liquefied natural gas terminal in lithuania sea expert group... · komentaras, manau čia total...
TRANSCRIPT
2011 m. balandžio 6 d.
Liquefied Natural Gas Terminal in Lithuania April, 2013
Klaipėdos Nafta 2
Infrastructure Gas trading
72.3% 10.2% 17.5%
LNG Terminal project Oil transshipment terminal
appointed by the Government of Lithuania on July 10, 2010
for LNG Terminal Project implementation
The Republic of Lithuania
(represented by the Ministry of Energy)
UAB “Achemos grupė”
Free float on Nasdaq OMX
Vilnius
LNG Terminal Project -Ownership
Klaipėdos Nafta 3
LNG Terminal Project - Background
Major objectives of the National Energy Strategy of Lithuania assigned to LNG terminal:
• Supply of natural gas will be diversified and the country will not be dependent on a single gas
supplier,
• Lithuania on its own will be able to cover emergency demand for natural gas.
• The country will gain access to international gas markets.
• Preconditions to form both national and regional gas markets in Lithuania will be created with the
possibility in the future to supply gas to neighboring countries.
• LNG terminal will start operation on December 2014.
The necessity to have an alternative energy source appear:
• Following EU requirement (S994/2010 ES ) to ensure alternative gas supply from 3rd
December 2014 – to secure an alternative gas supply source,
• After shutdown of Ignalina Nuclear Power Plant on 31 December 2009, Lithuania had
became even more dependent on natural gas import,
• As an outcome of above gas is being supplied to the country by single pipeline from
Russia (Gazprom) through the Republic of Belarus,
Klaipėdos Nafta 4
Development of Gas Transmission System of Lithuania
Klaipėdos Nafta 5
LNG terminal future core activities
LNG terminal infrastructure LNG terminal gas trading
LNG storage
Regasification
NG supply to gas grid
LNG procurement
NG sales
Klaipėdos Nafta 6
LNG terminal infrastructure scope
Floating Storage and Regasification Unit (FSRU)
LNG storage capacity:
170.000 m3
Regasification capacity:
~11 mmcm/day
Leased from Höegh LNG for
10 years with a purchase
option
Gas pipelines
18 km long and 700 mm wide
gas pipeline that connects
FSRU to the gas grid;
Includes 3 km of horizontal
directional drilling under the
lagoon
Jetty
Offshore jetty facility
located in the southern part of
the Port of Klaipėda
Jetty
High pressure gas pipelines
High pressure
loading arm
FSRU LNG carrier
18 km
Gas metering
station
Klaipėdos Nafta 7
LNG Terminal Main Parameters
TECHNOLOGY Floating Storage Regasification
Unit (FSRU).
LOCATION Southern part of Klaipeda
seaport, near Pig Back island
FSRU SUPPLIER Norwegian company Hoegh LNG
STORAGE
CAPACITY 170 000 m3
LOADING
CAPACITY
9000 m3/h of LNG.
Ship-to-ship transfer through
flexible hoses
ANNUAL
CAPACITY
2-3 bcma of regasified NG
up to 11 mln m3 per day
PIPELINE
THROUGHPUT
6 mln. m3 per day with further
expansion planned
CONFIDENTIAL
8 8
Baltic
sea
Pig’s Back
island
Jetty and
FSRU
Gas pipeline
Klaipėdos Nafta 9
LNG terminal high pressure gas pipeline
Klaipėdos Nafta 10
LNG Project Plan
2013
Territory Planning, Special plan, detail plan (SEA, Right of the
way for pipeline, jetty area)
2011 2012 2014
Port Dredging
(Klaipeda Port
Authority)
Pipeline Design
Construction of FSRU Vessel and Delivery to Klaipėda Port Procurement of
FSRU Vessel
Laying of Pipeline Jurbarkas – Klaipėda (Lietuvos Dujos)
LNG Procurement
EIA report, public
consultations,
approval
EIA screening, technical
design of dredging area
Conception, receipt of permits, safety and navigation issues, project management, construction supervision
(Lead Advisor)
2015
Commissioning
Works of
TERMINAL
Pre-Project Study of
Pipeline Permit for pipeline construction,
Pipeline construction
Permit for jetty construction,
Cconstruction of Jetty
Concept of LNG terminal,
“Expansion plan, SEA
Jetty Design
Finalizing safety report according Seveso II Risk and Safety Assessment, QRA, 1
issue of safety report
EIA program
Permit according directive 2010/75/EU
requirements
Pre-Project Study of
Jetty
Pipeline EPC
procurement
Pipeline EPC
procurement
18 months
4months 5 months
totally 38 months
Klaipėdos Nafta 11
LNG Project permitting Plan (Pre-permitting, 18 month) New Regulation for trans-European energy infrastructure (TEN-E Guidelines)
In July of 2010 Government of Lithuania by resolution appointed
“Klaipedos nafta” to implement LNG terminal project;
In November of 2010 Interdepartmental Working group formed by the order
of Minister of Energy issued concept of LNG terminal.
In May of 2011 “Klaipedos nafta” started “Expansion plan” and Strategic
environmental assessment (SEA) of LNG project:
Official announcement for public was issued;
3 alternative locations were selected for LNG terminal;
Presentation of LNG terminal concept and scoping of SEA with 18 authorities and
institutions;
Klaipėdos Nafta 12
LNG Project permitting Plan (Pre-permitting, 18 month) New Regulation for trans-European energy infrastructure (TEN-E Guidelines)
In September of 2011 “Expansion plan” and SEA reports were issued:
The main parameters of LNG terminal were defined;
Environmental and social economic aspects were investigated (air, water, coastal
issues, flora, fauna, soil, geology, landscape, protected areas, public health,
cultural heritages sites, land usage);
Navigation study and Concept risk assessment report were prepared;
LNG terminal plan was coordinated with port future expansion study;
2 locations of LNG terminal for further investigation were recommended;
Pipeline routes were defined;
Detail project implementation schedule was prepared;
In October public consultation in 2 municipalities were held;
In November coordination of Expansion plan and SEA report with
authorities and institutions;
In December “Expansion plan” was approved by ministry of Energy;
Klaipėdos Nafta 13
LNG Project permitting Plan (Pre-application, 11 months) New Regulation for trans-European energy infrastructure (TEN-E Guidelines)
EIA program (4 month):
Preparation of the EIA program (November – December 2011);
Publicity measures for the EIA program, December 2011;
Notification submission to the Republic of Latvia, January 2012;
Obtaining agreements on EIA program from authorities, January-
February 2012;
Obtaining agreement on EIA program from Competent authority,
February 2012; Manau, kad prie pre-application turi būti nurodytas bendras laikas , t. y. 11 mėn, taip pat ir 10 skaidruolėje reikėtų pateikti bendrą laiką.
Klaipėdos Nafta 14
LNG Project permitting Plan (Pre-application, 11 months) New Regulation for trans-European energy infrastructure (TEN-E Guidelines)
EIA report (6 months):
Basic design of the pipeline, December 2011 – March 2012;
Basic design of the Jetty, October 2011 – March 2012;
Contract with Hoegh LNG, detail design and parameters of the FSRU,
March 2012;
Risk assessment input to EIA report from Safety report according
Seveso II requirements (quantitative risk assessment, safety zones,
HAZID, risk management plan, ship collision analysis), December 2011 –
April 2012;
Preparation of EIA report, December 2011 – May 2012;
Publicity of EIA report, end of May 2012;
EIA report submission to the republic of Latvia, June 2012 Komerntaras: Kadangi Saugos ataskaita rengta PAV metu, o kitos nebuvo ir greičiausiai nebus, todėl ir schemoje ji turi būti aiškiai įterpta prie PAV atasakitos pre-
application stadijoje.
Klaipėdos Nafta 15
LNG Project permitting Plan (Pre-application, 11 months) New Regulation for trans-European energy infrastructure (TEN-E Guidelines)
Public hearings, 4 municipalities, June 2012;
EIA report public consultations in Latvia, 1 municipality, July 2012;
Obtaining agreements from authorities, August - September 2012;
Transboundary consultations with the republic of Latvia under the Espoo
Convention regarding EIA report in Vilnius, September 2012
Obtaining agreement on EIA report from competent authority and adoption
of decision on EIA alternatives, end of October 2012
Total permitting period: 28 months Komentaras, manau čia total permiting period reikia rašyti totlal pre-application period ir neskaičiuoti laiko praleisto rengiant plėtros planą ir jo SPAV. Nes tai yra pre-
permiting stadija, kurios nereglamentuoja TEN-E reglamentas.
Klaipėdos Nafta 16
LNG Project permitting Plan (territory planning, 18 months) New Regulation for trans-European energy infrastructure (TEN-E Guidelines)
Report of special plan, December 2012;
Financial offers for land owners, January 2013;
Public consultations of special plan report, March 2013;
Obtaining agreement on Special plan report from authorities, April – May
2013;
Negotiation with land owners, agreement on right of the way, February -
June 2013;
Approval of special plan by the ministry of Energy, June 2013;
Administrate act for the right of the way, July 2013;
Total permitting period with territory planning: 38 months Komentaras. Čia irgi bendrą laiką reikia rašyti mėn be plėtros plano.
Klaipėdos Nafta 17
Advantages of Streamlining Environmental Assessments of
Projects of Common Interest (PCIs)
A “one-stop-shop” approach for permitting;
Pre-application and Permitting periods have time limit;
More precise planning of PCIs and avoid delays in schedule;
Clear procedures and sequence of permitting;
A transparent process of public consultation and stakeholders.
Klaipėdos Nafta 18