FACADE PROJECT LIAM BAINES ASSIGNMENT 3 SARC321 15 OCTOBER 2014
PLAN LIAM BAINES ASSIGNMENT 3 SARC321 15 OCTOBER 2014
Joint project, however this document contains my Indi-vidual contribution; facade design.
Typical ground floor plan and core layout for the office block.
West, South and East Ele-vations are all to have Alu-cobond facades, while the North Elevation is to make maximum use of the sunlight with a glass curtain wall.
GSEducationalVersion
+3,7002 Ground Floor +3,7002 Ground Floor
+7,4003 1st Floor +7,4003 1st Floor
+11,1004 2nd Floor +11,1004 2nd Floor
+14,8005 3rd Floor +14,8005 3rd Floor
+18,5006 4th Floor +18,5006 4th Floor
+22,2007 5th Floor +22,2007 5th Floor
+25,9008 6th Floor +25,9008 6th Floor
+29,6009 7th Floor +29,6009 7th Floor
+33,30010 8th Floor +33,30010 8th Floor
+37,00011 9th Floor +37,00011 9th Floor
1 North Elevation 1:200
NORTH ELEVATION LIAM BAINES ASSIGNMENT 3 SARC321 15 OCTOBER 2014
Curtain Wall facade with opaque glass along the slab and column segments. Allows deepest light penetration into the office block.
GSEducationalVersion
1 2 3 4 5
+3,700Ground Floor
+3,700Ground Floor
+7,4001st Floor
+7,4001st Floor
+11,1002nd Floor
+11,1002nd Floor
+14,8003rd Floor
+14,8003rd Floor
+18,5004th Floor
+18,5004th Floor
+22,2005th Floor
+22,2005th Floor
+25,9006th Floor
+25,9006th Floor
+29,6007th Floor
+29,6007th Floor
+33,3008th Floor
+33,3008th Floor
+37,0009th Floor
+37,0009th Floor
1 West Elevation 1:200
WEST ELEVATION LIAM BAINES ASSIGNMENT 3 SARC321 15 OCTOBER 2014
Alucobond facade with windows above desk height, and Alucobond Cassette System along the slab and column seg-ments.
GSEducationalVersion
1 Alucobond Detail 1:50
2 Section AA 1:50
Selected 600x600mm20mm Ceiling tile w/selected Aluminiumsuspended ceiling grid
Alucabond cassetteSystem
R2.8 FibreglassInsulation
90x45 H1.2 timberframing construction
600x600mm CastInsitu RC column w/steel reinforcing toEngineers design
10mm Membraneto top of ecoply
Carpet
75mm RC topping w/reinforcing as perengineers design
Stresscrete 200mm RCprecast plank floor system
w/20mm H3.2 plywoodinfill
Selected 600x600mm20mm Ceiling tile w/selected Aluminium
suspended ceiling grid
Thermosash 40mm doubleglazing
CommercialAluminium windowJoinery
R2.8 Fibreglass Insulation
Ecoply Rigid Air Barrier
90x45 H1.2 timber framingconstruction
Alucobond casettesystem over 7mmEcoply Rigid AirBarrier w/proprietary tape.The Ecoply barrieris fixed to 90x45H1.2 timberframing w/R2.8fibreglassinsulation. Thetimber framing isthen fixed to RCconcreteconstruction w/M16 Bolts
2/ 10mm GIB Fyreline walllining
7mm Ecoply rigidair barrier
R2.8 fibreglassinsulation
90x45 H1.2 timberframing @ 600mmctrs w/ dwangs @800mm verticalcentres
600x600mm Cast Insitu RCcolumn w/ steel reinforcing
to Engineers design
Thermosash 40mmdouble glazing
CommercialAluminium windowJoinery
ALUCOBOND DETAIL LIAM BAINES ASSIGNMENT 3 SARC321 15 OCTOBER 2014
GSEducationalVersion
1 Curtainwall Detail 1:50
2 Section BB 1:50
Selected 600x600mm20mm Ceiling tile w/selected Aluminiumsuspended ceiling grid
600x600mm CastInsitu RC column w/steel reinforcing toEngineers design
Carpet
75mm RC topping w/reinforcing as perengineers design
Stresscrete 200mm RCprecast plank floor system
w/20mm H3.2 plywoodinfill
Selected 600x600mm20mm Ceiling tile w/selected Aluminium
suspended ceiling grid
Thermosash 40mm doubleglazing
Thermosashcurtain facadesystem suspendedin front of slab on10mm mild steelbracket attachingvertical mullions tothe slab
Frosted glazing onslab layer
600x600mm Cast Insitu RCcolumn w/ steel reinforcing
to Engineers design
Thermosash curtainwall stick system w/double glazing
Aluminium facadesystem windowJoinery
Frosted glazing onslab layer
Fire safing