low impact developement site planner

34
www.ContechES.com Development and Application of a Web- Based Post-Construction Stormwater BMP Feasibility Screening Tool Vaikko Allen, CPSWQ, LEED-AP Director Stormwater Regulatory Management Contech Engineered Solutions [email protected]

Upload: contech-engineered-solutions

Post on 17-Jul-2015

68 views

Category:

Engineering


0 download

TRANSCRIPT

www.ContechES.com

Development and Application of a Web-

Based Post-Construction Stormwater

BMP Feasibility Screening Tool

Vaikko Allen, CPSWQ, LEED-AP

Director Stormwater Regulatory Management

Contech Engineered Solutions

[email protected]

www.ContechES.com

www.ContechES.com

www.ContechES.com

www.ContechES.com

LID is Sweeping the Nation!!!

Photo credits: SvR Design Company, Seattle, WA

www.ContechES.com

LID implementation doesn’t have to be this

be complicated!

www.ContechES.com

LID Design Hierarchy

www.ContechES.com

LID Site Planner – Purpose

A fast, easy to use tool that follows a Low Impact Development

(LID) design approach and is consistent with regulations that

prioritize Green Infrastructure

Helps minimize the cost and delay of redesigns by prompting

users to consider a wide range of common site constraints

early in the design process

Captures specific site conditions precluding the use of

infeasible BMPs

Allows flexibility to select flow through treatment controls

where runoff reduction is not feasible

Provides a summary report with links to design guides,

standard details and specifications for stormwater

management approaches that are likely to be feasible and

approved on the project

www.ContechES.com

LID Site Planner – Core Functionality

Collect site informationo Project name, project location, total disturbed area, total project area,

dominant land use

Divide site into discrete drainage management areas

(DMA) with dominant land surface types

Apply screening questions to identify feasible BMPs for

each DMA

Capture and report constraints precluding more favorable

BMPs

Summarize feasible BMPs and provide links to standard

specifications and typical drawings

www.ContechES.com

Dominant Unit Process BMPINFILTRATION Bioretention

INFILTRATION Permeable pavement

INFILTRATION Infiltration trench or gallery

INFILTRATION Drywell

RAINWATER HARVEST Rainwater Harvest

EVAPOTRANSPIRATION Green Roofs

FILTRATION Conventional Biofiltration

FILTRATION High Rate Biofiltration

FILTRATION Media Filter

GRAVITATIONAL SEPARATION Swale

GRAVITATIONAL SEPARATION Hydrodynamic Separator

BMPs represented

www.ContechES.com

Land surface type drives BMP selection

Considering LEED benefits and O&M concerns, Rainwater

Harvesting and Green Roof priority may be reversed

BMP Selection Based on Land Surface TypeUnit Process INFILTRATION HARVEST ET FILTRATION SETTLING

Unit Operation BioretentionPermeable

pavement

Infiltration

trench or

gallery

DrywellRainwater

Harvest

Green

RoofsBiofiltration

High Rate

Biofiltration

Media

FilterSwale Separator

Roofs X X X X X X X X X

Primary

Roads, High

Use Parking

Lots X P P P X X X X X

Landscaped

areas X X

Walkways,

courtyards X X X P P X X X X X

Secondary

roads,

parking lots X X P P P X X X X X

Notes:

X = Suitable BMP

P = Pretreatment required

www.ContechES.com

Orange County - 2011 Technical Guidance Document

Ventura County – 2011 Technical Guidance Manual

Delaware article 3.06.2 – Post construction BMP standards

and specifications

2009 MD Stormwater Design Manual, Chapter 3 -

Performance criteria for urban BMP design

2012 Stormwater Management Manual for Western

Washington

WEF MOP 23 – Design of Urban Stormwater Controls

BMP Feasibility Criteria Sources

www.ContechES.com

Unit Process INFILTRATION HARVEST ET FILTRATION SETTLING

Unit Operation BioretentionPermeable pavement

Infiltration gallery

DrywellRainwater

HarvestGreen Roofs Biofiltration

HR

BiofilterFilter Swale Separator

High Groundwater within 5-10' of surface

Sensitive Groundwater, <100' to extraction well

Expansive Soils

Contaminated soils

Low permeability soils (<0.5"/hr infiltration rate)

Lack of control over soil compaction during

construction

Adjacent to foundations and utilities

High spill potential PT PT PT PT PT PT PT PT

Slopes >5%

Potable water demand minimization Xeri Xeri Xeri

Fertilizer, pesticide, herbicide minimization O O O O

< 4% of EIA available for BMPs

Discharge to surface required (no stormdrain)

Existing plumbing or structure not supporting green

roof

Existing plumbing not supporting harvest

Insufficient supply or demand for harvested water

Maintenance equipment, access and expertise

availability

Ecological or geomorphic water balance sensitivity

Notes:

PT = Requires pretreatment

Xeri = Xeriscaping or using drought tolerant vegetation

O = Organic landscaping with native or adapted plants can minimize impacts

Site Constraint Screening

www.ContechES.com

Seasonal high groundwater within

5’ to 10’ of surface

Sensitive groundwater,

groundwater extraction well within

100‘

Expansive soils

Contaminated soils or groundwater

Potential BMP location adjacent to

foundation or utilities that may be

compromised by infiltration

Low permeability soils <0.5 “/hr

infiltration rate or NRCS class C, D

Infiltration System Constraints

This photo shows one of the houses

damaged by the 2005 Laguna Beach

Landslide. The house experienced an

undermining by the landslide but

remained intact. Photo by Pam Irvine,

California Geological Survey (CGS).

www.ContechES.com

Bioretention

A stormwater control measure that

is comprised of plants and

engineered soil located in a

landscape depression. The plants

and soil cleanse stormwater and

retain pollutants and stormwater is

infiltrated into native soils.

Conventional bioretention system

size is dictated by the permeability

of native soils and is commonly

>10% of the size of the

contributing impervious area.

www.ContechES.com

Permeable Pavement

Permeable hardscape materials

including asphalt, concrete and

paver block systems allow the

movement of water and air around

or through the paving material

while providing a durable surface

for pedestrian, bicycle and

vehicular traffic.

Infeasibility criteria

• High spill potential

• Heavy sediment and gross

solids loads

• High traffic roads and parking

lots

• Not available to treat roof runoff

www.ContechES.com

Infiltration Gallery

Infiltration trenches and galleries store stormwater below grade in a stone matrix and/or a

perforated pipe, chamber or vault shaped vessel designed to release stormwater into native soils

over time.

Pretreatment Required

www.ContechES.com

Dry Well

A vertical stormwater injection well

used to access permeable soil

layers at some depth below the

surface.

Pretreatment Required

www.ContechES.com

Rainwater Harvesting

Capture of stormwater runoff from

roofs, streets and other impervious

areas for beneficial use as

irrigation or for other non-potable

indoor and outdoor uses.

Feasibility constraints:

• Rainwater harvest and use is

limited or prohibited due to

water rights conflicts

• Local building code or public

health restrictions prohibit

rainwater harvest and use

• Inadequate demand for

harvested water considering all

allowed uses including,

irrigation, indoor non-potable

use, cooling water makeup,

etc.

www.ContechES.com

Green Roof

A green roof intercepts and stores

rainwater within vegetation and a

growing medium located on a roof

surface.

Only applicable where land

surface type is “Roof”.

Feasibility Constraints:

• Existing roof will not support

additional weight of green roof

(Extensive roof up to 50# wet,

Intensive roof up to 150# wet)

• Green roof would require

supplemental irrigation in Arid

(<10"/annual precip) or Semi-

arid Climate (10-20" annual

precip)

www.ContechES.com

Conventional Biofilter

A stormwater control measure that

filters stormwater as it passes

through plants and engineered.

Biofiltration may allow incidental

infiltration it differs from

bioretention in that it contains an

under drain which collects treated

stormwater and discharges it from

the site. Conventional biofiltration

sizing is typically greater than 4%

of the contributing impervious

area.

Constraints:

• High spill potential requires

pretreatment

• >4% of contributing effective

impervious area required

• Site must be tolerant of

vegetation and wildlife

www.ContechES.com

High Rate Biofilter

High rate biofiltration systems are

typically <1/20th the size of

conventional biofiltration due to the

use of optimized soils that have

sustained infiltration rates of more

than 50”/hr. They may also be

configured to allow incidental

infiltration.

Constraints:

• Require 3’ minimum drop from

grade to outlet invert

• Site must be tolerant of

vegetation and wildlife

• Susceptible to spills and heavy

sediment and gross solids

loading

www.ContechES.com

Media Filter

Media filters use a bed of

engineered media without

vegetation to filter stormwater prior

to discharge downstream. They

are commonly installed below

grade.

Constraints:

• Regulatory approval as stand

alone BMP required unless

used as pretreatment

• Require 3’ minimum drop from

grade to outlet invert

www.ContechES.com

Swale

A swale is a long linear vegetated

ditch designed to provide a

residence time of at least 7-10

minutes for stormwater runoff.

Pollutants settle out and are

filtered as they travel the length of

the swale. Swales typically

provide significant volume

reduction through incidental

infiltration and evapotranspiration.

Constraints:

• Susceptible to spills and heavy

sediment and gross solids

loading

• Long linear space required

(100 ft min)

www.ContechES.com

Hydrodynamic

Separator

Hydrodynamic separators are flow

through treatment systems using

internal baffles, weirs, plates and

other flow directing features to

optimize removal of floating and

sinking pollutants. Most commonly

used as pretreatment in an LID

application.

Constraints:

• Typically a pretreatment BMP

• Regulatory approval as stand

alone treatment not assured

• Require 3’ minimum drop from

grade to outlet invert

• Not able to address dissolved

pollutants

www.ContechES.com

Users can save and retrieve an unlimited number of their own

projects

Users cannot view others projects

Basic login information auto-populated on new projects

Contech support is available on request

o Where assistance is requested, questions directed to a local resource

based on project zip code or user information

If requested, Contech can review project details and can assist

with feasibility screening and stormwater plan development

Confidentiality

www.ContechES.com

Demonstration

• This is a Preliminary screening tool

• Precursor to detailed stormwater

management plans

• Local criteria supersede default criteria

www.ContechES.com

Demonstration

www.ContechES.com

Demonstration

www.ContechES.com

Demonstration

www.ContechES.com

Demonstration

www.ContechES.com

Demonstration

www.ContechES.com

Report Contains:

Project information

Contact information

DMA information

Selected BMP(s)

◦ Description

◦ Web link to specifications,

drawings, design information

Non-selected feasible BMPs

◦ Description

Infeasible BMPs

◦ Reasons for infeasibility

DMA Report

www.ContechES.com