lkh quadrant graz 2020 urban development and mobility management [ mobility contract ]
DESCRIPTION
LKH Quadrant Graz 2020 Urban Development and Mobility Management [ Mobility Contract ] . Based on content provided by ZIS+P . Content. Facts Initial Situation Objective: Scenario ‘Change 2020’ Mobility Contract Process, Next Steps. Based on content provided by ZIS+P . - PowerPoint PPT PresentationTRANSCRIPT
1
ECOMM Graz 2010 Martin Kroißenbrunner
LKH Quadrant Graz 2020
Urban Development and Mobility Management
[ Mobility Contract ]
Based on content provided by ZIS+P
2
ECOMM Graz 2010 Martin Kroißenbrunner
• Facts• Initial Situation• Objective: Scenario ‘Change 2020’• Mobility Contract• Process, Next Steps
Content
Based on content provided by ZIS+P
3
ECOMM Graz 2010 Martin Kroißenbrunner
City of Graz - Facts
• Area of 127 km²• ~ 260,000 inhabitants • ~ 121,000 employees• ~ 70,000 daily commuters
4
ECOMM Graz 2010 Martin Kroißenbrunner
City of Graz - Facts
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1982 1988 1991 1998 2004 2008
31.0% 25.3% 23.6% 21.3% 19.3% 18,8%
8.3%11.7% 12.5% 14.2% 14.1% 16.1%
33.8% 37.2% 37.3% 37.5% 38.2% 35.7%
8.8% 8.2% 8.7% 8.7% 9.1% 9.5%
18.1% 17.6% 17.9% 18.2% 19.3% 19.9%
Mod
al s
hare
%
PT
Private car as passenger
Private car as driver
Bycicle
Pedestrian
Modal Share
5
ECOMM Graz 2010 Martin Kroißenbrunner
CityCenter
Hospital
District
Involved main partners:
• City of Graz
• Province of Styria (transport)
• Regional Hospital Management
• Medical University Graz
Mobility Contract – Initial Situation
6
ECOMM Graz 2010 Martin Kroißenbrunner
• Hospital District of Graz with 12,000 employees, visitors and patients
• Capacity of the local transport network at its limit
Plans for a new Medical University and enlargement of the Hospital District
In the future: +4,000 persons/day (employees, students, visitors, patients)
Mobility Contract – Initial Situation
7
ECOMM Graz 2010 Martin Kroißenbrunner
Objective: Scenario ‘Change 2020’
•2.100 •2.500 •3.500•2.300
•3.200•4.100
•12.400
•16.800 •13.300
•1.900
•2.700•2.200•5.300
•6.900•8.300
•-
•5.000
•10.000
•15.000
•20.000
•25.000
•30.000
•35.000
•2004 •Trend 2020 •‘Change"•2020
•Year/Scenario
• Num
ber o
f trip
s pe
r 13
hour
s
•Public transport
•Private car as driver
•Private car as passenger
•Bicycle
•Pedestrian+7%+35%
Number of trips/workday (Hospital District)
Goal to be achieved: private car traffic
from 60% => 49%
8
ECOMM Graz 2010 Martin Kroißenbrunner
• Four partners with defined- responsibilities- financing- time schedules
• ‘Broader’ Mobility Management approach to enable city development in an area where the transport system is at its limit
• Private contract between key partners in accordance with the approval of the land use plan / building permission process
• Obligation of the contract partners for setting defined measures
Mobility Contract – Principles
9
ECOMM Graz 2010 Martin Kroißenbrunner
City of Graz
Mob
ility
Con
trac
t
Province of Styria, Transport
Regional Hospital Management (KAGes)
Medical University Graz (MUG)
Mobility Contract – The Partners
10
ECOMM Graz 2010 Martin Kroißenbrunner
Overview: Infrastructural Measures
11
ECOMM Graz 2010 Martin Kroißenbrunner
Mobility ContractFour Fields
Mob
ility
Con
trac
t
Mobility Management and Organisation• Mobility management - Implementation• Job ticket,...• Limitation of parking (no. of parking lots)• Limitation of trips by car • Project management etc.
Measures Pedestrians and Cycling• Accessibility and network for pedestrians • Accessibility and network for cyclists• Cycle parking • Elevators etc.
Measures Public Transport• Tram line extension • Improved urban and regional bus scheme• Internal bus shuttle • Improved accessibility p.t. stations–hospital
etc.
Measures Car Traffic• Accessibility in cases of emergency• Adaptation of road network/capacity• Limitation of parking (no. of parking lots)• Limitation of trips by car
12
ECOMM Graz 2010 Martin Kroißenbrunner
Example: Measures PT (Time Schedule)
Schedule PT
0 12 24 36 48 60 72 84 96 108
Extension of tram line 7 (PT1)Additional trams to the Hospital (PT2)
Bus lane on Hilmteichstraße (PT3A)
Bus lane on Riesstraße (PT3B)Bus lane on Elisabethstraße (PT3C)
Re-organisation and densification of city bus lines (PT4)
Re-organisation of Hospital-internal City bus line(PT5)Densification of regional bus lines(PT6)
Setting-up Park-and-Ride parking lots (PT7)Utilisation of the Park-and-Ride parking lot Fölling (PT8)
Parking lots for participants of carpools (PT9)Taxi stands (PT10)
Attractive access (PT1)Busstops in the area of Riesplatz and Leonhardplatz (PT12)
MUG KindergartenMUG Modul e1MUG Module 2
Dental clinicSupply centre incl. garage
Surgical ward and blood bank
Months
PreparationPreliminary decisionInterim phasePlanningSubmission to committeesImplementationCompletion of buildingsCompletion of buildingsCompletion of buildings
1/1/2010 1/1/2011 1/1/20121/1/2013 1/1/2014 1/1/2015 1/1/20161/1/2017 1/1/20191/1/2018
13
ECOMM Graz 2010 Martin Kroißenbrunner
• 43 Measures• Approx. €16 – 20m investment• Clear responsibility, detailed time schedules• Controlling of implementation• Evaluation
Crucial measures: • Limitation of parking lots• Limitation of trips by car
Crucial points of contract (negotiations):• Sanctions, financing measures
Mobility ContractContents
14
ECOMM Graz 2010 Martin Kroißenbrunner
Process, Next Steps
• Negotiations: start 8 June 2010
• Mobility contract signed by all 4 partners in June 2010
• Agreement by the authority to land use plan, new buildings, new functions (June – September 2010)
• Step by step Mobility Management, infrastructure and new buildings/functions 2011 – 2020
• Project management Mobility Management
• Annual evaluation of results, actual development – objective ‘change‘ 2020
15
ECOMM Graz 2010 Martin Kroißenbrunner
Thank you for your attention!
City of Graz – Dpt. for Traffic PlanningMartin Kroißenbrunner
Europaplatz 20, 7th floor, A - 8011 Graz
Tel.: +43/316/872-2881 Fax.: +43/316/872-2889
e-mail: [email protected]
www.graz.at