Lick Creek TrailProject Status Report
City Council MeetingMay 22, 2014
Background
• 2002 – Proposed in the Bikeway and Pedestrian Master Plan
• 2004 – Prioritized by the Hike and Bike Task Force and adopted by City Council as a High Priority
• 2008 – Funding included in bond referendum approved by voters ($4.4 million)
• 2011 – Awarded contract to Halff Associates to conduct a preliminary design study
• May 2012 – Route alternatives presented to Council
• January 2013 – Awarded design contract to Halff Associates
Segment A
Segment A
Segment A (Eagle/Longmire/Barron) Reconstruct sidewalks Address ADA issues Stripe bike lanes Minimize impacts to landscaping, fences, and
neighborhood signs inside the ROW Keep all improvements inside the existing ROW
or existing public access easements
Segment B
Segment C
Budget Information
Project Budget: $4,410,000 Expended to Date: $590,983 Balance: $3,819,017
Construction Estimate w/10% Contingency: $3,400,000
Budgeted Annual O&M Costs: $33,000
Schedule Information
July 2014: Bid for Construction August 2014: Award Construction Contract September 2014: Receive/Review Initial
Submittals, Hold Preconstruction Conference, and Establish Notice To Proceed Date
October 2014: Notice To Proceed With Construction
October 2015: Final Completion