![Page 1: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/1.jpg)
Low Impact Development Site Planning and Design
Scott MillarPlanning and Development Office
RIDEM
![Page 2: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/2.jpg)
Smart Development for a Cleaner Bay Act
Use LID as the primary method of stormwater management
![Page 3: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/3.jpg)
Stormwater Manual Standard No. 1
“LID Site Planning and Design Strategies must be used to the maximum extent practicable…”
![Page 4: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/4.jpg)
Goal 1: Avoid the impacts to natural features and predevelopment hydrology
Objective 1. Protect open space to maintain hydrology
Objective 2. Protect surface waters, wetlands, and buffers
Objective 3. Minimize clearing and grading
Objective 4. Reduce soil compaction
![Page 5: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/5.jpg)
Goal 2: Reduce runoff volume and increase groundwater recharge
Objective 5. Maintain native vegetation to minimize lawns, fertilizers, and pesticides
Objective 6. Minimize impervious surfaces
![Page 6: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/6.jpg)
Goal 3: Manage the impacts at the source
Objective 7. Infiltrate precipitation as close as possible to the point it reaches the ground
Objective 8. Break up or disconnect the flow of runoff over impervious surfaces
![Page 7: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/7.jpg)
Goal 3: Manage the impacts at the source
Objective 10. Revegetate previously cleared areas
Objective 9. Provide source controls to minimize stormwater pollutants
![Page 8: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/8.jpg)
Past Stormwater Management
![Page 9: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/9.jpg)
AVOIDAVOID
REDUCEREDUCE MANAGE
MANAGE
![Page 10: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/10.jpg)
Why should communities avoid and reduce impacts?
• Community character is preserved• Local flooding is reduced• Saves money
![Page 11: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/11.jpg)
Natural Hydrology
![Page 12: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/12.jpg)
Center for Watershed Protection
Maintain Pre-development Hydrology
![Page 13: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/13.jpg)
Center for Watershed Protection
Altered Hydrology
![Page 14: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/14.jpg)
Center for Watershed Protection
0
0.5
1
1.5
2
2.5
3
Rainfall Parking LotRunoff
Forest Runoff
Inch
es
![Page 15: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/15.jpg)
Impervious Cover Impacts
1. Hydrology Impacts
2. Physical Impacts
3. Biological / Habitat Impacts
4. Water Quality Impacts
5. Health Impacts
![Page 16: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/16.jpg)
Impervious Cover Influences Wet Weather Stream Flow
Center for Watershed ProtectionCenter for Watershed Protection
![Page 17: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/17.jpg)
More Frequent Flooding
Center for Watershed Protection
Higher Flood Levels
Impervious Cover Influences Wet Weather Stream Flow
![Page 18: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/18.jpg)
Impervious Cover Influences Dry Weather Stream Flow
Center for Watershed Protection
![Page 19: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/19.jpg)
Impervious Cover
Physical Impacts
• Channel enlargement• Riparian cover reduced• Warmer stream temperatures
![Page 20: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/20.jpg)
Watershed with less than 5%
impervious cover.
Photo Copyright 1999, Center for Watershed Protection
![Page 21: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/21.jpg)
Watershed with 10% impervious cover.
Photo Copyright 1999, Center for Watershed Protection
![Page 22: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/22.jpg)
Watershed with 20% impervious cover.
Photo Copyright 1999, Center for Watershed Protection
![Page 23: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/23.jpg)
Watershed with 30% impervious cover.
Photo Copyright 1999, Center for Watershed Protection
![Page 24: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/24.jpg)
0
20
40
60
80
100
0 10 20 30 40 50Percent Impervious Cover in Watershed
Num
ber a
nd D
iver
sity
of
Aqua
tic L
ife
Impervious Cover ImpactsBiological / Habitat
![Page 25: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/25.jpg)
Center for Watershed Protection
Impervious Cover ImpactsWater Quality
![Page 26: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/26.jpg)
Center for Watershed Protection
Oil & GreaseOil & Grease
BacteriaBacteria
PesticidesPesticides
NutrientsNutrients
Muddy WaterMuddy Water
Heavy Metals Heavy Metals (e.g. (e.g. Zinc, Copper, Lead)Zinc, Copper, Lead)
Harmful pollutants in Harmful pollutants in runoff include:runoff include:
Impervious Cover ImpactsHealth
![Page 27: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/27.jpg)
10% 40%25%
Good
Fair
Poor
Watershed Impervious Cover
Stre
am Q
ualit
y
60% 100%
Sens
i tive
Impa
cted
Damaged
Impervious Cover Model
Severely Damaged
Relationship Between Impervious Relationship Between Impervious Cover and Stream QualityCover and Stream Quality
Center for Watershed Protection
![Page 28: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/28.jpg)
![Page 29: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/29.jpg)
![Page 30: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/30.jpg)
![Page 31: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/31.jpg)
So what should communities do?
![Page 32: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/32.jpg)
![Page 33: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/33.jpg)
Guidance Manual Chapters1. Conservation Development2. Buffer Standards3. Site Clearing and Grading4. Roadway Standards5. Parking Requirements6. Compact Development7. LID Landscaping8. Special Use Ordinances
• Stormwater Utilities• Impervious Cover• Review and Inspection Fees
![Page 34: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/34.jpg)
45 Site Planning and Design Techniques
• Current Practice• Recommended Practice• Perceptions and Realities• Economic and Stormwater Benefits• Case Studies• References
![Page 35: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/35.jpg)
How can we Avoid the Impacts?
• Conservation Development• Buffer standards• Site clearing standards• Tree protection ordinances
![Page 36: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/36.jpg)
Conservation Development
“a creative land use technique that allows a community to guide growth to the most appropriate areas within a parcel of land to avoid impacts to the environment and to protect the character-defining features of the property.”
![Page 37: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/37.jpg)
Existing Conditions
![Page 38: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/38.jpg)
Yield Plan
![Page 39: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/39.jpg)
Conservation Plan
![Page 40: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/40.jpg)
Comparisons
Conventional Conservation
Wetland Lots: 24 0 Average Lot: 3 acres .52 acresStreet Length: 9,059 3,720Open Space: 1.4% 82%
![Page 41: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/41.jpg)
Goal 1: Avoid the impacts to natural features and predevelopment hydrology
Objective 1. Protect open space to maintain hydrologyObjective 2. Protect surface waters, wetlands, and buffersObjective 3. Minimize clearing and gradingObjective 4. Reduce soil compaction
![Page 42: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/42.jpg)
![Page 43: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/43.jpg)
Buffer Standards
![Page 44: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/44.jpg)
![Page 45: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/45.jpg)
Buffer Benefits
• Decreases watershed impervious cover• Flood control• Provides habitat• Reduces stream warming• Greenway corridors• Increases property values• Protects water quality
![Page 46: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/46.jpg)
Buffer Encroachment
![Page 47: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/47.jpg)
Site Clearing Standards
http://croptechnology.unl.edu/
![Page 48: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/48.jpg)
![Page 49: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/49.jpg)
![Page 50: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/50.jpg)
Limited Disturbance Zone
Construction staging area
Owner Discretion Zone
Low Impact Development: A Guidebook for North Carolina- 2009
Driveway Disturbance Zone
![Page 51: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/51.jpg)
Forest Conservation and Tree Protection Ordinances
Horsley Witten Group, Inc.
![Page 52: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/52.jpg)
Trees Reduce Stormwater Runoff
One mature beech tree can intercept over 2,000 gallons of runoff annually
![Page 53: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/53.jpg)
• Trees should be identified and protected
• Require percent tree canopy cover• Require bonds to cover tree
replacement
Recommended Ordinance Requirements
![Page 54: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/54.jpg)
• Fence off the crown
![Page 55: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/55.jpg)
How can we Reduce the Impacts?
• Compact development• Roadway standards• Parking requirements• LID landscaping
![Page 56: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/56.jpg)
Compact Development
![Page 57: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/57.jpg)
Impervious Cover Associated with Residential Lot Sizes
Lot Size Dwelling Units/Acre
% Impervious Cover
10 Acres 0.1 2.4%
5 Acres 0.2 5%
3 Acres 0.333 8%
2 Acres 0.5 12%
1 Acre 1 20%
.5 Acre 2 25%
.25 Acre 4 38%
![Page 58: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/58.jpg)
Site: 20%impervious cover
Watershed: 20%impervious cover
Site: 38%impervious cover
Watershed: 9.5% impervious cover
Site: 65%impervious cover
Watershed: 8.1%impervious cover
1 unit per acre 4 units per acre 8 units per acre
Protecting Water Resources with Higher-Density Development, US EPA
![Page 59: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/59.jpg)
![Page 60: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/60.jpg)
![Page 61: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/61.jpg)
Roadway Design
• Pavement length and width • ROW width• Cul-de-sac radius• Sidewalk design• Curb requirements• Driveway design
![Page 62: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/62.jpg)
Wide StreetWide Street
9 houses9 houses
$ 40,400 to repave$ 40,400 to repave
$4,500/house$4,500/house
Pavement length and width
![Page 63: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/63.jpg)
Narrow StreetNarrow Street
14 houses14 houses
$ 24,200 to repave$ 24,200 to repave
$1,700/house$1,700/house
Pavement length and width
![Page 64: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/64.jpg)
Pavement length and width
![Page 65: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/65.jpg)
Cul-de-sac Radius
![Page 66: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/66.jpg)
Alternative Designs
![Page 67: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/67.jpg)
Cul-de-sac Radius
![Page 68: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/68.jpg)
Sidewalk Design
![Page 69: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/69.jpg)
Sidewalk Design
![Page 70: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/70.jpg)
Curb Requirements
![Page 71: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/71.jpg)
![Page 72: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/72.jpg)
![Page 73: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/73.jpg)
Driveway Design
![Page 74: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/74.jpg)
Shared Driveway
![Page 75: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/75.jpg)
Parking Guidance
![Page 76: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/76.jpg)
Parking Guidance• Establish both minimum and maximum
parking ratios
Conventional parking layout
![Page 77: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/77.jpg)
Parking Layout Using LID Techniques
![Page 78: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/78.jpg)
• Encourage shared parking
![Page 79: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/79.jpg)
• Allow off-site parking, where practical• Reduce parking stalls
![Page 80: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/80.jpg)
LID Landscaping
• Require natural vegetation and encourage native landscaping
![Page 81: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/81.jpg)
Goal 2: Reduce stormwater volume and increase groundwater recharge
Objective 5. Maintain native vegetation to minimize lawns, fertilizers, and pesticides
Objective 6. Minimize impervious surfaces
![Page 82: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/82.jpg)
Ordinance Checklist for 45 LID Site Planning and Design
Techniques
![Page 83: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/83.jpg)
Objective VI: Minimize impervious surfaces
15. Did your community adopt compact growth ordinances such as conservation development, planned development or mixed use development?
16. Are residential streets required to be as narrow as possible to accommodate traffic volumes without compromising safety?
a. Do you require road widths of 22 feet or less for subdivisions of 40 or fewer homes or average daily trips less than 400?
b. Do you require road widths of 26 feet or less for subdivisions of 40-200 homes or average daily trips of 400-2,000?
17. Are street right-of–way widths required to be less than 45 feet?
18. Driveway lengths and widths are required to be reduced to the extent possible, pervious surfaces and shared driveways are encouraged wherever appropriate?
a. Do you require driveways to be 9 feet or less (one lane) and 18 feet or less (two lanes)?
b. Do you allow pervious surfaces to be used for residential driveways?
c. Do you allow shared driveways to be used in residential developments?
19. Do you allow the flexibility with curbs in residential streets to encourage side of the road drainage into vegetated open swales, where possible?........................................
![Page 84: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/84.jpg)
Incorporating LID into Comprehensive Plans
Goal: Avoid the Impacts
Objective 1: Protect undisturbed open space
Action 1.1 Adopt Conservation Development
Action 1.2 Require limits of disturbance on site plans
![Page 85: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/85.jpg)
Summary
• LID: A R M• Avoid & Reduce: Municipal Responsibility• LID Community Benefits
![Page 86: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/86.jpg)
Questions?
![Page 88: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/88.jpg)
![Page 89: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/89.jpg)
Avg lot size=just over 1 acreROW=60 ft
Road width=30 ftCul-de-sac radius=38 ft
*
*
* SW BMP
Curb and gutter drainage system
![Page 90: Low Impact Development Site Planning and Design...Low Impact Development Site Planning and Design Scott Millar Planning and Development Office RIDEM. Smart Development for a ... LID](https://reader034.vdocuments.us/reader034/viewer/2022051813/60337235e23d94667e62ee0c/html5/thumbnails/90.jpg)