lorence mechanical excavations of urban rail unnels
TRANSCRIPT
FLORENCE, 15TH DECEMBER 2020
MECHANICAL EXCAVATIONSOF URBAN RAIL TUNNELS
FLORENCE HIGH SPEED RAILWAY UNDERPASS
Ing. Raffaele ZURLO
15th december 2020
CEO INFRARAIL FIRENZE
Copertina sezione- alternativa 2
Sottotitolo sezione
2
3
PROJECT OBJECTIVES
[Testo livello 01] Inserire qui il testo corpo 20 pt
[Testo livello 02] Inserire qui il testo corpo 18 pt
[Testo livello 03] Inserire qui il testo corpo 16 pt
[Testo livello 04] Inserire qui il testo corpo 14 pt
[Testo livello 05] Inserire qui il testo corpo 12 pt
3
4Progetto Infrarail Firenze I Raffaele Zurlo
TRAFFIC FLOW
THE RAILWAY HUB OF FLORENCE:
▪ 56% regional trains ▪ 29% long-distance trains ▪ 6% freight trains ▪ 7% technical trains TOTAL: 890 trains/day
REG
HS
IC
Freighttrains
Technicaltrains
TOTAL
100%
30% 70% 100%
ItinerariesonSMN ItinerariesnotonSMN Total
88% 12% 100%
73% 27% 100%
0% 100% 100%
78% 22% 100%
59% 41%
TRAFFIC DISTRIBUTION BY TRANSPORTATION TYPE AND ITINERARY
4
5Progetto Infrarail Firenze I Raffaele Zurlo
CAPACITY ANALYSIS
CURRENT CRITICAL ISSUES:
1. Convergence of flows in thesame direction
2. Conflicts among traffic flowsin the opposite direction atthe Hub junction as well as atthe head station of SantaMaria Novella
Flows in the opposite direction
5
6Progetto Infrarail Firenze I Raffaele Zurlo
CAPACITY ANALYSIS
CURRENT CRITICAL ISSUES:
1. Convergence of flows in thesame direction
2. Conflicts among trafficstreams in the oppositedirection at the Hub junctionas well as at the head stationof Santa Maria Novella
Traffic projections
+ 48%
6
7Progetto Infrarail Firenze I Raffaele Zurlo
PROJECT FRAMEWORK
High Speed Railway Link for urban penetration
Total length: 7,819 mOperating speed: 100 km/hGradient : 17,94 ‰Standard tunnel section average surface:70 square meters
WORKS:
▪ 2 main single-track tunnels ▪ Transverse tunnels every 410 m▪ Belfiore High Speed Station
▪ Railway overpass
Lot 2
Lot 1
7
8Progetto Infrarail Firenze I Raffaele Zurlo
NEW CONFIGURATION OF THE HUB
EXPECTED BENEFITS:
1. Reduction of transit times(about 15 minutes)
2. Separation between high-speed and regional trains
1. Greater availability of surfacetracks at Firenze Santa MariaNovella
2. Increased capacity andregularity of the Hub in favorof regional trains
Traffic projections
+ 48%
8
9Progetto Infrarail Firenze I Raffaele Zurlo
IFR - Infrarail Firenze is a special-purpose company, set up inSeptember 2019 by RFI - ReteFerroviaria Italiana in order tocomplete the constructionproject of the Florence HighSpeed railway underpass and thenew High Speed Belfiore Station.
RFI & IFR
9
10Progetto Infrarail Firenze I Raffaele Zurlo
INFRARAIL FIRENZE
Share capital€ 5,500,000
Human Resources
65
Our missionImproving Florence urbanmobility and preserving
urban aesthetics by carryingout underground
infrastructure constructionworks and international
archistars’ projects
10
11
GEOLOGY OF THE FLORENCE AREA
Lake deposits Lake depositsFirenze-Prato-Pistoia
Alluvial deposits
Recent deposits
Lake depositsFirenze-Prato-Pistoia
Progetto Infrarail Firenze I Raffaele Zurlo
Belfiore High Speed Railway Station
Campo di MarteSouth Entrance
RifrediNorth Entrance
Fortezza da Basso
Campo di MarteSouth EntranceFortezza da Basso
Belfiore High Speed Railway Station
Rifredi North Entrance
11
12
Lake deposits Lake depositsFirenze-Prato-Pistoia
Alluvial deposits
Recent deposits
Lake depositsFirenze-Prato-Pistoia
Progetto Infrarail Firenze I Raffaele Zurlo
Belfiore High Speed Railway Station
Campo di MarteSouth Entrance
RifrediNorth Entrance
Fortezza da Basso
Campo di MarteSouth Entrance
Fortezza da Basso
Belfiore High Speed Railway Station Rifredi
North Entrance
FLORENCE GROUNDWATER
Hydraulic Conductivity
+ 1,85m
+ 1,95m
+ 1m
- 0,8m
- 1,35m
-0,75m
12
13
Lake deposits Lake depositsFirenze-Prato-Pistoia
Alluvial deposits
Recent deposits
Lake depositsFirenze-Prato-Pistoia
Progetto Infrarail Firenze I Raffaele Zurlo
Campo di MarteSouth EntranceFortezza da Basso
Belfiore High Speed Railway Station Rifredi North
Entrance
FLORENCE GROUNDWATER
+ 0,8m
- 0,5m
+ 0,35m
- 0,35m
+ 1,4m
- 0,7m
13
Confirmed by monitoring data, basically lower than expected values
Confirmed by monitoring data, basically lower than expected values
Confirmed by monitoring data, basically lower than expected values
14
Star
t p
oin
t
Cam
po
di
Mar
te w
ell
Pk
0.0
0
Mec
han
ized
Tun
nel
ing
star
t p
oin
tP
k 1
31
7
Co
nso
lidat
ion
wo
rks
Iniz
io C
0P
k 3
28
4
Fin
e C
0P
k 3
60
5
HS
Rai
lway
Stat
ion
Pk
43
23
Pk
47
76
Fin
ish
po
int
Mec
han
ized
Tun
nel
ing
star
t p
oin
tP
k 6
89
1
Progetto Infrarail Firenze I Raffaele Zurlo
HIGH SPEED RAILWAY LINK
BOLOGNA ROMA
Lunghezza 1
Alt
ezza
10
L= 2.115 m L= 3.006 mL= 453 m L= 1.317 m
14
Railway UnderpassTunnel diameter: 9.43mTotal lenght: about 7 kmConnecting transversetunnels every 410m Tunnels inter-axis: 18m
15
EPB (Earth Pressure Balance)
Progetto Infrarail Firenze I Raffaele Zurlo
FLORENCE TBM Machine Type: TBM Earth Pressure Balance (EPB)
Total length (back up included)
111m
Total weight 14700kN
Radius capability 270m
Operating pressure
4 bar
Machine Type: TBM Earth Pressure Balance (EPB)
TBM Ref. Characteristics Value
Cutter Head
Boring Diameter 9,43 m
Weight 1390 kNNr. of Single Cutters 4+2 (peripheral)Nr. of Double Cutters 21Central Cutter nr 2 x 4 cutters Cutter Diameter 17"Nr. of Scrapers 124
Capability
Power 4530 kWTheoretical speed 80 mm/minMax Torque 28151 kNOperating Thrust 24429 kN
Shield
Front Max. diameter 9,40 mRear Max diameter 9,38 mTotal Length 10,085 mErector rot. speed loaded 1 r/min
Erector rot. speed unloaded 2 r/min
15
16Progetto Infrarail Firenze I Raffaele Zurlo
FLORENCE TBMEPB (Earth Pressure Balance): OPERATING PRINCIPLES
Stability of the tunnel face →production of heavy slurry
16
17
THE PRODUCTION CYCLE
Progetto Infrarail Firenze I Raffaele Zurlo
Heavy slurry:Excavated soil + Additives
Foam→ Polyfoamer ECO/1002,25 l/m3 clay soils1,75 l/m3 sand soils
Water → 400 ÷ 500 l/m3
Polymers/Bentonite → 1 ÷ 3%
17
18
In order to obtain an optimal slurry, it is necessary to use surfactants (foam)
Progetto Infrarail Firenze I Raffaele Zurlo
THE PRODUCTION CYCLE
18
19
Prebuilt concrete segments are produced and installed in order to create the segmental lining, which must ensure stability and waterproofing of the cavity.
Progetto Infrarail Firenze I Raffaele Zurlo
THE PRODUCTION CYCLE
UNIVERSAL RINGThickness: 40cmStrenght class: C40/50Exposure class: XC2-XF1Steel: B450C
19
20
The slurry is put on the conveyor belt and sent to the final storage by train
Progetto Infrarail Firenze I Raffaele Zurlo
THE PRODUCTION CYCLE
20
21Progetto Infrarail Firenze I Raffaele Zurlo
PRODUCTION SITES
1.670.800 m3
(bulk)
52.500 m3
590.900
m3
677.400 m3
350.000 m3
Foaming agents with polymers
• Polyfoamer ECO/100 for type 1-soils (clay-loam)
• Polyfoamer ECO/100 and Mapedrill XG01 for type-2 soils
(gravelly loam soil - sand – clay) and for intermediate soils.
21
22
SANTA BARBARA
Florence
S. Giovanni Valdarno
S. Barbara
1.670.800 m3
(bulk)
1.350.000 m3
Column ATable 1, part IV, attachment 5, title V of D.lgs. 152/2006
WasteAdrastea S.r.l.
Pomezia
621.000 m3
729.000
m3147.140 m3
Column «A»or
Column «B» surplusEx cava Bruni
Serravalle Pistoiese
22.000 m3
151.260 m3
180.000 m3 (supposed)
Characterization of mechanized-excavated soil
• Type 1-soils (clay): toxiciy test (day 28)
• Type-2 soils (gravel): toxicity test (day 14)
Surfactant > 15mg/KgToxicity level cannot be accepted (fish embryo toxicity test (FET) with the zebrafish (Danio rerio) and Aliivibrio fischeri Toxicity Tests (formerly Vibrio Fischeri)
22
23
SANTA BARBARA
Progetto Infrarail Firenze I Raffaele Zurlo 23
24
Waterproofing is ensured by the following elements:
Progetto Infrarail Firenze I Raffaele Zurlo
Stability is ensured by the traditional structural elements:
STABILITY AND WATERPROOFING
• Segmental lining geometry
• Concrete and reinforcing steel characteristics
But especially…
• Back filling between the segmental lining and the soil
• Excellent quality of the concrete • Micro cracking to be avoided• Sealing elements and related positioning • Accurate installation of the segmental lining
24
25
Prebuilt concrete segments are produced and installed in order to create the segmental lining, which must ensure stability and waterproofing of the cavity.
Progetto Infrarail Firenze I Raffaele Zurlo
THE PRODUCTION CYCLE
25
26Progetto Infrarail Firenze I Raffaele Zurlo
THE INJECTION SYSTEMThe injection of concrete segments is fundamental to reduce subsidence and to ensure lining’s waterproofing
Back filling:Bicomponent resin
Component ACement 350 ÷ 400 kg/m3
Filler/Bentonite 45 ÷ 50 kg/m3
Water 800 l/m3
Component BSilicate based hardener 70% ÷ 80% (weight)
26
27
SUBSIDENCE MONITORING
Andamento dei cedimenti attesi in condizioni di "green field" lungo il perimetro delle mura
0
0.005
0.01
0.015
0.02
0.025
0.03-10 40 90 140 190
Canna binario dispari Entrambe le canne Canna binario pari
A B C D
Bastione Rastriglia Cinta muraria Ovest
k = 0.35Vp = 0.4%
Bastione Rastriglia Cinta muraria Est Mura
27
A
D
C
B
Expected subsidence <1,5cm
28
SUBSIDENCE MONITORINGBoscardin e Cording (1989)
Category of damage Description of typical damage
0 - negligibleHairline cracks
Approx. Crack width 0.1 mm
1 - very slightFine cracks that can easily be treated during normal decoration
Approx. Crack width 1 mm
2 - slightCracks easily filled. Redecorating probably required
Approx. Crack width 5 mm
3 - moderate
The cracks require some opening up and can be patched by a mason.
Recurrent cracks can be masked by suitable linings. Repointing of external
brickwork and possibly a small amount of brickwork to be replaced.
Approx. Crack width 5-15mm or number of cracks >34 – severe Extensive repair work involving bricking out and replacing section of walls,
especially over doors and windows.
Approx. Crack width 15-25mm but also depends on number of cracks
5 – very severe This requires a major repair job involving partial or complete rebuilding.
Approx. Crack width usually >25mm but also depends on number of cracks
28
Vp 0,4%
Vp 1%
29
SUBSIDENCE – FORTEZZA DA BASSO
29
Boscardin e Cording (1989)
Category of
damageDescription of typical damage
2 - slightCracks easily filled. Redecorating probably required
Approx. Crack width 5 mm
Intervento preventivoCompensation grouting.
MEMBRANE MIX❖ Cement class 425 type I÷IV - UNI197/1.❖ Water/cement ratio = 3.5❖ Filler/cement ratio = 1❖ Bentonite/water ratio = 2.0%❖ Density ≈ 1.32 t/m3
❖ Marsh funnel viscosity > 40÷45 s/l;❖ Volumetric efficiency after 4 hours: 98% (bleeding<2%);❖ Average composition/m3:• Cement ≈ 236 kg/m3;• Filler ≈ 236 kg/m3;• Water ≈ 827 lit/m3;• Bentonite ≈ 17 kg/m3.
PRE-TREATMENT MIX❖ Cement class 525 type I÷IV - UNI197/1.❖ Water/cement ratio = 4.0❖ Filler/cement ratio = 1❖ Bentonite/water ratio = 2.0%❖ Density ≈ 1.28 t/m3
❖ Marsh funnel viscosity 30÷40 s/l❖ Volumetric efficiency after 4 hours: 98% (bleeding<2%);❖ Average composition/m3:• Cement ≈ 210 kg/ m3
• Filler ≈ 210 kg/ m3
• Water ≈ 841 lit/ m3
• Bentonite ≈ 17 kg/ m3
• Additives ≈ 4 kg/ m3
❖ Injection parameters:• Injection pressure = 0.8÷1.1 Mpa• Injection rate = 5÷20 l/min
MITIGATION MEASURES MIX❖ Cement class 425 type I÷IV - UNI197/1.❖ Water/cement ratio = 2.0❖ Filler/cement ratio = 1❖ Bentonite/water ratio = 4.5%❖ Density ≈ 1.48 t/ m3
❖ Marsh funnel viscosity > 40÷45 s/l❖ Volumetric efficiency after 4 hours: 98%
(bleeding<2%);❖ Average composition/m3:• Cement ≈ 386 kg/ m3
• Filler ≈ 366 kg/ m3
• Water ≈ 733 lit/ m3
• Bentonite ≈ 15 kg/ m3
• Additives ≈ 4 kg/ m3
❖ Injection parameters:• Injection pressure = 1.5÷2.0 Mpa• Injection rate = 2 l/min
30
SUBSIDENCE MONITORING
30
31
NTC2018 UPDATE ORIGINAL DETAILED DESIGN DRAWN UP BETWEEN 2008 AND 2010
2020 – Railway stationn. 5 CH tests
2020
2020 - DH
2020 - CH
2020 - CH
2020 - DH
2020 - DH
2020 - DH
2020 - DH
2020 - DH
31
32
NTC2018 UPDATE – SEISMIC ANALYSIS
Piano Comunale di Protezione Civile del Comune di Firenze. Attachments: C22 e C23
Most active seismic zone considered.(Intersection between zone S3*** and highest amplification values)
• Vu=100aa• Cu=2• Subsoil classes B, C and E• Coordinates: 43.783043; 11.235701
SLV B C E
ag [g] 0.203 0.203 0.203
Fo 2.407 2.407 2.407
TC [s] 0.316 0.316 0.316
SS 1.2 1.406 1.462
CC 3.85 1.536 1.824
ST 1 1 1
amax [g] 0.244 0.285 0.297
On a conservative prediction : amax = 0.297g
32
33
NTC2018 UPDATE – SEISMIC ANALYSIS
Final coating checkThe seismic risk assessment has been carried out by a pseudo-static analysis (Bilotta et Al.)
33
34
The seismic condition does not affectdimensioning, as the dynamic stresses occure on the same scale as the staticones. The related load combinations do notinvolve load increase (unitaryamplification factor).
34
NTC2018 UPDATE – SEISMIC ANALYSIS
35Progetto Infrarail Firenze I Raffaele Zurlo
SUB-BALLAST MATS
35
36Progetto Infrarail Firenze I Raffaele Zurlo
Thank you for your kind attention!