© 2014 HDR, Inc., all rights reserved. CMAA Presentation April 19, 2017 Little Patuxent WRP 8 th Addition - Biosolids Processing Facilities Improvements

Upload: dinhcong

Post on 06-Feb-2018

217 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

© 2014 HDR, Inc., all rights reserved.

CMAA Presentation April 19, 2017

Little Patuxent WRP 8th Addition - Biosolids Processing Facilities Improvements

Page 2: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Joshua Gliptis, P.E.

Howard County Bureau of Utilities

Project Manager

Brian Balchunas, P.E., BCEE

HDR

Project Manager

David Hill, DBIA

Clark Construction

Construction Executive

Introductions

Page 3: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Project purpose, background

o Existing Treatment Plant and Processes

o Master Plan

o PER

Choosing CMAR Delivery

Selection Process

CMAR Mechanics and Results

o Design Collaboration and Innovation

o GMP Development

o Collaboration

o Project Scope Refined

Final Design

Current Project Status

Agenda

Page 4: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Project Objective: Design and construct a reliable, cost-effective, and

socially responsible treatment facility resulting in

beneficial use of LPWRP biosolids in Maryland, for a

changing and unpredictable regulatory environment.

Little Patuxent WRP Mission Statement: Provide environmentally responsible, reliable and cost

effective water reclamation services to Howard County.

Page 5: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Project Purpose and Background

Page 6: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Existing Little Patuxent WRP

Page 7: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

RDP advanced alkaline stabilization process for Class A EQ biosolids (dewatered cake)

Existing LPWRP Solids Process

Centrifuge

Dewatering

Primary

Clarifiers

To Land

Application

Secondary

Clarifiers

Gravity

Thickener Solids

Screening

Thickened

Primary Solids

Storage

DAF

Thickeners

RDP

Process

Lime

Thickened

WAS Storage

Heat

Page 8: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Develop a Biosolids Master Plan that provides a framework for reliable,

cost-effective, and socially responsible treatment and beneficial use of

LPWRP biosolids in a changing and unpredictable regulatory

environment.

Evolving regulations for agricultural land application

o Winter land application ban

o Phosphorus Management Tool

More versatile biosolids product desired (i.e., useable in various markets)

Biosolids volume reduction

Workplace environment challenges with corrosive and dusty lime stabilization process

2013 Biosolids Master Planning

Page 9: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Versatile Class A EQ product, multiple end-uses

Volume reduction

Relative cost

Reliability

Manageable process complexity

Greatly improved work environment

Reduced chemical costs (no lime!)

Master Planning Recommendation

Anaerobic Digestion Heat Drying Dewatering

Class A Biosolids

Replace RDP with anaerobic digestion and heat drying

Page 10: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Solids thickening and storage improvements

Digester configuration

o Repurpose two existing pretreatment reactors,

add third new digester

o Risk: Constructabililty issues and site impacts

Additional nutrient management

o P: Struvite control with chemical addition

o N: Centrate treatment - Deammonification

o Risk: relatively new technologies and limited

vendors

Dryer options – rotary drum or belt

o Belt dryers selected – less complex, lower

operations and maintenance demands

o Risk: relatively new and nearly unprecedented

size of units; Site constraints

2014 Preliminary Engineering Report – Bridging Document

Page 11: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Choosing Delivery by Construction Manager at

Risk (CMAR)

Page 12: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Complexity of Project

o Maintenance of Plant Operations

o Site Constraints

o Innovative technology selection and procurement

Speed in delivery

Manage Risk

Eliminate Exhaustive/Defensive Engineering

Collaboration

o Selection of most qualified team

o Selection of key equipment and vendors

Price Certainty

o Estimates done by Contractor at each milestone

o Guaranteed Maximum Price established (GMP)

Schedule Certainty

CMAR Delivery – Why Do It? What are the Benefits?

Page 13: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Howard County Selection Process

Page 14: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Both follow Howard County’s Quality Based Selection process

o Expressions of Interest

o Technical Proposals (Top 3-4)

o Interviews

o Consider Compensation for Proposals and Interviews

County develops solicitation for Engineer

o Issued summer 2015

o Under contract October, 2015

County and Engineer (acting as Owner’s Rep) Develop Solicitation for CMAR

o Issued late 2015

o Under contract March 2016

CMAR Contracts

o Pre-construction – modeled after County’s professional services agreements

o Construction – modeled after County’s construction agreements

o Incorporated lessons learned from previous CMAR and DB agreements

o EJCDC and DBIA reference documents as resources

Engineer and CMAR Solicitations

Page 15: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

CMAR Delivery Mechanics and Results

Page 16: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Review, comment on Preliminary (30%) and Intermediate (60%) design submittals

Other CMAR responsibilities

o Early procurement of dryer systems and other major equipment items

o Value engineering proposals

o Constructability reviews

o Site utilization plan

o Maintenance of plant operations plan

o Schedule

• Key Milestones

» October 2018 Start of Phase I Processes

» Working backwards leads to Early and On-Time Delivery of Final Design and GMP1 NTP

o Procurement plan

o Site Specific Safety Plan

CMAR Involved from Early Design Stages

Page 17: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Estimates completed on each design submittal

o Final GMP consistent with original 30% estimate

Competitive bids for each of the major bid packages

Joint interview and review of bidding companies (Owner, Engineer, CMAR)

o Risk assessment

o Scope verification

o Quality

o Understanding of delivery process

Meet to review Owner Allowances and CMAR Contingencies

o Place risk where it is best controlled

Negotiated GMP within three weeks of receiving bids

NTP for Phase 1 – February, 2017

GMP Development

Page 18: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Workshops

o Identifies the key decisions needed

o Facilitates decisions for the owner

o Opportunity for top and mid level team

members to share ideas

Partnering

o Promotes High Level PM Discussions

o Venue for voicing concerns or highlighting

positives

o Involve key sub-contractors and vendors

Value Engineering

BIM

Outreach

Envision

Collaborative Approach…

Page 19: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Right scope

o Digester configuration and construction

methods

o Phosphorus removal

o Equipment selection

Tough decisions

o Split Substation and MCC locations (PH1

Design Revision)

o Relocate dryer building

o Improved operations and site utilization

… Leads to Results

Page 20: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

From where we started design…

PLANT

EFFLUENT

LINE

DIGESTER

NO. 3

PRODUCT

STORAGE AND

TRUCK LOADING

DIGESTER

NO. 1

DIGESTER

NO. 2

WETLAND

BUFFER

ADMINISTRATION

BUILDING

ADDITION

CENTRATE

TREATMENT

DIGESTED

SOLIDS

STORAGE

WAS

THICKENING

MODS.

DEWATERING

AND DRYING

BUILDING

ODOR

CONTROL

BIOFILTERS

DIGESTER GAS

FLARE NO. 2DIGESTER

GAS

TREATMENT

DIGESTER

BUILDING

NO. 1

BOILER

BUILDING

REPLACE

SUBSTATION

PS-2

STREAM BUFFER

CENTRATE

EQUALIZATION

DIGESTER

BUILDING

NO. 2

MODIFIED

GARAGE

Page 21: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

… through collaboration the process evolved …

PRODUCT

STORAGE AND

TRUCK LOADING

DIGESTER

NO. 1

DIGESTER

NO. 3

CENTRATE

TREATMENT

WAS

THICKENING

MODS.

DEWATERING

AND DRYING

BUILDING

ODOR

CONTROL

BIOFILTERS

BIOGAS FLARE

DIGESTER

GAS

TREATMENT

REPLACE

SUBSTATION

PS-2

DIGESTER

NO. 2

NEW DIGESTER

CONTROL

BUILDING

THICKENED

SOLIDS

STORAGE

1

2

GRAVITY

THICKENERS

DIGESTED

SOLIDS

STORAGE

PRIMARY

SOLIDS

SCREENING

PHOSPHORUS

PRECIP.

PHASE 2

PHASE 1

Page 22: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

… to where we are today

Page 23: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Finalized digester configuration

o Three new digesters for improved performance, operations

Phosphorus precipitation for struvite management

Deammonification process selection for centrate treatment

Belt dryer pre-selection

2016-2017 Final Design

Page 24: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

LPWRP Biosolids Improvements

Centrifuge

Dewatering

Primary

Clarifiers

To Customer

Anaerobic

Digesters

Belt Dryer

Secondary

Clarifiers

GBT

Gravity

Thickener

Digested

Solids Storage

Product

Storage

Solids

Screening

Thickened

Solids

Storage

Phosphorus

Precipitation

Centrate

Treatment

(to plant

drain)

Page 25: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Project Status

Page 26: Little Patuxent WRP 8th Addition - Biosolids Processing ... · PDF fileHDR Project Manager David Hill, DBIA Clark Construction Construction Executive Introductions ... o Issued summer

Phase 1

o NTP – February 2017

o Digester construction to begin – June 2017

o Digester start-up – July 2018

o Remainder of construction – through early 2019

Phase 2

o Preliminary Design submittal – April 2017

o Intermediate Design submittal – July 2017

o GMP Contract Documents – September 2017

o GMP negotiations – through December 2017

o Construction – to mid 2020

Project Status and Schedule