load and renewable forecast in grid operations and planning: ercot experiences€¦ · ·...
TRANSCRIPT
IEEE T&D 2014
Load and Renewable Forecast in Grid Operations and
Planning
April 15 , 2014
Load and Renewable Forecast in
Grid Operations and Planning:
ERCOT Experiences
2
Table of Contents
– Load and Wind resources in ERCOT
– Mid-term Load Forecast
– Short-term Wind Potential Forecast and ERCOT Large Ramp
Alert System
– Conclusions and Future Work
• Acronyms for this presentation:
– WGR: Wind-powered Generation Resource
– AS: Ancillary Service
– STWPF: Short-term Wind Power Forecast
– COP: Current Operating Plan
– RUC: Reliability Unit Commitment
– ELRAS: ERCOT Large Ramp Alert System
April 15, 2014
6
Correlation between Wind and Load
April 15, 2014
0
2000
4000
6000
8000
10000
12000
0
10000
20000
30000
40000
50000
60000
70000
80000
load wind
7
Performance of Day-ahead Mid-term Load Forecast
April 15, 2014
0.00%
0.50%
1.00%
1.50%
2.00%
2.50%
3.00%
3.50%
4.00%
Day-ahead load forecast error in 2013 (MAPE)
8
Importance of Wind Forecast
“the seamless integration of wind plant output forecasting – into both
power market operations and utility control room operations – is a
critical next step in accommodating large penetrations of wind energy in
power systems”
• DOE, 20% Wind Energy by 2030 (Washington, DC: DOE, 2008),
http://www.20percentwind.org/20p.aspx?page=Report.
April 15, 2014
9
Challenges in Wind Forecast
• Relatively concentrated geographic region for wind installation (lack
of spatial diversity)
• Texas weather can change rapidly
• Severe changes in wind generation output caused by different
types of extreme weather (large wind ramps)
• Frontal system, trough, or dry line/Thunderstorms/Low-level jets/Weakening
pressure gradients/Strengthening pressure gradients
• There is an approximation of hypothetical wind speed-power curve
to the real one
Hypothetical
Power Curve Actual Wind Farm
Power
The steep part of the power curve from 4-12 m/s is where power increases strongly
with speed.
April 15, 2014
11
Forecast vs. Observed Time Series – November 2012 (Low
MAE month despite high wind variability)
April 15, 2014
12
Performance of Day-ahead Wind Forecast
0.0%
2.0%
4.0%
6.0%
8.0%
10.0%
12.0%
Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13
Mean Absolute Percent Error (MAPE) of Installed Capacity (day-ahead wind forecast)
2013
Annual
MAPE for
day-ahead
wind
forecast
=8.3%
April 15, 2014
13
Performance of Hour-ahead Wind Forecast
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
6.0%
7.0%
8.0%
Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13
Mean Absolute Percent Error (MAPE) of Installed Capacity (hour-ahead wind forecast)
2013
Annual
MAPE for
hour-ahead
wind
forecast
=5.3%
April 15, 2014
14
Wind Forecast Used for Scheduling
• WGRs must keep the COP (current operating plan) up to date to reflect latest wind
forecast and changes in capacity or resource status; and DAM (day-ahead market)
and RUC (reliability unit commitment) use the COP for the WGR in their scheduling.
April 15, 2014
16
ERCOT Large Ramp Alert System
• The main focus of ELRAS is to provide the probabilities of Wind
Power ramp events of various MW changes over various time frames
– The far right graph shows that there is a 30% chance of the wind output
changing by 2000 MW or more between 18:00 and 21:00
– Information is provided for both the system and region levels
U
P
April 15, 2014
17
• As the Operators enter the Operating Day, they are able to execute
hourly RUC studies
– The Operators would like to wait as close to real-time as possible to commit a
Resource
• The Operator is also able to begin using the ERCOT Large Ramp Alert
System (ELRAS)
– ELRAS provides probabilistic forecast information for the next 6 hours
– The displays include animated graphics of weather conditions
Market and Operations
April 15, 2014
18
Conclusions and Future Work
• Continue to improve the performance of load forecast by a better
understanding of drivers behind the energy consumption
• With ERCOT’s improved capability to perform Hourly RUC
studies and more easily commit Resources within the Operating
Day, the ISO and Market Participants will likely put more focus on
shorter-term wind power forecasting (1-6 hours out)
– It is generally best to wait closer to real-time in order to have a more
accurate picture of system conditions before committing Resources
• Probabilistic forecast information will very likely play a key role in
Grid Operations in the near future
– There is still work to be done in the incorporation of the probabilistic
forecasts in the control room
April 15, 2014
19
Questions
Pengwei Du
Senior Operation Engineer-Renewable
Integration, Ph.D.
The Electric Reliability Council of Texas
(o) 512-248-6453
(c) 510-366-1875
April 15, 2014