Long Term Study Transmission Results. Objectives:. ERCOT and ERCOT stakeholders, with the support of a Department of Energy Grant, improved and expanded the existing Long Term Study (LTS) processes. Specifically, the Transmission Analysis component of the LTS seeks to: - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/1.jpg)
Long Term Study Transmission Results
May 21st, 2013
![Page 2: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/2.jpg)
2
Objectives:
ERCOT and ERCOT stakeholders, with the support of a Department of Energy Grant, improved and expanded the existing Long Term Study (LTS) processes. Specifically, the Transmission Analysis component of the LTS seeks to:
•Create a repeatable process to identify intra-regional system needs for both reliability and economic efficiency.
•Study a full spectrum of scenarios to identify similar and contrasting transmission system needs to facilitate various resource portfolios.
•Inform shorter-term study horizons with “least regrets” solutions as study assumptions become more certain.
•Procure and customize a tool to identify ancillary service needs for increasing amounts of non-traditional resources.
May 21, 2013
![Page 3: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/3.jpg)
3
Agenda
• Process Review
• Scenario Selection – Transmission Analysis
• Base Case Development
• Reliability Import Expansion Analysis
• Base Case Overloads
• Economic Themes / Observed Congestion
• Major Findings
• Integrating Renewable Energy / KERMIT Analysis
May 21, 2013
![Page 4: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/4.jpg)
4May 21, 2013
Process Review
![Page 5: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/5.jpg)
5
Selected Cases for Transmission Analysis
ERCOT chose to perform a full transmission analysis for each scenario that modified a resource build, load, or dispatch cost enough to modify transmission system needs.
May 21, 2013
![Page 6: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/6.jpg)
6
Scenario Selection - Wind
May 21, 2013
CompleteIn ProgressOmitted from Trans Analysis
![Page 7: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/7.jpg)
7
Scenario Selection - Load
May 21, 2013
![Page 8: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/8.jpg)
8
Scenario Selection – Resource Sites (2032)
May 21, 2013
Business as usual Business as Usual / Retirements
![Page 9: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/9.jpg)
9
Scenario Selection – Resource Sites (2032)
May 21, 2013
Business as Usual‘All Technologies’ / Updated Wind
Business as Usual – HighNat Gas Price
![Page 10: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/10.jpg)
10
Scenario Selection - Resource Sites (2032)
May 21, 2013
Drought – No PTC or emission costs
Drought – No PTC, emission costs, low gas price
![Page 11: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/11.jpg)
11
Resource Sites (2032)
May 21, 2013
Drought – PTC, Water Costs, Emissions cost
![Page 12: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/12.jpg)
12
Base Case Reliability Upgrades (2032)
May 21, 2013
![Page 13: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/13.jpg)
13
Transformer Base Case Reliability Upgrades: 2022
May 13th 2013
![Page 14: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/14.jpg)
14May 13th 2013
Transformer Base Case Reliability Upgrades: 2032
![Page 15: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/15.jpg)
15
Economic Studies
Each economic project selected for analysis targeted scenario-specific opportunities for production cost savings. Reoccurring themes included:
May 21, 2013
Expanded imports into Houston
Expanded imports into Dallas Expanded connectivity to the San Antonio 345kV ring
![Page 16: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/16.jpg)
16
Economic Studies Continued
Each economic project selected for analysis targeted scenario-specific opportunities for production cost savings. Reoccurring themes included:
May 21, 2013
Expanded connectivity to the Texas Panhandle
Expanded Access to Coastal Wind
![Page 17: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/17.jpg)
17
Major Findings: Retirements
The retirement of legacy gas-fired resources within ERCOT’s urban load centers:•Greatly increases the need for reliability upgrades in and around urban load centers
•Accelerates the need for new import paths (most notably in Houston; a new import is required within the ten-year study horizon)
•Creates economic opportunities in Houston, Dallas, and San Antonio for transmission expansion.
May 21, 2013
![Page 18: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/18.jpg)
18
Major Findings: Beyond 345kV
Expanding the ERCOT system beyond 345kV was cost-effective for select scenarios. If high gas prices and/or continuation of the production tax credit for wind persist, then 500kV solutions are cost-effective for the delivery of concentrated renewable energy to major load centers. Select Drought Scenarios yielded similar results.
May 21, 2013
![Page 19: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/19.jpg)
19
Major Findings: Extended Drought / Extreme Load
Increased system loading coupled with water availability issues threatened the economic viability of existing and potential future thermal units. The net effect accelerated the need and quantity of expanded imports into Houston, Dallas, and San Antonio.
May 21, 2013
![Page 20: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/20.jpg)
20May 13th 2013
Major Findings: Extended Drought / Extreme Load
![Page 21: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/21.jpg)
21
Note: If municipal utilities operating in a vertically integrated structure repower or expand existing urban resources, then transmission import needs will be largely offset.
May 13th 2013
Major Findings: Extended Drought / Extreme Load
![Page 22: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/22.jpg)
22
Major Findings: Beyond CREZ
Wind-dominated resource expansion scenarios sited wind in the Texas panhandle beyond the current design capacity of the CREZ System.
May 21, 2013
![Page 23: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/23.jpg)
23
Major Findings: Beyond CREZ
Multiple scenarios in the Long Term Study suggested that expansive wind development in the Texas Panhandle may threaten steady state stability under certain conditions. Based upon this assessment, the ERCOT Dynamic Studies performed a detailed assessment of LTS findings.
If wind development in the Texas Panhandle is comparable or higher than what was modeled in the LTS, then additional exports from the region are needed for steady-state stability. Numerous projects return production cost savings commensurate with their costs for high gas price and environmental scenarios.
May 21, 2013
![Page 24: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/24.jpg)
24
Integrating Renewables / KERMIT analysis
ERCOT procured a time-series simulation model to assess the adequacy of ancillary services needed to balance portfolios with increasing proportions of renewables.
May 21, 2013
![Page 25: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/25.jpg)
25
Integrating Renewables / KERMIT Analysis
DNV KEMA’s KERMIT model was modified to represent the ERCOT market, complete with existing and probable future resources.
May 21, 2013
![Page 26: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/26.jpg)
26
Integrating Renewables / KERMIT Study
Increased wind penetration and diversity of wind sites decreased the frequency of small magnitude net load ramps on a five-minute basis.
May 21, 2013
![Page 27: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/27.jpg)
27
Integrating Renewables / KERMIT Study
May 21, 2013
Increased wind penetration greatly increased the magnitude and frequency of 15-min net load ramps
![Page 28: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/28.jpg)
28
Integrating Renewables / KERMIT Study
May 21, 2013
Seldom-occurring high-magnitude net load ramps required a significant increase in seasonal deployment of quick-start / non-spin capacity.
![Page 29: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/29.jpg)
29
Integrating Renewables / KERMIT Observations
With increasing penetration of wind;•Large magnitude ramps occurred more frequently.
•Small magnitude ramps occurred less frequently.
Based upon these observations, ERCOT modeled new ancillary products with complementary ramping characteristics. These products: •Represent online resources or resources with zero-startup time•Include only resources capable of ramping to full load within 5 minutes, and• Are technology neutral.
May 13th 2013
![Page 30: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/30.jpg)
30
Integrating Renewables / KERMIT Study: Scenario 3/8 Results
ERCOT calculated a portfolio of ancillaries to maintain equal or better than actual frequency performance.
May 21, 2013
Actual Reserves 2012
Initial KERMIT Run
Scenario 3 Scenario 8
Total Nameplate Renewables10 GW 10 GW 20 GW 50 GW
Min Max Max Max Max
Regulation Reserves240 940 600 600 600
Responsive Reserves (Gen) 1400 1400 1050 1050 1050
Responsive Reserves (Load) 1400 1400 1400 1400 1400
New 5-min product in SCED – – –
800 1300
Non Spin QS*470 2000
1650 1650 1650
Non Spin 30-min product ** – – –
Total 3510 5740 4700 5500 6000
* 15-min product – 5-min start, 10-min ramp ** Cold Start
![Page 31: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/31.jpg)
31
Integrating Renewables / KERMIT Study: 20 GW Results
May 21, 2013
![Page 32: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/32.jpg)
32
Integrating Renewables / KERMIT Study: 50 GW Results
May 21, 2013
![Page 33: Long Term Study Transmission Results](https://reader036.vdocuments.us/reader036/viewer/2022062301/56813898550346895da048e3/html5/thumbnails/33.jpg)
33
Review:
ERCOT and ERCOT Stakeholders developed a repeatable process to determine:
•Reliability-driven transmission system upgrades and economic alternatives across a spectrum of probable resource builds.
• Document major findings for use in shorter-term study horizons as resource assumptions become more certain.
•Implement a tool and study framework for identifying complementary ancillary service needs for increasing proportions of non-traditional resources
May 21, 2013