long shutdown 2013: electrical distribution activities
DESCRIPTION
Long shutdown 2013: Electrical distribution activities . 09/03/2012 IEFC 2012 Workshop F. Duval on Behalf of EN/EL group. Activities during LS1 Ongoing consolidation & upgrade details After LS1 activities. Electrical distribution activities. - PowerPoint PPT PresentationTRANSCRIPT
Long shutdown 2013:Electrical distribution activities
09/03/2012IEFC 2012 Workshop
F. Duval on Behalf of EN/EL group
• Activities during LS1
• Ongoing consolidation & upgrade details
• After LS1 activities
Electrical distribution activities
IEFC Workshop - François Duval 209/03/2012
Next talk is dedicated to cabling activities (copper & fibres)
• 3 different types of activities:
1. Consolidation and upgrade of the Electrical Network
The ageing EL infrastructure must be updated to significantly increase availability rate and to meet CERN new requirements.
Beyond the present CERN needs, these renovation activities have been defined according to the future CERN power demand. That’s why EL have worked with users on a 15 years power demand forecast.
A complete program of consolidation & upgrade have been defined until 2025 and will be edited soon. This program cost is estimated at approximately 80 MCHF and shall be concentrated on 3 long shutdowns starting with LS1.
Activities during LS1
IEFC Workshop - François Duval 309/03/2012
• 3 different types of activities:
2. Maintenance operations
Since 2009 and the LHC start up, many maintenance operations have been postponed (mainly on 400 kV and 66 kV substations) because Christmas breaks have been shortened and because LHC Cryo could not be stopped. These postponed maintenance tasks must be done in 2013 in addition to regular scheduled maintenance.
A complete stop of the 400 kV will be necessary for 4 weeks (in April 2013) to maintain the 400 kV circuit breakers and accessories. RTE will take profit of this stop to run its own maintenance program on the Bois-Tollot substation and on the Genissiat/Bois-Tollot Over Head Line. During these 4 weeks, only 60 MVA will be available from the substation on Swiss SIG side. (close to A gate in Meyrin) 60 MVA are enough to run CERN with all accelerators turned off but the cost of energy is 1.5 times the French price. (Coordination needed to avoid high consuming LS1 activities during this period)
Activities during LS1
IEFC Workshop - François Duval 409/03/2012
• 3 different types of activities:
3. Requests from users
Many requests have been announced and must be detailed in terms of workload and schedule.The estimated EL contribution, for all the requests known today matches the maximum acceptable by ELThe major requests, not including LHC, are
- LINAC 4 and its connection to the Booster- HIE ISOLDE- RAMSES system- Filters and compensators upgrades- Experiments: ELENA, COMPASS, NA62, East Hall B157- PS access project- LIU activities
Activities during LS1
IEFC Workshop - François Duval 509/03/2012
• EL is increasing sharply its manpower in order to face a huge program of work.
– Manpower of EL was 72 in 03/2011, 82 in 03/212 and is expected to be 88 in 01/2013
– Agreements have been signed with AGH Krakow to have 12 technicians operational in 2013.
– 3 fellows, 4 PJAS, UPAS and 2 tech. students already joined the group
– It’s important to have them early enough to integrate and train them so that they will be fully operational for the highest workload period
– Having more people will become inefficient because of a lack of supervision
Activities during LS1
IEFC Workshop - François Duval 609/03/2012
• Prioritisation
– In spite of the substantial increase of EN-EL resources our workload is already at 100% of our capacity
– Further requests will leads to prioritisation of activities by LS1 management
Activities during LS1
IEFC Workshop - François Duval 709/03/2012
Priority Definition
0 safety
1 Beam to 6.5 - 7 TeV
2 Reliable operation
3 CERN approved projects
4 Not approved projects
Ongoing consolidation & Upgrade
IEFC Workshop - François Duval 809/03/2012
Reminder: • Replace ageing and/or not reliable equipment
• Simplification for better operations and reliable protection systems
• Standardisation for easier maintenance & operation
• Elimination of identified weak points
• Redundancy availability
• Characteristics adapted to the CERN future needs
Reliability – Availability – Safety – Evolution
Ongoing consolidation & Upgrade
IEFC Workshop - François Duval 909/03/2012
Power cables 3.3/18/66 kV, control cables and optical fibres 90 km in 7 km long trenches
Tubes buried in 2011 Cables pulled in 2012 Cables connected and
commissioned during LS1
Cost: 17 MCHF 6 FTE
SPS Power Cables: Layout
Ongoing consolidation & Upgrade
IEFC Workshop - François Duval 1009/03/2012
SPS Power Cables: tubes laying
Ongoing consolidation & Upgrade
IEFC Workshop - François Duval 1109/03/2012
SMB- SPS Power Cables: cables length 1971
2011
18 km cable> 80 joints
18 km cable8 joints
Ongoing consolidation & Upgrade
IEFC Workshop - François Duval 1209/03/2012
• Laying of cables during machine operation• Works executable out of LS1 period• Contractually shall be terminated before August 2012
SPS Power Cables: Pulling cables
• We ask to be allowed to pull the cables into the BAs during machine run (risk of theft)
Pulling machine
Ongoing consolidation & Upgrade
IEFC Workshop - François Duval 1309/03/2012
CCC Re-powering - Prevessin
CCC2012 New Substation BE91
2012New 3.3 kV power generation station
Redundant feeders18 kV network3.3 kV secured network400 V distribution network
Ongoing consolidation & Upgrade
IEFC Workshop - François Duval 1409/03/2012
CCC repowering - BE91 Substation
WHY: Increase 18 kV Prévessin
distribution Creation of a secured
power station for the SPS and Prévessin
Construction of a new LV substation to ensure full redundant infrastructure (EL + CV) for the CCC
After LS1 Activities
IEFC Workshop - François Duval 1509/03/2012
Meyrin 2012
Main substation ME9
Main substation ME59
Today Meyrin + LHC1 feeder 66 kV from Prevessin
B513 as an example of Meyrin User
Alternative feeder from SIG
After LS1 Activities
IEFC Workshop - François Duval 1609/03/2012
Meyrin 2015
Main substation ME9
New 66 kV from Prevessin
66 kV substation MEH59
Main substation ME59
Today Meyrin + LHC1 feeder 66 kV from Prevessin
B513 as an example of Meyrin User
Alternative feeder from SIG
Ongoing consolidation & Upgrade
IEFC Workshop - François Duval 1709/03/2012
• Redundant feeder for Meyrin• Necessary step to cope with power increase after LS1• Necessary step to allow Meyrin consolidation between LS1 and LS2
MEH59ME59
ME59 - Indoor 18 kVMEH59 - Outdoor 66 kV
66 kV in Meyrin- MEH59 Substation
B 112
Ongoing consolidation & Upgrade
IEFC Workshop - François Duval 1809/03/201218
Configuration since 1966
2014
Then…
• Two phases to redistribute power flow• After 2013, the rest of the job can be
done during machines runs.
ME59 Substation
Local distribution
Rest of Meyrin
Ongoing consolidation & Upgrade
IEFC Workshop - François Duval 1909/03/2012
Other projects•BA5 substation replacement
₋ First replacement of 6 SPS substations₋ Replacement include 18 kV, 230 V switchboards and 48 V redundant battery
charger system
•66 kV protection upgrade₋ Upgrade for advanced digital functionality₋ Replacement of ageing electronics
•BE substation ₋ Necessary redistribution of cubicles to add new feeders (BE91, New SMB, etc)
•Computer center B513 dedicated loop₋ Power increase on ISOLDE loop means that B513 must be fed separately
•New SCADA system for power network supervision₋ Developed together with EN/ICE using PVSS technology₋ Upgrade for new functionality (power flow forecast, event replay,..)
Many consolidation & upgrade activities on the power network have already started in parallel with beam operations.
The final connections and commissioning, which can only be done during shutdowns, are scheduled for LS1.
In other words, EL workload will be high in 2012 as well.
Ongoing consolidation & Upgrade
IEFC Workshop - François Duval 2009/03/2012
After LS1 Activities
IEFC Workshop - François Duval 2109/03/2012
Prevessin2013
Upgrade of BE substation
2012New 3.3 kV power generation station
2012 New Substation BE91
2011-2012SPS consolidation
2012-2013New 18 kV and 66 kV
power line to ME59 and MEH59
2013Consolidation 66 kV protection system
CERN Wide
After LS1 Activities
IEFC Workshop - François Duval 2209/03/2012
Meyrin
2017-2019Upgrade of ME9
2019Upgrade ME10
2012New 18 kV and 66 kV from
BE and SEH9
2013New MEH59
2020-2021Upgrade SEM12
2015-2019Upgrade of 18 kV transport
power lines
2012-2015Upgrade of ME59
2014B513 dedicated loop
Direct redundancy lost in 2010: Network reconfiguration is now necessary
After LS1 Activities66 kV power demand upgrade
Redundancy limitEHT4/EHT5
IEFC Workshop - François Duval 2309/03/2012
After LS1 Activities66 kV power demand upgrade
Present configuration
09/03/2012 24IEFC Workshop - François Duval
After LS1 Activities66 kV power demand upgrade
09/03/2012 25IEFC Workshop - François Duval
LS2 upgraded configuration
After LS1 Activities66 kV power demand upgrade
09/03/2012 26IEFC Workshop - François Duval
Redundant configurationAdvanced upgraded configuration
After LS1 Activities66 kV power demand upgrade
09/03/2012 27IEFC Workshop - François Duval
Ideal configuration
After LS1 Activities
IEFC Workshop - François Duval 2809/03/2012
Other activities
•Replacement of SPS substations
•North area consolidation & Upgrade
•PS distribution Upgrade (with LIU)
•West Area Upgrade (new projects)
Conclusions
IEFC Workshop - François Duval 2909/03/2012
The LS1 step cannot be missed by EL. Otherwise, most of the works will be postponed to LS2 (3 years)
The risk is a significant increase of failure rate due to:
• ageing electronics used in core protection relays• ageing devices (> 40 years)• loss of possible alternative configurations because of
increased power demands