    DATA SHEET

    Construction of Pump House for the LPDS (3mx3m)

    District :Erode Village : Thoddampalayam

    Taluk :Sathyamangalam

    Rate Amount

    Rs Ps Rs. Ps

    1 2 3 4 5 6

    1 1m3

    Earthwork excavating and depositing

    on bank within initial lead of 10 M.& initial lift of 2M.

    In hard stiff clay,stiff black cotton, hard red earth, shales,

    murram, gravel, stoneyearth, and earth mixed with

    small size boulders as per S.S.20.B.and S.I.62. 57.50 1m3

    57.50

    for foundation

    2 1m3

    supplying and filling the basement with filling sand

    in layers of not more than 15cm thick as well ramped

    consolidated..etc 633.50 1m3

    633.50

    3 1m3

    Filling charges 9.00 1m3

    9.00

    642.50

    SUB DATA

    CEMENT MORTAR 1:4 FOR 1Cu.m.

    360.0 Kg. Cement 4400.00 1 M.T 1584.00

    1m3

    Sand 633.50 1m3

    633.50

    1m3

    Mixing charges 29.70 1m3

    29.70

    2247.20

    Rate For 1 Cu.M. = Rs. 2247.20

    CEMENT MORTAR 1:5 FOR 1Cu.m.

    288.0 Kg. Cement 4400.00 1 M.T 1267.20

    1.0 Cu.M Sand 633.50 1 Cu.M 633.50

    1.0 Cu.M 29.70 1 Cu.M 29.70

    1930.40

    Rate For 1 Cu.M. = Rs. 1930.40

    MAIN DATA

    4 Cost of cement concrete 1:5:10 using 40 m.m.

    size H.B.Stones For 10 Cu.M.

    9.0 Cu.M H.B.Stones 40 m.m. size 594.50 1 Cu.M 5350.50

    4.5 Cu.M Cement mortar 1:5 1930.40 1 Cu.M 8686.801.8 Nos. Mason II class 162.00 1 No. 291.60

    17.7 Nos. Muzdoor class I 112.00 1 No. 1982.40

    14.1 Nos. Muzdoor class II 101.00 1 No. 1424.10

    17735.40

    Rate For 1 Cu.M. = Rs. 1773.54 1301.64

    1

    1 2 3 4 5 6

    Sl.No. Quantity Description of item Unit

  • 7/28/2019 Lps Estimte & Rcc Room

    2/39

    5 Random rubblemasonry in C.M.1:5 for 10 Cu.M

    10.0 Cu.m Random rubble stone for masonry work 296.00 1 Cu.M 2960.00

    1.0 Cu.M Bond stone 394.50 1 Cu.M 394.50

    3.4 Cu.M Cement mortar 1:5 1930.40 1 Cu.M 6563.36

    7.1 Nos. Mason I class 179.00 1 No. 1270.90

    10.6 Nos. Mason II class 162.00 1 No. 1717.20

    14.1 Nos. Muzdoor class I 112.00 1 No. 1579.20

    14.1 Nos. Muzdoor class II 101.00 1 No. 1424.1015909.26

    Rate For 1 Cu.M. = Rs. 1590.92 1590.93

    6 Brickwork in CM 1:5 using best country bricks of size 83/4x4 1/2x 2 3/4

    for 2.83 m

    1300 nos Bricks 2421.00 1000nos 3147.30

    0.708 m3

    C M 1:5 1930.40 1 m3

    1366.72

    1 No Mason I class 179.00 1 No. 179.00

    3 Nos Mason II class 162.00 1 No. 486.00

    2 Nos Muzdoor class I 112.00 1 No. 224.00

    6Nos Muzdoor class II 101.00 1 No. 606.006009.02

    Rate For 1 Cu.M. = Rs. 2123.33 600.9

    7 Plastering with cement mortar 1:5

    12m.m. thick for 1 sq.m.

    0.14 Cu.m Cement mortar 1:5 1930.40 1 Cu.M 270.26

    1.1Nos Mason I class 179.00 1 No. 196.90

    0.5No Muzdoor class I 112.00 1 No. 56.00

    1.10 Nos. Muzdoor class II 101.00 1 No. 111.10

    634.26

    Rate For 1 Sq.M. = Rs. 63.42 63.43

    8

    a r ca ng an supp y ng an erec ng requ re no ostructural steel members like MS angle as purlins of size

    65mmx65mm

    1 kg Cost of MS angles 52.00 1 kg 52.00

    1m2

    Fabrication and erection labour charges 12.30 1m2

    12.30

    Add 2.50% for wastage 1.3

    65.60

    Rate For 1 Kg = Rs. 65.60

    9 10 m2

    sheet 6mm thck of approved quality for roofing with

    necessary U and J bolts and nuts,bitumen GI washers

    etc..

    11 m2

    AC corrugated sheet 138.00 1m2

    1518.0020Nos Adjustable GI J bolt of 6mm dia 5.00 1No 100.00

    2.20 Nos Fitters II nd class 146.00 1No 321.20

    1.1 Nos Carpenter I st claa 176.00 1No 193.60

    3.20 Nos Muzdoor class I 112.00 1 No. 358.40

    20 Nos Bitumen Washers 15mm dia 1.00 1 No. 20.00

    Rate for 1 Sq.m-Rs 251.12 2511.20

  • 7/28/2019 Lps Estimte & Rcc Room

    3/39

    10 100 m2

    White Washing 2 coats freshly burnt shell lime etc

    0.07 m3

    Shell lime 850.00 1m3 59.50

    1.60 Nos Mason II class 162.00 1 No. 259.20

    0.50 Nos Muzdoor class I 112.00 1 No. 56.00

    2.70 Nos Muzdoor class II 101.00 1 No. 272.70

    LS Gum ganjee water,Brush,Scaffolding charges ...etc... 7.60

    655.00

    Rate for 1 Sq.m-Rs 6.55

    1110 m

    2 Painting 2coats on new iron works for door without

    priming coats etc

    2.22 litres Enamel paint 150.00 Litre 333.00

    1.10 Nos Painter I st class 143.00 1 No 157.30

    490.30

    Rate for 1 Sq.m-Rs 49.03

    Certified that the above rates are adopted as per the current P.W.D standard shedule ofrates for the year 2008-09

    Counter signed

    Assistant Executive Engineer, Junior Engineer,

    Agricultural Engineering Department, Agricultural Engg Department,

    Gobichettipalayam Gobichettipalayam

  • 7/28/2019 Lps Estimte & Rcc Room

    4/39

    Construction of Pump House for the LPDS (3mx3m)

    District :Erode Village : Thoddampalayam

    Taluk :Sathyamangalam

    Length Breadth Depth Quantity Rate Amount

    M. M. M. M3

    1 2 3 4 5 6 7 8 9

    1 Earthwork excavating and

    depositing on bank within

    initial lead of 10 M.&

    initial lift of 2M.In hard stiff clay

    stiff black cotton, hard red earth,

    shales,murram, gravel, stoneyearth,

    and earth mixed with small size

    boulders as per S.S.20.B.and S.I.62.

    For foundation

    1x1 11.72 0.60 0.90 6.33

    1x1 1.20 0.50 0.15 0.09

    6.42 57.50 369.15

    2

    Cost of cement concrete 1:5:10 using

    40 m.m.HB stony julli

    All round Main Wall 1x1 11.72 0.60 0.15 1.05

    For step 1x1 1.20 0.50 0.15 0.09

    1.14 1773.54 2030.35

    3Random rubblemasonry in C.M.1:5

    BGL:- All round Main Wall 1x1 11.72 0.45 0.75 3.96

    AGL:- Basement all round 1x1 11.72 0.45 0.60 3.16

    7.12 1590.92 11327.19

    4 Brick work in CM1:5

    Back side Wall 1x1 3.46 0.23 2.40 1.91

    Front Side wall 1x1 0.23 2.10 1.67

    Side Walls 1x2 2.40 0.23 2.40+2.10/2 2.48

    For Step1 1x1 0.50 0.20 0.12

    For Step2 1x1 0.25 0.20 0.06

    6.25

    Deduction:- For Door 1x1 0.23 2.00 0.46

    For Cement jolly work 1x1 0.23 0.45 0.065.72 2123.33 12151.82

    5 supplying and filling the basement with filling sand

    in layers of not more than 15cm thick as well ram

    consolidated..etc

    For Basement 1x1 2.18 0.30 1.82

    1.82 642.50 1168.14

    Sl.

    no.Nos.Description of work

    1.20

    2.78

    1.00

    0.60

    1.20

    3.46

    DETAILED CUM ABSTRACT ESTIMATE

  • 7/28/2019 Lps Estimte & Rcc Room

    5/39

    6 Supplyng and fixing of MS Door of

    size 1mx2m 1No 4500.00 4500.00

    7

    Supplyng and fixing of RCC jolly of size-

    0.60mx0.45m 1No 300.00 300.00

    8 Flooring concrete in CC1:5:10 1x1 2.78 2.18 0.15 0.91 1773.54 1612.25

    9 Fabricating and supplying and erecting

    required no of structural steel members

    like MS angle as purlins of size ISA6565-

    6mm thick

    Purlins 1x4 5.80 kg/m 92.80 65.60 6087.68

    10 Supplying and laying of asbestos cment

    fully corrugated sheet 6mm thck of

    approved quality for roofing with

    necessary U and J bolts and

    nuts,bitumen GI washers etc..

    1x1 3.00 10.50 251.12 2636.76

    11 Plastering in cm1:5-12mm thick

    InnerSide:Back wall 1x1 3.00 2.40 7.20

    Front Wall 1x1 2.40 2.10 5.04

    Side Wall 1x2 3.00 2.40+2.10/2 13.5

    OuterSide:Back wall 1x1 3.46 2.40 8.30

    Front Wall 1x1 3.46 2.10 7.27

    Side Wall 1x2 2.40 2.40+2.10/2 10.8

    For Step1 1x1 1.20 0.45 0.54

    For Step2 1x1 1.20 0.45 0.54

    Floor 1x1 3.00 3.00 9.0062.19

    Deduction:- For Door 1x1 2.00 2.00

    For Cement jolly work 1x1 0.45 0.27

    59.92 63.42 3800.13

    12 White Washing 2 coats freshly burnt

    shell lime etc 1x1 59.92 6.55 392.48

    13Painting 2coats on new iron works for

    door without priming coats etc

    For door1x2 1.00 2.00 4.00 49.03 196.12

    46572.06

    or 47000

    1.00

    0.60

    3.50

    4.00

  • 7/28/2019 Lps Estimte & Rcc Room

    6/39

  • 7/28/2019 Lps Estimte & Rcc Room

    7/39

  • 7/28/2019 Lps Estimte & Rcc Room

    8/39

    Construction of Pump House for the LPDS (3mx3m)

    District :Erode Village : Thoddampalayam

    Taluk :Sathyamangalam

    Length Breadth Depth Quantity Rate Amount

    M. M. M. M3

    1 2 3 4 5 6 7 8 9

    1 Earthwork excovating and

    depositing on bank within

    initial lead of 10 M.&

    initial lift of 2M.In hard stiff clay

    stiff black cotton, hard red earth,

    shales,murram, gravel, stoneyearth,

    and earth mixed with small size

    boulders as per S.S.20.B.and S.I.62.

    For foundation

    1x1 12.92 0.60 0.90 6.98

    1x1 1.20 0.50 0.15 0.09

    7.07 57.50 406.34

    2

    Cost of cement concrete 1:5:10 using

    40 m.m.HB stony julli

    All round Main Wall 1x1 12.92 0.60 0.15 1.16

    For step 1x1 1.20 0.50 0.15 0.09

    1.25 1773.54 2221.89

    3Random rubblemasonry in C.M.1:5

    BGL:- All round Main Wall 1x1 12.92 0.45 0.75 4.36

    AGL:- Basement all round 1x1 12.92 0.45 0.60 3.49

    7.85 1590.92 12486.97

    4 Brick work in CM1:5

    Back side Wall 1x1 3.46 0.23 2.40 1.91

    Front Side wall 1x1 0.23 2.10 1.67

    Side Walls 1x2 3.00 0.23 2.40+2.10/2 3.11

    For Step1 1x1 0.50 0.20 0.12

    For Step2 1x1 0.25 0.20 0.06

    6.87

    Deduction:- For Door 1x1 0.23 2.00 0.46

    For Cement jolly work 1x1 0.23 0.45 0.066.34 2123.33 13470.40

    5 supplying and filling the basement with filling sand

    in layers of not more than 15cm thick as well ram

    consolidated..etc

    For Basement 1x1 2.78 0.30 2.32

    2.32 642.50 1489.65

    2.78

    0.60

    DETAILED CUM ABSTRACT ESTIMATE

    Sl.

    no.Description of work Nos.

    1.00

    3.46

    1.20

    1.20

  • 7/28/2019 Lps Estimte & Rcc Room

    9/39

  • 7/28/2019 Lps Estimte & Rcc Room

    10/39

  • 7/28/2019 Lps Estimte & Rcc Room

    11/39

  • 7/28/2019 Lps Estimte & Rcc Room

    12/39

    Sl

    No.

    1 Earth work excavation and depositing on

    bank within initial lead and initial lift in

    hard stiff clay, stiff black cotton, hard red

    earth slabs etc as per Ss 20B & SI 62 for foundation

    1 x 1 79.20 0.50 0.90

    2 Sand filling with filling sand including

    watering etc. for

    Foundation 1 x 1 79.20 0.50 0.10

    Basement 1 x 1 1.20 1.20 0.30

    Steps 1 x 1 1.20 1.00 0.10

    3 CC 1:4:8 using 40mm HBGS metal for

    Foundation 1 x 1 79.20 0.50 0.20

    Basement for step 1 x 1 1.20 1.00 0.20

    Basement 1 x 1 1.20 1.20 0.15

    4 R.R. Masonry in CM 1:5 for

    Footing 1 x 1 79.20 0.50 0.60

    Basement 1 x 1 6.92 0.45 0.45

    5 Brick work in CM 1:5 using II Class

    Bricks of size 22cm x 11cm x 7.5cm for super structures.

    All round main Wall 1 x 1 79.00 0.23 3.05

    Deduction for Door 1 x 1 1.00 0.23 2.00

    Deductions for Jolly 1 x 1 0.60 0.23 0.45

    Deduction for Lintel 1 x 1 1.20 0.23 0.10

    Description of Work L B D

  • 7/28/2019 Lps Estimte & Rcc Room

    13/39

    Step-I 1 x 1 1.20 0.80 0.00

    Step-II 1 x 1 1.20 0.60 0.00

    Step-III 1 x 1 1.20 0.40 0.00

    Step-IV 1 x 1 1.20 0.20 0.00

    6 Centering charges lintel and roof slab

    including strutting

    Roof Slab 1 x 1 28.00 11.50

    Roof Slab Side 1 x 1 79.00 0.10

    Deduct Wall placement 1 x 1 6.92 0.23

    Lintel Bottom 1 x 1 1.00 0.23

    Lintel Front side 1 x 1 1.00 0.03

    Lintel Back side 1 x 1 1.20 0.10

    Lintel side 1 x 2 0.23 0.10

    7 Supplying and fabricating and placing in

    osition of steel rods for RCC slab1 x 1

    8 Supplying and fixing of RCC jolly of size

    0.60M x 0.45M

    1 x 1

    9 RCC in 1:2:4 using 20mm HBGS jelly for

    roof slab, sunshade and lintel

    Roof Slab 1 x 1 28.00 11.50 0.10

    Lintel 1 x 1 1.20 0.23 0.10

    1 x 1 0.075+0.052.00

    10 Supplying and fixing of M.S. Door of size1.00Mx2.00M in M.S. angle 40mm x

    40mm x 6mm M.S. angle

    40mmx40mmx6mm MS flat

    1 x 1

    11 Plastering in CM 1:5, 20mm thick

    Pump Room inner side 1 x 4 1.50 3.05

    Sunshade 1.00 0.45

  • 7/28/2019 Lps Estimte & Rcc Room

    14/39

    Pump Room Outer side 1 x 4 1.96 4.05

    Steps, Treads 1 x 4 1.20 0.20

    Side of step-IV 1 x 2 0.80 0.15

    Side of step III 1 x 2 0.60 0.15

    Side of step VI 1 x 2 0.40 0.15

    Side of Step-I 1 x 2 0.20 0.15

    Sides of soffits of Door 1 x 1 6.00 0.23

    Sides of soffits of Jolly 1 x 1 2.10 0.23

    Deduct for Door 1 x 2 1.00 2.00

    Deduct for Jolly 1 x 2 0.60 0.45

    Floor Plastering 1 x 1 1.50 1.50

    12 Plastering in CM 1:3- 12mm thick for

    Ceiling Inner side of pump Room 1 x 1 28.00 1.50

    Ceiling outer side Projection 1 x 1 8.64 0.20

    Ceiling outer side face 1 x 1 9.44 0.10

    Sunshade Bottom side 1 x 1 1.00 0.45

    1 x 1 0.075+0.05

    2.00

    Sunshade of Top side 1 x 1 1.00 0.45

    13 Pointing with CM 1:3 in RR Masonry

    1 x 1

    14 Weathering course over RCC ro9of

    including fixing one course of pressed tile

    etc. complete

    1 x 1 2.36 2.36

    15 Colour washing two coats with approved

    Cement paint for cement plastered

    surfaces & Sunshades top and side surface

    1 x 1

    Basement 9.60 0.45

    Sunshade side face 1.90

  • 7/28/2019 Lps Estimte & Rcc Room

    15/39

    16 White washing two coats for ceiling

    surfaces and sunshade bottom

    1 x 1

    T ESTIMATE

    Vill :

    Taluk Hosur

    Dist :

    Fiel :

    Name of work : Construction of Pump Room

    Sl

    No.

    1 5.60 m3 50 1 m

    3 280

    2 1.17 m3 322.3 1 m

    3 377.09

    Qty Rate Per Amount

  • 7/28/2019 Lps Estimte & Rcc Room

    16/39

    5 3.63 m3 1761.86 1 m

    3 6,395.55

    6 5.348 m2 382 1 m

    2 2,042.92

    7 0.30 Qtl 3292.6 1Qtl 987.78

    15 5.37 m2 5.5 1 m

    2 29.53

    3 1.70 m3 1656.37 1 m

    3 2,815.82

    8 1No. 500 1No. 500

    4 3.89 m3 1379.69 1 m3 5,366.99

    10 1No. 3850 1No 3,850.00

    9 0.613 m3 2677.86 1 m

    3 1,641.52

    12 5.94 m2 61.28 1 m

    2 364

    11 34.34 m2 96.87 1 m

    2 3,326.51

    14 32.66 m2 7.75 1 m2 253.11

    13 5.57 m2 272.27 1 m

    2 1,516.54

    16 4.32 m2 55.42 1 m

    2 239.41

  • 7/28/2019 Lps Estimte & Rcc Room

    17/39

    Ass

    ista

    nt

    Exe

    .

    En

    gin

    eer

    Assistan

    t

    Enginee

    r

    Agr

    icul

    tur

    al

    En

    gin

    eeri

    ng

    Dept.

    Hos

    ur

    13.23

    30,000.00

    17 L.S.

  • 7/28/2019 Lps Estimte & Rcc Room

    18/39

    35.640 5.60m3 8 0.30479951 2.438 28 28.2

    8.25 0.30479951 2.515 11.5

    8.50.30479951 2.591 79 79.2

    8.75 0.30479951 2.667

    3.960 0.62 9 0.30479951 2.743

    0.432 0.43 9.25 0.30479951 2.819

    0.120 0.12 9.5 0.30479951 2.896

    4.512 0.17 m3 9.75 0.30479951 2.972

    10 0.30479951 3.048

    10.25 0.30479951 3.124

    10.5 0.30479951 3.2

    7.920 1.24 10.75 0.30479951 3.277

    0.240 0.24 11 0.30479951 3.353

    0.216 0.22 11.25 0.30479951 3.429

    8.376 1.70 m3 11.5 0.30479951 3.505

    11.75 0.30479951 3.581

    12 0.30479951 3.658

    12.25 0.30479951 3.734

    23.760 2.49 12.5 0.30479951 3.81

    1.401 1.4 12.75 0.30479951 3.886

    25.161 3.89 m3 13 0.30479951 3.962

    13.25 0.30479951 4.039

    13.5 0.30479951 4.115

    13.75 0.30479951 4.191

    14

    0.30479951 4.267

    14.25 0.30479951 4.343

    55.419 3.82 14.5 0.30479951 4.42

    0.460 0.46 14.75 0.30479951 4.496 0.460

    0.062 0.06 15 0.30479951 4.572 0.062

    0.028 0.03 15.25 0.30479951 4.648 0.028

    ContentsContents

  • 7/28/2019 Lps Estimte & Rcc Room

    19/39

    0.000 0.144 15.5 0.30479951 4.724

    0.000 0.108 15.75 0.30479951 4.801

    0.000 0.072 16 0.30479951 4.877

    0.000 0.036 16.25 0.30479951 4.953

    54.869 3.63 m3 16.5 0.30479951 5.029

    16.750.30479951 5.105

    17

    0.30479951 5.182

    17.25 0.30479951 5.258

    322.000 5.57 17.5 0.30479951 5.334

    7.900 0.944 17.75 0.30479951 5.41

    1.592 1.592 18 0.30479951 5.486 1.592

    0.230 0.23 18.25 0.30479951 5.563

    0.025 0.03 18.5 0.30479951 5.639

    0.120 0.12 18.75 0.30479951 5.715

    0.046 0.046 19 0.30479951 5.791

    328.729 5.348 m2 19.25 0.30479951 5.867

    19.5 0.30479951 5.944

    19.750.30479951 6.02

    0.000 0.30 Qtl. 20 0.30479951 6.096

    20.25 0.30479951 6.172

    0.000 1 No. 20.5

    0.30479951 6.248

    20.75 0.30479951 6.32521

    0.30479951 6.401

    21.25 0.30479951 6.477

    32.200 0.557 21.5 0.30479951 6.553

    0.030 0.008 21.75 0.30479951 6.629

    0.028 22 0.30479951 6.706. .

    32.258 0.613 m3 22.5 0.30479951 6.858

    22.75 0.30479951 6.934

    0.000 1No. 23

    0.30479951 7.01

    23.25 0.30479951 7.087

    23.5 0.30479951 7.163

    23.75 0.30479951 7.239

    18.300 14.4 24 0.30479951 7.315

    0.208

  • 7/28/2019 Lps Estimte & Rcc Room

    20/39

    31.752 18.81 24.25 0.30479951 7.391

    0.960 0.96 24.5 0.30479951 7.468

    0.240 0.24 24.75 0.30479951 7.544

    0.180 0.18 25 0.30479951 7.62

    0.120 0.12 25.25 0.30479951 7.696

    0.060 0.06 25.50.30479951 7.772

    1.380 1.38 25.75 0.30479951 7.849

    0.483 0.48 26 0.30479951 7.925

    4.000 4 26.25 0.30479951 8.001 4.000

    0.540 0.54 26.5 0.30479951 8.077 0.540

    2.250 2.25 26.75 0.30479951 8.153

    51.185 34.34 m3 27 0.30479951 8.23

    27.25 0.30479951 8.306

    27.5 0.30479951 8.382

    27.75 0.30479951 8.458

    42.000 2.25 28 0.30479951 8.534

    1.728 1.728 28.25 0.30479951 8.611

    0.944 0.944 28.5 0.30479951 8.687

    0.450 0.45 28.75 0.30479951 8.763

    0.119 29 0.30479951 8.839

    29.25 0.30479951 8.915

    0.450 0.45 29.5 0.30479951 8.992

    45.691 5.94 m2 29.75 0.30479951 9.068

    30 0.30479951 9.144

    30.25 0.30479951 9.22

    30.5 0.30479951 9.296

    4.320 30.75 0.30479951 9.373

    31 0.30479951 9.449

    31.25 0.30479951 9.525

    31.5 0.30479951 9.601

    31.75

    0.30479951 9.677

    5.570 5.57 m2

    32 0.30479951 9.75432.25 0.30479951 9.83

    32.5

    0.30479951 9.906

    51.185 32.66 m2 32.75 0.30479951 9.982

    33 0.30479951 10.058

    0.118

    4.32 m2

  • 7/28/2019 Lps Estimte & Rcc Room

    21/39

    33.25

    0.30479951 10.135

    5.37 m2 33.5 0.30479951 10.211

  • 7/28/2019 Lps Estimte & Rcc Room

    22/39

  • 7/28/2019 Lps Estimte & Rcc Room

    23/39

    Hosur

  • 7/28/2019 Lps Estimte & Rcc Room

    24/39

    Sl

    No.

    1 Earth work excavation and depositing on

    bank within initial lead and initial lift in

    hard stiff clay, stiff black cotton, hard red

    earth slabs etc as per Ss 20B & SI 62 for foundation

    1x1 6.92 0.9 0.9

    2 Sand filling with filling sand including

    watering etc. for

    Foundation 1x1 6.92 0.9 0.1

    Basement 1x1 1.2 1.2 0.3

    Steps 1x1 1.2 1 0.1

    3 CC 1:4:8 using 40mm HBGS metal for

    Foundation 1x1 6.92 0.9 0.2

    Basement for step 1x1 1.2 1 0.2

    Basement 1x1 1.2 1.2 0.15

    4 R.R. Masonry in CM 1:5 for

    Footing 1x1 6.92 0.6 0.6

    Basement 1x1 6.92 0.45 0.45

    5 Brick work in CM 1:5 using II Class

    Bricks of size 22cm x 11cm x 7.5cm for super structures.

    All round main Wall 1x1 6.92 0.23 2.4

    Deduction for Door 1x1 1 0.23 2

    Deductions for Jolly 1x1 0.6 0.23 0.45

    Deduction for Lintel 1x1 1.2 0.23 0.1

    Description of Work Nos. L B D

  • 7/28/2019 Lps Estimte & Rcc Room

    25/39

    Step-I 1x1 1.2 0.8 0.15

    Step-II 1x1 1.2 0.6 0.15

    Step-III 1x1 1.2 0.4 0.15

    Step-IV 1x1 1.2 0.2 0.15

    6 Centering charges lintel and roof slab

    including strutting

    Roof Slab 1x1 2.36 2.36 -

    Roof Slab Side 1x1 9.44 - 0.1

    Deduct Wall placement 1x1 6.92 0.23 -

    Lintel Bottom 1x1 1 0.23 -

    Lintel Front side 1x1 1 - 0.025

    Lintel Back side 1x1 1.2 0.1 -

    Lintel side 1x2 0.23 - 0.1

    7 Supplying and fabricating and placing in

    osition of steel rods for RCC slab1x1 - - -

    8 Supplying and fixing of RCC jolly of size

    0.60M x 0.45M

    1x1 - - -

    9 RCC in 1:2:4 using 20mm HBGS jelly for

    roof slab, sunshade and lintel

    Roof Slab 1x1 2.36 2.36 0.1

    Lintel 1x1 1.2 0.23 0.1

    0.075+0.

    2

    10 Supplying and fixing of M.S. Door of size

    1.00Mx2.00M in M.S. angle 40mm x

    40mm x 6mm M.S. angle

    40mmx40mmx6mm MS flat

    1x1 - - -

    11 Plastering in CM 1:5, 20mm thick

    Sunshade 1x1 1 0.45

  • 7/28/2019 Lps Estimte & Rcc Room

    26/39

    Pump Room inner side 1x4 1.5 - 2.4

    Pump Room Outer side 1x4 1.96 - 2.4

    Steps, Treads 1x4 1.2 0.2 -

    Side of step-IV 1x2 0.8 - 0.15

    Side of step III 1x2 0.6 - 0.15

    Side of step VI 1x2 0.4 - 0.15

    Side of Step-I 1x2 0.2 - 0.15

    Sides of soffits of Door 1x1 6 - 0.23

    Sides of soffits of Jolly 1x1 2.1 - 0.23

    Deduct for Door 1x2 1 - 2

    Deduct for Jolly 1x2 0.6 - 0.45

    Floor Plastering 1x1 1.5 1.5 -

    12 Plastering in CM 1:3- 12mm thick for

    Ceiling Inner side of pump Room 1x1 1.5 1.5 -

    Ceiling outer side Projection 1x1 8.64 0.2 -

    Ceiling outer side face 1x1 9.44 - 0.1

    Sunshade Bottom side 1x1 1 0.45 -

    0.075+0.

    2

    Sunshade of Top side 1x1 1 0.45 -

    13 Pointing with CM 1:3 in RR Masonry

    14 Weathering course over RCC ro9of

    including fixing one course of pressed tile

    etc. complete1x1 2.36 2.36 -

    15 Colour washing two coats with approved

    Cement paint for cement plastered

    surfaces & Sunshades top and side surface

    1x1

    Sunshade side face 1x1 1.9 -

    Basement 1x1 9.6 - 0.45

  • 7/28/2019 Lps Estimte & Rcc Room

    27/39

    16 White washing two coats for ceiling

    surfaces and sunshade bottom

    1x1 - - -

    T ESTIMATE

    Vill : Poonapalli

    Taluk : Hosur

    Dist : Krishnagiri

    Fiel : 24, 29 & 30

    Name of work : Construction of Pump Room

    Sl

    No.

    Qty Descript

    ion

    Rate Per Amount

  • 7/28/2019 Lps Estimte & Rcc Room

    28/39

    1 5.60 m3 Earth

    work

    excavati

    on and

    depositi

    ng on

    bankwithin

    initial

    lead and

    initial

    lift in

    hard stiff

    clay,

    stiff

    black

    cotton,hard red

    earth

    slabs etc

    as per Ss

    20B &

    SI 62 for

    foundati

    50 1 m3 280

    2 1.17 m3 Sand

    filling

    withfilling

    sand

    includin

    g water

    etc.

    322.3 1 m3 377.09

    3 1.70 m3 CC

    1:4:8

    using

    40mm

    HBGS

    Metal

    1656.37 1 m3 2,815.82

    4 3.89 m3 R.R.

    Masonry

    in CM

    1:5

    1379.69 1 m3 5,366.99

  • 7/28/2019 Lps Estimte & Rcc Room

    29/39

    5 3.63 m3 Brick

    work in

    CM 1:5

    using II

    Class

    Bricks

    of size22cm x

    11cm x

    7.5cm

    all round

    main

    walls

    1761.86 1 m3 6,395.55

    6 5.348 m2 Centerin

    g

    charges

    lintel

    and roof

    slab

    includin

    g

    strutting

    382 1 m2 2,042.92

    7 0.30 Qtl Supplyin

    g and

    fabricating and

    placing

    in

    position

    of steel

    rods for

    RCC

    slab

    3292.6 1Qtl 987.78

    8 1No. Supplying &

    fixing &

    RCC

    ell

    500 1No. 500

  • 7/28/2019 Lps Estimte & Rcc Room

    30/39

    15 5.37 m2 White

    washing

    5.5 1 m2 29.53

    Ass

    ista

    ntExe

    .

    En

    gin

    eer

    Assistan

    t

    Enginee

    r

    9 0.613 m3 RCC

    1:2:4

    using

    20mm

    ell

    2677.86 1 m3 1,641.52

    10 1No. Supplyin

    g andfixing of

    M.S.

    Door

    3850 1No 3,850.00

    11 34.34 m2 Plasterin

    g in

    CM 1:5

    96.87 1 m2 3,326.51

    12 5.94 m2 Ceiling

    Plasterin

    1:3

    61.28 1 m2 364

    13 5.57 m2 Weather

    ing

    Course

    272.27 1 m2 1,516.54

    14 32.66 m2 Colour

    washing

    7.75 1 m2 253.11

    16 4.32 m2 Pointing

    in CM

    1:3

    55.42 1 m2 239.41

    17 Unfores

    eenItems

    L.S. 13.23

    Total #######

  • 7/28/2019 Lps Estimte & Rcc Room

    31/39

    Agr

    icul

    tur

    al

    En

    gineeri

    ng

    Dep

    t.

    Agricultural

    Enginee

    ring

    Dept.

    Hos

    ur

  • 7/28/2019 Lps Estimte & Rcc Room

    32/39

    5.60m3

    0.62

    0.43

    0.12

    0.17 m3

    1.24

    0.24

    0.22

    1.70 m3

    2.49

    1.4

    3.89 m3

    3.82

    0.46

    0.06

    0.03

    Contents

  • 7/28/2019 Lps Estimte & Rcc Room

    33/39

    0.144

    0.108

    0.072

    0.036

    3.63 m3

    5.57

    0.944

    1.592

    0.23

    0.03

    0.12

    0.046

    5.348 m2

    0.30 Qtl.

    1 No.

    0.557

    0.008

    0.613 m3

    1No.

    0.208

  • 7/28/2019 Lps Estimte & Rcc Room

    34/39

    14.4

    18.81

    0.96

    0.24

    0.18

    0.12

    0.06

    1.38

    0.48

    4

    0.54

    2.25

    34.34 m3

    2.25

    1.728

    0.944

    0.45

    0.45

    5.94 m2

    5.57 m2

    32.66 m2

    0.118

    4.32 m2

  • 7/28/2019 Lps Estimte & Rcc Room

    35/39

    5.37 m2