load and renewable forecast in grid operations and planning: ercot experiences€¦ ·  ·...

19
IEEE T&D 2014 Load and Renewable Forecast in Grid Operations and Planning April 15 , 2014 Load and Renewable Forecast in Grid Operations and Planning: ERCOT Experiences

Upload: vuongthuan

Post on 21-May-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

IEEE T&D 2014

Load and Renewable Forecast in Grid Operations and

Planning

April 15 , 2014

Load and Renewable Forecast in

Grid Operations and Planning:

ERCOT Experiences

2

Table of Contents

– Load and Wind resources in ERCOT

– Mid-term Load Forecast

– Short-term Wind Potential Forecast and ERCOT Large Ramp

Alert System

– Conclusions and Future Work

• Acronyms for this presentation:

– WGR: Wind-powered Generation Resource

– AS: Ancillary Service

– STWPF: Short-term Wind Power Forecast

– COP: Current Operating Plan

– RUC: Reliability Unit Commitment

– ELRAS: ERCOT Large Ramp Alert System

April 15, 2014

3

Annual Energy & Peak Demand (2003-2012)

April 15, 2014

4

Installed Wind Generation in ERCOT

April 15, 2014

5

Wind Resource

April 15, 2014

6

Correlation between Wind and Load

April 15, 2014

0

2000

4000

6000

8000

10000

12000

0

10000

20000

30000

40000

50000

60000

70000

80000

load wind

7

Performance of Day-ahead Mid-term Load Forecast

April 15, 2014

0.00%

0.50%

1.00%

1.50%

2.00%

2.50%

3.00%

3.50%

4.00%

Day-ahead load forecast error in 2013 (MAPE)

8

Importance of Wind Forecast

“the seamless integration of wind plant output forecasting – into both

power market operations and utility control room operations – is a

critical next step in accommodating large penetrations of wind energy in

power systems”

• DOE, 20% Wind Energy by 2030 (Washington, DC: DOE, 2008),

http://www.20percentwind.org/20p.aspx?page=Report.

April 15, 2014

9

Challenges in Wind Forecast

• Relatively concentrated geographic region for wind installation (lack

of spatial diversity)

• Texas weather can change rapidly

• Severe changes in wind generation output caused by different

types of extreme weather (large wind ramps)

• Frontal system, trough, or dry line/Thunderstorms/Low-level jets/Weakening

pressure gradients/Strengthening pressure gradients

• There is an approximation of hypothetical wind speed-power curve

to the real one

Hypothetical

Power Curve Actual Wind Farm

Power

The steep part of the power curve from 4-12 m/s is where power increases strongly

with speed.

April 15, 2014

10

ERCOT Short-term Wind Power Forecast

April 15, 2014

11

Forecast vs. Observed Time Series – November 2012 (Low

MAE month despite high wind variability)

April 15, 2014

12

Performance of Day-ahead Wind Forecast

0.0%

2.0%

4.0%

6.0%

8.0%

10.0%

12.0%

Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13

Mean Absolute Percent Error (MAPE) of Installed Capacity (day-ahead wind forecast)

2013

Annual

MAPE for

day-ahead

wind

forecast

=8.3%

April 15, 2014

13

Performance of Hour-ahead Wind Forecast

0.0%

1.0%

2.0%

3.0%

4.0%

5.0%

6.0%

7.0%

8.0%

Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13

Mean Absolute Percent Error (MAPE) of Installed Capacity (hour-ahead wind forecast)

2013

Annual

MAPE for

hour-ahead

wind

forecast

=5.3%

April 15, 2014

14

Wind Forecast Used for Scheduling

• WGRs must keep the COP (current operating plan) up to date to reflect latest wind

forecast and changes in capacity or resource status; and DAM (day-ahead market)

and RUC (reliability unit commitment) use the COP for the WGR in their scheduling.

April 15, 2014

15

ERCOT Large Ramp Alert System

16

ERCOT Large Ramp Alert System

• The main focus of ELRAS is to provide the probabilities of Wind

Power ramp events of various MW changes over various time frames

– The far right graph shows that there is a 30% chance of the wind output

changing by 2000 MW or more between 18:00 and 21:00

– Information is provided for both the system and region levels

U

P

April 15, 2014

17

• As the Operators enter the Operating Day, they are able to execute

hourly RUC studies

– The Operators would like to wait as close to real-time as possible to commit a

Resource

• The Operator is also able to begin using the ERCOT Large Ramp Alert

System (ELRAS)

– ELRAS provides probabilistic forecast information for the next 6 hours

– The displays include animated graphics of weather conditions

Market and Operations

April 15, 2014

18

Conclusions and Future Work

• Continue to improve the performance of load forecast by a better

understanding of drivers behind the energy consumption

• With ERCOT’s improved capability to perform Hourly RUC

studies and more easily commit Resources within the Operating

Day, the ISO and Market Participants will likely put more focus on

shorter-term wind power forecasting (1-6 hours out)

– It is generally best to wait closer to real-time in order to have a more

accurate picture of system conditions before committing Resources

• Probabilistic forecast information will very likely play a key role in

Grid Operations in the near future

– There is still work to be done in the incorporation of the probabilistic

forecasts in the control room

April 15, 2014

19

Questions

Pengwei Du

Senior Operation Engineer-Renewable

Integration, Ph.D.

The Electric Reliability Council of Texas

(o) 512-248-6453

(c) 510-366-1875

[email protected]

April 15, 2014