ltr-nrc-17-23 np-attachment - supporting information for ...ltr-nrc-17-23 np-attachment - supporting...
TRANSCRIPT
-
Westinghouse Non-Proprietary Class 3
L TR-NRC-17-23 NP-Attachment
Supporting Information for the NRC Audit of the D5 CPR Correlation (Non-Proprietary)
March 2017
Westinghouse Electric Company 1000 Westinghouse Drive
Cranberry Township, PA 16066
© 20 17 Westinghouse Electric Company LLC All Rights Reserved
-
@Westinghouse 1
-
,.....-------------------- - ----
• Introduction
• Purpose and Desired Outcome
• Day 1 - RAI 36
• Day 2 - RAI 36 I Other RAI Discussions
• Day 3 - RAI 36 I Other RAI Discussions
• Summary and Closeout
@Westinghouse 2
-
• Meeting Location and Emergency Response protocol - Building exits and muster point
• March Nuclear Safety Culture Trait at Westinghouse:
Decision Making
Attributes: • DM.1 Consistent Processes
• DM.2 Conservative Bias
• DM.3 Accountability for Decisions
@Westinghouse 3
-
Audit Participants
- Westinghouse : • Uffe Bergmann • Juan Casal • Patricia Quaglia • Jean-Marie Le Corre (by phone) • Gunilla Norback (by phone) • Ed Mercier • Brad Maurer
- NRC: • Joshua Kaizer • Reed Anzalone • Josh Whitman • John Lehning • Kate Lenning
@Westinghouse 4
-
• Purpose of the Audit - Discuss the outstanding RAls related to the review of
WCAP-17794-P (05 CPR Correlation)
• Desired Outcome - Reach a common understanding regarding responses to
the RAls which will enable completion of a successful review for the topical report going forward
@Westinghouse 5
-
@Westinghouse 6
-
• Requests for Additional Information (35) - Responses submitted August 2016 - Additional RAls:
• RAI 36 - November 2016 • RAI 37 - with Audit Plan
• Resolutions - RA Is resolved ( 21 ) - 1 , 2, 5, 8, 1 0, 11 , 12, 1 3, 14, 1 5, 1 6, 1 9,
21, 23, 24,26,27, 30, 31, 32, and 35
• To Be Addressed in the Audit - Require further discussion (7) - 7, 9, 20, 22, 25, 33, and 34 - Supporting Information provided to aid discussion (9) - 3, 4,
6, 17, 18, 28, 29, and 36, 37
@Westinghouse 7
-
L
• CPR Critical Power Ratio
• FRIGG Thermal-Hydraulic Test Loop at the Westinghouse Facilities in Vasteras, Sweden
• SLMCPR Safety Limit Minimum Critical Power Ratio
• TC Thermocouple
@Westinghouse 8
-
Westinghouse Non-Proprietary Class 3
RAls 3, 28, 37 © 2017 Westinghouse Electric Company LLC. All Rights Reserved
L TR-NRC-17-23 NP-Attachment
Data statistics supporting RAI 3 • •
@Westinghouse 9
-
@Westinghouse 10
-
Westinghouse Non-Proprietary Class 3
RAls 3, 28, 37 © 2017 Westinghouse Electric Company LLC. All Rights Reserved
L TR-NRC-17-23 NP-Attachment
- Data statistics supporting RAI 37 - . ~ ~
a,b,c
@Westinghouse 11
-
@Westinghouse 12
-
Westinghouse Non-Proprietary Class 3
RAls 3, 28, 37 Summary and Discussion
@Westinghouse 13
© 2017 Westinghouse Electric Company LLC. All Rights Reserved
L TR-NRC-17-23 NP-Attachment
-
@Westinghouse 14
-
• Frequency of TCs registering dryout at Spacer 2, coincident with TCs at other elevations, is[ ]'d~ring the cosine test
• Repeated data points at[
Jae radial power distribution are shown below (same as discussed in
previous RAI answer, but now labelled according to TC elevation) - No trend observed in CPR error for dryout registered by TCs at Spacer 2
a,b,c
@Westinghouse 15
-
• Repeat tests were performed at[ r·c subcooling, and at specific flow levels. The radial power distribution was as close to[
Ja,c • In principle the repeat points are taken at the same
conditions, but to account for any small deviations, a comparison of CPR is more appropriate than comparing the measured critical powers directly
[ ]a,c
• Hence, the derived standard deviation of is indeed representative of (only) the measurement uncertainty (since nearly identical input conditions were used in the CPR correlation)
@Westinghouse 16
-
• Heat losses were experimentally determined after the latest upgrade of the FRIGG loop, and have since then been applied generically in later tests.
= [ r·c • The heat losses are applied directly to the measured critical power, thus
reducing it by[ Ja,c a,c • As part of FRIGG procedures a heat balance test is
performed before each test campaign to verify applicability of the above values Ja,c - Conditions: [ different
powers - Example test matrix applied before the cosine test is
shown on right. It covers changes in outlet temperature of( Ja,c @Westinghouse
17
-
@Westinghouse 18