATE THE NECESSARY TECHNIQUES & EQUIPMENT NEEDED TO BE SUCCESSFUL
Natural RCC Diamond Ground RCC Asphalt
• Speed Limit < 35 mph• Ports• Distribution centers• Industrial yards• Residential roads• Parking lots
• Speed Limit > 35 mph• Collector / Arterial local roads• Highway Shoulders• State routes
• Any pavement type
• Lowest Cost• Most sensitive to contractor
skill level• Least smooth• “Asphalt” appearance
• Medium cost increase• Increased construction time• Improved smoothness, skid
resistance• Reduced noise
• Highest cost• Increased construction time• Least sensitive to contractor
skill level• Improved smoothness, skid
resistance
App
licat
ions
Fact
ors
![Page 19: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/19.jpg)
- 19 -
THE FINAL SURFACE TYPE DICTATES THE NECESSARY TECHNIQUES & EQUIPMENT NEEDED TO BE SUCCESSFUL
Natural RCC Diamond Ground RCC Asphalt
![Page 20: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/20.jpg)
- 20 -
THE SURFACE APPEARANCE AND TEXTURE OF RCC IS SIMILAR TO ASPHALT PAVEMENT
HMARCCPCC
• Similar appearance & texture as asphalt only light grey instead of black
• Surface texture depends on aggregate gradation and paste content
• Diamond ground RCC is similar to diamond ground concrete
• Trowelled RCC similar appearance as conventional concrete
Diamond Ground RCCDiamond Ground Conventional Concrete
![Page 21: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/21.jpg)
- 21 -
RCC MIX DESIGN USES SAME MATERIALS AS CONVENTIONAL CONCRETE, HOWEVER IN DIFFERENT COMBINATIONS
Achieves Similar or Better Engineering Properties Than Conventional Concrete
Typical Engineering Properties
Conventional (psi)
RCC(psi)
Compressive Strength 3,000 - 5,000 4,000 -10,000
Flexural Strength (MOR)
500 – 700 500 - 1,000
Elastic Modulus 3.0 – 5.0 million
3.0 – 5.5 million
15
47
30
712
36
46
3
0
10
20
30
40
50
60
Cement + FA Coarse Agg Fine Agg Water
% T
otal
Wei
ght
Typical Mix Design
Roller Compacted Concrete
Conventional Concrete
Conventional Concrete RCC
![Page 22: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/22.jpg)
- 22 -
22
MIXTURE DESIGN PROCEDUREStep 1: Chose well – graded aggregates
• Most important aspect of mix design (85% of mixture)• Selection based on gradation test results of available aggregates• Quantity of aggregate sources depends on # of aggregate bins at production plant• Impacts stability, workability, compactibility, segregation potential, and strength plus everything else• Need to achieve a balance of angularity and surface appearance
• Rounded aggregates increase workability but reduce stability• Typically prefer crushed coarse aggregate and natural sand
• Maximum top size is ¾”, recently began using as small as ½”
![Page 23: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/23.jpg)
- 23 -
23
MIXTURE DESIGN EXAMPLE
Step 2: Evaluate Combined Gradation
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
100.0
Perc
ent P
assi
ng (%
)
Sieve Size
RCC
Spec Upper Limit
Spec Lower Limit
1/2 in Power 45
3/4 in Power 45
1 in Power 45
3/4"1/2"3/8"# 4#16#100#200 1"
![Page 24: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/24.jpg)
- 24 -
24
MIXTURE DESIGN PROCEDURE
Step 3: Develop moisture – density relationship plots• Minimum 450 lbs cement / CY• 12% Type I Portland cement is selected for the
first trial batch• Based % on weight, so make enough and do
not worry about volumes yet• Mix the cement dry, and then add water
(ASTM D1557)
• Perform a modified Proctor test at the selected cement content
• Construct moisture-density relationship curve (Use spreadsheet)
• Determine Maximum Dry Density (MDD) and Optimum Moisture Content (OMC)
Opt
imum
Moi
stur
e
Maximum Dry Density
![Page 25: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/25.jpg)
- 25 -
MIXTURE DESIGN EXAMPLE
Develop Mix Volumetrics
145.0152.85.4%
11.5%11.5%0.0%
205525
Batch Size (CF) 27
Batch Weight (lbs/CY)
Bulk Specific Gravity (OD)
Absolute Volume (CF)
450 3.150 2.2890 2.350 0.000
693 2.650 4.1911906 2.630 11.612866 2.620 5.299211 1.000 3.388
Soil Mechanics
Mix Quantities
Target Aggregate #3 %
Target Coarse Aggregate %Target Fine Aggregate%
% Fly Ash (of cement replace)
% Cementitious
Total Water content (lbs)
Fine AggregateIntermediate Aggregate
Coarse Aggregate
CementFly Ash
Max Wet Density (lbs/CF)Optimum % Moisture
Ingredient
% Cement
Max Dry Density (lbs/CF)Mix Weight Per CY
Water Weight = (152.8-145.0) x 27
Total Dry Materials = 145.0 x 271. Select Cement content2. CA = (Total Dry-cement) x % Target
![Page 26: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/26.jpg)
- 26 -
26
MIXTURE DESIGN PROCEDUREStep 4: Cast samples to measure compressive strength
(ASTM C 1435)• Calculate trial mix proportions• Batch RCC materials
– Maintain percent Optimum Moisture Content as determined in step 3
– Use varying cementitious contents such as 10, 12 and 14 percent
• Make compressive strength test cylinders for each cement content
![Page 27: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/27.jpg)
- 27 -
27
Intended Goals of the Research• Increase haul time while maintaining workability• Retain moisture• Improve surface finish• Increase compressive strength• Increase density behind paver• Currently using Grace VSC500 @ 3 cwt
ADMIXTURES ARE BEING USED TO IMPROVE WORKABILITY AND INCREASE HAUL TIME
![Page 28: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/28.jpg)
- 28 -
Factors to Consider• High production rates: 50 to 300+CY / hr• Excellent mixing efficiency for dry materials• Highly consistent mix properties, • Mobile – 1 load, 1 Day Set up and calibration• Need to find good location, obtain permits• Self contained – Gen set, batch house• 2 man operation• # of Aggregates depends on Feeder system
WE RECOMMEND USING A PUGMILL MIXER DUE TO HIGH PRODUCTION RATES & EFFICIENT MIXING PROCESS
![Page 29: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/29.jpg)
- 29 -
![Page 30: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/30.jpg)
- 30 -
RCC IS PLACED WITH HIGH DENSITY ASPHALT PAVERSAchieving Density & Smoothness is Critical
• High density screed (Vogele or ABG Titan)• High initial density from paver (90% - 96%)• Smoother surface due to higher initial density• Less “roll down” to achieve final density• High-production (6 to 8 ft/min)• 10 to 30 ft width• Lift thick range: 4” to 9”
High Density Paver
![Page 31: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/31.jpg)
- 31 -
![Page 32: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/32.jpg)
- 32 -
ROLLERS ARE USED TO ACHIEVE DENSITY AND PROVIDE FINISH
• Initial: 10 - 12 ton static & vibratory roller• Establish roll pattern (check density a lot!)• Adjust roll pattern based on moisture content • Compact to 98% density - wet• Adjust moisture content if needed – impacts
smoothness & compaction• Finer mixes achieve density easier
• Combination, dual steel or rubber tired • Maximum weight - 6 short ton
• Remove roller marks• Once completed, keep roller off of the area
Initial Compaction Finish Rolling
Fairforest WayGreenville, SCGrape Creek Road – San Angelo, TX
Fairforest WayGreenville, SC
![Page 33: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/33.jpg)
- 33 -
• Need high density paver• Attach shoe to screed• Maximum angle 15o
• Use plate tamper to improve edge durability
• No saw cutting required• Pave adjacent lane next day• Lowest cost
• Pave for 50 minutes then move back to beginning and match original lane
• Do not compact original lane within 2 ft of edge until adjacent lane is paved
• Recommend a longitudinal saw cut• Use small loader to create fresh vertical
transverse joint• Move quickly – keep moist!• Coordination is key, avoid breakdowns
Angular Cold Joint Fresh (Hot) Joints
• Pave width of lane• Saw cut full depth early next
morning • Remove with blade & loader • Expect waste
• Reduce waste with paver shoe & plate tamper
• Pave adjacent lane and match thickness of existing lane
• Good performance, limited load transfer
Vertical Cold Joint
LONGITUDINAL JOINTS CAN BE BUILT 3 DIFFERENT WAYS
2 ft
![Page 34: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/34.jpg)
- 34 -
MANHOLES & CURBS ARE EASILY INCORPORATED INTO STREETS
• Traditional curb & gutter placed before RCC• Serves as compaction aid• Joint may need to be sealed
• Alternatively, ribbon curb can be placed• Drill & grout rebar into cold RCC• Place ribbon curb afterwards
• Plywood plate is placed on top of hole before RCC is placed
• After paving, two methods are available:• Dig RCC immediately while fresh, place
manhole and re - compact material with hand tampers
• Saw cut hardened RCC, place manhole, tie in with conventional concrete
Curb & Gutter Manholes, Inlets
![Page 35: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/35.jpg)
- 35 -
QC / QA PROCESS INCLUDES TESTING FOR DENSITY, MOISTURE CONTENT & COMPRESSIVE STRENGTH
• Tested with nuclear gage in direct mode • Test density behind paver & after roller to
establish rolling patterns to achieve density• Achieve 98% of modified proctor wet density• Nuclear gage gives general moisture
fluctuation indication - Calibrate with oven dried moisture
• Oven dried is most accurate
• Cylinders prepared with vibratory hammer according to ASTM C1435
• 3 to 4 cylinders per set• Strength timing often depends on traffic
opening (1, 3, 7, 28 days)• Cores can be obtained where density is not
being achieved
Compressive StrengthMoisture & Density
![Page 36: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/36.jpg)
- 36 -
WHEN CURED & SAW CUT RCC PERFORMANCE IMPROVES
• Applied at same rate or slightly higher than conventional concrete
• Ensure uniformity with application process• Apply as soon as possible behind roller
operation• Recommend WR Meadows 1200 to 1600• Ensures durable surface
Curing Saw Cut & Fill Joints• More aesthetically pleasing• Early entry saw very effective, shortly
following placement• Recommend sawing within 2 - 6 hours to
avoid uncontrolled cracking• Depth: 1” to 2” • Spacing: Maximum 36 times thickness
![Page 37: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/37.jpg)
- 37 -
SOME FACTORS TO CONSIDER WHEN BIDDING PROJECTS
• Volume of RCC paving on the project• Site geometry• Project phasing• Pavement thickness • Pavement width• Final surface characteristics• Traffic control• Opening to traffic• Daily working schedule
![Page 38: LWhite & CZollingerRCC Pavements - Recent Advances in the ...• Drill & grout rebar into cold RCC • Place ribbon curb afterwards • Plywood plate is placed on top of hole before](https://reader035.vdocuments.us/reader035/viewer/2022071403/60f702315ae269541d03d9ff/html5/thumbnails/38.jpg)
- 38 -
Questions?
Leslie White, P.E.
678-388-5807
Corey J. Zollinger, P.E.
713-722-6084