Methodology for Casting of Lift
Core walls
-
7/30/2019 Lift Shaft
2/21
For the construction of lift core walls ,For the construction of lift core walls ,
a combination of L&T wall formwork systema combination of L&T wall formwork systemwithwith
lift shaft system for supporting internal shutterslift shaft system for supporting internal shutters
andand
Travelling climbing system for External shuttersTravelling climbing system for External shuttersis suggestedis suggested
This gives the advantage of a fasterThis gives the advantage of a faster
progress for lift cores without waiting forprogress for lift cores without waiting for
the floor slab to completethe floor slab to complete
-
7/30/2019 Lift Shaft
3/21
With the suggested methodology, the lift core walls canWith the suggested methodology, the lift core walls can
progress ahead independent of the slab castingprogress ahead independent of the slab casting
-
7/30/2019 Lift Shaft
4/21
Typical section of a lift core wall showing inside and outsideTypical section of a lift core wall showing inside and outside
shutters with supporting platform arrangementshutters with supporting platform arrangement
-
7/30/2019 Lift Shaft
5/21
Formwork details:
L&T Wall formwork with Travelling climbingsystem (CB 150F) used for Outer face of corewall.
L&T Lift shaft platform system used with wallformwork for Inner face / opening.
Outer shutter panels are supported on a pair ofbrackets.
Each pair of shutter panel with brackets havingin-built safety such as necessary handrails forconcreting & shutter platforms.
Tower cranes used for lifting of shutters from one
-
7/30/2019 Lift Shaft
6/21
The lift shaft platform system is suitable for lift core / RC-walls close to each other.
The Climbing Formwork System comprises of shaft main beam resting in pocketsprovided in the already cast RC-Wall. The cross beams are provided over this.Wooden planks over the cross beams form the lift shaft platform. Leveling of the
platform is possible by operation of spindle within the gravity pawls.
The main beam have gravity pawls which unlocks it self from the pockets when liftedupwards and lock itself at the next pocket location. The gravity pawls are hingedand have one way movement only, the platform thus has high levels of safety.
The platform as a whole alongwith the main beam, gravity pawls, cross beams andplatform can be lifted as one unit.
This platform facilitates resting of the wall formwork and alignment.
Ideal system for speedy
construction.
Eliminates the need for
scaffolding to support the Wall
Formwork. High levels of safety - full proof
system.
Minimum skill & operation for
anchoring & shuttering at each
level.
Liftshaft
platformrestingin thepockets
SALIENT FEATURESSYSTEM DESCRIPTION:
Details showing the arrangement of Lift shaft platform and shutters insideDetails showing the arrangement of Lift shaft platform and shutters inside
Lifting Bkt.
Sling fromCrane
To be cast
Pocket to suitPawl
Freshly cast
Pocket to suitPawl Climbing
Pawl Lift shaftPlatform
Already CastWall
Lifting Bkt.
Sling fromCrane
To be cast
Pocket to suitPawl
Freshly cast
Pocket to suitPawl Climbing
Pawl Lift shaftPlatform
Already CastWall
Sling fromCrane
To be cast
Freshly cast
Climbing Pawl
Lift shaft Platform
Already CastWall
Pocket to suit Pawllift shaftplatformbeing
lifted tothe nextlevel
Sling fromCrane
To be cast
Freshly cast
Climbing Pawl
Lift shaft Platform
Already CastWall
Pocket to suit Pawllift shaftplatformbeing
lifted tothe nextlevel
-
7/30/2019 Lift Shaft
7/21
Details showing the climbing system 150 F and shutters outside
SHIFTING OF PANELTO NEXT LEVEL USINGCRANE
VERTICAL WALER
ROLL BACKOF SHUTTERS
-
7/30/2019 Lift Shaft
8/21
L&T Formwork System is being used for the
construction of the LIFT CORE WALLS
Project: TSI Business Park At Hyderabad
Contractor: M/s. Shapoorji Pallonji & CoLtd.
The total catered area is :
2 sets of lift core(typ floor) of phase I=1140 sqm2 sets of lift core(typ floor) of phase II/III=1650 sqm
The total catered area :2790 sqm
-
7/30/2019 Lift Shaft
9/21
Structure details Total number of lift core = 5 (Two in phase I, Two
in phase-II and One in phase3)
Thickness of wall 230mm (Inner) & 350mm/500mm (Outer)
Total number of vertical floors/ pours is 23 Pouring height per lift 4.00m (max.)
The formwork is designed for:Design lateral concrete Pressure : 41.6 kN/Sq.m
Allowable rate of pour :1.00 m /hour
-
7/30/2019 Lift Shaft
10/21
Plan of Lift core wall shuttering for phase 1Plan of Lift core wall shuttering for phase 1
-
7/30/2019 Lift Shaft
11/21
Method statement1. Casting of Starter with timber sides to suit walldimensions.
2. Assembly of formwork: (For 1st Pour)
3.Removal of formwork (for 1st
Pour)
4.Erection of Inside/outside platforms and erectionof formwork for second/next lift and concreting
5. De-shuttering of formwork and transfer to nextlevel along with platforms with the help of crane.
Step 4&5 repeated till the entire structure is
-
7/30/2019 Lift Shaft
12/21
Method statement ..contdAssembly of formwork: (For 1st Pour)
1. Placing of Shutter panel, check the line and level, then placing along the
one side of the wall.2. Inserting the Tierods upto other side wall surface covered by PVC pipe at
the required locations (ie. As per scheme drawing & design calculations)
3. Placing of other side Shutter panel and check the edges with plumb, thenplacing other shutter panels continuously.
4. Extending the Tie rods and fixing with Anchor plate & wingnut.5. Placing Alignment props / Supporting bracket with Head adapter assembly& Foot adapter assembly.
6. Joining the shutter panels together by Splices with Connecting pins.
7. Fixing of Timber spacers (for wall thickness) on the top between theshutter panels
8. Plumbing of shutters by using alignment struts / plumb bobs.,Checking thestraight line/Checking the wall thickness at the top.
9. Universal inside corners and Universal outside fixing to be fixed accordingto the requirements of wall corners.
10.Stop anchors, Ties ,Anchor cones covered with PVC sleeves to be fixed forsubsequent lift done for climbing system. Place the shaft pocket for shaft
-
7/30/2019 Lift Shaft
13/21
12 MMDENS PLY
ALIGNMENTSYSTEM
H16 - BEAM
WORKINGPLATFORM
STD. STEELWALER
LIFTINGBRACKET
C /S ELEVATION
WALL FORMWORK SYSTEM
STEEL WALER
12 MM THK PLY.
TIE SYSTEM
H-BEAMS
PLAN
-
7/30/2019 Lift Shaft
14/21
Method statement ..contd
Removal of formwork:
First removal of Tie rods, Alignment struts, accessories
Removal of shutters (each separately) with the help ofcrane
Cleaning and shifting of shutter panels (with alignmentprops / supporting brackets) to next lift / length.
-
7/30/2019 Lift Shaft
15/21
Method statement ..contdCB150F-making
1. After dismantling the shutters, remove anchor cone using DKspanner and fix climbing cone.
2. Climbing bracket 150F 2 nos (to suit stop anchor location whichis already left in conc.) should be made as a set by bracing with NB 40pipes and couplers.
3. Fix working platforms with ISMC runners and 2 thick planks.
4. Fix the Vertical waling (roler below the waler should sit over thebracket and scissor action spindle (in collapsed condition) with the helpof Locking pins.
5. Brace the vertical walers properly with horizontal and Diagonal byNB 40 pipes & couplers.
6. Fix the vertical waler with Climbing bracket tightly with wedges toprevent movement.
7. Fix Handraill post on each bracket and hand railing at 2 levels
should be done with NB 40 pipes & couplers.
-
7/30/2019 Lift Shaft
16/21
Climbing system 150F with outside shuttersClimbing system 150F with outside shutters
-
7/30/2019 Lift Shaft
17/21
Method statement ..contdCB150F/Lift shaft platforms erection
1 Lift the entire assembly of climbing bracket 150F (by putting thesling on the top of the vertical walers) with the help of crane and placeover the climbing cone correctly. Lock the climbing bracket with thelocking pin to arrest upward movement of bracket from climbing conehead.
2 Follow the procedures described in the assembly of wall formwork,however the alignment props to be removed.
3. Vertical walers should be connected with horizontal walers usingwaling to bracket holders.
4. Top leveling of shutters and adjustment of verticality done byadjusting the screws at the bottom of the vertical walers. Aligning ofshutters should be done with Scissor action spindles.
5. Check the verticality of the shutter using plumb bob.
6. Make lift shaft platform at ground with climbing pawl.
7. Shift the platform with help of crane & place it where the pocketsalread rovided.
-
7/30/2019 Lift Shaft
18/21
Botom View of shaft platform insideBotom View of shaft platform inside
-
7/30/2019 Lift Shaft
19/21
Lift shaft platform with inside shuttersLift shaft platform with inside shutters
-
7/30/2019 Lift Shaft
20/21
Method statement ..contdDismantling and shifting to next level after concreting of typical
pour
Roll back the shutters from concrete face.
Put the crane sling in the hook provided in the Vertical waler.
Take out the locking pin in the climbing bracket, so that the climbing
bracket can be free for lifting. Lift the entire assembly (including shutter panel and climbing bracket
150F assembly) and place it in next position.
Remove Inner shutter panels & shift by crane to available placetemporarily. (low level slab if any)
Lift the Inner shaft platform to next higher level. This entire operation is repeated to complete the core wall
Folded Dowel bars will be taken out by chipping & Bent to requiredposition.
Structural consultants should approve the slab casting & freestandingheight of core walls.
-