Project Status Update
April 17, 2014
I an Galsworthy
Low Level Road Project
p o r t m e t r o v a n c o u v e r.c o m 2
Low Level Road Project
p o r t m e t r o v a n c o u v e r.c o m 3
Purpose:
To provide for future increased rail capacity.
Makes space for the rail expansion and installat ion of two new rail t racks.
Closes three exist ing at grade rail crossings – t rain lengths & whist ling.
Constraints:
Narrow corr idor of interest – steep slopes/ exist ing road & rail.
Low Level Road Project
p o r t m e t r o v a n c o u v e r.c o m 4
Typical Sect ion
p o r t m e t r o v a n c o u v e r.c o m 5
Low Level Road Project
Delivery:
Lead: Port Met ro Vancouver
Project Managem ent Services: MMM Group
Technical Design Services: Stantec Consult ing
Cont ractor: B&B Heavy Civil Const ruct ion Ltd
Project Cost : $101.6M
Scheduled Com plet ion : 31 October 2014
Funding: Asia-Pacific Gateway & Corr idor I nit iat ive (AGPCI ) – March 2015
p o r t m e t r o v a n c o u v e r.c o m 6
Low Level Road Project
Funding Partners:
Transport Canada; Port Met ro Vancouver;
CN Rail; CP Rail; Translink;
City of North Vancouver.
Ow ner:
City of North Vancouver – Low Level Road
- Spir it Trail
Port Met ro Vancouver – Cargill Neptune overpass
p o r t m e t r o v a n c o u v e r.c o m 7
Play LLR Video…
p o r t m e t r o v a n c o u v e r.c o m 8
Schedule
2012 2013 2014 2015
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
REVISED
FUNDING DEADLINE
MARCH 31, 2015
ORIGINAL
FUNDING DEADLINE
MARCH 31, 2014
CNV COUNCIL
DECISION
JUNE 18
MAIN CONSTRUCTION
COMMUNICATIONS (ONGOING)
FINAL
OPEN
HOUSE
SEPT 22
DETAILED DESIGN
FUNDING AGREEMENTS
PERMITTING & APPROVALS
WE ARE
HERE
TENDER RFQ
•Original Completion – End of Q1 2013 (May 2012) •Current Completion – End of Q3 2014 (Sep 2012)
p o r t m e t r o v a n c o u v e r.c o m 9
Current Status
Com pleted:
• Overall – 65% Complete including:
Neptune Cargill Overpass – 60% Complete
Excavat ion – 95% Complete
Retaining Wall Const ruct ion - 80% Complete
Rail Relocat ions – 90% Complete
Underground Ut ilit y Relocat ions– 90% Complete
BC Hydro Relocat ions – 95% Complete
Fort is Relocat ions – 80% Complete
p o r t m e t r o v a n c o u v e r.c o m 10
Current Status – Cont’d. Com pleted:
• Majority of walls at full height
• Western detour implemented to allow cont inued wall const ruct ion along Low Level Road and Esplanade
• Erect ion of Neptune/ Cargill Overpass
• Ut ilit ies relocat ions (BC Hydro, Fort is, and Telus)
• Relocat ion of railway at west end
Current / Ongoing:
• Permanent Cargill Hydro connect ion installat ion ongoing along Low Level Road
• Const ruct ion of Spir it Trail br idges
• Erect ion of Pedest r ian Overpass on E. 3 rd st reet
• Cast - in-place wall to house the Public art
p o r t m e t r o v a n c o u v e r.c o m 11
Low Level Road Project – Progress Photos
p o r t m e t r o v a n c o u v e r.c o m 12
Low Level Road Project – Progress Photos
p o r t m e t r o v a n c o u v e r.c o m 13
Low Level Road Project – Progress Photos
p o r t m e t r o v a n c o u v e r.c o m 14
p o r t m e t r o v a n c o u v e r.c o m 15
p o r t m e t r o v a n c o u v e r.c o m 16
Low Level Road Project – Progress Photos
Neptune Cargill Overpass Looking West North Span Beams being installed
p o r t m e t r o v a n c o u v e r.c o m 17
p o r t m e t r o v a n c o u v e r.c o m 18
p o r t m e t r o v a n c o u v e r.c o m 19
p o r t m e t r o v a n c o u v e r.c o m 20
p o r t m e t r o v a n c o u v e r.c o m 21
p o r t m e t r o v a n c o u v e r.c o m 22
p o r t m e t r o v a n c o u v e r.c o m 23
p o r t m e t r o v a n c o u v e r.c o m 24
p o r t m e t r o v a n c o u v e r.c o m 25
Low Level Road Project – Progress Photos
Neptune Cargill Overpass Looking East North Span Beams being installed (left) South Approach Ramp (right)
p o r t m e t r o v a n c o u v e r.c o m 26
Thank you