liambaines_construction_facades

6
FACADE PROJECT LIAM BAINES ASSIGNMENT 3 SARC321 15 OCTOBER 2014

Upload: liam-baines

Post on 18-Jul-2015

99 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: LiamBaines_Construction_FACADES

FACADE PROJECT LIAM BAINES ASSIGNMENT 3 SARC321 15 OCTOBER 2014

Page 2: LiamBaines_Construction_FACADES

PLAN LIAM BAINES ASSIGNMENT 3 SARC321 15 OCTOBER 2014

Joint project, however this document contains my Indi-vidual contribution; facade design.

Typical ground floor plan and core layout for the office block.

West, South and East Ele-vations are all to have Alu-cobond facades, while the North Elevation is to make maximum use of the sunlight with a glass curtain wall.

Page 3: LiamBaines_Construction_FACADES

GSEducationalVersion

+3,7002 Ground Floor +3,7002 Ground Floor

+7,4003 1st Floor +7,4003 1st Floor

+11,1004 2nd Floor +11,1004 2nd Floor

+14,8005 3rd Floor +14,8005 3rd Floor

+18,5006 4th Floor +18,5006 4th Floor

+22,2007 5th Floor +22,2007 5th Floor

+25,9008 6th Floor +25,9008 6th Floor

+29,6009 7th Floor +29,6009 7th Floor

+33,30010 8th Floor +33,30010 8th Floor

+37,00011 9th Floor +37,00011 9th Floor

1 North Elevation 1:200

NORTH ELEVATION LIAM BAINES ASSIGNMENT 3 SARC321 15 OCTOBER 2014

Curtain Wall facade with opaque glass along the slab and column segments. Allows deepest light penetration into the office block.

Page 4: LiamBaines_Construction_FACADES

GSEducationalVersion

1 2 3 4 5

+3,700Ground Floor

+3,700Ground Floor

+7,4001st Floor

+7,4001st Floor

+11,1002nd Floor

+11,1002nd Floor

+14,8003rd Floor

+14,8003rd Floor

+18,5004th Floor

+18,5004th Floor

+22,2005th Floor

+22,2005th Floor

+25,9006th Floor

+25,9006th Floor

+29,6007th Floor

+29,6007th Floor

+33,3008th Floor

+33,3008th Floor

+37,0009th Floor

+37,0009th Floor

1 West Elevation 1:200

WEST ELEVATION LIAM BAINES ASSIGNMENT 3 SARC321 15 OCTOBER 2014

Alucobond facade with windows above desk height, and Alucobond Cassette System along the slab and column seg-ments.

Page 5: LiamBaines_Construction_FACADES

GSEducationalVersion

1 Alucobond Detail 1:50

2 Section AA 1:50

Selected 600x600mm20mm Ceiling tile w/selected Aluminiumsuspended ceiling grid

Alucabond cassetteSystem

R2.8 FibreglassInsulation

90x45 H1.2 timberframing construction

600x600mm CastInsitu RC column w/steel reinforcing toEngineers design

10mm Membraneto top of ecoply

Carpet

75mm RC topping w/reinforcing as perengineers design

Stresscrete 200mm RCprecast plank floor system

w/20mm H3.2 plywoodinfill

Selected 600x600mm20mm Ceiling tile w/selected Aluminium

suspended ceiling grid

Thermosash 40mm doubleglazing

CommercialAluminium windowJoinery

R2.8 Fibreglass Insulation

Ecoply Rigid Air Barrier

90x45 H1.2 timber framingconstruction

Alucobond casettesystem over 7mmEcoply Rigid AirBarrier w/proprietary tape.The Ecoply barrieris fixed to 90x45H1.2 timberframing w/R2.8fibreglassinsulation. Thetimber framing isthen fixed to RCconcreteconstruction w/M16 Bolts

2/ 10mm GIB Fyreline walllining

7mm Ecoply rigidair barrier

R2.8 fibreglassinsulation

90x45 H1.2 timberframing @ 600mmctrs w/ dwangs @800mm verticalcentres

600x600mm Cast Insitu RCcolumn w/ steel reinforcing

to Engineers design

Thermosash 40mmdouble glazing

CommercialAluminium windowJoinery

ALUCOBOND DETAIL LIAM BAINES ASSIGNMENT 3 SARC321 15 OCTOBER 2014

Page 6: LiamBaines_Construction_FACADES

GSEducationalVersion

1 Curtainwall Detail 1:50

2 Section BB 1:50

Selected 600x600mm20mm Ceiling tile w/selected Aluminiumsuspended ceiling grid

600x600mm CastInsitu RC column w/steel reinforcing toEngineers design

Carpet

75mm RC topping w/reinforcing as perengineers design

Stresscrete 200mm RCprecast plank floor system

w/20mm H3.2 plywoodinfill

Selected 600x600mm20mm Ceiling tile w/selected Aluminium

suspended ceiling grid

Thermosash 40mm doubleglazing

Thermosashcurtain facadesystem suspendedin front of slab on10mm mild steelbracket attachingvertical mullions tothe slab

Frosted glazing onslab layer

600x600mm Cast Insitu RCcolumn w/ steel reinforcing

to Engineers design

Thermosash curtainwall stick system w/double glazing

Aluminium facadesystem windowJoinery

Frosted glazing onslab layer

Fire safing

CURTAIN WALL DETAIL LIAM BAINES ASSIGNMENT 3 SARC321 15 OCTOBER 2014