lsm new
Post on 17-Jan-2016
214 views
DESCRIPTION
line of balaneTRANSCRIPT
![Page 1: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/1.jpg)
LINEAR SCHEDULING METHOD
LINE OF BALANCE
Nabil Dmaidi 1
![Page 2: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/2.jpg)
Line of Balance
Nabil Dmaidi 2
Line of balance is a method of showing repetitive work that may exist in a project program as a single line on the graph rather than a series of individual activities on a bar chart .
line of balance chart can be used for any project where there a number of separate but common activities to undertake or an activity with long duration . They are not well suited to individual activities that have a shorten duration that are undertaken
![Page 3: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/3.jpg)
Nabil Dmaidi 3
![Page 4: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/4.jpg)
Nabil Dmaidi 4
![Page 5: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/5.jpg)
Nabil Dmaidi 5
As can be seen the difference between the two methods is a line of balance chart can be summarize a group of similar activities onto one line and consequently a large number of common activities onto a much smaller document .
Unlike the bar chart which shows the duration of a particular activity , a line of balance chart shows the rate at which the work that makes up all the activities
![Page 6: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/6.jpg)
Nabil Dmaidi 6
The line of balance does not show direct relationship between individual activities ; it shows an output relationship in different operations in that one Must be completed at a particular rate for the subsequent relationship to proceed at the required rate operation .
![Page 7: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/7.jpg)
Nabil Dmaidi 7
Line of balance where used Many types of projects contain repeated blocks of
activities. Examples of these kinds of projects include road and high-rise construction.
In both of these types of projects there is a set of tasks repeated across many work areas.
![Page 8: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/8.jpg)
Nabil Dmaidi 8
The Line-of-Balance (also known as the Vertical Production Method) is a graphical technique that can be used in conjunction with Arrow or Precedence Diagrams
2EXC FNDSBLDG 2
7F&P FNDS& SLABBLDG 2
8FRAMEBLDG 2
2EXC FNDSBLDG 3
7F&P FNDS& SLABBLDG 3
8FRAMEBLDG 3
2EXC FNDSBLDG 4
7F&P FNDS& SLABBLDG 4
![Page 9: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/9.jpg)
Nabil Dmaidi 9
In the Line-of-Balance diagram, the x-axis represents (as in the bar chart) the timeline of the project. The y-axis identifies the work areas that define the project. The blank chart below is the starting point for the Line-of-Balance schedule.
![Page 10: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/10.jpg)
Nabil Dmaidi 10
As crews arrive on the project, they begin at the first work area and move through the project. In the figure below, Activity A has a total duration of 10 weeks. Spread across each of the work areas the productivity of Activity A can be shown to be 2 weeks per floor.
![Page 11: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/11.jpg)
Now consider the implication of an Activity B that has a productivity of one week per floor. If we try to start Activity B as soon as possible, then the start of activity B on the first floor can occur at the end of week 2.
![Page 12: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/12.jpg)
Nabil Dmaidi 12
As we continue to add Activity B throughout the remaining work areas we can see that Activity B starts on the second floor, at the end of week 4; on the third floor, at the end of week 6 and so on; as shown in the diagram below.As you look at this chart, what do you think the red dashed lines mean?
![Page 13: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/13.jpg)
The diagram below shows that you should delay starting Activity B for four weeks. If you do that, then you will keep the crew productive for their entire stay on your project. If you were running a real project, you might include a bit extra time in case things backup, but you would likely not start Activity B as soon as it could start!
The breaks in the Activity B line, shown as red dashed lines above, are significant. This gap means that the crew is waiting around for Activity A to clear out before it can start. In the case of the project above, starting work as soon as you can will result in a lost productivity of 4 crew weeks.
![Page 14: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/14.jpg)
![Page 15: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/15.jpg)
LINEAR SCHEDULING METHOD
![Page 16: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/16.jpg)
Linear Scheduling MethodLinear Scheduling Method
Definition:Is a graphical scheduling method focusing on continuous resource utilization in repetitive activities .(simple diagram to show location and time at which a certain crew will be working on a given operation. It is believed that it originally adopted the idea of Line-Of-Balance method.
Nabil Dmaidi 16
![Page 17: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/17.jpg)
Application LSM is used mainly in the construction industry to schedule
resources in repetitive activities commonly found in highways, pipelines, high-rise building and rail construction projects (Linear projects).
![Page 18: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/18.jpg)
Characteristics Shows repetitive nature of the construction. Progression of work can be seen easily. Sequence of different work activities can be easily
understood . Have fairly high level of detail. Can be developed and prepared in a shorter time
period than other formats.
Nabil Dmaidi 18
![Page 19: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/19.jpg)
Advantages of LSM
Provides more information concerning the planned method of const. than a bar chart.
In certain types of projects, LSM offers some advantages over the network approach.
The main advantages of LSM over Critical Path Method is its underlying idea of keeping resources continuously at work . In other words , it schedules activities in such a way that :
1-resource utilization is maximized 2-interruption in on-going process is minimized
![Page 20: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/20.jpg)
These benefits are achieved in LSM by scheduling the start date of an activity at the date which will provide a continuous work flow for the resource. In contrast to CPM, this date is not necessarily the earliest possible start date of an activity.
Graphical presentation of LSM is also another advantage over the Critical Path Method when a project consists of repetitive activities.
![Page 21: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/21.jpg)
Three diagrams are in LOB:1. Production Diagram
Shows the relationships of the assembly operations for a single unit. Similar to AOA, except that it shows only one unit of production.
2. Objective DiagramUsed to plot the planned or actual number of units produced vs. time. LSM diagram resembles this diagram.
3. Progress DiagramShows the number of units for which each of the subassembly operations has been completed.
Nabil Dmaidi 21
![Page 22: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/22.jpg)
Difference between Objective Diagram and LSM : O.D. is used to schedule or record the cumulative events of
unit completion.
LSM is used to plan or record progress on multiple activities that are moving continuously in sequence along the length of a single project.
Nabil Dmaidi 22
![Page 23: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/23.jpg)
Implementation of LSM
Can be used for continuous activities rather than discrete activities.
Transportation projects; highway const., highway resurfacing and maintenance, airport runway const. and resurfacing, tunnels, mass transit systems, pipelines, railroads.
High-rise building construction Repetitive building units
Nabil Dmaidi 23
![Page 24: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/24.jpg)
Activity Production Rates Obtained by the usual estimating methods as a
function of the activity, equip. characteristics, labor, and job conditions.
The initial rate should be associated with the min. direct cost of accomplishing the single activity.
Nabil Dmaidi 24
![Page 25: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/25.jpg)
Buffers
When const. activities progress continuously in a chain, some spacing between activities is required.
This spacing serves as a buffer and may require distance or time interval between activities.
Nabil Dmaidi 25
![Page 26: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/26.jpg)
Activity Intervals Used to describe the period of time between the start and
finish of an activity at a particular location. Intervals can be indicated by a broad line, two narrow
lines, etc. Monitoring Progress Working calendar can be marked with a moving symbol or
a line, tape, etc. vertically across the diagram. Progress on individual activities would be marked by
location rather than time.
Nabil Dmaidi 26
![Page 27: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/27.jpg)
1. Project Time Optimization The total project time may be such that indirect costs and
liquidated damages assessed are more costly than the expense of accelerating certain activities.
Cost-duration analysis can be used to minimize the total cost, as follows :
a) Identify all activities that can be accelerated or decelerated.
b) Among the above, consider only those that are at a buffer
limitation at both the start and the finish of the activity.
Nabil Dmaidi 27
![Page 28: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/28.jpg)
Nabil Dmaidi 28
c) Of these, select the one activity with the lowest cost slope
associated with acceleration (or deceleration).
d) Accelerate (or deceleration) the activity rate of production
the maximum feasible amount.
e) Repeat the above steps successively until the optimum
project cost and associated duration are obtained.
![Page 29: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/29.jpg)
Nabil Dmaidi 29
2. Discrete ActivitiesDiscrete are best scheduled by other methods. Once the duration is determined by network analysis, it can be scheduled on the LSM diagram and coordinated with the linear activities.
3. Seasonal AdjustmentsWhen developing LSM, appropriate adjustments can be made for seasonal effect on construction progress.
![Page 30: LSM new](https://reader036.vdocuments.us/reader036/viewer/2022081516/55cf917d550346f57b8dda49/html5/thumbnails/30.jpg)
Project progress is often estimated by the S-curve with bar chart development.
In LSM, the determination of activity progress is facilitated and made more rigorous.
Nabil Dmaidi 30
4. Project Progress and Resource Management