logic programming in a construction planning workbench generation of a draft construction schedule...
TRANSCRIPT
![Page 1: LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING WORKBENCH Generation of a draft construction schedule from an IFC model (3D to 4D CAD)](https://reader035.vdocuments.us/reader035/viewer/2022070306/55165b635503469d698b4f74/html5/thumbnails/1.jpg)
LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING
WORKBENCHGeneration of a draft construction
schedule from an IFC model
(3D to 4D CAD)
![Page 2: LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING WORKBENCH Generation of a draft construction schedule from an IFC model (3D to 4D CAD)](https://reader035.vdocuments.us/reader035/viewer/2022070306/55165b635503469d698b4f74/html5/thumbnails/2.jpg)
A CRC-CI Research Project
• Research Project – • CRC-CI 2002-056-C:
Contract Planning Workbench
• It investigates the feasibility of generating a draft construction schedule from an IFC repository, that is an automatic 3D to 4D CAD process
• Project Team – • Fanny BoulaireA (CSIRO)
• John Crawford (CSIRO)
• Robin DrogumullerA (CSIRO)
• Cheryl McNamaraA (CSIRO)
• Gerardo TrinidadA (CSIRO)
• Guillermo Aranda-Mena (RMIT^)
• Rod Gameson (UNewcastle)
• Willy Sher (UNewcastle)
• Peter Ward (Unewcastle)
• David Marchant (Woods Bagot)
• Nick Windmeyer (John Holland)
![Page 3: LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING WORKBENCH Generation of a draft construction schedule from an IFC model (3D to 4D CAD)](https://reader035.vdocuments.us/reader035/viewer/2022070306/55165b635503469d698b4f74/html5/thumbnails/3.jpg)
3D to 4D Transformation
CPW
C – Identify building componentsA – Associate construction activitiesR – Estimate required resourcesS – Define sequence of activities
Building Information Model
Draft Construction Schedule
![Page 4: LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING WORKBENCH Generation of a draft construction schedule from an IFC model (3D to 4D CAD)](https://reader035.vdocuments.us/reader035/viewer/2022070306/55165b635503469d698b4f74/html5/thumbnails/4.jpg)
System Architecture
3d CAD
ExpressDM
CARS
MSProject
CommonPoint
CRC-IFCViewerCRC-ICT
Tools
LogicPrograms Schedule
CORE
4d simulation
view stages in theconstruction
generates aschedule
![Page 5: LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING WORKBENCH Generation of a draft construction schedule from an IFC model (3D to 4D CAD)](https://reader035.vdocuments.us/reader035/viewer/2022070306/55165b635503469d698b4f74/html5/thumbnails/5.jpg)
Logic Programming
• A declarative and relational style of programming based on first-order logic
• PROLOG - original logic programming based on Horn clauses
• A programmer writes a "database" of "facts“, e.g. human(“Gerry”) and "rules", e.g. mortal(X) :- human(X).
![Page 6: LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING WORKBENCH Generation of a draft construction schedule from an IFC model (3D to 4D CAD)](https://reader035.vdocuments.us/reader035/viewer/2022070306/55165b635503469d698b4f74/html5/thumbnails/6.jpg)
Simple Prolog Example
AB
C A & BD C
PrologEngine
A, BC A & B
C
CD C
D
A, B
C A & B
D C
------
A, B, C
C A & B
D C
-------
A, B, C, D
C A & B
D C
--------
No more new facts
![Page 7: LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING WORKBENCH Generation of a draft construction schedule from an IFC model (3D to 4D CAD)](https://reader035.vdocuments.us/reader035/viewer/2022070306/55165b635503469d698b4f74/html5/thumbnails/7.jpg)
Logic Programming in CPW
IF (X is a reinforced concrete beam) AND (Y is a reinforced concrete slab) AND (X is connected to Y)THEN (X and Y are constructed together)
A is a reinforced concrete beamB is a reinforced concrete slabA is connected to B
A and B are constructed together
![Page 8: LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING WORKBENCH Generation of a draft construction schedule from an IFC model (3D to 4D CAD)](https://reader035.vdocuments.us/reader035/viewer/2022070306/55165b635503469d698b4f74/html5/thumbnails/8.jpg)
Relationships Between Elements
• Connected: Column (C) is connected to beam (B)• Supports: Footing (F) supports column (C)• Constructed before: Footing (F) constructed before
column (C)• Constructed together: Slab (S) and beam (B) are
constructed together• Connected but not supported: Ground slab (G) is
connected to, but not supported by column (C)
![Page 9: LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING WORKBENCH Generation of a draft construction schedule from an IFC model (3D to 4D CAD)](https://reader035.vdocuments.us/reader035/viewer/2022070306/55165b635503469d698b4f74/html5/thumbnails/9.jpg)
Output of CPW
ID Name Duration Predecessors1 place reinforcement of columns 3.5 hrs 102 place formwork of columns 19.3 hrs 13 pour concrete of columns 2.5 hrs 24 wait for concrete of columns to cure 40 hrs 35 strip formwork of columns 9.5 hrs 4
…..11 wait for concrete of footings to cure 40 hrs 10
• List of building elements or components (C)• List of construction activities associated with the building components (A)• List of required resources (R)• Sequence logic between activities (S)
Table fragment listing construction activities and their precedence relations
![Page 10: LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING WORKBENCH Generation of a draft construction schedule from an IFC model (3D to 4D CAD)](https://reader035.vdocuments.us/reader035/viewer/2022070306/55165b635503469d698b4f74/html5/thumbnails/10.jpg)
Precedence Constraints
1
3
4
5
Start End
2
Duration:Task 1: 5 daysTask 2: 6 daysTask 3: 9 daysTask 4: 4 daysTask 5: 5 days
Predecessors(i) = {j | (j,i) Edges}Predecessors(4) = {1, 2}
Successor(i) = {j | (i,j) Edges}Successor(1) = {3, 4}
IF i Predecessors(j) THENStart(i) + Duration(i) Start(j)
Start(1) 0Start(2) 0Start(3) Start(1) + 5Start(4) Start(1) + 5Start(4) Start(2) + 6Start(5) Start(2) + 6
![Page 11: LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING WORKBENCH Generation of a draft construction schedule from an IFC model (3D to 4D CAD)](https://reader035.vdocuments.us/reader035/viewer/2022070306/55165b635503469d698b4f74/html5/thumbnails/11.jpg)
Tasks + Precedence = Schedule
Construction sequence when reinforced concrete columns, beams and slabs are erected monolithically:• column reinforcement• column formwork• scaffolding and formwork for beams and slabs • beam and slab reinforcement• column, beam and slab concrete
![Page 12: LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING WORKBENCH Generation of a draft construction schedule from an IFC model (3D to 4D CAD)](https://reader035.vdocuments.us/reader035/viewer/2022070306/55165b635503469d698b4f74/html5/thumbnails/12.jpg)
Resource Constraints
1
3
4
5
Start End
2
Resources Required:Task 1: 1 unit R1 + 5 units R2Task 2: 2 units R1 + 2 units R2Task 3: 2 units R1 + 4 units R2Task 4: 2 units R1 + 3 units R2Task 5: 3 units R1 + 2 units R2
Resources Available:5 units of R17 units of R2
At any given time, the amount of resources in used is less than or equal to the amount of resources available.
Task 1 and Task 2 can proceed concurrently, but Task 3, Task 4 and Task 5 can not proceed concurrently as required resources will exceed available resources
Duration:Task 1: 5 daysTask 2: 6 daysTask 3: 9 daysTask 4: 4 daysTask 5: 5 days
![Page 13: LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING WORKBENCH Generation of a draft construction schedule from an IFC model (3D to 4D CAD)](https://reader035.vdocuments.us/reader035/viewer/2022070306/55165b635503469d698b4f74/html5/thumbnails/13.jpg)
Another Output of CPWID Name Duration Predecessors Resources21 place formwork 3.9 hrs 5,14 carpenter[400%],labourer[400%]22 place reinforcement 0.7 hrs 16,21 steel tradesman[400%]23 pour concrete 0.9 hrs 17,22 concrete mixer,concrete tradesman[400%],labourer[400%],trowelling machine24 cure conrete 40 hrs 18,23 25 strip formwork 1.8 hrs 19,24 labourer[400%]
Prepared as an ODBC data source for MS Project (version 2003)
![Page 14: LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING WORKBENCH Generation of a draft construction schedule from an IFC model (3D to 4D CAD)](https://reader035.vdocuments.us/reader035/viewer/2022070306/55165b635503469d698b4f74/html5/thumbnails/14.jpg)
Simply a Graph
foundations
interior walls doors
chimney tiles
exterior walls
windows
roof
Building a simple house
![Page 15: LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING WORKBENCH Generation of a draft construction schedule from an IFC model (3D to 4D CAD)](https://reader035.vdocuments.us/reader035/viewer/2022070306/55165b635503469d698b4f74/html5/thumbnails/15.jpg)
Using Constraint ProgrammingB u ild in g a Ho u se
D o o rs2 d a ys
S tag e B
In te rio r W a lls4 d a ys
C h im n ey3 d a ys
S tag e D
S tag e E
T ile s3 d a ys
R o of2 d a ys
W in d o ws3 d a ys
S tag e C
E x te rio r W a lls3 d a ys
S tag e A
F o un d atio ns7 d a ys
S tag e ST
T T
T T
T T
T T
T T
T T
T T
T T
S
A S
B A
C A
D A
D C
E B
E D
E C
0
7
4
3
3
2
2
3
3
start
foundations
interior walls
exterior walls
chimney
roof
doors
tiles
windows
Start
A
B C
D
E
![Page 16: LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING WORKBENCH Generation of a draft construction schedule from an IFC model (3D to 4D CAD)](https://reader035.vdocuments.us/reader035/viewer/2022070306/55165b635503469d698b4f74/html5/thumbnails/16.jpg)
Constraint Logic Programming
• A programming framework based (like Prolog) on first-order logic with a constraint solver added
• CLP = LP + Constraint Solver
• Can be more efficient in certain problems such as scheduling, planning and resource allocation
![Page 17: LOGIC PROGRAMMING IN A CONSTRUCTION PLANNING WORKBENCH Generation of a draft construction schedule from an IFC model (3D to 4D CAD)](https://reader035.vdocuments.us/reader035/viewer/2022070306/55165b635503469d698b4f74/html5/thumbnails/17.jpg)
Thank You