lipke thetcpiindicator
TRANSCRIPT
-
8/20/2019 Lipke TheTCPIIndicator
1/31
The To Complete
er ormance n ex…
performance TCPI vs CPIWalt Lipke
PMI - Oklahoma City Chapter
1.0
1.1
1.2
1.3
I n d e x
TCPI CPI Threshold
+1 405 364 [email protected]
www.earnedschedule.com
0.7
0.8
0.9
0.0 0.2 0.4 0.6 0.8 1.0
Fraction Complete
-
8/20/2019 Lipke TheTCPIIndicator
2/31
The To Complete Performance Index (TCPI)from Earned Value Management describes theperformance efficiency required to achieve acost objective.
Beyond its usual application, the TCPI indicator
performance to effect a project recovery. Thisvirtually unknown aspect is the focus of this
KPM 2009 - TulsaCopyright © Lipke 20092
-
8/20/2019 Lipke TheTCPIIndicator
3/31
Introduction
Evaluation of EAC
Application to Project Recovery
Evaluating the Recovery Strategy Schedule Analysis
Summary & Conclusions
KPM 2009 - TulsaCopyright © Lipke 20093
-
8/20/2019 Lipke TheTCPIIndicator
4/31
EVM provides a method of describing projectperformance numerically …a significant
status
The most often used and best understoodindicator from EVM is the Cost PerformanceIndex, CPI = EV / AC
achieving the accomplishment with respect tothe cost investment made
KPM 2009 - TulsaCopyright © Lipke 20094
-
8/20/2019 Lipke TheTCPIIndicator
5/31
Whereas CPI describes the past, TCPI providesinformation about the future
TCPI is defined as the work remainin to be accomplished divided by the amount of unspent
funding where TC = Target Cost or Desired Cost Outcome
What does TCPI tell us?
The index value describes the costperformance efficiency required for theremainder of the project to achieve the desired
KPM 2009 - TulsaCopyright © Lipke 20095
final cost
-
8/20/2019 Lipke TheTCPIIndicator
6/31
Traditionally, TCPI is used by customers oroversight organizations to assess thereasonableness of an estimated final cost orEstimate at Completion (EAC)
For this application,
The customer evaluates the EAC provided bythe PM from the value of the TCPI computed
KPM 2009 - TulsaCopyright © Lipke 20096
-
8/20/2019 Lipke TheTCPIIndicator
7/31
TCPI Value Predicted Outcome
≤ . c eva e
> 1.10 Not Achievable
KPM 2009 - TulsaCopyright © Lipke 20097
-
8/20/2019 Lipke TheTCPIIndicator
8/31
When TCPI is equal to or less than 1.00, thereis confidence that the EAC can be achieved
,than 1.10 the project is considered to be “out of
control;” the EAC is very likely unachievable Between the two declarative values, 1.00 and
1.10, the PM’s actions become ever more.
intervention to improve cost performance veryprobably will be required to achieve the EAC
KPM 2009 - TulsaCopyright © Lipke 20098
-
8/20/2019 Lipke TheTCPIIndicator
9/31
TCPI CPI Threshold
1.1
1.2
1.3
x
TCPIExceed Threshold @ 0.35
0.8
0.9
1.0
I n d e
CPI = 0.850
0.7
0.0 0.2 0.4 0.6 0.8 1.0
Fraction Complete
KPM 2009 - TulsaCopyright © Lipke 20099
-
8/20/2019 Lipke TheTCPIIndicator
10/31
The planned final cost (BAC) will not beachieved if this performance, CPI = 0.850,
TCPI continually increases as the project
progresses, exceeding the threshold value of1.10 at fraction complete of approximately 0.35
The rate of TCPI increase becomes ever larger.
KPM 2009 - TulsaCopyright © Lipke 200910
-
8/20/2019 Lipke TheTCPIIndicator
11/31
What is the evidence that when TCPI>
1.10,the project is irrecoverable?
,empirical or theoretical studies to validate the
claim. In the next few slides, we’ll look at the behavior
of TCPI in more detail …and state my opinion
KPM 2009 - TulsaCopyright © Lipke 200911
-
8/20/2019 Lipke TheTCPIIndicator
12/31
A revealing view can be obtained using calculus…from TCPI in a different form:- – –
where CR (Cost Ratio) = TC / BAC
EV% = EV / BAC
For notation simplicity:
y = TCPI, x = EV%, a = CR, b = CPI-1
The equation to examine becomes:y = (1 – x)/(a – bx)
KPM 2009 - TulsaCopyright © Lipke 200912
-
8/20/2019 Lipke TheTCPIIndicator
13/31
As an example, let us analyze a project havingcost performance which will not achieve the-1 = = . , .
The point of interest is when TCPI equals the
threshold value (1.10)x = (ya – 1)/(yb -1)
= ((1.1 ∗ 1.1) – 1)/((1.1 ∗ 1.2) -1)
= .
KPM 2009 - TulsaCopyright © Lipke 200913
-
8/20/2019 Lipke TheTCPIIndicator
14/31
What is the rate of increase of TCPI at the
threshold value (1.10)?
complete can be examined using the first
calculus derivative: dy/dx = (b – a)/(a – bx)2
At the point of interest (TCPI = 1.10), thederivative can be evaluated:
. – . . – . .= (0.1)/(1.1 – 0.7875)2
=
KPM 2009 - TulsaCopyright © Lipke 200914
.
-
8/20/2019 Lipke TheTCPIIndicator
15/31
What happens to the rate of increase of TCPI
when performance continues and fraction
dy/dxEV%
1.0240.656
2.5000.750
1.4790.700
KPM 2009 - TulsaCopyright © Lipke 200915
-
8/20/2019 Lipke TheTCPIIndicator
16/31
For modest increases in EV%, it is seen fromthe numbers in the table that dy/dx (i.e. theTCPI rate) has larger and larger rates ofchange
Once the threshold is exceeded, there is little
positive impact …the project is very rapidlybecoming “out of control”
, .appears to be a reasonable criterion for makingthe assertion that the EAC put forth by the PM
KPM 2009 - TulsaCopyright © Lipke 200916
-
8/20/2019 Lipke TheTCPIIndicator
17/31
Application to ProjectRecovery
PMs applying EVM possess early warning tools Forecast of final cost, IEAC = BAC / CPI
’ ,the following data: CPI = 0.850, BAC = $1000,
MR = $100 What is projected for the future?
If CPI does not improve, BAC will be exceeded
= = .
MR will be consumed, IEAC > TAB
The project is headed for a budget overrun
KPM 2009 - TulsaCopyright © Lipke 200917
-
8/20/2019 Lipke TheTCPIIndicator
18/31
Application to ProjectRecovery
What is the PM’s prerogative when the project
is 80 percent complete?
final cost and graphing it as shown previously,
the answer is readily seen As observed in the next slide, the value of TCPI
is so large it is nearly off the chart; the.
KPM 2009 - TulsaCopyright©
Lipke 200918
-
8/20/2019 Lipke TheTCPIIndicator
19/31
Application to ProjectRecovery
vs
TCPI CPI Threshold
1.1
1.2
1.3TCPI = 1.259
@0.80
0.8
0.9
1.0
I n d e
CPI = 0.850
0.7
0.0 0.2 0.4 0.6 0.8 1.0
KPM 2009 - TulsaCopyright©
Lipke 200919
-
8/20/2019 Lipke TheTCPIIndicator
20/31
Application to ProjectRecovery
From our previous discussion, the PM knowsthat when TCPI ≥ 1.10 the project is regarded
very likely needed
In this instance, as uncomfortable as it may be,negotiation with the customer cannot beavoided
project is 30 percent complete?
KPM 2009 - TulsaCopyright©
Lipke 200920
-
8/20/2019 Lipke TheTCPIIndicator
21/31
Application to ProjectRecovery
The simple answer is “No”
At 30 percent complete, TCPI = 0.937, a good,
current performance does not improve the
project will overrun the funding available (TAB) However, with this value for TCPI, the PM has
an opportunity to take action thereby avoiding…
impending negotiation if the present cost
performance continues
KPM 2009 - TulsaCopyright©
Lipke 200921
-
8/20/2019 Lipke TheTCPIIndicator
22/31
Application to ProjectRecovery
What is the period of opportunity for the PM to
make a positive performance change?
TCPI exceeds 1.10 to recover the project
Is the period of opportunity sufficient forrecovery to be successful?
For our example, let’s look at the graph …
KPM 2009 - TulsaCopyright©
Lipke 200922
-
8/20/2019 Lipke TheTCPIIndicator
23/31
Application to ProjectRecovery
vs
TCPI CPI Threshold
1.1
1.2
1.3TCPI = 0.937
@ 0.30
TCPI > 1.10@ 0.72
0.8
0.9
1.0
I n d e
0.7
0.0 0.2 0.4 0.6 0.8 1.0
.
KPM 2009 - TulsaCopyright©
Lipke 200923
-
8/20/2019 Lipke TheTCPIIndicator
24/31
Application to ProjectRecovery
For a project of reasonable size, having morethan 40 percent of the period of performance to
,has a very good chance for being successful
with the recovery action
KPM 2009 - TulsaCopyright©
Lipke 200924
-
8/20/2019 Lipke TheTCPIIndicator
25/31
Evaluating the RecoveryStrategy
The TCPI has application, as well, in creating aviable recovery strategy …a trade-off between
commitments to the customer (TAB &
negotiated product delivery date) To resolve the condition of unsatisfactory cost
performance, the PM creates a plan fortransformin the cost erformance from the
present value of CPIa (actual value) to animproved efficiency, CPIs (strategy value)
KPM 2009 - TulsaCopyright © Lipke 200925
-
8/20/2019 Lipke TheTCPIIndicator
26/31
Evaluating the RecoveryStrategy
TCPI plays a role in evaluating whether the
change desired can realistically be achieved.For this purpose, the following formula for TCPIis used:
TCPI = (1 – EV%) / (CPIs-1 – CPIa-1 ∗ EV%)
,change has a good likelihood of beingachievable when the calculated value for TCPI
. … whether there is sufficient opportunity for theimprovement to succeed
KPM 2009 - TulsaCopyright © Lipke 200926
-
8/20/2019 Lipke TheTCPIIndicator
27/31
The To Complete Schedule Performance Index
(TSPI) facilitates analysis similar to the TCPI TSPI is e ual to the lanned duration for the
work remaining divided by the durationavailable:
where PD is the planned duration
ES is the Earned Schedule
…generally: PD, the negotiated duration (ND), orestimated duration (ED)
KPM 2009 - TulsaCopyright © Lipke 200927
computation
-
8/20/2019 Lipke TheTCPIIndicator
28/31
The use of TSPI is available for schedule
management and control in a parallel manner tocost and TCPI
Is the project schedule recoverable?
What is the period of opportunity for the PM to
Is the period of opportunity sufficient forschedule recovery to be successful?
Both TCPI & TSPI are needed to havecomplete capability for the cost–scheduleperformance trade-off necessary for project
KPM 2009 - TulsaCopyright © Lipke 200928
recovery
-
8/20/2019 Lipke TheTCPIIndicator
29/31
TCPI is definitely more than the simplecalculation for determining the performance rate
TCPI has application in evaluating the realism
of the bottom up derived EAC …it was shownthat the value of 1.10 is a reasonable criterionfor determining when a project is notrecoverable and is “out of control”
KPM 2009 - TulsaCopyright © Lipke 200929
-
8/20/2019 Lipke TheTCPIIndicator
30/31
Use of TCPI was extended to the evaluation of
the opportunity and the performancetransformation envisioned for project recovery TCPI may also be used in creating the tactical
changes of personnel and overtime adjustments
Throu h Earned Schedule the methodsdescribed for TCPI are made applicable toschedule analysis, as well
his/her efforts for controlling and managing theproject
KPM 2009 - TulsaCopyright © Lipke 200930
-
8/20/2019 Lipke TheTCPIIndicator
31/31
“The To Complete Performance Index …an expanded view,”
The Measurable News, 2009 Issue 2: 18-22 [W. Lipke] “Project Recovery …It Can Be Done,” CrossTalk, January
: - . p e
Practice Standard for Earned Value Management. NewtownSquare, PA: Project Management Institute 2005.
. .
KPM 2009 - TulsaCopyright © Lipke 200931